PMP Course PDF
PMP Course PDF
PMP Course PDF
PREPERATION
COURSE
AshrafOsman, MBA, PMP ashrafnur89@gmail.com
Ashraf Osman
MBA, PMP
NOTICE
Hello, This is ASHRAF OSMAN from Sudan, I'm MBA & PMP holder and trainer as well.
it is my pleasure to share this slides with you. I spent almost 3 months to prepare them.
Feel free to share it with your friends but please, don't use them for commercial use.
Ashraf Osman
MBA, PMP
OVERVEIW
About PMP exam
61 200 4
IS REQUIRED QUESTIONS HOURS
MBA, PMP
OVERVEIW
About PMP exam
405 3 60
DOLLAR YEARS PDUs
The cost of the exam Are tha validity of the Must be earned to
for PMI members & certificate maintain the
$555 for non-members. certificate
membership cost is
$139
Ashraf Osman
MBA, PMP
INTRODUCTION TO PMP EXAM
planning
Executing: 53 questions 24%
Ashraf Osman
MBA, PMP
INTRODUCTION
TO PROJECT
MANAGEMENT
PMP PREPARATION COURSE
Ashraf Osman
MBA, PMP
WHAT IS THE PROJECT?
A TEMPORARY ENDEAVOR
UNDERTAKEN TO CREATE UNIQUE
PRODUCTS, SERVICES OR RESULT.
Ashraf Osman
MBA, PMP
PROJECT VS OPERATION
TEMPORARY ONGOING
UNIQUE REPETITIVE
Ashraf Osman
MBA, PMP
1- GENERAL
TO BE A GOOD MANAGEMENT SKILLS
PROJECT MANAGER
YOU SHOULD HAVE
2- INTERPERSONAL SKILLS
3- UNDERSTANDING
PROJECT ENVIRONMENT
Ashraf Osman
MBA, PMP
MANAGING A PROJECT
MEANS
Ashraf Osman
MBA, PMP
THE PROJECT CONSTRAINTS
SCOPE
RISK QUALITY
THE
PROJECT
COST TIME
PROGRAM MANAGEMENT
FOCUSES ON INTERDEPENDENCIES
WHAT IS THE OF PROJECTS AND DESCRIBES
THE BEST APPROACH TO
PROGRAM? ACHIEVE PROGRAM OBJECTIVES
Ashraf Osman
MBA, PMP
MARKET CUSTOMER
DEMAND REQUEST
WHY ARE
PROJECTS
UNDERTAKEN?
ORGANIZATION LEGAL
NEED REQUIREMENT
PROJECT
MANAGEMENT OFFICE
(PMO)
COORDINATES RESOURCES
DEVELOPS PROJECT MANAGEMENT
METHODOLOGIES, BEST PRACTICES, AND
STANDARDS
REPOSITORY OF PROJECT TEMPLATES AND
DOCUMENTS
MONITORING QUALITY OF PROJECTS
Ashraf Osman
MBA, PMP
TYPES OF PMOS
THEY ARE THREE
MBA, PMP
PROJECT
LIFE
CYCLE
COMPANY.COM
PROJECT PHASE
DELIVERABLE
PHASE
Ashraf Osman
MBA, PMP
PHASE TO PHASE
RELATIONSHIPS
PHASE 1
PHASE 1 PHASE 2 PHASE 1 PHASE 2
PHASE 2
Ashraf Osman
MBA, PMP
PROJECT
STAKEHOLDERS
PROJECT STAKEHOLDERS ARE INDIVIDUALS
AND ORGANIZATIONS WHO ARE ACTIVELY
INVOLVED IN THE PROJECT, OR WHOSE
INTERESTS MAY BE POSITIVELY OR
NEGATIVELY AFFECTED AS A RESULT OF
PROJECT EXECUTION OR SUCCESSFUL
COMPLETION
Ashraf Osman
MBA, PMP
PROJECT
STAKEHOLDERS
STAKEHOLDERS' INFLUENCE
POSITIVE NEGATIVE
Ashraf Osman
MBA, PMP
TYPE OF ORGANIZATIONS
Ashraf Osman
MBA, PMP
FUNCTIONAL ORGANIZATION
IN A FUNCTIONAL ORGANIZATION, THE TEAMS WORKING ON THE PROJECT DONT REPORT DIRECTLY
TO THE PM. INSTEAD, THE TEAMS ARE IN DEPARTMENTS, AND THE PROJECT MANAGER NEEDS TO
BORROW THEM FOR THE PROJECT.
ALL OF THE PROJECT WORK TYPICALLY HAPPENS WITHIN A PARTICULAR DEPARTMENT, AND THAT
DEPARTMENTS MANAGER IS COMPLETELY IN CHARGE OF EVERYTHING.
PROJECT CEO
COORDINATION
Ashraf Osman
STAFF STAFF STAFF
MBA, PMP
WEAK MATRIX O R G A N I Z A T I O N
WEAK MATRIX ORGANIZATIONS MAINTAIN MANY OF THE CHARACTERISTICS OF A
FUNCTIONAL ORGANIZATION, AND THE ROLE OF THE PROJECT MANAGER IS MORE OF A
COORDINATOR.
CEO
PROJECT
COORDINATION
STAFF STAFF STAFF
Ashraf Osman
STAFF STAFF STAFF
MBA, PMP
BALANCEDMATRIXO R G A N I Z A T I O N
WEAK MATRIX ORGANIZATIONS MAINTAIN MANY OF THE CHARACTERISTICS OF A
FUNCTIONAL ORGANIZATION, AND THE ROLE OF THE PROJECT MANAGER IS MORE OF A
COORDINATOR.
CEO
PROJECT
COORDINATION
PROJECT
MANAGER STAFF STAFF
Ashraf Osman
STAFF STAFF STAFF
MBA, PMP
STRONGMATRIX ORGANIZATION
PROJECT MANAGERS HAVE MORE AUTHORITY THAN FUNCTIONAL MANAGERS, BUT THE
TEAM STILL REPORTS TO BOTH MANAGERS.
CEO
PROJECT
COORDINATION
STAFF STAFF P.M
Ashraf Osman
STAFF STAFF P.M
MBA, PMP
PROJECTIZED ORGANIZATION
THE PROJECT MANAGER MAKES ALL OF THE DECISIONS ABOUT A PROJECTS BUDGET,
SCHEDULE, QUALITY, AND RESOURCES.
ALL OF THE PROJECT WORK TYPICALLY HAPPENS WITHIN A PARTICULAR DEPARTMENT,
AND THAT DEPARTMENTS MANAGER IS COMPLETELY IN CHARGE OF EVERYTHING.
CEO
PROJECT
COORDINATION
Ashraf Osman
STAFF STAFF STAFF
MBA, PMP
ENTERPRICE
ENVIRONMENTAL FACTORS
ORGANIZATIONAL
PROCESS ASSETS
Ashraf Osman
MBA, PMP
ENTERPRISE ORGANIZATIONAL
ENVIRONMENTAL FACTORS PROCESS ASSETS
(EEF) (OPA)
Ashraf Osman
MBA, PMP
THANK YOU
ADD/FOLLOW ME ON LINKEDIN PROFILE : ASHRAF OSMAN, MBA, PMP
https://www.linkedin.com/in/ashraf-osman-mba-pmp-1a148498/
Facebook page:https://www.facebook.com/pmpheros/?ref=aymt_homepage_panel
Ashraf Osman
MBA, PMP
Ashraf Osman
MBA, PMP
MBA, PMP
A PROCESS IS SET OF
INTERRELATED ACTIVITIES THAT
ARE PERFORMED TO ACHIEVE PRE-
SPECIFIED SET OF PRODUCTS,
SERVICES OR RESULTS.
AASSH
HRRAAFF N
OOSU
MRA, N
P ,MM
PB, A
M, BPAM P
Ashraf Osman
MBA, PMP
AASSH
HRRAAFF N
OOSU
MRA, N
P ,MM
PB, A
M, BPAM P
INITIATION
PROCESS
GROUP
AASSH
HRRAAFF N
OOSU
MRA, N
P ,MM
PB, A
M, BPAM P
1. PROJECT
DEVELOP STATEMENT OF
WORK
PROJECT
CHARTER 2. BUSINESS CASE
4.ORGANIZATIONAL
PROCESS ASSETS
5. ENTERPRISE
ENVIRONMENTAL
FACTORS
Ashraf Osman
MBA, PMP
WE CALL THEM
INPUTS
DEVELOP
PROJECT
CHARTER 1.EXPERT
JUDGMENT
WHAT DO WE DO WITH THESE INPUTS
TO DEVELOP PROJECT CHARTER?
2. FACILITATION
TECHNIQUES
Ashraf Osman
MBA, PMP
WE CALL THEM
TOOLS AND
TECHNIQUES
Ashraf Osman
MBA, PMP
OUTPUTS
PROJECT CHARTER
Ashraf Osman
MBA, PMP
DEVELOP PROJECT
CHARTER
INPUTS, TOOLS & TECHNIQUES & OUTPUTS
MBA, PMP
IDENTIFY
STAKEHOLDERS
INPUTS, TOOLS & TECHNIQUES & OUTPUTS
Two(2) processes
MBA, PMP
YOU!
ASHRAF OSMAN, MBA, PMP
ashrafnur89@gmail.com |053-039-2489 | Riyadh, Saudi Arabia
Linkedin: https://www.linkedin.com/in/ashraf-osman-mba-pmp-1a148498/
Facebook page:https://www.facebook.com/pmpheros/?ref=aymt_homepage_panel
PROJECT
I N T E G R A T I O N
M A N A G E M E N T
A S H R A F O S M A N , M B A , P M P Ashraf Osman
MBA, PMP
THIS KNOWLEDGE AREA IS
ALL ABOUT INTEGRATING
ALL OTHER KNOWLEDGE
AREAS,IT CONSISTS OF: INTEGRATION
DEVELOP PROJECT
CHARTER
DEVELOP PROJECT
MANAGEMENT PLAN (SCOPE+TIME+COST..
+ STAKEHOLDERS)
DIRECT AND MANAGE
PROJECT WORK
PERFORM INTEGRATED
CHANGE CONTROL
MBA, PMP
The process of developing a document
that formally authorizes the existence of
Ashraf Osman
MBA, PMP
DEVELOP PROJECT CHARTER
Ashraf Osman
MBA, PMP
PROJECT
STATEMENT OF BUSINESS CASE AGREEMENTS
WORK
Narrative description of Determines whether or not When a project is being
products, services, or results the project is worth the performed for an external
to be delivered by a project . required investment customer. It also includes
DEVELOP It contains:
CHARTER description
Strategic plan
1.Purpose / Justifications
2. Measurable Project objectives
and success criteria
3. High-level requirements
4. High-level project description
5. High-Level Risks
6. Summary of Milestone
Schedule
1. PROJECT CHARTER
2. OUTPUTS FROM OTHER
PROCESSES
3. EEF
DEVELOP
4. OPA PROJECT MANAGEMENT PLAN
1. EXPERT JUDGEMENT
2. FACILITATION
TECHNIQUES
OUTPUTS
1- PROJECT MANAGEMENT
PLAN
Ashraf Osman
MBA, PMP
PROJECT CHARTER
PLANS
FROM SCOPE TO
STAKEHOLDER
PLAN
3
BASELINES
Ashraf Osman
MBA, PMP
The process of leading
and performing the
work defined in the
project management
DIRECT
plan and implementing AND
approved changes to MANAGE
achieve the projects PROJECT
objectives WORK
Ashraf Osman
MBA, PMP
DIRECT & MANAGE PROJECT WORK
Ashraf Osman
MBA, PMP
DELIVERABLE
ANY OUTPUT PRODUCED: E.G.
PRODUCT, SERVICE, RESULTS,
REPORTS, DOCUMENTS .ETC.
WORK
Outputs PERFORMANCE
DATA
THE RAW OBSERVATIONS AND
MEASUREMENTS IDENTIFIED DURING
ACTIVITIES BEING PERFORMED TO CARRY
OUT THE PROJECT WORK. DATA IS
GATHERED THROUGH WORK EXECUTION
AND PASSED TO THE CONTROLLING
PROCESSES OF EACH PROCESS AREA
FOR FURTHER ANALYSIS. ITS CALLED
STATUS REPORT
MONITOR AND
CONTROL
PROJECT WORK
THE PROCESS OF TRACKING,
REVIEWING, AND REPORTING
PROJECT PROGRESS AGAINST
THE PERFORMANCE OBJECTIVES
DEFINED IN THE PROJECT
MANAGEMENT PLAN.
MBA, PMP
MONITOR AND
CONTROL
PROJECT WORK
IT INCLUDES
1. Comparing actual project
performance against project
plan.
2. Assess and implement
needed corrective / preventive
actions
3. Analyzing and tracking and
monitoring Project risks and
implementing risk responses
accordingly
4. Monitoring Implementation of
approved changes
Ashraf Osman
MBA, PMP
MONITOR AND CONTROL PROJECT WORK
WORK
PERFORMANCE
INFORMATION
information resulted from when
these raw measurement are
analyzed
WORK
PERFORMANCE
REPORTS
Is the summation of WPI in physical
or electronic form
PERFORM INTEGRATED CHANGE CONTROL
03 Reviewing 04 Managing
and approved
PERFORM
approving changes
INTEGRATED change
CHANGE requests
CONTROL
Ashraf Osman
MBA, PMP
PERFORM
INTEGRATED
CHANGE
CONTROL
Ashraf Osman
MBA, PMP
INPUTS Close
1. Project Management Plan
2. Accepted Deliverables Project or
Phase
3. OPA
MBA, PMP
PMP PREPARATION COURSE
THANK YOU.
I hope you enjoyed
my presentation.
Linkedin: https://www.linkedin.com/in/ashraf-osman-mba-pmp-1a148498/
Facebook page:https://www.facebook.com/pmpheros/?ref=aymt_homepage_panel
MBA, PMP
OVERVIEW
Plan out all of the Find out all of the Detailed description
work youll do to stakeholders needs of the work that will
define your scope, and write them down be done and
make sure the team is so that you know produced.
planning to do the what to build and
right work, and your requirements
control it. can be measured and
tracked.
Ashraf Osman
MBA, PMP
PLAN SCOPE
MANAGEMENT
THE PROCESS OF
CREATING A SCOPE
MANAGEMENT PLAN
THAT DOCUMENTS HOW
THE PROJECT SCOPE
WILL BE DEFINED,
VALIDATED, AND
CONTROLLED.
IT FIGURES OUT WHAT
WORK YOULL DO AND
WHATS OUT OF SCOPE.
Ashraf Osman
MBA, PMP
1. Project management plan
Ashraf Osman
MBA, PMP
COLLECT REQUIREMENTS
The process of determining, documenting, and
managing stakeholder needs and requirements
to meet project objectives.
By sitting down with all of the stakeholders for
your project and working out what their needs
are, and thats what you do in the Collect
Requirements process
Ashraf Osman
MBA, PMP
COLLECT REQUIREMENTS
TOOLS
INPUTS & OUTPUTS
TECHNIQUES
8. Prototypes
9. Benchmarking
Ashraf Osman 10.Context diagrams
MBA, PMP 11. Document analysis
INPUTS (EXPLANATIONS)
GROUP GROUP
03 DECISION- 04 CREATIVITY
MAKING TECHNIQUES
1.Unanimity 1. Brainstorming.
2. Majority 2. Nominal group technique.
3. Plurality 3. Idea/mind mapping.
4. Dictatorship 4. Affinity diagram.
05 PROTOTYPES 06 BENCHMARKING
07 FACILITATED
WORKSHOPS 08 CONTEXT
DIAGRAMS
Bring together stakeholders with It shows the boundaries of the
different perspectives to talk product scope by highlighting
about the product the product and its interfaces
with people, processes, or
systems
OUTPUTS
1.REQUIREMENTS 2.REQUIREMENTS
DOCUMENTATION TRACEABILITY MATRIX
Ashraf Osman
MBA, PMP
INPUTS
1. Scope management plan
DEFINE
2. Project charter
3. Requirements documentation
4. Organizational process assets
SCOPE
TOOLS & TECH The process of developing a
1. Expert judgment detailed description of the project
2. Product analysis and product.
( turning the requirement into
product and then analyze it ) it describes the project, service, or
3. Alternatives generation result boundaries by defining which
4. Facilitated workshops of the requirements collected will be
included in and excluded from the
OUTPUTS project scope.
1. Project Scope Statement
2. Project Document Updates
Ashraf Osman
MBA, PMP
PROJECT SCOPE
STATEMENT
(OUTPUT)
Project Scope Statement defines
what work will be performed and
what work is excluded.
Ashraf Osman
MBA, PMP
EXAMPLE WBS BUILDING
Ashraf Osman
MBA, PMP
CREATE WBS is very important as it is an
input to FIVE core processes
WBS
COST ACTIVITY
ESTIMATING DEFINITION
RESOURCE
PLANNING
COST RISK
BUDGETING PLANNING
INPUTS TOOLS & OUTPUTS
TECHS
1. Scope 1. Decomposition 1. Scope Baseline
management plan 2. Expert judgement 2. Project documents
2. Project scope updates
statement
3. Requirements
documentation
4. EEF
5. OPA
CREATE WBS
SCOPE BASELINE
WBS
(OUTPUTS) Deliverable-oriented
breakdown of a project into
smaller components
Ashraf Osman
MBA, PMP
VALIDATE
SCOPE
VALIDATE SCOPE IS THE
PROCESS OF THE
CUSTOMER ACCEPTING
THE PROJECT
DELIVERABLES.
Ashraf Osman
MBA, PMP
THANK YOU
NEXT CHAPTER: PROJECT SCHEDULE MANAGEMENT
Linkedin: https://www.linkedin.com/in/ashraf-osman-mba-pmp-1a148498/
Facebook page:https://www.facebook.com/pmpheros/?ref=aymt_homepage_panel
Ashraf Osman
MBA, PMP
PROJECT TIME
MANAGEMENT
PMP Preparation Course
ASHRAF OSMAN, MBA, PMP
Ashraf Osman
MBA, PMP
PLAN
SCHEDULE
MANAGEMENT
The process of establishing the policies,
procedures, and documentation for
planning, developing, managing, executing,
and controlling the project schedule
Ashraf Osman
MBA, PMP
1. PROJECT
PLAN MANAGEMENT PLAN
2. PROJECT CHARTER
SCHEDULE 3. EEF
MANAGEMENT 4. OPA
1. EXPERT
JUDGEMENT
INPUTS, TOOLS AND 2. ANALYTICAL
TECHNIQUES & OUTPUTS TECHNIQUES
3. MEETINGS
1. SCHEDULE
MANAGEMENT
PLAN
01 02
SCHEDULE MANAGEMENT PLAN
Project schedule model
Level of accuracy (+/- %)
development (software)
CONTENTS
03
Units of measure
04
Project schedule model
maintenance (update)
05
Control thresholds
06
Performance
Measurement(EVM)
DEFINE
ACTIVITIES
THE PROCESS OF IDENTIFYING
AND DOCUMENTING THE
SPECIFIC ACTIONS TO BE
PERFORMED TO PRODUCE Define Activities will decompose
THE PROJECT DELIVERABLES. the work package into smaller
components, are called schedule
activities.
CREAT WBS
WORK
PACKAGE
DEFINE ACTIVITIES
ACTIVITY
Ashraf Osman
MBA, PMP
1. SCHEDULE
DEFINE MANAGEMENT PLAN
2. SCOPE BASELINE
ACTIVITIES 3. EEF
4. OPA
1. DECOMPOSITION
INPUTS, TOOLS AND 2. ROLLING WAVE
TECHNIQUES & OUTPUTS PLANNING
3. EXPERT JUDGMENT
1. ACTIVITY LIST
2. ACTIVITY
ATTRIBUTES
3. MILESTONE LIST
TOOLS & TECHNIQUES
Ashraf Osman
MBA, PMP
DEFINE ACTIVITIES
OUTPUTS
Ashraf Osman
MBA, PMP
The process of
TOOLS &
identifying and INPUTS TECHNIQUES OUTPUTS
documenting 1. SCHEDULE 1. PRECEDENCE 1. PROJECT
relationships MANAGEMENT DIAGRAMMING SCHEDULE
among the PLAN METHOD (PDM) NETWORK
2. ACTIVITY LIST 2. DEPENDENCY DIAGRAMS
project activities DETERMINATION
3. ACTIVITY 2. PROJECT
3. LEADS AND
ATTRIBUTES DOCUMENTS
LAGS
4. MILESTONE UPDATE
LIST
5. PROJECT
SCOPE
SEQUENCE STATEMENT
ACTIVITIES 6. EEF
7. OPA
PDM
PRECEDENCE DIAGRAMS USE OR RECTANGLES TO REPRESENT
THE ACTIVITIES, WHICH ARE CALLED NODES.
THE NODES ARE CONNECTED WITH ARROWS SHOWING THE
DEPENDENCIES BETWEEN ACTIVITIES.
THIS METHOD IS ALSO CALLED ACTIVITY ON NODE (AON).
FINISH TO START START TO START
PDM
01 1. Most frequently used 02 1. The independent
2. Describes that the activity must start before
independent activity must the dependent activity can
finish before the start.
The precedence dependent activity can 2. B doesn't start before A
start Starts
diagramming 3. B doesn't start before A e.g. Project work started
method has four is finished (SS) Project Management
e.g. foundation -concrete activities started
logical
relationships/ FINISH TO FINISH START TO FINISH
dependencies 1. The independent activity 1. The independent activity
03 04
must finish before the must start before the
dependent activity finishes dependent activity can
2. B doesn't finish before finish
A is finished 2. This logical relationship
e.g. Last chapter written is seldom used
(FF) Entire book completed B doesn't finish before A
starts
e.g. shifts
DEPENDENCY DETERMINATION
ALSO 4 DEPENDENCIES
ACTIVITY A ACTIVITY A
LEAD LAG
ACTIVITY B ACTIVITY B
Lead Lag
Speed up the successor Delay successor
activities and require activities and require
time to be subtracted time added either to
from the start date or the start date or to the
the finish date of the finish date of the
activity scheduled activity scheduled
ESTIMATE
ACTIVITY
RESOURCES
The process of estimating the type and
quantities of material, human resources,
equipment, or supplies required to perform
each activity for accurate duration and cost
estimation.
Ashraf Osman
MBA, PMP
ESTIMATE ACTIVITY
RESOURCES
Manpower
Machineries
We call it
the "4 M" Material
Money
Ashraf Osman
MBA, PMP
1. SCHEDULE MANAGEMENT
PLAN
2. ACTIVITY LIST
3. ACTIVITY ATTRIBUTES
ESTIMATE 4. RESOURCE CALENDARS
5. RISK REGISTER
ACTIVITY 6. ACTIVITY COST ESTIMATES
7. EEF
RESOURCES 8. OPA
1. EXPERT JUDGMENT
2. ALTERNATIVE ANALYSIS
INPUTS, TOOLS AND 3. PUBLISHED ESTIMATING
DATA
TECHNIQUES & OUTPUTS 4. BOTTOM-UP ESTIMATING
5. PROJECT MANAGEMENT
SOFTWARE
1. ACTIVITY RESOURCE
REQUIREMENTS
2. RESOURCE BREAKDOWN
STRUCTURE
3. PROJECT DOCUMENTS
UPDATES
INPUTS
RISK REGISTER
RESOURCE CALENDAR
PROJECT
ALTERNATIVE BOTTOM-UP PUBLISHED
MANAGEMENT
ANALYSIS ESTIMATING ESTIMATING DATA
SOFTWARE
Different way or Further Decomposition Primavera, MS They rely on articles,
resources to do of activity to estimate project ...etc books, journals, and
the work. the resources & cost. periodicals that collect,
e.g Brick Or Wood? e.g Painting activity = analyze, and publish
Hand Or Automated? labour + ladder + data from other
painting bucket peoples projects.
ACTIVITY RESOURCE
OUTPUTS
REQUIREMENTS
Types and quantities of
resources required for each
activity in a work package
RESOURCE BREAKDOWN
STRUCTURE (RBS)
The resource breakdown
structure is a hierarchical
representation of resources
by category and type
PROJECT DOCUMENTS
UPDATES
Like activity list, activity
attributes, risk register,
activity cost
Ashraf Osman
estimates...etc
MBA, PMP
ESTIMATE
ACTIVITY
DURATIONS
The process of estimating the number of
work periods needed to complete individual
activities with estimated resources.
Ashraf Osman
MBA, PMP
.1 SCHEDULE MANAGEMENT PLAN
.2 ACTIVITY LIST
.3 ACTIVITY ATTRIBUTES
.4 ACTIVITY RESOURCE
ESTIMATE
ESTIMATE
REQUIREMENT
.5 RESOURCE CALENDARS
.6 PROJECT SCOPE STATEMENT
ACTIVITY
ACTIVITY .7 RISK REGISTER
.8 RESOURCE BREAKDOWN
DURATIONS
STRUCTURE
DURATIONS .9 EEF .10 OPA
.1 EXPERT JUDGMENT
.2 ANALOGOUS ESTIMATING
3 PARAMETRIC ESTIMATING
INPUTS, TOOLS AND 4 THREE-POINT ESTIMATING
TECHNIQUES & OUTPUTS 5 GROUP DECISION-MAKING
TECHNIQUES
.6 RESERVE ANALYSIS
ESTIMATE
ESTIMATING Is used to estimate total project duration
Useful in the early stages of project
DURATIONS
parameters.
PARAMETRIC
Parametric estimating uses a statistical
ESTIMATING
relationship between historical data
and other variables
Ashraf Osman
MBA, PMP
.1 SCHEDULE MANAGEMENT PLAN
.2 ACTIVITY LIST
.3 ACTIVITY ATTRIBUTES
.4 PROJECT SCHEDULE NETWORK
ESTIMATE
DIAGRAMS
DEVELOP
.5 ACTIVITY RESOURCE REQUIREMENTS
.6 RESOURCE CALENDARS
.7 ACTIVITY DURATION ESTIMATES
ACTIVITY
SCHEDULE
.8 PROJECT SCOPE STATEMENT
.9 RISK REGISTER
.10 PROJECT STAFF ASSIGNMENTS
DURATIONS
.11 RESOURCE BREAKDOWN STRUCTURE
.12 EEF .13 OPA
.1 SCHEDULE BASELINE
.2 PROJECT SCHEDULE
.3 SCHEDULE DATA
.4 PROJECT CALENDARS
.5 PROJECT MANAGEMENT PLAN
UPDATES
.6 PROJECT DOCUMENTS UPDATES
CRITICAL PATH METHOD (CPM)
Longest Duration Path (not longest path) through the network diagram
Near critical path : close in duration to critical path. sometimes the near CP
can be the CP which will increase the risk.
Total Float (Slack) :amount of time that an activity can be delayed without
delaying the project finish date
Ashraf Osman
MBA, PMP
RESOURCE LEVELING
IS A METHOD TO FLATTEN THE
RESOURCE SCHEDULE WHEN RESOURCES ARE
OVER-ALLOCATED
OPTIMIZATION
TECHNIQUES IT WILL LENGTHEN THE SCHEDULE
RESOURCE SMOOTHING
A TECHNIQUE THAT ADJUSTS THE
ACTIVITIES OF A SCHEDULE MODEL
SUCH THAT THE REQUIREMENTS FOR
RESOURCES ON THE PROJECT DO
NOT EXCEED CERTAIN PREDEFINED
RESOURCE LIMITS.
Ashraf Osman
IT WILL NOT AFFECT THE SCHEDULE
MBA, PMP
MODELING
TECHNIQUES
Simulation allow project managers
to examine the feasibility of the
project schedule under different
conditions, variables and events
(Monte Carol analysis)
MBA, PMP
SCHEDULE COMPRESSION
The approach is to add more The activities that would normally
resources to activities on the critical done in sequence, are allowed to be
path to complete the project earlier done in parallel or with some overlap
CRASHING
FAST TRACKING
CONTROL
SCHEDULE
The process of monitoring the status of
project activities to update project progress
and manage changes to the schedule
baseline to achieve the plan
Ashraf Osman
MBA, PMP
1. PROJECT MANAGEMENT PLAN
ESTIMATE
2. PROJECT SCHEDULE
ACTIVITY
SCHEDULE
5. SCHEDULE DATA
6. OPA
1.WORK PERFORMANCE
INFORMATION
2. SCHEDULE FORECASTS
3. CHANGE REQUESTS
4. PROJECT MANAGEMENT PLAN
UPDATES
5. PROJECT DOCUMENTS UPDATES
6. OPA UPDATES
THANK
YOU
ASHRAF OSMAN, MBA, PMP
Linkedin: https://www.linkedin.com/in/ashraf-osman-mba-pmp-1a148498/
Facebook https://www.facebook.com/pmpheros/?ref=aymt_homepage_panel
Page:
Ashraf Osman
MBA, PMP
PROJECT COST
management
PMP PREPARATION COURSE
Cost of using,
Cost of maintaining
Cost of supporting the product,
service or result
MBA, PMP
Project 1 Project 2
Life cycle
3000 3500
cost
PLAN COST MANAGEMENT
The process that establishes the policies, procedures, and
documentation for planning, managing, expending, and controlling
project costs.
TOOLS
INPUTS TECHNIQUES
OUTPUTS
01 Level of accuracy
02 Units of measure
06 Funding Decisions
07 Reporting formats
Ashraf Osman
MBA, PMP
ESTIMATE COSTS
ESTIMATE COSTS IS THE PROCESS OF CALCULATING
THE COSTS OF THE IDENTIFIED RESOURCES NEEDED TO
COMPLETE THE PROJECT WORK.
INPUTS
3. Scope baseline
4. Project schedule
5. Risk register
6. EEF
7. OPA
1. Expert judgment
2. Analogous estimating
3. Parametric estimating
TOOLS & 4. Bottom-up estimating
5. Three-point estimating
6. Reserve analysis
TECHNIQUES 7. Cost of quality
8. Project management software
9. Vendor bid analysis
10.Group decision-making techniques
ESTIMATE COSTS
Ashraf Osman
MBA, PMP
DETERMINE BUDGET
The process of aggregating the estimated costs of
individual activities or work packages to establish an
authorized cost baseline
TOOLS
INPUTS TECHNIQUES OUTPUTS
MBA, PMP
CONTROL COSTS
THE PROCESS OF MONITORING THE STATUS OF THE
PROJECT TO UPDATE THE PROJECT COSTS AND
MANAGING CHANGES TO THE COST BASELINE
1. Project management plan
2. Project funding requirements
TECHNIQUES
4. Performance reviews
5. Project management software
6. Reserve analysis
OUTPUTS
3. Change requests
4. Project management plan updates
5. Project documents updates
6. OPA updates
CONTROL COSTS
EARNED VALUE
ANALYSIS
The rabbit wouldn't have
lost the race if someone
informed about its
performance time to time
EARNED VALUE Schedule Performance
ANALYSIS
METHODOLOGY
TO TRACK:
Cost Performance
Ashraf Osman
MBA, PMP
BENEFITS OF EVA
Reliable project costs and
schedule data for more
effective decision-making
Early identification of potential
problems
Accurate prediction of project
costs at completion
What did we get for money
spent
How much will the project cost
to complete
When will the project be
complete
EARNED VALUE ANALYSIS
PV BAC
PLANNED BUDGET AT
VALUE COMPLETION
PV tells you what you plan to do BAC is the sum of all budgets
allocated to a project
EV AC
EARNED ACTUAL
VALUE COST
EV is the quantification of the the cost incurred for executing
worth of the work done work on a project
SCHEDULE COST
VARIANCE (SV) VARIANCE (CV)
SPI = EV/PV
CPI = EV/AC
EAC= AC + BAC - EV
(CPI x SPI)
ETC From now on, how much MORE
(ESTIMATE TO money will it take to finish the
COMPLETE) project?
SUMMARY
Estimate At Completion (EAC) Ashraf Osman
MBA, PMP
What do we currently expect the
TOTAL project (at completion) to cost ?
SUMMARY
YOU HAVE A PROJECT TO BUILD A NEW FENCE. THE FENCE IS FOUR SIDED.
EACH SIDE IS TO TAKE ONE DAY TO BUILD AND IS BUDGETED FOR $1,000
PER SIDE.
THE SIDES ARE PLANNED TO BE COMPLETED ONE AFTER THE OTHER.
TODAY IS THE END OF DAY THREE.
CALCULATE
PV
ACTIVITY STAUTS
EV
AC
SIDE 1 Complete, spent $1,000
BAC
CV
SIDE 2 Complete, spent $1,200
CPI
SV
SIDE 3 50% done, spent $600
SPI
EAC
SIDE 4 Not yet started ETC
VAC
ANSWERS Ashraf Osman
MBA, PMP
PV = 1,000 + 1,000 + 1,000= 3,000 WE SHOULD HAVE DONE $3,000 WORTH OF WORK.
EV = 1,000 + 1,000 + (50% X 1000) = 2500 WE HAVE ACTUALLY COMPLETED $2,500 WORTH OF WORK
BAC = 1,000 + 1,000 + 1,000 + 1,000= 4000 OUR PROJECT BUDGET IS $4,000.
CPI = 2,500 / 2,800 = 0.893 WE ARE ONLY GETTING 89 CENTS OUT OF EVERY DOLLAR WE PUT INTO THE PROJECT.
SPI = 2,500 / 3,000 = 0.833 WE ARE ONLY PROGRESSING AT 83% OF THE RATE PLANNED
EAC = 4,000 / .893 = 4479 WE CURRENTLY ESTIMATE THAT THE TOTAL PROJECT WILL COST $4,479
ETC = 4.479 2,800 = 1679 WE NEED TO SPEND $1,679 TO FINISH THE PROJECT
VAC = 4,000 4,479 = -479 WE CURRENTLY EXPECT TO BE $479 OVER BUDGET WHEN THE PROJECT IS COMPETED.
Ashraf Osman
MBA, PMP
THANK YOU
Linkedin: https://www.linkedin.com/in/ashraf-osman-mba-pmp-1a148498/
Facebook https://www.facebook.com/pmpheros/?ref=aymt_homepage_panel
Page:
Ashraf Osman
MBA, PMP
PROJECT QUALITY
MANAGEMENT
PMP PREPARATION COURSE
CONTROL QUALITY
Look at each deliverable and inspect it for defects.
Customer satisfaction
Prevention of defects and reworks
Everyone's responsibility
Continuous improvement (Plan
Do Check Act)
Is a quality management
approach
Mostly used in manufacturing
and services industries
Is focuses on process
improvement and variation
reduction by applying Six
Sigma methodologies SIX SIGMA
A quality philosophy of
applying continuous
small improvements
toreduce costs and
ensure consistency.
KAIZEN TECHNOLOGY
QUALITY VS
QUALITY
GRADE
Ashraf Osman
MBA, PMP
STEAK FOOL
The steak is a high-grade meal The fool is a law-grade meal
But if the steak didn't meet the expectation and the fool did,
then the steak is a low quality while the fool is a high quality
MBA, PMP
QUALITY PIONEERS
MBA, PMP
SEVEN BASIC
QUALITY TOOLS
(7QC TOOLS)
Ashraf Osman
MBA, PMP
SEVEN BASIC
QUALITY TOOLS
(7QC TOOLS)
CHECK SHEETS
They are especially useful for
gathering attributes data while
performing inspections to identify
defects.
For example, data about the
frequencies or consequences of
defects collected in checksheets are
often displayed using Pareto diagrams.
MBA, PMP
SEVEN BASIC
QUALITY TOOLS
(7QC TOOLS)
FLOW CHART
A flowchart is a type of diagram that
represents an algorithm, workflow or
process, showing the steps as boxes of
various kinds, and their order by
connecting them with arrows. This
diagrammatic representation
illustrates a solution model to a given
problem.
MBA, PMP
SEVEN BASIC
QUALITY TOOLS
(7QC TOOLS)
CONTROL CHART
Used to objectively define a process and variation
Process containing only common causes of
variation is considered stable, implying that the
variation is predictable within the established
control limits
Processes containing special as well as common
causes of variation are considered unstable. In
such cases the special causes fall outside the
established control limits
Control charts can be plotted for tracking
Production failures, defects by
schedule/effort/cost and variances
By: AshrafOsman,MBA, PMP
Ashraf Osman
MBA, PMP
SEVEN BASIC
QUALITY TOOLS
(7QC TOOLS)
MBA, PMP
SEVEN BASIC
QUALITY TOOLS
(7QC TOOLS)
HISTOGRAM
Also called (Frequency Distribution Chart)
A bar graph that groups the data by
predetermined intervals to show the frequency of
the data set
Used to measure and analyze the data and
identify Defect Classification, Delivery Times,
Survey Findings
MBA, PMP
SEVEN BASIC
QUALITY TOOLS
(7QC TOOLS)
PARETO CHART
Also called (80 20 rule)
Provides the ability to Categorize
Items, usually by content (type of
defect, position, process, time, etc.)
Identify the causes or characteristics
that contribute most to a problem
Decide which basic causes of a problem
to work on first
Sort the data in descending order by
occurrence/frequency of
cause/characteristics.
MBA, PMP
SEVEN BASIC
QUALITY TOOLS
(7QC TOOLS)
SCATTER DIAGRAM
It is used for problem-solving and
understanding cause and effect
relationships
It shows if a relation exists between
Two variables
Types of Correlations
Positive correlation
Negative correlation
No correlation
FLOW CHART
CONTROL CHART
SEVEN
BASIC HISTOGRAM
QUALITY
TOOLS PARETO CHART
SCATTER DIAGRAM
MBA, PMP
Plan Quality Management (T&T)
Benchmarking Design of Experiments Cost of Quality
Describes how the Analyzing the process that How the product is doing
organizations quality policies make the project & product before issuing change request
will be implemented. It contains: scope and improve them e.g variance in height, number
1-Standard of bugs, number of
2-Roles& Responsibility crashes...etc
3-Reports
4-Metrics
5-The deliverable that will be
tested
QA QC
Makes Sure that we are Makes Sure that results
doing the right thing in of what weve done are
the right way what we are expected
MBA, PMP
https://www.facebook.com/pmpheros/?ref=aymt_homepage_panel
Ashraf Osman
MBA, PMP
In the Plan Human Resource Management
process, you plan out exactly which resources
youll need, what their roles and
responsibilities are, and how youll train your
team and make sure they stay motivated.
Plan Human Resource Management
1 plan out the staffing needs for your project,
and how youll manage and reward the team
Acquire Project Team
2 put together your team. This means you
may need to negotiate for some of the
resources.
Develop Project Team
3 Forming the team and train them
The process of
identifying and
TOOLS & TECHNIQUES
documenting project
1. Organization charts and position descriptions
roles, responsibilities,
2. Networking
required skills, 3. Organizational theory
reporting 4. Expert judgment
relationships, and 5. Meetings
creating a staffing
OUTPUTS
management plan
1. Human resource management plan
Project organization chart includes people or
relationships that may not necessarily show
up on a company organization chart. If youve
got a team built from multiple consultants
and subcontractors, this chart will be the only
place where everyone is listed at once.
A- Responsibility
Assignment Matrix - RAM
(who will do what?)
B- RACI Matrix
(Responsible -
Accountable - Consult -
Inform)
3- TEXT ORIENTED FORMAT
ORGANIZATIONS CHARTS
ORGANIZATION
THEORIES
Ashraf Osman
MBA, PMP
MASLOWS HIERARCHY OF NEEDS
ORGANIZATION THEORIES
HERZBERGS THEORY OF MOTIVATION
ORGANIZATION THEORIES
THEORY X & THEORY Y
ORGANIZATION THEORIES
EXPECTANCY THEORY
ORGANIZATION THEORIES
MANAGEMENT STYLES
AUTOCRATIC
The Project manager makes all the decisions
DEMOCRATIC
The Project Team is involved in the decision
making process
LAISSEZ FAIRE
The Project Manager leaves everything on the
team. The team is self-led
EXCEPTIONAL
The Project Manager only pays attention to the
top 10% of the performers and bottom 10% of
the performers
OUTPUTS: HUMAN RESOURCE MANAGEMENT PLAN
Staff Acquisition
Timetable
Release Criteria
Training Needs
Recognition and Rewards
Compliance
Safety
Ashraf Osman
MBA, PMP
ACQUIRE
PROJECT INPUTS
OUTPUTS
MBA, PMP
DEVELOP
PROJECT INPUTS
The process of
improving
TOOLS & TECHNIQUES
competencies, team
1. Interpersonal skills
member interaction,
2. Training 3. Team-building activities
and overall team 4. Ground rules 5. Colocation
environment to 6. Recognition and rewards
enhance project 7. Personnel assessment tools
performance
OUTPUTS
MBA, PMP
TYPES OF PROJECT
MANAGER POWER
EXPERT
The authority of the project manager comes from
experience with the technology of the application area
REWARD POWER
The project manager has the authority to reward
the project team
optimize project
OUTPUTS
performance
1. Change requests
2. Project management plan updates
3. Project documents updates
4. Enterprise environmental factors updates
Ashraf Osman
5. Organizational process assets updates
MBA, PMP
CONFLICT
RESOLUTION
Ashraf Osman
Ashraf Osman
MBA, PMP
CONFLICT RESOLUTION TECHNIQUES
consensus argument
Lose-lose solution
Used to avoid fight
CONFRONTING
/PROBLEM COLLABORATING COMPROMISING
SOLVING
CONFLICT RESOLUTION TECHNIQUES
https://www.linkedin.com/in/ashraf-osman-mba-pmp-1a148498/
https://www.facebook.com/pmpheros/?ref=aymt_homepage_panel
Ashraf Osman
MBA, PMP
PMP PREPARATION COURSE
PROJECT
COMMUNICATIONS
MANAGEMENT
ASHRAF OSMAN, MBA, PMP
Ashraf Osman
MBA, PMP
PROJECT COMMUNICATION MANAGEMENT
Ashraf Osman
MBA, PMP
APPETIZERS
PLAN
MANAGE CONTROL
COMMUNICATIONS
COMMUNICATIONS COMMUNICATIONS
MANAGEMENT
COMMUNICATION
CAN BE:
Other project Other
PROJECT
managers projects
Internal, external,
vertical & Horizontal.
Project
management
team
Ashraf Osman
MBA, PMP
/ NORTH HAMPSHIRE
FORMAL WRITTEN
PROJECT CHARTER,
PLAN,
LONG DISTANCE
COMMUNICATION
FORMAL VERBAL
PRESENTATION ,
SPEECHES
PLAN 1. PROJECT MANAGEMENT
PLAN
COMMUNICATION 2. STAKEHOLDER REGISTER
3. EEF
MANAGEMENT 4. OPA
1.COMMUNICATION
REQUIREMENTS ANALYSIS
THE PROCESS OF DEVELOPING AN 2. COMMUNICATION
TECHNOLOGY
APPROPRIATE APPROACH AND PLAN 3. COMMUNICATION
FOR PROJECT COMMUNICATIONS MODELS
BASED ON STAKEHOLDERS 4. COMMUNICATION
INFORMATION NEEDS AND METHODS
5. MEETINGS
REQUIREMENTS, AND AVAILABLE
ORGANIZATIONAL ASSETS
1.COMMUNICATION
MANAGEMENT PLAN
2. PROJECT DOCUMENT
UPDATES
Ashraf Osman
MBA, PMP
PLAN COMMUNICATION MANAGEMENT (T&T)
SENDER RECIEVER
MESSAGE
ENCODE DECODE
NOISE
MEDIUM
NOISE
DECODE ENCODE
FEEDBACK-MESSAGE
COMMUNICATION MANAGEMENT PLAN (OUTPUT)
PROJECT
STAKEHOLDER
MANAGEMENT
Ashraf Osman
MBA, PMP
OVERVEIW
Project Stakeholder Management includes
the processes required to identify the
people, groups, or organizations that could
impact/impacted by the project, to analyze
their expectations /impact on the project,
and to develop strategies for effectively
engaging stakeholders in project decisions
and execution. Stakeholder management
also focuses on continuous communication
with stakeholders.
IDENTIFY STAKEHOLDERS PLAN STAKEHOLDER
MANAGEMENT
Interest
ASSESSMENT INFORMATION
Major requirements, main
02 expectations, potential influence in
the project, phase in the life cycle
with the most interest
SUPPORTIVE LEADING
04 05
CONTENTS
https://www.linkedin.com/in/ashraf-osman-mba-pmp-1a148498/
https://www.facebook.com/pmpheros/?ref=aymt_homepage_panel
Ashraf Osman
MBA, PMP
PMP PREPARATION COURSE
PROJECT RISK
MANAGEMENT
PERFORM
PLAN RISK IDENTIFY
QUALITATIVE
MANAGEMENT RISKS
RISK ANALYSIS
PERFORM
PLAN RISK CONTROL RISKS
QUANTITATIVE
RESPONSES
RISK ANALYSIS
Risk is uncertainty
Ashraf Osman
MBA, PMP
INPUTS
.1 Project management plan
PLAN RISK .2 Project charter
.3 Stakeholder register
MANAGEMENT .4 EEF .5 OPA
Ashraf Osman
MBA, PMP
RISK MANAGEMENT PLAN
CONTENTS
METHODOLOGY
METHODOLOGY
ROLES & RESPONSIBILITY
METHODOLOGY
BUDGETING
METHODOLOGY
TIMING
RISK CATEGORIES
RISK MANAGEMENT PLAN
CONTENTS
DEFINITIONS OF RISK
PROBABILITY & IMPACT
STAKEHOLDERS
METHODOLOGY
TOLERANCES
METHODOLOGY
REPORTING FORMATS
TRACKING
Ashraf Osman
MBA, PMP
PROBABILITY
IMPACT
TOOLS &
INPUTS OUTPUTS
TECHS
.1 Risk management plan .1 Documentation reviews .1 Risk register
.2 Cost management plan .2 Information gathering
.3 Schedule management plan techniques
.4 Quality management plan .3 Checklist analysis
.5 HR management plan .4 Assumptions analysis
.6 Scope baseline .5 Diagramming techniques
.7 Activity cost estimates .6 SWOT analysis
.8 Activity duration estimates .7 Expert judgment
.9 Stakeholder register
.10 Project documents
.11 Procurement documents
.12 EEF .13 OPA
PERFORM
QUALITATIVE
RISK ANALYSIS
Ashraf Osman
MBA, PMP
PERFORM
QUALITATIVE
RISK ANALYSIS
MBA, PMP
PROBABILITY & IMPACT ASSESSMENT/
PROBABILITY AND IMPACT MATRIX
FIRST, WE ASSESS
THEN WE RANK
THE RISKS AS
THE RISK USE
FOLLOWS:
THE MATRIX
PROJECT DOCUMENTS UPDATES(OUTPUTS)
Assumptions log updates
Ashraf Osman
MBA, PMP
PERFORM QUANTITATIVE RISK ANALYSIS
INPUTS
3. Schedule mgmt plan
4. Risk register
5. EEF
6. OPA
TECHNIQUES
2. Quantitative Risk Analysis & Modeling
techniques
3. Expert Judgment
AVIOD MITIGATE
TRANSFER ACCEPT
PLAN RISK RESPONSES (T&T)
STRATEGIES FOR NEGATIVE RISKS OR THREATS
EXPLOIT ENHANCE
SHARE ACCEPT
PLAN RISK RESPONSES (T&T)
STRATEGIES FOR POSITIVE RISKS OR OPPORTUNITIES
1- Active acceptance:
may involve the creation of
contingency plans to be
implemented if the risk occurs
2- Passive acceptance:
leaves actions to be
determined when risk occured
(workarounds)
CONTINGENT RESPONSE STRATEGIES (T&T)
Some responses are designed for use only if certain events occur. For some
risks, it is appropriate for the project team to make a response plan that will
Contingency Plan: Fire fighting system will operate when the there is a fire.
RISKS
The process of implementing risk response
plans, tracking identified risks, monitoring
residual risks, identifying new risks, and
evaluating risk process effectiveness
throughout the project
CONTROL RISKS
.1 Risk reassessment
TOOLS &
.2 Risk audits
.3 Variance and trend analysis
TECHNIQUES
.4 Technical performance measurement
.5 Reserve analysis
.6 Meetings
OUTPUTS
.2 Change requests
.3 Project management plan updates
.4 Project documents updates
.5 Organizational process assets updates
PMP PREPARATION COURSE
THANK
YOU!
https://www.linkedin.com/in/ashraf-
ASHRAFOSMAN, MBA, PMP
osman-mba-pmp-1a148498/
PROJECTPROCUREMENTS
MANAGEMENT
Ashraf Osman
MBA, PMP
OVERVIEW
2. CONDUCT PROCUREMENTS
DECIDE ON THE SELLER(S) YOU ARE GOING TO WORK WITH,
FINALIZE & SIGN THE CONTRACT
3. CONTROL PROCUREMENTS
MAKE SURE YOUR COMPANY IS GETTING WHAT YOU PAID FOR,
MAKING CHANGES TO THE CONTRACT, AND CORRECTING ANY
PROBLEMS WITH THE SELLERS WORK.
4. CLOSE PROCUREMENTS
Ashraf Osman CONFIRM THAT THE WORK WAS DONE RIGHT AND THAT ALL
T W
The process of documenting project A H
H ET
procurement decisions, specifying the W H
approach, and identifying potential
ER
sellers.
O H
TO ACQUIRE?
W
It determines whether to acquire
N E
M
outside support and if so, what to
H
U
W
acquire, how to acquire it, how much is
HC
needed, and when to acquire it.
HOW
1. PROJECT MANAGEMENT PLAN
2. REQUIREMENTS DOCUMENTATION
3. RISK REGISTER
1. MAKE-OR-BUY ANALYSIS
TECHS
3. MARKET RESEARCH
4. MEETINGS
Factor to consider:
- Availability
- Cost
- Skills
4. STANDARDIZED PROCUREMENT
DOCUMENTS, FORMS AND CONTRACTS
FIXED PRICE
Used in construction rather than IT
CONTRACTS
the buyer has the least cost risk in
this type of contract because the
seller will bear the additional costs
3 TYPES
MBA, PMP
COST
REIMBURSABLE
CONTRACTS
ITS A COMBINATION OF
FIXED PRICE AND COST
REIMBURSABLE
CONTRACTS
IT IS AWARDED WHEN
THE TOTAL AMOUNT OF
THE MATERIAL COST IS
NOT KNOWN AT THE
TIME OF CONTRACT.
CAN GROW IN
CONTRACT VALUE
MEDIUM RISK
CONDUCT
PROCUREMENTS
Ashraf Osman
MBA, PMP
CONDUCT PROCUREMENTS
Ashraf Osman
MBA, PMP
INPUTS
1. Project management plan
2. Procurement documents
CONTROL
3. Agreements
4. Approved change requests
OUTPUTS
it ensures that both the sellers
1. Work performance information
and buyers performance meets 2. Change requests
procurement requirements 3. Project management plan updates
according to the terms of the 4. Project documents updates
legal agreement 5. OPA updates
INPUTS
1. PROJECT MANAGEMENT PLAN
2. PROCUREMENT DOCUMENTS CLOSE
PROCUREMENTS
MBA, PMP