The Four FIDIC 1999 Contract Condition
The Four FIDIC 1999 Contract Condition
The Four FIDIC 1999 Contract Condition
Peter L Booen
FIDIC's Principal Drafter and GIBB's Head of Contracts
In the 1977 edition of the Red Book, its Explanatory Memorandum stated that
"The Clauses of universal application have been grouped together and are
referred to as Part I ", and there were no payment terms in Part I. Numerical
data was to be contained in an Appendix to Tender, but other date (including
payment provisions, law and language) was to be included in a Part II of each
contract. The document concluded with notes intended as an aide-memoire in the
preparation of the Part II.
The 1980 edition of the Yellow Book similarly contained clauses of universal
application in Part I; and numerical data was to be contained in an Appendix to
Tender. Other data was to be included in Part II, and brief guidance for its
preparation was included.
The Foreword of the 1987 edition of the Red Book stated that " The Clauses of
general application have been grouped together in this document and are
referred to as Part I"; the latter contained detailed payment provisions, but
nothing for an advance payment. Again, numerical data was to be contained in
an Appendix to Tender, and other data (law, language, etc.) was to be included in
a Part II of each contract. Guidance and example wording for the preparation of
this Part II was published in a separate volume ("Part II").
The 1987 edition of the Yellow Book contained a more detailed Part I,
and introduced a Preamble for insertion of essential data in lieu of an Appendix
to Tender. The data which was to be included to the relevant Part I provisions
were necessary.
Thus, the Red and Yellow Books have developed in the direction of "user-
friendliness", where the "users" are the individuals who write and administer the
contracts. Prior to 1987, these Books contained the terms which were not
expected to be changed; and any job-specific terms had to be drafted by the user.
The 1987 edition included far more within the Part I, accepting the reality that
many users amend it. These users needed to take care in avoiding errors in their
drafting of each Part II, and tenderers had to be careful to read the tender
documents thoroughly.
1 Short Form of Contract, which may be suitable for a small contract (say,
under US$ 500 000) if the construction time is short (say, less than 6 months), or
for relatively simple or repetitive work (say, dredging), irrespective of whether
the design is provided by the Employer or the Contractor, and of whether the
project involves civil, electrical, mechanical and/or construction works.
3 Conditions of Contract for Plant and Design-Build ("the Plant & E-B
Book" or "P&DB"), which are recommended for the provision of electrical
and/or mechanical plant, and for the design and execution of building or
engineering works. The scope of this Book thus embraces both old Yellow and
Orange Books, for all types of Contractor-designed works.
However, in the following circumstances, the EPC Book is not suitable and the
Plant & D-B Book is considered preferable.
The remainder of this paper focuses on the three "New Books" for major works,
namely CONS, P&DB and EPCT They each comprise three parts:
GENERAL CONDITIONS
Guidance for the Preparation of the Particular Conditions (GPPC)
Letter of Tender, Contract Agreement and Dispute Adjudication Agreements
In order to use these Conditions, each contract's Conditions of Contract is to be
defined by wording included in the Foreword of each GPPC:
The Conditions of Contract comprise the "General Conditions", which form part
of the "Conditions of Contract for..." First Edition 1999 published by the
Federation Internationable des Ingenieurs-Conseils (FIDIC), and the following
"Particular Conditions", which include amendments and additions to such
General Conditions.
The GPPC then provides guidance on what (if any) provisions may be
appropriate for a contract's Particular Conditions, and on the preparation of the
other tender documents.
A principle that we applied throughout the drafting has been to facilitate the
preparation of the tender documents, and in particular the preparation of the
Conditions of Contract. Unlike most other published form of Conditions, those
published by FIDIC recognise the reality that the tender documents for a
particular project typically have to include provisions which are not appropriate
for other projects. Preparation of the tender documents has been facilitated by:
In the Construction and Plant & D-B Books, where further non-technical data is
required, the sub-clause refers to this data being stated in the Appendix to
Tender: the published example of which thus provides a check-list of these
essential items. The EPC Book does not refer to an Appendix to Tender, so the
non-technical data to be specified by the Employer is stated to be in the
Particular Conditions; and a check-list of the General Conditions' references to
such data is included in the introduction to the GPPC.
In all three New Books, their Forewords state that the General Conditions were
drafted on the principle that users would find it more convenient if any
provisions which they did not wish to apply could simply be deleted or not
invoked, than if additional text had to be written in the Particular Conditions
(because the General Conditions did not cover their requirements). If this
criterion was considered inapplicable for a Sub-Clause, it is intended to contain
provisions that were considered applicable to most contracts.
It should therefore be noted that some of the provisions contained in the General
Conditions may be inappropriate for an apparently-typical contract. The basic
concept was to provide maximum convenience for users, particularly those who
prepare the tender documents, for whom a degree of competence is necessary.
Thus, as much text as possible is incorporated into the General Conditions,
including some from the old Part II. Some provisions cannot apply unless
invoked/enabled by the insertion of the required data; and provisions can readily
be disabled by omission of the data or by deletion. Consider, for example, the
following Sub-Clauses:
When tender documents are being prepared, the General Conditions (particularly
those which refer to the Particular Conditions) should be reviewed by suitably-
qualified personnel with the relevant expertise, including the contractual,
technical and procurement aspects. Whilst it would be unwise for them to distort
the allocation of risks contained in the General Conditions, these personnel need
to ensure that all the complete Conditions of Contract, the General and Particular
Conditions, are appropriate for the works, the Employer and the jurisdiction.
In particular, they will need the FIDIC Contracts Guide, which has just been
published.
DETAILS OF THE NEW BOOKS FOR MAJOR WORKS
The New Books have 20 clauses, covering similar subject matter in all three
Books except:
Construction 3 The Engineer 5 Nominated 12 Measurement
Subcontractors and Evaluation
Plant &D-B 3 The Engineer 5 Design 12 Tests after
Completion
EPC Book 3 The Employer's 5 Design 12 Tests after
Administration Completion
Wherever possible, similar wording is used in all three New Books in the
equivalent Sub-Clauses. Clause 1 commences with Definitions, some of which
are illustrated in the charts at the end of each Foreword. Each New Book has its
particular set of tender documents:
A Construction or Plant & D-B Contract will also include a Letter of Acceptance
and/or a Contract Agreement, and either document may bring the Contract into
force. Typically, the Contract Agreement will bring an EPC Contract into force.
Two of the General Provisions specify principles that need no repetition later:
The next Sub-Clause, 2.5, sets out the procedure for the Employer to follow in
the event of a claim against the Contractor. Similar procedures apply to claims
by either Party:
2.5 Employer's claims for money, and for extension of a Defects Notification
Period under 11.3
20.1 Contractor's claims for money, and for extension of a Time for Completion
under 8.4
The Employer is not entitled to withhold an interim payment for reasons that
were not previously notified to the Contractor with particulars substantiating the
Employer's claim. In the same way that Sub-Clause 20.1 requires the Contractor
to comply with a claims procedure, Sub-Clause 2.5 specifies an appropriate
procedure for the Employer. One major difference between these Sub-Clauses is
the absence of any provision imposing strict time constraints on the Employer, it
being considered that any wording could give rise to unfairness in terms of when
the Employer's Personnel should have become aware of a defect giving rise to a
claim.
In the Construction and Plant & D-B Books, Clause 3 describes the role of the
Engineer. Sub-Clause 3.1 (a) states that the Engineer is deemed to act for the
Employer except as otherwise stated in other Conditions. This sub-paragraph (a)
specifies what is generally the Engineer's actual role under his agreement with
the Employer, but does not state that the Engineer acts impartially because of the
problems caused when such a statement proves false. If the Employer perceives
the advantages of the Engineer being required to act impartially, and he has the
professionalism to do so, Sub-Clauses 3.5 may be amended in the Particular
Conditions.
The Engineer may delegate authority under Sub-Clause 3.2 although there is no
defined "Engineer's Representative". The role of these delegated assistants is to
assist the Engineer.
In the EPC Book, Clause 4 covers the equivalent provisions for turnkey projects,
maintaining the similar clause structure. It commences with provisions entitling
(but not requiring) the Employer to appoint a Representative with delegated
powers. Under Sub-Clause 3.4, The Employer's entitlement to issue instructions
is constrained by the need for them to state the contractual obligation and the
Sub-Clause containing such obligation.
Clause 3 concludes with Sub-Clause 3.5 which sets out the procedure for
agreeing or determining various matter: including Employer's claims,
Contractor's claims, and the evaluation of Variations and of the Construction
Book's Works. All New Books have many provisions requiring a matter to be
agreed or determined in accordance with Sub-Clause 3.5.
"If the Contractor suffers delay and/or incurs Cost as a result of ..., the contractor
shall give notice... and shall be entitled subject to Subject to Sub-Clause 20.1 to:
(b) payment of any such Cost, which shall be included in / added to / the
Contract Price.
After receiving this notice, ... shall proceed in accordance with Sub-Clause 3.5 to
agree or determine these matters."
In the Construction Book, the Contractor is only responsible for the design of the
Permanent Works to the extent specified in the Contract. Sub-paragraphs (a) to
(d) specify general requirements in respect of such designs, unless they are
defined otherwise in the Particular Conditions. These general requirements are
also stated (in 13.3 (b)) as being applicable to any subsequent Contractor-
designed "value engineering" proposals, unless otherwise agreed by both Parties:
see below.
Under Sub-Clause 4.10, the Employer is stated to have made available all
relevant data on sub-surface and hydrological conditions by the Base Date,
which is 28 days before the date of submission of the Tender. In the
Construction and Plant & D-B Books, "Unforeseeable" is defined as "not
reasonably foreseeable by an experienced contractor by the date for submission
of the Tender", allowing nearly 28 days after the Base Date for tenderers to
assess the date. The Employer is also required to make available the same types
of date that comes into his possession thereafter.
In the Construction and Plant & D-B Books, Sub-Clause 4.12 defines "physical
conditions" and covers those which are "Unforeseeable". Under a new provision,
the engineer may also review whether other physical conditions in similar parts
of the Works were more favourable than could reasonably have been foreseen
when the Contractor submitted the Tender. This provision may be particularly
relevant for a tunnel, where there may be adverse conditions, in respect of
similar parts of the Works, will not result in a net reduction in the Contract Price
(otherwise, an Employer might have been tempted to conceal favourable
information from tenderers).
In the Plant & D-B and EPC Books, Sub-Clause 4.5 covers nominated
Subcontractors; and Clause 5 covers the aspects related to contractor-design,
including the review (under Sub-Clause 5.2) of Contractor's Documents. It
should be noted that the defined term "Contractor's Documents" only includes
the technical documents which the Contractor is required to submit, and that the
review procedure only applies to whichever of these documents are required to
be reviewed, all in accordance with the Employer's Requirements. It might
appear that the Engineer (under Plant & D-B) and the Employer (under the EPC
Book) can interfere with the Contract's design by requiring changes without
admitting that they are Variations. Under the Plant & D-B Book, this could
happen in respect of documents for which the Engineer's approval is required,
and would presumably result in dispute.
Under the EPC Book, Sub-Clause 5.2 contains no reference to an "approval" for
the Employer to withhold, so the Contractor can proceed (after the "review
period") even if no "consent" has been given. The Employer is not expected to
require the Contractor to produce detailed drawings, although it was impractical
to define the extent of "Contractor' Documents" within the General Conditions,
Also under the EPC Book:
(i) Sub-clause 7.3 only requires the Contractor to notify, before off-Site
covering-up or packaging, to the extent specified in the Contract,
(ii) Sub-Clause 7.6 omits the paragraph requiring the Contractor's compliance
with the Employer's instruction, instead referring to the need for it to comply
with Sub-Clause 3.4, and
Sub-Clause 7.7 defines the date when each item of Plant and Materials becomes
the property of the Employer. In the event of suspension, property passes when
conditions 8.10 (a) & (b) have been satisfied, without further pre-conditions
relation to payment.
Clause 8 covers the time-related aspects. Sub-Clause 8.3 covers the provision of
programmes showing how the Contractor proposes to execute the Works. Each
such programme is to be supported by a report describing the methods that the
Contractor proposes to adopt. Programmes are not "approved": the
contractor~proceeds in accordance with the Programme, except to the extent that
(i) he has been advised of its non-compliance, or (ii) it does not actually comply,
with the Contract. Unrealistic Programmes do not provide a sound basis for
claims.
i) "The Contractor shallbe entitled... " which is not stated as being subject to
anyone's opinion.
ii) "... subject to Sub-Clause 20.1 ..." the second and the final paragraphs of
which may affect the entitlement to an extension of time.
iii) "... to an extension ... if and to the extent ... that completion ...is ...
delayed...": so the extension should typically be calculated by reference to the
delay in completion attributable to a listed cause. It may have disrupted progress
but may not itself have been the cause of any delay in completion. For example,
a listed cause may only delay works which are not on the critical path and thus
do not delay "completion for the purposes of Sub-Clause 10.1 ".
iv) "... completion for the purposes of Sub-Clause 10.1 ...": its first sentence
(sub-paragraph (i) defines the extent of the work which is to be completed within
the Time for Completion, and which is relevant when considering extensions of
time. The work must include the matters described in Sub-Clause 8.2 (a) & (b)
but may exclude, as permitted in Sub-Clause 10.1(a), "any minor outstanding
work and defects which will not substantially affect the use of the Works or
Section of their intended purpose".
Clause 9 covers Tests on Completion, with more detail being provided in the
Plant & D-B and EPC Books because of the importance of such Tests in
determining whether the Works satisfy the Employer's requirements. Under the
Construction Book, Tests on Completion may be less important, except in
respect of any parts of the Works designed by the Contractor.
Defects Liability obligations are specified in Clause 11. Sub-Clause 11.3 entitles
the Employer to claim (under Sub-Clause 2.5) extension of the Defects
Notification Period.
i) the measured quantity of the item is changed by more than 10% from the
quantity of this item in the Bill of Quantities of other Schedule,
ii) this change in quantity multiplied by such specified rate for this item exceeds
0.01 % of the Accepted Contract Amount,
iii) this change in quantity directly changes the Cost per unit quantity of this item
by more than 1%, and
iv) this item is not specified in the Contract as a "fixed rate item";
In the Pant & D-B and EPC Books, Clause 12 covers the possible Tests after
Completion, which may be carried out by the Employer (Plant & D-B Book) or
Contractor (EPC Book). There did not seem to be clear views as to who typically
carried out Tests after Completion, so we solved the dilemma by providing for
either arrangement.
In the Construction and Plant & D-B Books, Sub-Clause 13.8 specifies the
adjustments for changes in cost, so as to avoid users having to write the
necessary text in the Particular Conditions. These provisions are based upon the
assumed availability of suitable cost indices. The formula defines the adjustment
multiplier (Pn) to be applied to the contract value of each month's work. Note
that Pn is the "multiplier" and is not the amount to be added to the contract value
of each month's work. Pn will typically be more than unity, due to inflation.
Sub-Clause 14.1 sets out the financial principles of the Contract, remeasurement
or lumpsum. The remainder of Clause 14 describes the procedures for payments
to the Contractor, which in the EPC Book are not subject to the issue of Payment
Certificates. Payment procedures commence with the Contractor's submission of
a (monthly of other) Statement, with supporting documents which are to include
the progress report under Sub-Clause 4.21.
In the EPC Book: Sub-Clause 14.5 envisages that other provisions (such as a
Schedule of Payments) may entitle the Contractor to payment for Plant and/or
Materials prior to arrival at the Site; Sub-Clause 14.6 requires the Employer to
notify the Contractor of any items in the Statement with which the Employer
disagrees; and Sub-Clause 14.7 (b) defines the Employer's obligation as being to
pay the amount which "is due" in respect of each Statement. The contractor's
entitlement to financing charges under Sub-Clause 14.8 then arises form the
Employer may have paid all of the amount not notified as disagreed under Sub-
Clause 14.6.
Under the Construction and Plant & D-B Books, the entitlement to financing
charges under Sub-Clause 14.8 is based upon when the Engineer received the
Statement, progress report and other supporting documents, irrespective of the
date on which the interim Payment Certificate (if any) was issued. Such
certification date. could, for example, be after the date defined in Sub-Clause
14.7 (b) by which payment should have been made.
Clause 17 covers risk and responsibility. Sub-Clause 17.1 defines the extent to
which each Party indemnifies the other in respect of claims for personal injury or
damage to property. Sub-Clause 17.2 defines the Contractor's responsibility for
care of the Works. Sub-Clause 17.3 lists the risks which, if they eventuate,
entitle the Contractor to compensation in respect of loss or damage to the Works,
Goods or Contractor's Documents. Depending upon the matters stated in Clause
19, some of the risks listed in Sub-Clause 17.3 may be so exceptional as to be
Force Majeure.
The Works are to be insured in the joint names of the Contractor and Employer.
The insurer should make each claims payment jointly to both the Parties,
although this seldom happens. If a Subcontractor is named in the insurance
policy as additional insured, the insurer would thus make each claims payment
jointly to each such additional insured as well as the two Parties: which could
require a physically-large cheque to make the payment! The situation is covered
in the fourth paragraph of Sub-Clause 18.1.
If the insuring Party fails (or is unable) to effect and keep in force its insurance,
the other Party may effect the insurance at the cost of the defaulting Party. For
various reasons, such other Party may not do so, possibly because insurance is
no longer available at commercially reasonable terms. Sub-Clause 18.1 therefore
concludes with provisions that address these circumstances.
Under Sub-Clause 18.2 (d), The insuring Party is~required to effect insurance in
respect of some of the Employer's risks, excluding (in each case) risks which are
not insurable at commercially reasonable terms and the exclusions described in
sub-Paragraph (e). If this cover ceases to be available, the last Paragraph of Sub-
Clause 18.2 comes into effect.
General Conditions
Guidance for the Preparation of the Particular Conditions Letter of Tender,
Contract Agreement, and Dispute Adjudication Agreements
User-Friendliness
CONS + P & DB : If a General Condition necessitates further data, the sub-
clause makes reference to this data being contained in the Appendix to Tender
EPCT* data in Particular Conditions: GPPC's checklist
(a) users would find it more convenient if any provision which they did not wish
to apply could be deleted or not invoked, than if they had to write a Particular
Condition;
or
(b) in other cases, where the application of (a) was considered inappropriate, the
General Conditions contain provisions which were considered applicable to most
contracts.
1. General Provisions
2. The employer
3. The Engineer - CONS + P & DB
The Employer's Adminiatration - EPCT
4. The Contractor
5. Nominated Subcontractors - CONS
Design - P & DB + EPCT
6. Staff and Labour
7. Plant, Materials and Workmanship
8. Commencement, Delays and Suspension
9. Tests on Completion
10. Employer's Taking Over
11. Defects Liability
12. Measurement and Evaluation - CONS
Tests after Completion - P & DB + EPCT
13. Variations and Adjustments
14. Contract Price and Payment
15. Termination by Employer
16. Suspension and Termination by Contractor
17. Risk and Responsibility
18. Insurance
19. Force Majeure
20. Claims, Disputes and Arbitration
Claims
If the Contractor suffers delay and/or incurs Cost as a result of..., the Contractor
shall give notice... and shall be entitled subject to Sub-Clause 20.1 to:
(a) an extension of time for any such delay, if completion is or will be delayed,
under Sub-Clause 8.4, and
(b) payment of any such Cost, which shall be ... Contract Price. After receiving
this notice,... shall proceed in accordance with Sub-Clause 3.5 to agree or
determine these matters.
3.4 If the Employer intends to replace the Engineer, the Contractor is to be given
42 days' notice, which is to include replacement's experience. No replacement if
the Contractor raises reasonable objection
3.5 Each Party shall give effect to each determination unless the Contractor
notifies dissatisfaction within 14 days
P & DB + EPCT, When completed, the Works Shall be fit for. the purposes for
which the Works are intended as defined in the Contract
Clause 7 - Testing