1. Consider the list of activities shown in the table for the manufacture of a washing machine. Which of the
following flow of tasks is not correct for the given data?
a. ACFGJ
b. BCDEHJ
c. ACDEFGJ
d. BCFGJ
e. BCDEIJ
2. Which of the following control charts is/are used to study discrete variables?
1. X-bar chart
2. R chart
3. p chart
a. Only 1
b. Only 2
c. Only 3
d. Both 1 and 2
e. Both 1 and 3
3. McKisley Co. sells mango juice tins to a retail superstore. Once in 12 days, the delivery boy stops
by and checks the inventory level. He then places an order that is delivered 4 days later. The average
demand is 200 tins and the standard deviation of demand is 25 tins. The retail store wants enough
inventory on hand to meet the demand 90 percent of the time. (z-value=1.28). Calculate the restocking
level.
a. 205 tins
b. 209 tins
c. 225 tins
d. 232 tins
4. When you buy a new car, you are interested to know if there is any complaint from the customers with
respect to defective parts being used in the manufacture of the car. Which aspect of quality are you
concerned with?
a. Reliability
b. Durability
c. Conformance
d. Aesthetics
5. A manufacturing company uses two types of machines to produce the final finished goods. The type to be
used depends on the demand for goods. During summer, the demand is low and machine A is used while
machine B is used during winter when the demand is high. The average demand in summer is 400 and in
winter it is 1,200. Assuming that the probability of demand being low or high is equal, what is the expected
cost of using Machine B.
a. $ 42,000
b. $ 21,000
c. $ 41,000
d. $ 20,500
6. Consider the table given. Your company has to do the flooring and painting at 4 places namely
Ridgewood Estate, Wellington House, Belvedere Park and Wood rose Retreat. There are three steps
involved in the process and each of these steps must be completed prior to moving on to the next step.
You can work on only one job at a time at each step. The due date for the completion of each of the jobs
is also given in the table. You decide to use the 'First Come First Served' sequencing rule. Which job will
get delayed beyond the due date and what is the average delay?
8. Which of the following statements is/are true regarding product customization in the supply chain?
1. When customization occurs early in the supply chain, products will tend to be more costly.
2. When customization occurs late in the supply chain, the lead times to the customer will tend to be longer.
9. You are in charge of ordering items at a department store. , The average daily demand for one of
the products is 20 units with a standard deviation of 4. If you order the product directly from
the manufacturer, they will take, on an average, 16 days to supply with a standard deviation in lead
time of 2. If you wish to ensure 95% service level, what should be the reorder point with safety
stock? (z-value = 1.65)
a. 381 units
b. 391 units
c. 445 units
d. 462 units