17 II.7 Earthing
17 II.7 Earthing
17 II.7 Earthing
EARTHING
1.0 GENERAL:
1.1 Earthing of each tower is to be done after the foundation has been casted.
1.2 The earthing connection which was fixed to the stub during concreting of the chimney and
taken out horizontally below the ground level is used for earthing.
1.3 As given at para 8.6.1 of Chapter – 4 of this section, this earthing connection is generally
provided on Leg 1 and additional earthing, if required, is provided on Leg 3 for pipe type
earthing. For counterpoise earthing, the earthing connection is provided on all the four legs.
1.4 The installation of the earthing shall be done in accordance with IS : 5613 – 1989 (Part 3 /
Section 2) for 400 kV lines or IS : 5613 – 1985 (Part 2 / Section 2) for 220 kV and 132 kV
lines.
2.3 A hole of the required diameter and depth is augured in the earth for the earthing pipe.
2.5 A mixture of coke and salt is filled in the hole in which the earthing pipe is provided.
2.6 The earthing strip which was fitted to the stub of the tower leg is then connected to the
earthing pipe.
2.7 The Railway authorities specify that the size of the pipe used for earthing should be of 38
mm diameter. Therefore, for towers on both sides of the Railway crossing, 2 pipes
connected together are to be used for earthing.
2.8 In case of difficult locations, the pipe may be laid horizontally or slanting and within the
tower base or foundation pit.
3.2 The wires are connected to each of the legs and taken radially away from the tower and
embedded horizontally below ground level. The depth of burial below ground level and the
length of each wire are normally kept according to the values given in the table below.
However, the length of each wire may be increased if the resistance requirements are not
met.
4.2 The additional earthing shall be done without interfering with the foundation concrete even
though the earth strip / counterpoise lead remains exposed at the tower end.
4.3 The connections in such cases shall be made with the existing lattice member holes on the
leg just above the chimney top.
Earthing 127
APPENDIX – A
128 Construction Manual for Transmission lines
APPENDIX – B