PB Thermal Station Costs
PB Thermal Station Costs
PB Thermal Station Costs
SEPTEMBER 2009
Prepared By:
DISCLAIMER NOTICE
This report has been prepared exclusively for the benefit of the Electricity Commission.
PB New Zealand Ltd (PB) will not be liable to any other persons or organisation and
assumes no responsibility to any other person or organisation for or in relation to any
matter dealt with or conclusions expressed in the Report, or for any loss or damage
suffered by any other persons or organisations arising from matters dealt with or
conclusions expressed in the report (including without limitation matters arising from any
negligent act or omission of PB or for any loss or damage suffered by any other party
relying upon the matters dealt with or conclusions expressed in the Report). No person
or organisation other then the Electricity commission is entitled to rely upon the Report
or the accuracy or completeness of any conclusion and such other parties should make
their own enquiries and obtain independent advice in relation to such matters.
Reliance on Data
In preparing this Report, PB has relied on information supplied by and gathered from a
number of sources including public domain and proprietary data services, internet sites,
news services as well as parties involved in the industry. Any projections are estimates
only and may not be realised in the future. No blame or responsibility should be
attached to any of these sources for any factual errors or misinterpretation of data in the
Report. PB has not independently verified the accuracy of this information and has not
audited any financial information presented in this Report.
Limitations
This Report covers technical data relating to thermal generating plants and is based on
the facts known to PB at the time of preparation. This report does not purport to contain
all relevant information on all plant. PB has made a number of assumptive statements
throughout the Report, and the Report is accordingly subject to and qualified by those
assumptions. The uncertainties necessarily inherent in relying on assumptions and
projections mean that it should be anticipated that certain circumstances and events
may differ from those assumed and described herein and that such will affect the results.
PB Quality System:
Document Reference : 153012A Task 002 Thermal Power Station Advice Report -
O&M costs 002 final.doc
PARSONS BRINCKERHOFF
Thermal Power Station Advice
PB Report for the Electricity Commission
Contents
Page Number
1 Introduction ..................................................................................................................... 1
1.1 Background 1
1.2 Methodology 1
1.3 Scope 1
1.4 Exchange rates 2
2 O&M cost comparisons................................................................................................... 3
2.1 Introduction 3
2.2 Definitions 3
2.3 GEM assumptions 4
2.4 Other Energy markets 5
2.5 Previous PB reports 6
2.6 Other reference information 8
3 Analysis ......................................................................................................................... 10
3.1 Technology specific cost comparison 10
3.2 O&M costs & exchange rate movements 12
3.3 Summary 12
4 Glossary ......................................................................................................................... 14
List of tables
Table 1 Technology specific O&M costs iii
Table 2 NZ thermal plant O&M costs iii
Table 2.1 GEM technology specific O&M costs 4
Table 2.2 NZ thermal plant O&M costs GEM 4
Table 2.3 NEM generator O&M costs existing plant 5
Table 2.4 NEM new entrant O&M costs 5
Table 2.5 US generator O&M costs technology specific 6
Table 2.6 SOO O&M cost assumptions technology specific 6
Table 2.7 SOO O&M cost assumptions NZ thermal plant 7
Table 2.8 Peaking report O&M costs technology specific 7
Table 2.9 East Harbour report: O&M cost assumptions 8
Table 2.10 Marsden et al report O&M costs 8
Table 2.11 Poyry UK report O&M costs 9
Table 3.1 ST O&M costs comparison 10
Table 3.2 CCGT O&M costs comparison 10
Table 3.3 OCGT gas fuelled O&M costs comparison 11
Table 3.4 OCGT liquid fuelled O&M costs comparison 11
Table 3.5 Technology specific O&M cost recommendations 12
Table 3.6 NZ thermal plant O&M cost recommendations 13
Executive Summary
The Electricity Commission has engaged PB New Zealand Ltd to provide estimates of non-fuel,
fixed and variable O&M costs for thermal plant in New Zealand. A broad literature review of
comparative information from the Australian, North American and European energy markets
has been used in recommending appropriate estimates for thermal plant O&M cost
assumptions used in the Electricity Commissions Generation Expansion Model (GEM).
Operating and maintenance costs are subject to wide variation depending on the make and
model of plant, the operating regime, and whether coal, gas or liquid fuel is used. The
recommended values for non-fuel, fixed and variable O&M costs for new entrant thermal plant
technology types are presented in Table 1.
Table 1 Technology specific O&M costs
1
Values in 2009 New Zealand dollars.
The recommended values for non-fuel, fixed and variable O&M costs for existing New Zealand
thermal power stations are presented in Table 2.
Table 2 NZ thermal plant O&M costs
1
Values in 2009 New Zealand dollars.
1.2 Methodology
In order to provide the required information to the Commission, a broad literature
review of comparative information from the Australian, North American and
European energy markets has been performed supplementing PBs knowledge
and experience of working with thermal power station costs. This provides a basis
for the reconciliation and update of the existing GEM assumptions.
1.3 Scope
Thermal technologies considered are:
The above technologies cover the breadth of existing thermal plant in New
Zealand, and provide coverage for the generic main types of new thermal
generation included in the GEM modelling assumptions.
1
PB New Zealand Ltd. Thermal Power Station Advice: Report for the Electricity Commission. July 2009.
Otahuhu B CCGT;
Southdown CCGT;
Currency conversion rates used for the purposes of this report are as follows:
As definition of the terms relating to O&M costs varies widely, it has been
important to understand the assumptions made by each source of information as
to what has been included and excluded for each comparative value.
2.2 Definitions
All fixed and variable O&M costs referred to in the report exclude any costs
associated with fuel supply, transport and handling, Capex and major
refurbishment.
Major maintenance costs for gas turbine plant can also be included in the VOM
cost values. This is because maintenance is based on the equivalent operating
hours of the plant as opposed to coal fuelled steam turbine plant where
maintenance is periodic and treated as a fixed operating cost. Where the
reference information allows, the report will indicate whether major maintenance
has been included in the variable or fixed portion of gas turbine plant O&M costs.
Typically, gas fired plant has the lowest variable O&M costs and coal fuelled plant
has the highest costs associated with the costs of ash disposal and requirements
2
for flue gas desulphurisation (FGD).
These costs, defined as $/kW/year, typically include all fixed operating costs such
as spares, major periodic maintenance, insurance, O&M fees, property taxes and
leases and owners costs such as wages. Fixed costs should not vary with
changes in electricity generation levels.
2
No New Zealand plant currently have FGD installed.
The existing GEM cost assumptions have used a variety of sources, with some
reports more recent than others. Whilst some input O&M costs for thermal plant
do change over time, in general plant running costs are not expected to change
significantly due to the cost savings derived from technology advances off setting
any inflationary effects.
An ACIL Tasman report3 for NEMMCO estimated the costs of generation for
existing and future thermal assets. Information contained in the report on O&M
costs for existing and new entrant plant in the NEM are summarised in Table 2.3
and Table 2.4.
3
ACIL Tasman. Fuel Resource, new entry and generation costs in the NEM. April 2009.
All estimates were based in 2004 New Zealand dollars. Information previously
4
supplied is summarised in the following two tables.
The values provided in Table 2.6 included both the variable and fixed non-fuel
O&M costs for thermal generating plant, as inputs into calculating the LRMC of
different generating technologies.
4
PB Associates. Electricity Generation Database: Statement of Opportunities update 2006. October 2006.
Asset Variable
$/MWh
Huntly Power Station ST (Units 1-4) 9.6
Huntly OCGT (P40) 6.4
Southdown - CCGT 4.3
Otahuhu B - CCGT 4.3
TCC - CCGT 4.3
Whirinaki 6.4
Southdown - OCGT 6.4
Huntly CCGT (e3p) 4.3
This PB report5 provided estimates of both fixed and variable annual O&M costs
for gas and diesel fuelled peaking plant (OCGT) in New Zealand. All estimates
were based in 2008 New Zealand dollars. Information supplied as follows:
The O&M cost estimates were based on a 2% capacity factor and 30 starts per
year with an average duration of 6 hours operation.
The variable O&M costs for liquid fuelled plant are higher due to the reduced
operating hour intervals between scheduled maintenance associated with
operating an engine on liquid fuels.
The overall O&M costs for liquid fuelled plant are very sensitive to increases in
operating hours and rapidly increase if annual operating hours assumptions
increase. The costs are also very specific to the individual engines installed as
each manufacturer specifies different maintenance requirements for their
machines.
5
PB New Zealand Ltd. Cost Estimates for Thermal Peaking Plant, Version 002. June 2008.
The following information6 was prepared for the New Zealand Ministry of
Economic Development.
Values summarised in Table 2.10 are taken from a report 7 which examined
investment costs for the New Zealand electricity industry.
6
East Harbour Management Services Ltd. Costs of fossil fuel generating plant. May 2002.
7
Marsden, Poskitt and Small. Investment in the New Zealand Electricity Industry. 2004.
A Poyry Energy Consulting (PEC) report8 for the UK Government assumes the
non-fuel O&M costs contained in Table 2.11.
8
Poyry Energy Consulting. Analysis of carbon capture and storage cost-supply curves for the UK. January 2007.
Table 3.1 summarises the variance in the O&M costs for coal fuelled ST plant.
PB considers that the current GEM assumption for variable O&M costs is currently
in the correct range. The notable anomaly is the NEM value which appears low
considering the additional variable costs such as ash handling, limestone and FGD
expenses incurred by such plant.
The fixed O&M cost assumption in GEM appears high when compared with the
other values, and therefore PB recommends that $70/kW/year may be more in-
line with typical costs.
Table 3.2 summarises the variance in the O&M costs for gas fuelled CCGT plant.
Table 3.3 summarises the variance in the O&M costs for gas fuelled OCGT plant.
PB considers that the current GEM assumption for non-fuel variable O&M costs is
currently slightly below the correct range. PB would recommend increasing this to
$8/MWh in order to reflect actual current costs.
The fixed O&M cost assumption in GEM also appears slightly low when compared
with the other values, and therefore PB recommends that $16/kW/year may be
more in-line with typical costs.
Table 3.4 summarises the variance in the O&M costs for gas fuelled CCGT plant.
PB considers that the current GEM assumption for non-fuel variable O&M costs is
currently too high. PB would recommend decreasing this to $9.6/MWh in order to
reflect actual current costs.
PB has assumed a penalty factor of 1.2 on the OCGT plant liquid fuelled
variable O&M costs when compared to the gas fuelled equivalent to account for
the reduction in interval times between major maintenance. Running plant on
liquid fuels decreases the number of operating hours between service intervals.
3.3 Summary
3.3.1 Technology specific O&M cost recommendations
For Huntly Units 1-4, PB considers the variable O&M cost should be slightly higher
given Huntlys non-baseload operational role. For Whirinaki, in its role as dry year
reserve plant, PB considers the fixed O&M costs should be slightly higher due to
the nature of the contracting arrangement for the operation and maintenance of
the plant.