012 PRC Tacr PDF
012 PRC Tacr PDF
012 PRC Tacr PDF
This consultants report does not necessarily reflect the views of ADB or the Government concerned, and
ADB and the Government cannot be held liable for its contents. (For project preparatory technical
assistance: All the views expressed herein may not be incorporated into the proposed projects design.
RENEWABLE ENERGY DEVELOPMENT IN QINGHAI
PEOPLES REPUBLIC OF CHINA
PROJECT NUMBER : TA-7643 (PRC)
FINAL REPORT
Prepared for
By
NEWJEC Inc.
October, 2012
Renewable Energy Development
Final Report Contents
TABLE OF CONTENTS
EXECUTIVE SUMMARY
CHAPTER 1 INTRODUCTION
1.1 Background ............................................................................................................. 1 - 1
1.2 TOR ......................................................................................................................... 1 - 2
1.3 Objectives ................................................................................................................ 1 - 2
1.4 Structure of the Final Report ................................................................................... 1 - 2
-i-
Renewable Energy Development
Contents Final Report
- ii -
Renewable Energy Development
Final Report Contents
APPENDICES
Appendix 1 Terms of Reference
Appendix 2 National Development Plan and Provincial Development Plan
Appendix 3 Capacity Development Training
Appendix 4 Presentation Materials
Appendix 4-1 : Seminar
Appendix 4-2 : Interim Workshop
Appendix 4-3 : Final Workshop
Appendix 5 Seminar and Workshops
Appendix 6 Registered Companies and Applied Projects of Qinghai 930 Projects
in Haixi Prefecture
- iii -
Renewable Energy Development
List of Tables, Figures and Abbreviations Final Report
LIST OF TABLES
Table 4.1-1 Calculation Result of Short Circuit Level in 2020 for Relevant Substation
Buses .................................................................................................................... 4 - 2
Table 4.1-2 Specifications of DC Convergence Control Box ................................................... 4 - 3
Table 4.1-3 Specifications of Unit Step-up Transformer .......................................................... 4 - 4
Table 4.1-4 Specifications of Circuit Breaker ........................................................................... 4 - 4
Table 4.1-5 Main Electrical Equipment List .............................................................................. 4 - 5
Table 4.1-6 Specifications of Grid-connected Inverter ............................................................. 4 - 5
Table 4.1-7 Maximum Power of Direct Current (DC) Side ....................................................... 4 - 10
Table 4.1-8 Rated Output ......................................................................................................... 4 - 10
Table 4.2-1 Qinghai Grid .......................................................................................................... 4 - 15
Table 4.2-2 Demand Forecast in Golmud Area........................................................................ 4 - 17
Table 4.2-3 Power Balance in Golmud Area (Summer) ........................................................... 4 - 18
Table 4.2-4 Power Balance in Golmud Area (Winter) .............................................................. 4 - 19
Table 4.2-5 Solar Power Station............................................................................................... 4 - 22
Table 4.2-6 Grid Owner, Construction and Operation .............................................................. 4 - 24
- iv -
Renewable Energy Development
Final Report List of Tables, Figures and Abbreviations
Table 5.1-7 Sensitivity Analysis of FIRR/e with Soft Loan Introduced ..................................... 5 - 9
Table 5.1-8 Sensitivity Analysis of FIRR/e with Soft Loan, tariff at CNY 1.0 ........................... 5 - 10
Table 5.1-9 Reduction of CO2 Emission .................................................................................. 5 - 11
LIST OF FIGURES
Fig. 2.1-1 Description of Grid Stability (taking marching by persons as an example) .......... 2 - 7
Fig. 2.2-1 Required Capability on the FRT Function ............................................................ 2 - 16
Fig. 2.3-1 Demonstrative Research in Ota City, Japan ........................................................ 2 - 20
Fig. 2.3-2 Large-scale PV Power Plant located in Wakkanai City ........................................ 2 - 20
Fig. 2.3-3 Results of Output Fluctuations Preventive Control Testing
(Moving Average Target Control) ......................................................................... 2 - 21
Fig. 2.3-4 Large-scale PV Power Plant located in Wakkanai City ........................................ 2 - 22
Fig. 2.3-5 Demonstrative Microgrid in Los Alamos County ................................................... 2 - 23
Fig. 2.3-6 Residence Area in Los Alamos County ................................................................ 2 - 24
Fig. 2.3-7 Configuration of Microgrid in Albuquerque ........................................................... 2 - 25
Fig. 2.4-1 Southern View from 10MW Pilot Project Site ....................................................... 2 - 39
Fig. 2.4-2 Shadow made by Obstacles of the Surroundings ................................................ 2 - 40
Fig. 2.4-3 Illustrative Picture of Sunlight Orbit Projection ..................................................... 2 - 40
Fig. 2.4-4 Direct Sunlight and Diffused Sunlight ................................................................... 2 - 41
Fig. 2.4-5 Single-lens Reflex Camera and Fish-eye Lens .................................................... 2 - 41
Fig. 2.4-6 View of Fish-eye Lens with Tilt Angle 35 ............................................................ 2 - 42
Fig. 2.4-7 Visible Fields using Fish-eye Lens ....................................................................... 2 - 43
Fig. 2.4-8 Solar Orbit ............................................................................................................. 2 - 43
Fig. 2.4-9 Solar Orbit on Fish-eye Lens ................................................................................ 2 - 44
Fig. 2.4-10 Solar Orbit on Fish-eye Lens at the 10MW Pilot PV System Site ........................ 2 - 45
Fig. 2.4-11 Prediction of Power Generation ............................................................................ 2 - 48
Fig. 2.4-12 Macro Prediction System ...................................................................................... 2 - 50
Fig. 2.4-13 Graphics by the Weather Satellite ........................................................................ 2 - 50
Fig. 2.4-14 Sun Orbit and Movement of Cloud ....................................................................... 2 - 51
Fig. 2.4-15 Method of Getting Reflection Sunlight .................................................................. 2 - 53
Fig. 2.4-16 Reflection Light at 10MW PV Site (Tilt Angle 35)................................................ 2 - 53
Fig. 2.5-1 Input of Project Information................................................................................... 2 - 55
Fig. 2.5-2 Site Data by NASA (downloaded automatically) .................................................. 2 - 55
Fig. 2.5-3 Input of Energy Model ........................................................................................... 2 - 56
Fig. 2.5-4 Input of Cost Data ................................................................................................. 2 - 57
Fig. 2.5-5 Input of Financial Parameters ............................................................................... 2 - 57
Fig. 2.5-6 Input of Annual Income ......................................................................................... 2 - 57
Fig. 2.5-7 Costs & Income Summary .................................................................................... 2 - 58
Fig. 2.5-8 Financial Viability .................................................................................................. 2 - 58
Fig. 2.5-9 Yearly Cash Flow .................................................................................................. 2 - 58
Fig. 2.5-10 Cumulative Cash Flow Graph ............................................................................... 2 - 59
-v-
Renewable Energy Development
List of Tables, Figures and Abbreviations Final Report
- vi -
Renewable Energy Development
Final Report List of Tables, Figures and Abbreviations
- vii -
Renewable Energy Development
List of Tables, Figures and Abbreviations Final Report
CURRENCY EQUIVALENTS
ABBREVIATIONS
- viii -
Renewable Energy Development
Final Report List of Tables, Figures and Abbreviations
- ix -
Renewable Energy Development
Final Report Executive Summary
EXECUTIVE SUMMARY
Renewable Energy Development
Final Report Executive Summary
EXECUTIVE SUMMARY
I. INTRODUCTION
2. The Peoples Republic of China (PRC) is the world largest solar cell producer with
huge production capacity which shares around 50% of 29.5 giga Watt (GW) solar
cell productions in the world as of 2011. Although the worldwide solar cell market is
estimated to be shrunk from 2012 and onward due to aggressive cut feed-in-tariff
(FIT) incentive in European countries, domestic huge production capacity in PRC
will continuously contribute to domestic solar PV market expansion. With ambitious
long term target in expanding solar energy install capacity, and feed-in-tariff for solar
energy project announced in 2011, the PRC has witnessed a significant growth in
domestic solar PV market where solar PV installed capacity has surged by 2.9 GW
from 0.9 GW in 2010. During the Twelfth Five Year plan (2011 2015), the PRC has
newly set a target for solar PV install capacity by 20 GW.
-1-
Renewable Energy Development
Executive Summary Final Report
solar energy install capacity by 1,000 MW per year during the twelfth five-year plan
(2011-2015) period. By 2015, the planned solar energy install capacity will be 4,000
MW comprised of 3,500 MW of the grid-connected solar PV power plants, 300 MW
of the concentrating solar thermal power plants, and 200 MW of distributed solar PV
systems. The solar energy install capacity is planned to be expanded by 10,000 MW
in 2020 and by 20,000 MW by 2030. By the end of 2011, solar PV installed capacity
in Qinghai province reached 1,010 MW which was 47.2% of total solar PV installed
capacity in PRC, and 1,000 MW additional solar PV power plants will be in operation
by the end of 2012. Qinghai province has been and will continuously be a major
driver for solar energy development in PRC. But challenges lie ahead, in view of
grid-connectivity and stability, electricity yield risk, financial viability, system quality
assurance, and development planning, to realize sizable grid connected MW and
GW class solar PV investment as planned in twelfth five-year plan (2011-2015) and
onward till 2020.
In a power system consisting of many power stations and related network equipment
spreading over wide area, it is essential to control the supply-demand balance and
to optimally operate the power system to maintain the stability of power system
overall. Penetration of sizable grid-connected solar PV system into the grid in PRC
and Qinghai province is raising concern over supplydemand balance control and
grid stability. Such supply and demand imbalance due to rapid diffusion of solar PV
could cause (i) excessive power supply generation; (ii) frequent heavy and
unexpected power flow causing critical grid condition with small margin in N-1
criteria; and (iii) emergency trip at inter-connection lines. The output fluctuation of
grid-connected solar PV has to be supplemented by the power plants having peak
and middle peak output supply capacity. But, in parallel with enhancing transmission
capacity, solar PV power plant in PRC is also required to enhance its own system for
grid stability and safety function such as introducing Fault Ride Through (FRT)
function, increasing capacity of power conditioner, and improving Mater Control and
Monitoring (MCM) system.
-2-
Renewable Energy Development
Final Report Executive Summary
HVDC has high speed control system as well as large transmission capacity, and
power flow through the HVDC system can be changed and modulated using the
high speed control in timely manner. The power transmission capability and
modulation function are useful for recovery from the fluctuation of grid voltage and
frequency and disturbance in grid. HVDC as part of smart grid technology will be
essential for power system having high grid-connected solar PV and wind power
plants.
FRT function as a part of inverter system should be required for MW-class grid
connected solar PV system to keep grid stability. FRT function improves durability of
solar PV system during sudden accident in the grid to ensure continuous operation
to avoid grid collapse. Power conditioner having maximum power point tracking
(MPPT) and two-stage conversion structure with phase separation in inversion
section are essential functions for grid connected solar PV system, and enlarging
power conditioner capacity up to 500 kW will also be necessary as install capacity of
grid connected solar PV increases. MCM having supervisory system software with
solar PV power station, substation, and control center monitoring function is another
essential function for grid connected solar PV system. MCM with the secondary
battery system such as sodium-sulfur (NaS) battery is a cutting-edge technology
enabling grid-connected solar PV output stable.
-3-
Renewable Energy Development
Executive Summary Final Report
iii) Bidirectional
CNV inverter
300kVA (converter) for
DC bus bar (DC unit) grid connection
Power Power
collector collector
Electric double-layered
capacitor, 1 kWh
Fish-eye Lens devise estimating solar irradiation resources is cost efficient approach
to validate both satellite imaginary and site specific based solar irradiation estimates.
Solar irradiation forecasting derived from Fish-eye Lens devises has shown good
agreement with satellite imaginary and site measurement data. On a basis of solar
resource validation, forecasted electricity yield is estimated at 16,822 MWh/year (tilt
angle of PV modules at 35) and 17,083 MWh/year (at 25), which suggests that tilt
-4-
Renewable Energy Development
Final Report Executive Summary
angle lower than 35 of longitude and up to 25 are desirable tilt angle capturing the
direct and diffused sun-light, thereby maximizing output generation of solar PV
system. Due to output fluctuation of solar PV system, precise prediction of solar
irradiation is one of the core issues in terms of electricity yield projection and
electricity supply and demand control in grid system. Since several kinds of
estimation period (every 30 minute, 1 minute to several minutes interval,
one-second level interval) are required for appropriate supply and demand control,
weather forecast methods for these periods have to be developed.
Total loss before the inverter is 10%. Then the capacity of inverter is enough to have
90% of the capacity of the solar PV panels. Specifications of inverters may be
offered unilaterally by the inverter manufacturer; still it is important here that the user
engineers understand each item of the specifications. Users understanding of the
specifications of inverter should be at the same level as manufacturers engineers.
There are several steps to be taken to improve the knowledge of user engineers: (i)
installation conditions based on the specifications; (ii) necessary function for the
solar PV system at the site; (iii) specifications of the equipment in detail and
specified value gained from testing method; and (iv) appropriate combination of
devices, to achieve high efficiency, low cost, long life time, and easy maintenance.
The life of the transformer is estimated based on the maximum utilization factor and
the load factor and the life measurement method of transformer is established at
present. Considering a capacity factor of the solar PV system in the night period is
zero, less than 90 % of inverter capacity is good enough for the capacity of the
transformer. Generally speaking, a transformer has overloading capacity. It depends
on the insulator used in transformer, the load factor and ambient temperature. Load
factor of a transformer used for a grid-connected PV system will be less than 0.3. It
may be worth considering to downsize transformer capacity which is smaller than
solar PV installed capacity, though there is a need to investigate how much the
maximum power is, how many hours the continuous operation is, and how often
appear in appropriate period. On a basis of these considerations, a transformer with
smaller capacity may be introduced to PV system. Using smaller-capacity
transformer will reduce, not only installation cost, but also transformer's electric loss.
-5-
Renewable Energy Development
Executive Summary Final Report
10 MW Pilot Project has been designed to be installed with SPD (Surge Protective
Device) in each joint box. This is an agreeable design in order to prevent PV arrays
from lightning hazards. Some array which was hit by lightning would spread the
impact to other arrays. It might happen to flash over between frame and photovoltaic
cell of PV arrays. Surge will be passed on to other PV arrays. To avoid damage by
lightning, SPD is effective. Function of SPD is to equalize potential between
equipment and the ground, which prevent the occurrence of flash over.
SPD
For alterative current circuit, there are two kinds of power supply. One is effective
power and the other is reactive power. The PV system of 10MW Pilot Project will
supply only effective power, but transmission line needs reactive power because
there is line inductance and capacitance to the ground in transmission line. For this
reason, it is very appropriate to install SVC (Static Var Compensator) in the
substation to compensate the lack of reactive power. For 10MW Pilot case, a SVC
should be located at the transmission line's end.
Wiring is vibrating and rubbing against PV frame because wiring was not firmly fixed.
This condition damages the insolation of wiring. Therefore, wiring needs some more
length for setting to absorb vibration and to avoid rubbing against PV frame as
below.
-6-
Renewable Energy Development
Final Report Executive Summary
Direct current (DC) circuit generally needs insulation to the ground and some
monitoring and protection might be necessary. When grounding accident happens in
the DC circuit of a solar PV system, the DC fault current flows from PV array through
transformer. DC fault current flows in the transformer as shown in Fig.3.3-10. In this
case the transformer may experience insulation deterioration quickly by DC fault
current which is dangerous for maintenance staffs. If someone touches the wiring of
DC circuit and the wiring does not have enough insulation, electrical shock may be
occurred. Even if the inverter does not have this function, it is possible to set this
function outside the inverter, such as DC OVGR (Over Voltage Ground Relay).
270kV/350V
PV Transless Inverter
Transformer
Grounding
DC fault current
In the case of short-circuited failure, the fault current will flows from not only
transformer but also other transmission lines that are connected to PV system.
Therefore, the capacity of circuit breaker should be designed to have enough
endurance of those total current.
PV PV PV PV
A : Short circuit current from transformer
B : Short circuit current from PV system through other transmission
-7-
Renewable Energy Development
Executive Summary Final Report
Long term operation and maintenance requires more skill in handling complex
devices such as power conditioners. Generally, a power conditioner has several
electronics boards inside and replacing such boards requires specific skills. If
replacement of parts is conducted by manufacturers engineer, minimum 2 or 3 days
have to be given before arrival of engineers at the site. It is desirable for the plant
operator to obtain the special training in the guarantee period.
S= a N M
S: number of spare parts
D in stock
a: coefficient ( >1 )
At first "a" will be
Delivery time : month desirable 1.5 ~ 2.
(110/35kV Transformer)
power from six (6) PV power
b. 35 kV Transmission lines plants in Golmud solar park and
to connect with the 110kV grid.
PV1 PV2 PV3 PV4 PV5 PV6 a. PV power plant
-8-
Renewable Energy Development
Final Report Executive Summary
80
Within
1 Sec
China
30
Japan
20
(before March, 2017)
Assessing the grid condition either it must be paralleled off or must be operated
continuously, is the key point to ensure safety operation of FRT function. When a
fault occurred in the connected transmission line, the PV power plant must be
paralleled off. But, when a fault occurred in other transmission lines with voltage
drop, the PV power plant must be operated continuously.
The PV power plants in PRC should establish a complete and efficient line
protection. This line protection can catch a fault in the case of 1) above easily and
quickly. The proposed block diagram of the control system designed is shown below.
Grid protection circuit integrated in this block diagram is designed to meet the
requirements to connect with low voltage circuit (6.6kV) without circuit breaker.
Under this connection, control system of inverter must have the grid protection.
-9-
Renewable Energy Development
Executive Summary Final Report
PV-Array Grid
Detection Circuit
Drive Circuit of
for Vout & Fout
Inverter
Grid Protection
Circuit
Control Control
for for
1
MPPT* Vout & Iout
Control
for
FRT Operation
Projection of revenue and cost are laid out for coming twenty years to calculate
Financial Internal Rate of Return (FIRR) (see the table below). FIRR obtained was
4.95%, higher than the calculated WACC 3.42%. Financial Net Present Value
(FNPV) calculated using the discount rate 3.42% was CNY 22 million. However, we
should not take this result at face value. This analysis method was based on the
assumption that the financial projection was valued in real terms: under the
inflationary condition, the interest rate of bank loan was converted to real terms
when WACC was calculated, and the operation and maintenance cost was
considered to be constant in real terms.
Income and expense projections were made in nominal terms with loan repayment
schedule, and cash flow was calculated to obtain the return on equity. Only
operation and maintenance cost was adjusted for the inflation. The resulting IRR
(FIRR/e) should be compared with cost of equity in nominal terms. FIRR/e obtained
was 4.46%. This is much lower than NDRC Guideline value of 11% or the alternative
lower threshold 8%. The project is not likely to be financially attractive in project
owners point of view.
- 10 -
Renewable Energy Development
Final Report Executive Summary
With project life extension and CER revenue, low cost and long term credit will also
impact to improve FIRR/e. Given that financing plan comprised of 40% from equity
investment, 10% from domestic bank loan, and 50% of international and/or domestic
financial institution having low cost and long term credit (25 years tenor including 5
years grace and 2.60% loan interest) out of total project cost, FIRR/e under current
CNY 1.0 per kWh of off-take tariff will be improved significantly but still vulnerable to
certain adverse conditions.
FIRR/e
Change 20 years 25 years
w/o CER w/CER w/o CER w/CER
(a) Base case 5.18% 6.63% 7.59% 8.86%
(b) Capital cost overrun +10% 2.82% 4.24% 5.55% 6.78%
(c) Lower benefit -10% 2.58% 4.00% 5.34% 6.56%
(d) Faster deterioration -1.5% p.a. 3.79% 5.30% 6.31% 7.63%
(e) Delay of Construction 1 year 3.76% 4.88% 5.74% 6.78%
(f) CER income reduced -10% - 6.48% - 8.73%
(g) Higher Interest Rate +10% 4.76% 6.21% 7.21% 8.48%
(h) All of conditions above -1.93% -0.64% 0.00% 1.31%
Given that solar energy power plant will continuously be concentrated in Golmud,
Haixi prefecture, current 330 KV transmissions and substation capacity is no longer
sufficient enough to evacuate power from mushrooming solar PV power plants with
- 11 -
Renewable Energy Development
Executive Summary Final Report
more than 1,000 MW installed capacity in total which will be surged by 3,500 MW by
2015. Limited grid capacity for power evacuation risks stable power generation and
project cash flow, which will be a significant bottleneck of sustainable investment in
solar PV development in Qinghai. Thus, the presence of upgraded and expanded
transmission lines and substations are essential to evacuate surging power supply
from sizable solar PV plants. HVDC system which has high speed control system as
well as large transmission capacity, and power flow through the HVDC system can
be changed and modulated using the high speed control in timely manner. This
power changing and modulation is
useful for recovering from the
fluctuation of grid voltage and
frequency and disturbance of grid. 750
KV transmission line and 400kV HVDC
system are currently under
construction in Golmud should be in
operation to keep pace with solar PV
penetration into the grid in accordance
with install capacity target in provincial
twelfth five-year plan.
27. Upgrading Grid Code which Requires FRT Function: Improving Grid Stability
and Safety
When a fault occurs in a grid, the voltage drops and frequency and power flow are
also disturbed. Under this disturbed grid condition, the conventional power plants
connected to the grid try to keep sending power to the grid, which helps the grid
recover from the disturbed condition. If it drops out of N-1 criteria, the
interconnection lines must be disconnected or the whole grid will corrupts at worst.
The solar PV systems do not have the modulation capability, and it stops operation
(parallel off from grid) when voltage drop and/or disturbed frequency observed. This
parallel off is an unexpected trip. When the total capacity of PV plants that have
gone parallel off is too large, the gird collapses. To solve this problem there is a
technology developed which is called Fault Ride Through (FRT) function. This
function enables the inverters to keep operations when an instant voltage drop
and/or disturbed frequency encountered. The FRT function is essential to avoid the
unexpected trip and to keep the grid stability. Since the grid code to date does not
require FRT function for solar PV power plants, upgrading the grid code in which
FRT function is compulsory requirement for grid connection is urgently needed. On
top of it, as grid-connected solar PV is expected to be sharply increasing even within
a couple of years, low voltage recovery time (LVRT) is also suggested to be
shortened from 2.0 Sec to 0.5 Sec in immediate future for enhancing grid safety.
- 12 -
Renewable Energy Development
Final Report Executive Summary
The micro grid system has small size power grid and controls supply and demand
power within the system. It connects multiple power-generating facilities and
electrical storage devices, including natural-energy sources such as solar power,
thereby ensuring a stable supply of electricity. The micro-grid system provides
optimal control, adjusting and maintaining the balance between demand and supply
to ensure a stable supply of electricity. The micro grid system is also effective to
reduce the influence caused by the fluctuation of the large solar PV system to the
wide range power grid.
In case of micro-grid system in Los Alamos County in the United States which is up
and running in September 2012, solar PV power generation system and storage
batteries (1.0 MW of NAS batteries and 0.8 Lead battery) are introduced to compose
micro grid system with around $37 million of initial investment cost. Real-time price
signal system from the Energy Management System (EMS) of the power distribution
lines is also designed to monitor solar PV power generation, power storage volume
in the secondary batteries, and electricity consumption inside the grid system. In this
micro grid system, clustered PV power generation system and storage batteries that
connect between the power distribution substation and the switchgear are installed,
and demonstrate the ability to control variations in solar radiation with storage
batteries. EMS for controlling the system is introduced and the smart equipment on
the power distribution lines to simulate
distribution lines with a high PV power
penetration into the grid is operated. In
case of Qinghai, the similar concept of
Los Alamos micro grid is applicable.
Golmud city could be the candidate for
the micro grid system as the pilot
testing location, using abundant solar
PV electricity supply capacity from
adjacent solar park and the natural gas
resources as back-up.
- 13 -
Renewable Energy Development
Executive Summary Final Report
In parallel, building technical guidance and supervision team under the provincial
government authority is also suggested to conduct technical evaluation of whole
project cycle including construction and operation, and strengthen supervision and
guidance for solar PV owners who fail to attain originally predicted annual power
plant output. Moreover, solar energy projects using unique and variety of technology
such as various type of concentrating solar thermal power (CSP), concentrating PV
(CPV), micro-grid are expected to be emerging in immediate future. As less down 50
MW solar energy project is fallen in provincial government approving authority,
continuous capacity enhancement of such the provincial technical team and the
local design institute will also be essential to assure quality and performance of solar
energy projects in Qinghai.
Reliable solar irradiation data is essential to predict electricity yield throughout more
than 20 years of solar PV project life. Project site selection and electricity yield
forecasting are always based on historical solar irradiation data and changes in
weather patterns from year to year, and long term data are desirable for determining
a representative annual data set. Currently, solar irradiation forecasting uses the
approach (i) comparing locally measured ground data (at site and at metrological
station less than 10 km from the site) to the satellite-derived data for the same time
interval, and (ii) correcting any bias in the satellite data to generate the improved
- 14 -
Renewable Energy Development
Final Report Executive Summary
Considering the provincial government has set 20,000 MW of solar energy install
capacity by 2030 and has planned to concentrate solar energy power plant in
Golmud, enhancing metrological observatory system in Qinghai by (i) increasing
number of metrological observatory stations (one station in each 10 km mesh is
desirable), and (ii) accumulating continuous time series solar irradiation and related
weather data set will be a great help to gain developers and transmission operators
confidence in irradiation resource and electricity yield forecasting for sustainable
solar PV development in Golmud.
Financial assessment for the pilot 10 MW solar PV power plant indicates that
financial rate of return (FIRR) of 4.95% at base case scenario, which is marginally
higher than 3.42% of weighted average cost of capital (WACC). Setting appropriate
tariff level taking consideration into latest static investment cost trend and leveraged
cost of energy (LCOE) will be essential for sustainable solar energy development.
But, if credit enhancement support will be in place, the project could become
financially viable even with CNY 1.0 per kWh of off-take tariff level.
One approach found effective is to extend loan tenor and project life from 20 to 25
years. Longer loan tenor and project life will not only improve the financial
performance of projects, but also contribute to the reduction of carbon dioxide
emission for most of carbon dioxide emission from PV power generation comes from
production and installation processes of the equipment. Another effective and
important approach is an introduction of soft loan in funding plan. For capital
intensive, expensive PV projects it is quite important to have such funds having low
cost and long term tenor terms. Given that (i) extension of loan tenor and project life
from 20 to 25 years, and (ii) 2.6% of interest rate with 25 years tenor (including 5
- 15 -
Renewable Energy Development
Executive Summary Final Report
- 16 -
Renewable Energy Development Chapter 1
Final Report Introduction
CHAPTER 1
INTRODUCTION
Renewable Energy Development Chapter 1
Final Report Introduction
CHAPTER 1 INTRODUCTION
1.1 BACKGROUND
In February, 2005, the Renewable Energy Law was enacted in PRC. The Law
provides a feed-in tariff for some renewable technologies, and specifies grid-feed as
requirements and standard procedures, and establishes incentives and supervisory
measures for promoting renewable energy development. In 2007, NDRC 3 issued the
Medium and Long-Term Development Plan for Renewable Energy in PRC, which
aimed to increase the share of renewable energy to 10% by 2010, and to 15% by
2020. Besides, in November 2009, the State Council of PRC announced to reduce
carbon dioxide emissions per unit of gross domestic product by 40% to 45% by 2020
compared to 2005 level.
Increasing the share of renewable energy to achieve the targeted energy mix by 2020
will also reduce carbon dioxide emissions. The share of renewable energy of the total
primary energy mix has increased steadily, from 7% in 2005 to 9% in 2009, and likely
to reach the target of 10% in 2010. However, the growth of all renewable energy
sources has not been uniform. While wind power increased rapidly from 1.3GW in
2005 to 25GW in 2009, the growth rate of solar PV power generation was rather slow
as the unit cost for power generation stayed at high level.
However, the domestic market for solar PV power generation is expected to grow with
the government support. The government launched the first concession program for a
10 MW class grid-connected solar PV system in Dunghuang, Gansu Province in 2009,
and the nationwide grid-connected solar PV concession program with the total
installed capacity of 280MW in 2010. With the ambitious updated target to increase
solar energy install capacity up to 21 GW by 2015, installed capacity of solar energy
1 Photovoltaic
2 The Peoples Republic of China
3 National Development and Reform Commission
1-1
Chapter 1 Renewable Energy Development
Introduction Final Report
1.2 TOR 5
1.3 OBJECTIVES
1-2
Renewable Energy Development Chapter 1
Final Report Introduction
To achieve the objective, NEWJEC Inc., a Japanese consulting firm, was employed by
ADB through the international competitive bidding.
The Final Report presents the major documents prepared by the Consultant during
the course of the TA and organized according to the Table of Contents.
1-3
Renewable Energy Development Chapter 2
Final Report Advanced Technology for Grid-Connected Solar PV Systems
CHAPTER 2
ADVANCED TECHNOLOGY
FOR GRID-CONNECTED SOLAR PV SYSTEMS
Renewable Energy Development Chapter 2
Final Report Advanced Technology for Grid-Connected Solar PV Systems
2.1 International Best Practices for Grid Protection Design and System
Configuration for a 10MW-class Grid-connected Solar PV System
In a power system consisting of many power stations and related network equipment
spreading over wide area, it is essential to control the supply-demand balance and to
operate the power system property as to maintain the stability of total power system.
The frequency of power system is affected by the balance of power consumption and
power generation. The system frequency must be maintained within certain range in
order to avoid serious system accidents.
The importance of supply and demand control technologies especially in short period
is now given focus as the number and proportion of REs in power systems are being
increased.
In PRC, power demand has been rapidly increasing. To meet the increasing demand,
enhancement of power supply (power generation facilities) and expansion of
transmission and substation facilities are planned and implemented. Installation of
large-scale solar PV systems is one of the means to secure the power supply to meet
the increasing demand. However, power supply enhancement by installation of a
large-scale solar PV system brings the following concerns to a power grid.
1 Renewable Energy
2-1
Chapter 2 Renewable Energy Development
Advanced Technology for Grid-Connected Solar PV Systems Final Report
In Haixi Prefecture where Golmud is located, power supply will exceed the demand
and surplus power would be generated when all planned solar PV projects are
implemented. Following countermeasures are considered to deal with such surplus
power: 1) output control of solar PV systems, 2) expansion of transmission lines in
order to send the surplus power to other demand areas.
It still remains some issues to realize stable operation of the power grid even through
power supply-demand is balanced according to calculation, as it is difficult to estimate
and control power output of solar PV systems which are influenced by weather. As
countermeasures against this issue, it is required to collect and store the real-time
operation data and continuous operation record of the solar PV system. Therefore,
the facility that transmits such information is required to be installed in solar PV
systems.
Besides the power system expansion, countermeasures by the solar PV system are
expected for the grid stability. A solar PV system has a possibility of unexpected trip
when a power system disturbance (voltage sag, etc.) occurs, which can cause the
power system collapse. To prevent such problem in the power system, FRT is
equipped, which is essential facility for PV systems.
The impacts on the grid and countermeasures are summarized in Table 2.1-1, and
detail is described below.
2-2
Renewable Energy Development Chapter 2
Final Report Advanced Technology for Grid-Connected Solar PV Systems
On the other hand, the capacity of thermal and hydro power should be kept
above certain level in order to keep the grid stability. If the excessive power is
generated by wind/PV power plants, the excess power should be either reduced
or stored. In Germany and Spain, the excessive power frequently appears as a
number of wind power plants have been installed increasingly.
The countermeasures and outlook for the above impact in both countries are as
follows.
2) Impact-2: Heavy power flow causes frequent critical grid condition with
small margin of N-1 criteria 3.
The following matters result in heavy power flow and critical grid condition.
- Many wind power plants are constructed at the same location and the
concentrated power from the plants is transmitted through the same
transmission line.
- The long distance transmission lines are required between the wind power
plants and demand area because the plants are constructed at the location far
from the demand area.
- Generated power by wind power plant is sometimes bigger than the planned
3 N-1 criteria means Criteria on grid condition during shortage of one(1) equipment, such as transmission line or transformer
2-3
Chapter 2 Renewable Energy Development
Advanced Technology for Grid-Connected Solar PV Systems Final Report
Grid stability must be kept sufficient under single fault (N-1) condition. When the
margin between N-1 criteria and actual power flow is not enough, grid operator
should execute emergency operation to keep the stability. Power reducing
operation of wind power plants is one of the countermeasures in the emergency
operation.
If the TSOs can get data/information of such severe condition in advance, the
co-operation will become easier. For grid co-operation to maintain the grid stability,
the analyses taking into account of power flow of unexpected power should be
carried out by a joint research unit set up by the related TSOs.
When a fault occurs in a grid, the voltage drops and frequency and power flow
are also disturbed. Under this disturbed grid condition, the conventional power
plants connected to the grid try to keep sending power to the grid, which helps the
grid recover from the disturbed condition. If it drops out of N-1 criteria, the
interconnection lines must be disconnected or the whole grid will corrupts at
worst.
The wind/PV systems do not have the modulation capability, and it stops
operation (parallel off from grid) when voltage drops and/or disturbed frequency
observed. This parallel off means an unexpected trip. When the total capacity of
wind/PV plants that have gone parallel off is too large, the gird collapses. To
2-4
Renewable Energy Development Chapter 2
Final Report Advanced Technology for Grid-Connected Solar PV Systems
solve this problem there is a technology developed which is called FRT function.
This function enables the inverters to keep operations when an instant voltage
drop and/or disturbed frequency encountered.
The FRT function is essential to avoid the unexpected trip and to keep the grid
stability. At present, requirement on FRT function for wind PV system is
stipulated in the grid codes in Germany, Spain and other countries.
2-5
Chapter 2 Renewable Energy Development
Advanced Technology for Grid-Connected Solar PV Systems Final Report
in this section for introduction of the grid protection. Grid stability and necessity of FRT
is described taking Marching people as an allegory.
Now, the five (5) persons are marching hand in hand as Fig 2.1-1-a.
When person C suddenly slips, the following three (3) cases will be occurred.
If the marching line consists of three (3) persons, strength of marching line is weaker
than five (5) persons line, and the Case 3 will frequently occur by slipping accident. If
it consists of seven (7) persons, the strength is stronger than five (5) persons line.
Grid stability is as the same as marching line. In case of large number of generators is
connected in the grid (many persons in the marching line), the grid stability will be
much stronger than in the case of small number of generators is connected.
In addition to the above, the strength of each generator (strength of each person) is
also key point to keep grid stability. PV plants without FRT function are weak for
keeping grid stability (such as Case 3), even though these have large capacity (MW).
When an accident occurs, the PV plants will fall down due to the weakness of the PV
plants (such as person B and D in Case 3). If many PV plants fall down by one small
accident such as slipping, the grid will go into severe condition and in worst case, the
grid will be fully collapsed (Case 3).
FRT function improves the strength of PV plant during accident. The requirement of
FRT function is Continuous Operation (continuous standing such as person B and D
in Case 2) to avoid grid collapse (Case 3), and it is not Recovery of grid fluctuation
(to help slipped person such as person B and D in Case1). Generally, the recovery of
grid fluctuation is one of the tasks of hydro and thermal power plants.
2-6
Renewable Energy Development Chapter 2
Final Report Advanced Technology for Grid-Connected Solar PV Systems
A B C D E
A B C D E
Person C slips
Fig 2.1-1-a
A B C D E A B C D E A B C D E
Person C is quickly helped Person C falls down but person Person C falls down and
without falls down, and B and C can be standing with person B and C also fall down,
marching will be quickly person A and E support, and in worst case, person A and E
restarted. marching will be restarted after also fall down, and marching
person C stands. cannot be continued.
2-7
Chapter 2 Renewable Energy Development
Advanced Technology for Grid-Connected Solar PV Systems Final Report
In view of the total supply-demand balance in PRC grid, the power supply is in short,
and the new transmission lines are under construction also in Golmud. HVDC 6
system is one of the new transmission lines. Generally, HVDC system has high speed
control system as well as large transmission capacity, and power flow through the
HVDC system can be changed and modulated using the high speed control in timely
manner. This power changing capability and modulation function are useful for
recovery from the fluctuation of grid voltage and frequency and disturbance in grid.
On the above situation, the huge power generated by PV power plants in Golmud will
be sent to the load center nearby and consumed in the areas. The planned capacity of
PV power is too much for demand in Golmud grid and grid operator concerns about
the uneasy grid operation because of huge power of PV systems.
The grid operator intends to reduce power generation efforts and to give trip order to
the PV power plants without prior announcement. The data/information to be acquired
in order to execute the intended operation is required by the grid operator.
Research of PV inversion technology was started in the 1950s or 1960s, when SCR 7
based sinusoidal wave PV inverters were used; in the 1970s, GTO/BJT was used in
PV inverters; in the 1980s, single-board computer technology and VMOSFET/IGBT/
MCT devices provided conditions for development of large capacity PV inverters; in
the 1990s, advanced control technologies such as DSP 8 signal processor and
multi-level exchange, vector control, fuzzy logic control and neural networks found
applications in on-grid PV inversion systems, with inversion efficiency of 91 ~ 94%;
since 2000, the development of high performance dedicated on-grid inversion
modules increased the performance of on-grid inverters, with inversion efficiency
being increased to about 96%.
Insulation with normal shock transformer is the main form of grid-connected solar PV
2-8
Renewable Energy Development Chapter 2
Final Report Advanced Technology for Grid-Connected Solar PV Systems
(1) Realizing high quality electric energy conversion, strict consistency of current
frequency and phase output from grid-connected inverters with the grid, so that
the output power factor is as close to 1 as possible;
(2) Realizing safety protection requirements for system, such as output overload
protection, output short-circuit protection, input reversed connection protection,
DC overvoltage protection, AC overvoltage and undervoltage protection, island
9 Building-integrated Photovoltaics
2-9
Chapter 2 Renewable Energy Development
Advanced Technology for Grid-Connected Solar PV Systems Final Report
(3) Realizing high reliability, now PV grid-connected solar PV systems are installed
mainly in areas with severe natural conditions, therefore inverters should ensure
low fault rate in long time operation conditions, with powerful self-diagnosis ability.
Therefore, the designed inverters shall have rational circuit structure and
elements shall be strictly selected;
The main principles for requirements on inverters are: large power inverters on the
basis of high efficiency and low harmonic content, shall have adjustable power factor,
participate in grid dispatching, and also FRT function, able to resist certain grid fault.
2 - 10
Renewable Energy Development Chapter 2
Final Report Advanced Technology for Grid-Connected Solar PV Systems
1) Inverter Functions:
2 - 11
Chapter 2 Renewable Energy Development
Advanced Technology for Grid-Connected Solar PV Systems Final Report
i) The AC output side of inverters shall be provided with power generation metering
function, to meet the requirement to measure the power generated by the
connected PV module.
c) Other indicators
- Power consumption during night: 100W.
- Communication interface: RS485 port.
- Service ambient temperature: -25C +55C (the inverters shall be able to
work continually and reliably within this temperature range).
(6) Inverters
Inverters shall have complete function to automatically synchronize with the grid, and
have active power and reactive power regulation ability. It also need to have overload
ability and able to operate over long time at an overload, and can only conduct current
in one direction. Inverters also requires complete protection functions, with
comprehensive protection strategies including DC overvoltage/undervoltage, AC
overvoltage/undervoltage, AC overcurrent, short-circuit, over/under frequency, and
system transient power.
2 - 12
Renewable Energy Development Chapter 2
Final Report Advanced Technology for Grid-Connected Solar PV Systems
The quality of electric energy provided from inverters to AC load shall be under control,
and it shall be ensured to measure all electric energy quality on inverter AC side
(harmonics, voltage deviation, voltage unbalance, DC components, voltage
fluctuation and flicker), which shall meet the requirements of national standards,
industrial standards, and of State Grid Corporation and local power supply
departments.
It is desirable to have low current and voltage harmonic level. High harmonics will
increase the possibility of harmful effect to the connected equipment. The
permissible level of harmonic voltage and current depends on the power
distribution system characteristics, power supply type, the connected loads and
equipment, and the current regulation of the grid. Output from a PV system shall
have low current distortion, to ensure that no detrimental effect will be caused to
other equipment connected to the grid. Harmonics of different orders shall be
limited within the percentages listed in the table below.
The permissible value of harmonic current injected from a PV power station to the
grid shall be distributed according to the ratio of the installed capacity of the
station to the capacity of power supply equipment at this common connection
point.
35 and
250 15 12 7.7 12 5.1 8.8 3.8 4.1 3.1 5.6 2.6 4.7
12
2 - 13
Chapter 2 Renewable Energy Development
Advanced Technology for Grid-Connected Solar PV Systems Final Report
(The power supply equipment capacity at the common connection point of the
project will be determined later as the connection system has not been
determined.)
2) Voltage deviation
The voltage fluctuation and flicker of inverters shall meet the provisions in GB/
T12326-2008 Power quality - Voltage fluctuation and flicker. The limit values of
voltage variation are related to variation frequency and voltage level.
The short time flicker Pst and long time flicker Plt shall meet the limits set forth in
the table below.
Table 2.2-4 Short Time Flicker Pst and Long Time Flicker Plt
System voltage level LV MV HV
Pst 1.0 0.9 0.8
Plt 0.8 0.7 0.6
Notes: 1. In this standard, the measuring cycle for Pst and Plt is respectively taken as 10min
and 2h;
2. Values in brackets for MV are only applicable to cases that all users connected with
PCC are at the same voltage level.
4) Voltage unbalance
When the PV system is operating on grid (only output to 3 phases), the 3-phase
voltage unbalance at the grid connection shall not exceed the values specified in
GB/T 15534, and the negative sequence voltage unbalance at common
2 - 14
Renewable Energy Development Chapter 2
Final Report Advanced Technology for Grid-Connected Solar PV Systems
connection point shall not exceed 2%, or not exceed 4% for short time. For this,
the negative sequence voltage unbalance caused by the PV power station shall
not exceed 1.3%, or not exceed 2.6% for short time.
5) DC component
6) Power factor
When the output from the inverters in the PV system is greater than 50% of its
rated output, the average power factor shall be no less than 0.9 (leading or
lagging). The formula of average power factor for a period of time is:
EREAL
Power Factor = 2 2
EREAL + EREACTIVE
A large or medium sized PV power station shall have some ability to withstand
voltage anomaly, to avoid disengagement in case of grid voltage anomaly,
causing loss of grid power source. It must be ensured that the PV power station
will not interrupt grid-connected operation when the voltage at the connection
point is in the area of and above the voltage profile line in Fig. 2.2-1, and the PV
power station is permitted to stop supplying power to the grid line when the
voltage at the connection point is in the area below the voltage profile line in Fig.
2.2-1. (T1 = 1s, T2 = 3s)
2 - 15
Chapter 2 Renewable Energy Development
Advanced Technology for Grid-Connected Solar PV Systems Final Report
1.1
1.0
ULO 0.9
0.8
0.6
0.4
0.2
0
-1 0 T1 T2
A large or medium sized PV power station shall have some abilities to withstand
frequency anomaly, being able to operate with the frequency deviation in the grid
as shown in the table below.
Table 2.2-5 Required Operation Time for Large or Medium Size PV Power Station
in case of Grid Frequency Anomaly
Frequency range Operating requirements
below 48Hz To be determined according to the minimum frequency at which the PV power
station inverters are permitted to operate or the grid requirements
48Hz-49.5Hz Able to operate at least 10min. when it is below 49.5Hz
49.5 Hz -50.2Hz Continuous operation
50.2 Hz -50.5Hz Each time the frequency is above 50.2 Hz, the PV power station shall be able
to operate continuously for 2min, but also with the ability to stop feeding power
to the grid line within 0.2s, with the actual operation time determined by the grid
dispatching entity; at this time, PV power station originally in shutdown state is
not allowed to be connected to the grid.
above 50.5Hz Stop feeding power to the grid line within 0.2s, and PV power station originally
in shutdown state is not allowed to be connected to the grid.
2 - 16
Renewable Energy Development Chapter 2
Final Report Advanced Technology for Grid-Connected Solar PV Systems
A PV power station shall have certain overcurrent ability, and it shall be able
to work continuously and reliably for no less than 1 min. up to 120% rated
current, and for no less than 10s within 120%-150% rated current. When
short-circuit on grid side is detected, the short-circuit current output from PV
power station to grid side shall be no greater than 150% of rated current, and
the PV system shall be disconnected from the grid within 0.1s.
b) Anti-island operation
The lightning protection and grounding for PV system and grid connection
equipment shall conform to the provisions in SJ/T 11127.
The system shall have the function to protect the grid from reverse discharge
to the DC side.
2 - 17
Chapter 2 Renewable Energy Development
Advanced Technology for Grid-Connected Solar PV Systems Final Report
2.3 MCM 13
2.3.1 Latest International Technologies for Master Control and Monitoring for
Grid-connected Solar PV System
It shall perform data acquisition, tapping and analysis, determine the working status
and attenuation of assemblies, inverters, bus compartments, transformers and power
transmission lines, monitor the station operation conditions in real-time, analyze
methods to increase efficiency and power generation, and optimize the operation of
the grid-connected PV station, direct assembly matrix cleaning and angle adjustment
according to monitoring data, make timely repair and maintenance of bus
compartments, inverters, sun tracking devices and electrical facilities, adjust the
operation strategy of the station, perform remote intelligent monitoring and rational
dispatching, to realize optimized operation of the grid-connected PV power station
and maximum electric energy output.
Level II, data center: it is the comprehensive management center at substation for all
subordinated PV power station data, mainly deployed with large sized real-time
database and backup real-time database, and historical data with long time duration
are filed into disc matrix. It also performs analysis and statistics of all sampled data, to
provide data basis for decision-making and analysis at high level. Meanwhile, video
server, mail server and printout server are arranged in the network.
2 - 18
Renewable Energy Development Chapter 2
Final Report Advanced Technology for Grid-Connected Solar PV Systems
Level III, data monitoring: the monitoring center at control center mainly displays
various data, concurrently providing both access modes as customer based and WEB,
plotters and integrated computer are provided, and dynamic display of data with
rolling play-out on large screen is adopted.
The electric power grids in the world share the same direction of development,
appropriate control and stability. In general, an electric power grid includes all types of
supply power sources (thermal, hydro, nuclear and renewable). Recently, renewable
power is highlighted, because its energy potential is rapidly exploited by recent
technology innovation. One of the latest international technologies of MCM for
grid-connected solar PV system is called as a smart grid.
- In case of a small grid which consists of small, limited demand and dispersed
renewable power source in a small area, and it is controlled efficiently.
- The smart grid is highly expected by its efficiently energy use and goes forward to
the practical use.
2 - 19
Chapter 2 Renewable Energy Development
Advanced Technology for Grid-Connected Solar PV Systems Final Report
2 - 20
Renewable Energy Development Chapter 2
Final Report Advanced Technology for Grid-Connected Solar PV Systems
and then planned operation of the facilities with the objective of stabilizing PV power
output was conducted taking countermeasures against the peak power in the system
(see Fig. 2.3-3).
Fig. 2.3-3 shows the results of basic output fluctuations preventive control testing with
the use of NAS 14 batteries (PV power generation: 2 MW, NAS batteries power
generation: 0.5 MW). On this site, the preventive control is conducted with the use of
NAS batteries by taking the moving average deviation (moving average time frame:
30 minutes) as a target value for output from the PV power plant. A comparison of PV
power outputs was done and found that outputs from the power plant were smoothed
(the maximum range of fluctuations in PV power outputs of 1,269 kW was reduced to
516 kW in outputs from the PV power plant) and control with NAS batteries was
effective.
5000 100
Remaining capacity of battery PV output
4000
80
3000
2000 60
Power plant output
1000 40
0
NAS output 20
-1000
-2000 0
4:00 6:00 8:00 10:00 12:00 14:00 16:00 18:00 20:00
On the site located in Hokuto City, Yamanashi Prefecture, a 2MW PV power plant was
constructed and introducing various types of PV modules centering on leading-edge
solar cells to operate and evaluate the plant as well as developed and demonstrated
technologies contributing to future spread and cost cutting of large-scale PV power
generation technologies through the development of a voltage-control,
harmonic-resistant large-scale PV inverter (see Fig. 2.3-4). Particularly, this inverter
became Japans first inverter with built-in FRT function (capability of continuing power
generation without disconnecting PV power generation in case of any system
disturbance).
14 Natlium Sulfur
2 - 21
Chapter 2 Renewable Energy Development
Advanced Technology for Grid-Connected Solar PV Systems Final Report
(3) Lessons learned from Demonstrative Research of Ota City and Wakkanai City
regarding the Smart Grid
Result of demonstrative researches in Ota City and Wakkanai City showed that the
problem of voltage increase of the residential PV system with grid-connection can be
improved economically by installing battery for only limited residents, not for all PV
residents. Applying this idea to a large-scale grid which has solar PV systems
connected to the Grid, it is effective to install the battery in the substations in the areas
that have solar PV systems. Measurement and load control by the smart grid have
been shown effective for stabilization of total power system.
If the estimation of PVs output is possible, "on time tariff" which will change time to
time may be possible by the smart meter. The smart meter can realize this dynamic
tariff system and demand control.
2 - 22
Renewable Energy Development Chapter 2
Final Report Advanced Technology for Grid-Connected Solar PV Systems
generated, and store power in batteries if necessary. And EMS at households controls
the demand side response.
Price Signal
Small Commercial PV System 1MW (US side) General House (with smart
Building meter equipped)
2 - 23
Chapter 2 Renewable Energy Development
Advanced Technology for Grid-Connected Solar PV Systems Final Report
2 - 24
Renewable Energy Development Chapter 2
Final Report Advanced Technology for Grid-Connected Solar PV Systems
Output Monitoring
(Monitoring fluctuations
Microgrid
in PV output)
5MW
Management on
US side
2.3.2 Locally Appropriate MCM System in terms of Reliability, Efficiency and Cost
Under normal operation conditions, a PV power station shall provide at least the
following signals to the grid dispatching center:
1) Telemetering quantities
2 - 25
Chapter 2 Renewable Energy Development
Advanced Technology for Grid-Connected Solar PV Systems Final Report
Bidirectional active power electric energy and bidirectional reactive power electric
energy of 10kV line
2 - 26
Renewable Energy Development Chapter 2
Final Report Advanced Technology for Grid-Connected Solar PV Systems
Operation control of the whole PV power station is realized in the central control room
and from remote dispatching center. When monitoring and control are normal, the
operation of all levels, equipment operation status and breaker status are all under the
monitoring by the computer supervisory system. When local operation is performed,
operation of station control level should be blocked. In case of a fault in the
supervisory system, a signal shall be immediately sent to the dispatching side and the
remote control is blocked.
The station control level equipment of a solar energy PV power station mainly
consists of system host computer and operator stations, engineer management
station, printer, GPS 20 time calibration device and network system. The bay level of
the PV power station is divided as primary cells, where all equipment and devices
shall meet the relevant IEC 21 standards.
The computer supervisory system consists of the station control level, bay level and
network equipment. The bay level network structure is in a ring structure. The station
control level is the monitoring, measurement, control and management center of
equipment in the whole station, it is located in the control center and connected via
optical cables with bay level. The bay level is arranged in corresponding switching
cabinets in a relatively independent way by different voltage levels and electrical cells,
and in case of failure of station control level and network, the bay level can still
independently perform monitoring and circuit breaker control functions.
The computer supervisory system realizes reliable, rational and complete monitoring,
measurement and control of the PV power station, and also has all remote functions
for telemetering, remote signaling, remote control and remote regulation, able to
exchange information with the dispatching communication center. Each substation
room is provided with a communication manager computer, the information of bay
level equipment is uploaded via optical fiber ring net to the central control room, for
communication with the system via communication interface devices.
2 - 27
Chapter 2 Renewable Energy Development
Advanced Technology for Grid-Connected Solar PV Systems Final Report
(1) The computer supervisory system shall have the following functions
Types of acquired signals are in analog and status quantities (digital quantities),
and the scope of acquisition is as follows:
22 Sequence of Event
2 - 28
Renewable Energy Development Chapter 2
Final Report Advanced Technology for Grid-Connected Solar PV Systems
All microcomputer protection, DC system, UPS system and fire alarm system
signals.
The electric quantity in the whole station is collected by intelligent 0.2S class
electronic energy meters, and information is sent to electric quantity collector
via RS485 interfaces or by optical fiber communication. The electric quantity
collecting device transmits information to the supervisory system via RS485
interfaces or by optical fiber communication.
ii) Overlimit alarm: dead zone determination and overlimit alarm are
performed by time period according to the set limits, and the alarm
messages shall include alarm text, parameter values and alarm time.
2 - 29
Chapter 2 Renewable Energy Development
Advanced Technology for Grid-Connected Solar PV Systems Final Report
iii) SOE records: for digital quantities such as circuit breaker position
signals and relay protection operation signals that require rapid
response, SOE recording shall be made according to the time sequence
of the changes.
iv) When the breaker accidental trips or opening operations have reached
the designated number, an alarm message should be sent to alert the
user to make maintenance.
2) Maintenance requirements
23 Man-Machine Interface
2 - 30
Renewable Energy Development Chapter 2
Final Report Advanced Technology for Grid-Connected Solar PV Systems
b) Logic operation definition for multiple digital and analog quantities, etc.
1) Picture display
2 - 31
Chapter 2 Renewable Energy Development
Advanced Technology for Grid-Connected Solar PV Systems Final Report
d) Users can generate, make and modify graphs. A graph made at one
workstation can be sent to other workstations.
e) The time scale and sampling cycle of voltage bar chart and curves can be
selected by user.
f) Each graph shall be indicated with calendar time.
g) Data lacking in the graphs can be manually inserted.
1) Online calculation
2 - 32
Renewable Energy Development Chapter 2
Final Report Advanced Technology for Grid-Connected Solar PV Systems
d) Various forms
e) Forms shall be stored by time sequence, and the storage quantity and time
shall meet user requirements. It shall be 1 day for hourly value reports, 1 day
for daily reports and 1 month for monthly reports.
4) Remote functions
The computer supervisory system shall have remote functions, and the remote
information, main technical requirements, information transmission mode and
channels shall meet the real-time, safety and reliability requirements for grid
dispatching.
The inverter shall realize successful joint commissioning with the dispatching side,
and simulation test shall be passed before factory acceptance.
The station will be provided with GPS time calibration equipment, and time calibration
for all bay level equipment will be based on network.
Man-machine interface is the window for dialogue between people and computer, and
dialogue with computer can be done conveniently via mouse or keyboard on the
LCD 24 screen. Man-machine interfaces include:
2 - 33
Chapter 2 Renewable Energy Development
Advanced Technology for Grid-Connected Solar PV Systems Final Report
In addition, the system shall have disconnecting points to facilitate testing and fault
isolation. Measuring and control units at bay level can be maintained with portable
computer.
The computer supervisory system can realize the following management functions
according to operation requirements:
1) Running operation guidance: put forth directive processing ideas for typical
equipment anomaly/accident, prepare technical statistics form on equipment
operation, and provide corresponding operation guidance graphs;
2) Accident analysis retrieval: perform classified retrieval and relevant analysis for
large number of alarm signals produced in a sudden event, and an accident
guiding graph should be provided directly for typical accidents;
3) Online equipment analysis: analyze operation records and historical record data
2 - 34
Renewable Energy Development Chapter 2
Final Report Advanced Technology for Grid-Connected Solar PV Systems
of main equipment, and put forth equipment safe operation report and repair plan;
It shall have remote diagnosis function and remote diagnosis software shall be
provided.
2 - 35
Chapter 2 Renewable Energy Development
Advanced Technology for Grid-Connected Solar PV Systems Final Report
The station is provided with a satellite clock synchronization system, to receive the B
code standard timing signal from the GPS system, to calibrate clocks in the station
computer supervisory system and relevant equipment such as relay protection
devices. The time calibration error between units shall be less than 1ms. Combined
soft and hard time calibration method will be used, clock expansion will adopt
synchronization and active contact mode, providing microcomputer-based protection
and fault wave recording for the whole station and pulse time calibration contacts for
other intelligent equipment.
Host and operator station: CPU with main frequency 2.6G or over, memory 2G or over,
hard disk 320G or over; monitor: 21 color LCD monitor (1280 1024); and dual
network cards.
Engineer station: the same configuration as the host and operator station.
The computer supervisory system shall use internationally prevailing and advanced
industrial software with standard version and software license, and it shall be in
modular structure, with good openness, reliable and mature, convenient and suitable.
It shall be possible for user to install and generate software system.
The workstations at station control level shall use a mature and open multi-task
operation system, which shall include operation system, compiling system, diagnosis
system and various software maintenance and development tools. The compiling
system shall be easy to interface with system supporting software and application
software, and support multiple programming languages. A real-time operation system
complying with industrial standard shall be used at bay level. The operation system
shall be able to prevent data file loss or damage, support system generation and user
program loading, support virtual memory and be able to effectively manage a number
of peripheral equipment.
2 - 36
Renewable Energy Development Chapter 2
Final Report Advanced Technology for Grid-Connected Solar PV Systems
1) Real time performance: it can quickly access to database and also meet the
real-time function requirements even in parallel operations.
4) Parallel operation: parallel access to the same data in the database by different
programs (tasks) shall be permitted, and completeness of database in parallel
mode shall be ensured.
7) Convenience: the database system shall provide two database generation tools
for interactive and batch processing, as well as database dumping and loading
functions.
10) The system configuration software is designed for graph programming and data
generation. It shall meet requirements of all functions of the system, to provide
user with an interactive, object-oriented, convenient and flexible, easy to master
and diversified configuration tool, and some programming means similar to
macro and multiple practical functions shall be provided, to expand the functions
of the configuration software. It shall enable user to generate and modify online
graphs, curves, forms and reports with great convenience.
2 - 37
Chapter 2 Renewable Energy Development
Advanced Technology for Grid-Connected Solar PV Systems Final Report
structure, with good real-time response speed and expandability. It shall have error
detection ability. In case of error in any application software, it shall not affect the
normal operation of other software, except for prompt error message. Application
programs and data shall be mutually independent in structure. System backup disk
shall be provided.
The computer supervisory system has much communication interface drive software,
mainly:
Cabinets (or panels), including all complete set equipment or individual assemblies
mounted on them, shall have sufficient mechanical strength and be mounted in a
correct manner. It shall be ensured that cabinets (or panels) will not be damaged
during lifting, transport, storage and installation. The general technical conditions for
relay cabinets and panels in power system shall be satisfied.
Tilt angle of PV array is generally designed to have the same angle as the latitude of
the site. When the diffused sunlight is taken into account, optimum tilt angle of PV
array may be different from the latitude. In this subsection, an assessment method
employing fish eye projection picture taken at the PV site is introduced, and features
of diffused sunlight are explained.
Assessment of insolation using fish-eye lens is effective in the case that the solar PV
2 - 38
Renewable Energy Development Chapter 2
Final Report Advanced Technology for Grid-Connected Solar PV Systems
system surrounded by the obstacles which disturb direct sunlight to the solar PV
system. It is programmed that the solar PV system accepts diffused sunlight and
direct sunlight. In general assessment of insolation has three ways shown as below;
ii) Assessment of insolation at the specific point by the observation of satellite which
is using data from the satellite and the data from the meteorological observatory
are combined and all area insolation can be assessed in the world.
iii) Assessment of insolation by using fish-eye lens which is using fish-eye lens is not
easy to assess insolation but it can assess the natural characteristics of
environment. It is necessary to use the three kinds of assessment methods case
by case.
(1) Fig. 2.4-1 shows the picture taken at the south west corner of 10MW pilot PV pilot
project site, facing the southern direction.
tower
picture : 2011/0713
2 - 39
Chapter 2 Renewable Energy Development
Advanced Technology for Grid-Connected Solar PV Systems Final Report
There are no mountains near the candidate site, no other PV power stations or
any constructions can be seen up to the foot of mountains except a slim tower
with the height of more than 100 meters for measuring wind velocity. There is no
obstacle to disturb direct sunlight. The land for 10MW pilot PV site is very dry and
seems to be the desert. Generally, obstacles to PV arrays are not easy to find
because solar orbit is changing day by day through a year and the location of the
sun is changing minute by minute. (Fig. 2.4-2)
Fish eye projection picture is drawn by the program developed. A solar orbit is
shown on the fish eye lens. An illustrative picture is shown below. Fish eye
projection picture is to be considered as the representation of the sunlight orbit. It
is the same projection on the PV module. (Fig. 2.4-3)
Obstacles
(Building, tree, etc.)
2 - 40
Renewable Energy Development Chapter 2
Final Report Advanced Technology for Grid-Connected Solar PV Systems
(2) PV module generates electric power not only by direct sunlight but also diffused
sunlight reflected by objects (building, tree, etc.). Some kind of objects in the
atmosphere, especially cloud makes diffused sunlight and it will reach 20 ~ 30%
of total intensity. The area of the sky covered by clouds is presented in solid
angle (the surface area of a sphere). (Fig. 2.4-4)
Cloud
Direct Sunlight
Diffused Sunlight
Fig. 2.4-6 was taken by the camera using fish-eye lens. Fish eye lens and
camera for it is shown as in the Fig. 2.4-5.
Fig. 2.4-5
Single-lens Reflex Camera and Fish-eye Lens
2 - 41
Chapter 2 Renewable Energy Development
Advanced Technology for Grid-Connected Solar PV Systems Final Report
sun
tower
horizon
picture: 2011/07/16
The photo shows the surroundings of the PV array which is to be set and sky and
sun at the same time. From Fig. 2.4-6 it is seen that there is nothing to disturb the
sunlight orbit passing on PV arrays. The tower seen in Fig. 2.4-1 is too slim to
disturb the sunlight reaching PV array in this picture. The visible area of fish-eye
lens is wide enough to see all direction from the PV site. As shown in Fig. 2.4-7,
the scenery of semi-sphere is covered by one picture.
2 - 42
Renewable Energy Development Chapter 2
Final Report Advanced Technology for Grid-Connected Solar PV Systems
North
East West
South
picture: 2011/07/13
Using this picture it is possible to estimate insolation not only by direct sunlight,
but also diffused sunlight projected on the fish-eye lens (= the PV array). Cloud
near the sun is gleaming and this kind of cloud contributes to the diffused
sunlight.
Picture
Solar orbit is drawn as in
Fig. 2.4-8 Solar Orbit
Fig. 2.4-8.
2 - 43
Chapter 2 Renewable Energy Development
Advanced Technology for Grid-Connected Solar PV Systems Final Report
Dots in the picture show the position of the sun at every hour. The orbit of the sun on
22/03/2011, the day of the spring equinox, is shown in a straight line in Fig. 2.4-9.
North
East West
1 hour interval
: Winter
: Spring
Horizon
: Summer
South
The picture overlaid on the fish eye lens is Fig. 2.4-10, which shows whether any
obstacles for PV power generation are existent or not.
2 - 44
Renewable Energy Development Chapter 2
Final Report Advanced Technology for Grid-Connected Solar PV Systems
North
East West
: Winter
: Spring
: Summer
South
Fig. 2.4-10 Solar Orbit on Fish-eye Lens at the 10MW Pilot PV System Site
The tower located in the south which will give influence to sunlight orbit is negligible
as the obstacle because the tower is not seen in Fig. 2.4-10. Although the picture was
taken on July 16, 2011, the orbit of the sun from sunrise to sunset in every season can
be shown on the picture. This is the most important factor in the estimation of
generation of solar PV system.
Estimation of insolation for the site for 10 MW Pilot Project by QBE25 was presented
in their Feasibility Study Report (see Table 3.1-2 of Section 3.1.1.1). Comparing
26
their result with NASA 's 25 years average data, and the estimation with fish-eye lens
method shown in Table 2.4-1
Jan. Feb. Mar. Apr. May Jun. Jul. Aug. Sep. Oct. Nov. Dec. Total
QBE site 145.3 147.2 179.7 201.8 214.5 199.4 201.7 210.1 193.0 195.6 165.2 143.3 2197
NASA 176.7 168.3 196.9 193.8 186.3 167.4 170.5 172.1 168.0 198.4 179.1 169.0 2146
fish-eye 135.2 129.9 169.6 183.6 189.7 173.4 197.8 222.0 221.7 209.3 179.4 147.9 2159
2 - 45
Chapter 2 Renewable Energy Development
Advanced Technology for Grid-Connected Solar PV Systems Final Report
Fish eye lens method makes reference to NASA's yearly anticipation data. Three
different methods give different results for each month, but yearly insolation is not so
different and within a margin of a few per cent. Table 2.4-2 shows ratios of monthly
insolation estimation made by three different methods. Estimation by QBE value is
expressed 1.00 as basis index.
Using fish-eye lens projection system, power generation is estimated through the
whole year.
1) Estimation of insolation of direct sunlight was calculated by the solar orbit of each
month and hourly change of sunlight projection.
3) The power generation was calculated by the estimated insolation considering the
temperature rise of PV panel which reduced power generation. The result is
shown in Table 2.4-3.
Table 2.4-3 Estimation of Power Generation using Fish-eye Lens (Tilt angle 35)
Insolation with Average Power generation on Power generation on
month tilt angle 35 temperature direct current side alternative current
[kW/m2day] [C] [kWh/month] side [kWh/month]
1 4.36 -6.2 1,209,688 1,149,204
2 4.64 -3.1 1,140,868 1,083,824
3 5.47 1.9 1,450,160 1,377,652
4 6.12 7.2 1,539,550 1,462,572
5 6.12 11.6 1,535,355 1,458,587
6 5.78 16 1,381,272 1,312,208
7 6.38 18.6 1,536,558 1,459,730
8 7.16 17.7 1,707,878 1,622,485
9 7.39 12.9 1,752,311 1,664,696
10 6.75 6.4 1,681,482 1,597,408
11 5.98 0.7 1,484,350 1,410,133
12 4.77 -3.9 1,288,771 1,224,332
Total 70.93 6.65 17,708,243 16,822,830
2 - 46
Renewable Energy Development Chapter 2
Final Report Advanced Technology for Grid-Connected Solar PV Systems
Table 2.4-4 Estimation of Power Generation using Fish-eye Lens (Tilt angle 25)
Estimated energy at the tilt angle 25 was slightly bigger than that of tilt angle 35.
Suggestion that the maximum power generation by the pilot PV system can be
attained with tilt angle somewhere between 35 and 25. Therefore it is recommended
to observe the insolation by using test PV panels which are set at different tilt angles
between 35 and 25.
The relationship between supply and demand control and prediction factors is shown
in Fig. 2.4-11.
2 - 47
Chapter 2 Renewable Energy Development
Advanced Technology for Grid-Connected Solar PV Systems Final Report
Insolation estimation is important for supply and demand control. Since several
kinds of estimation period (every 30 minute, 1 minute to several minutes interval, one
second level interval) are required for appropriate supply and demand control,
weather forecast methods for these periods have to be developed.
1) As for short interval control (second level interval), the control based on the short
period prediction is difficult to apply and the high speed response equipment (the
battery and electric double layer capacitor and so on) is developed for this short
period fluctuation control.
2 - 48
Renewable Energy Development Chapter 2
Final Report Advanced Technology for Grid-Connected Solar PV Systems
Solar PV system generates electricity by direct and diffused sunlight and the strength
of diffused sunlight is 20 ~ 30% of the strength of direct sunlight. When the shadow of
cloud is projected on the PV array, power generation is reduced rapidly. This
phenomenon is the biggest problem for the power grid administrator in maintaining
the stability of the power grid. Therefore it is very important to predict the abrupt
change of generation power before it happens. In this subsection prediction of cloud
and its impact on power generation is described.
1) Macro Prediction
It is possible to predict the movement of cloud for a few hours or for a few days in
a macro view. However, it is impossible to acquire the concrete influence of a
small cloud at the PV site even by using satellite imagery.
Fig. 2.4-12 shows illustration of satellite photo. It is possible to predict roughly the
2 - 49
Chapter 2 Renewable Energy Development
Advanced Technology for Grid-Connected Solar PV Systems Final Report
Fig. 2.4-12 shows rough prediction of the cloud influence by 100 km scale
evaluation and it is applicable to the satellite photos in Golmud.
15hour, 04/03/2012
Met-satellite
Cloud
Fig. 2.4-12 Macro Prediction System Fig. 2.4-13 Graphics by the Weather
Satellite
2) Micro Prediction
On the satellite photo of this scale even the large PV power stations is merely a
dot. To predict the shade of cloud it is necessary to measure the shade at the site.
To predict the influence of cloud, the shade of clouds on the ground must be
forecasted for next minute or hour. Fig. 2.4-14 shows a possible way to predict
the shade. To forecast a cloud that interrupts the sunlight it is necessary to locate
clouds continuously and set them on the way of the sun path.
2 - 50
Renewable Energy Development Chapter 2
Final Report Advanced Technology for Grid-Connected Solar PV Systems
North
summer solstice
A
B
C
East West
equinox
winter
Fig. 2.4-14 shows the sun orbit in Golmud. It is possible to evaluate influence of
PV power generation to observe the site. Macro and micro prediction methods
are combined, and it provides useful information to predict power generation and
supply and demand control of the power grid.
For evaluating the sunlight of the site, it is important to assess the weather of the
site. In general meteorological data shows monthly days of fine, cloudy and rainy.
2 - 51
Chapter 2 Renewable Energy Development
Advanced Technology for Grid-Connected Solar PV Systems Final Report
Looking at these data, there is higher possibility that the sky is cloudy or rainy than
fine at Golmud. Cloud is one of major source of diffusion sunlight and having clouds in
the sky may not hinder PV generation that much.
It is often said that reflection of sunshine from PV modules disturbs driver who is
driving a car or gives uncomfortable feeling to some people in Japan. When such
case happened, the azimuth of PV panels is obliged to change. Fish-eye lens is
enabled to see whether reflection light of PV modules happens or what time it
happens. How to obtain reflection sunlight is shown in Fig. 2.4-15.
2 - 52
Renewable Energy Development Chapter 2
Final Report Advanced Technology for Grid-Connected Solar PV Systems
Picture image
Reflection
sunlight Center line
Reflection
Incident sunlight
2
1 sunlight
L1
center
Incident
Fisheye lens sunlight
L2
Tilt angle
Fig. 2.4-16 shows that reflection of sunlight projection to which gives the influence to
the objects (cars and/or people) is shown only in the morning and evening at summer
season. Thus, the fish eye lens can evaluate reflection of sunlight which affects
influence to the objects (cars and/or people) through a year.
North
Reflection
sunlight
projection
East West
South
2 - 53
Chapter 2 Renewable Energy Development
Advanced Technology for Grid-Connected Solar PV Systems Final Report
RETScreen is a tool that makes it easier for planners, decision-makers and industry to
consider energy efficient and RE technologies at the critically important initial planning
stage. This tool provides the following functions:
RETScreen can simplify preliminary evaluations with relatively little user input and
calculate key technical and financial viability indicators automatically. Based on cash
inflows, such as energy sales, fuel savings, incentives and production/GHG29 credits,
and cash outflows, such as equity investment, annual debt payments, O&M payments
and periodic costs, RETScreen shows NPV30, simple payback, IRR31 and etc. as
indicators. It also draws the curve of cumulative cash flow. A demonstration of
RETScreen usage for a PV project is shown below:
Basic project information such as project name, location, technology and type are
input as shown in Fig. 2.5-1. A user has to enter information in the yellow cells, but the
blue cells are optional. Here, in the cell of Analysis type, "Method 1" is a simplified
single spreadsheet option, and "Method 2" is a more detailed approach. After
specifying Golmud for Climate data location, and by selecting select climate data
2 - 54
Renewable Energy Development Chapter 2
Final Report Advanced Technology for Grid-Connected Solar PV Systems
location, the Golmud site data is downloaded from the Internet and shown as in Fig.
2.5-232. Fig. 2.5-1 and 2.5-2 are in the Start sheet of RETScreen.
In the Energy Model sheet (Fig. 2.5-3), Dairy solar radiation tilted (kWh/m2/d) is
shown and by specifying some technical parameters for PV system and inverter,
monthly Electricity exported to grid is calculated. Annual exported electricity to grid is
estimated to be 15,008MWh 33 in this case, a little smaller than the result of
Consultants study in this report. And user specifies Electricity export rate here.
32 In Fig. 2.5-2, Heating design temperature is the minimum temperature that has been measured for a frequency level of at
least 1% over the year, and Cooling design temperature is the minimum temperature that has been measured for a
frequency level of at least 99% over the year. Both parameters are used to estimate heating/cooling energy demand and are
not used in Golmud case.
33 This value is smaller than 16882.8MWh in Table 2.3-1, because latter value is estimated by the analysis with fish-eye lens to
take into account diffusion lights.
2 - 55
Chapter 2 Renewable Energy Development
Advanced Technology for Grid-Connected Solar PV Systems Final Report
Fig. 2.5-4 is the Cost Analysis sheet. A user specifies all the initial and operating
costs here. Cost estimation of 10MW Pilot PV system for Golmud is shown in Table
4.2-1. Total of equipment installation, building construction and other construction cost
are entered in Road construction cell, and ones of power conditioner, other
equipment and central control in the user specified Power Conditioner, Other Equip.
& Central Control cell. O&M cost is 7% of years depreciation as shown in the Section
4.2.
2 - 56
Renewable Energy Development Chapter 2
Final Report Advanced Technology for Grid-Connected Solar PV Systems
In the Financial Analysis sheet, a user specifies Financial parameters (Fig. 2.5-5)
and Annual income (Fig. 2.5-6). In 10MW Pilot Project case, there are not only
income tax but also VAT and additional tax. Unfortunately RETScreen doesnt have a
cell in which VAT and additional tax are input, so these values are entered in the cells
Other income (cost). In the Section 4.2, annual deterioration of output of the PV
system is assumed at 0.8%. To take this into account, -0.8% is input in the cell
Escalation rate in Electricity export income and Other income (cost).
Fig. 2.5-5 Input of Financial Parameters Fig. 2.5-6 Input of Annual Income
2 - 57
Chapter 2 Renewable Energy Development
Advanced Technology for Grid-Connected Solar PV Systems Final Report
2 - 58
Renewable Energy Development Chapter 2
Final Report Advanced Technology for Grid-Connected Solar PV Systems
At an early stage of feasibility study, we often have many uncertainties about many
project variables. The result of financial analysis is subject to errors and variations
due to such uncertainties. A user can check risks on uncertain input data by the Risk
Analysis sheet of RETScreen.
2 - 59
Chapter 2 Renewable Energy Development
Advanced Technology for Grid-Connected Solar PV Systems Final Report
RETScreen can show how the viability of the project changes when two key input
parameters vary simultaneously. Fig. 2.5-11 is an example of such a sensitivity
analysis. A user can evaluate the impact on the after-tax IRR-equity of fluctuations of
initial cost and electricity export rate, O&M cost and other cost (VAT 34 & additional
tax) for plus/minus 25% deviation. If we have the higher tariff at CNY 35 1,420 per
MWh shown in Table 4.2-4, the after-tax IRR-equity can be improved to approx. 6%.
To attain IRR more than 9%, initial cost have to be reduced by 25% and electricity
export rate shall be raised by 25%.
This kind of exercise can be made without special knowledge with RETScreen.
RETScreen has a Risk Analysis Model based on a Monte Carlo simulation which is
a method whereby a probability distribution of possible financial indicator outcomes is
generated by using randomly selected sets of values as input parameters, within a
predetermined range, to simulate possible outcomes. A predetermined range is
specified as Level of risk, the percentage of probability that the values fall outside
the confidence interval (e.g., an 80% confidence interval has a 20% level of risk). An
example of Monte Carlo simulation result on after-tax IRR-equity is shown in Fig.
2 - 60
Renewable Energy Development Chapter 2
Final Report Advanced Technology for Grid-Connected Solar PV Systems
2.5-13 36. With this result, we can see that the IRR will fall within the range of 3.40.4%
with approx. 12.5% probability, and there is only a 20% probability that the IRR will fall
outside the range between 1.7% and 5.0%.
36 In Fig. 2.5-13, vertical axis is Frequency and horizontal axis is After-tax IRR-equity.
2 - 61
Renewable Energy Development Chapter 3 Capacity Development in the Planning, Design,
Final Report Construction, and O&M of a Grid-connected Solar PV System
CHAPTER 3
The system consists of i) 300-kW solar PV system (PV system), ii) 75-kW output
power stabilization system (EDLC system), iii) 300-kW bi-directional inverter
(converter) for grid connection, iv) Inverter to supply power to loads, v) Monitor and
control system, and vi) Low-voltage incoming panel all shown in Fig.3.1-1.
3-1
Chapter 3 Capacity Development in the Planning, Design, Renewable Energy Development
Construction, and O&M of a Grid-connected Solar PV System Final Report
iii) Bidirectional
CNV inverter
300kVA (converter) for
DC bus bar (DC unit) grid connection
Power Power
collector collector
Electric double-layered
capacitor, 1 kWh
The system shown above is designed to output electric power that is output from the
PV system (i) and smoothed by the EDLC system (ii) to the low-voltage power
distribution line via the Converter (iii) and the low-voltage incoming panel (vi), and
also to supply power from the inverter (iv) to load using the DC bus bar as the powder
supply. The monitor and control system (v) is designed to record and make
measurement of system protection/control data such as voltages and currents of all
sections as well as analysis/assessment data such as the amount of solar radiation
and temperatures, and further to control the whole system.
3-2
Renewable Energy Development Chapter 3 Capacity Development in the Planning, Design,
Final Report Construction, and O&M of a Grid-connected Solar PV System
Fig. 3.1-3 Results of Tests of EDLC Effect with PV Output forcedly varied
at 1-Hz Frequency (With EDLC not controlled)
3-3
Chapter 3 Capacity Development in the Planning, Design, Renewable Energy Development
Construction, and O&M of a Grid-connected Solar PV System Final Report
Power (kW)
Fig. 3.1-4 Results of Tests of EDLC Effect with PV Output forcedly varied
at 1-Hz Frequency (With EDLC controlled)
3) It was verified that the inverter started up in a period of 1.14 seconds for the
targeted value of the order of 2 seconds. As conclusion, when the RE, such as
solar PV system is increasingly interconnected to the power grid system, the
EDLC equipment combining the solar PV system is very efficient to compensate
output of solar PV system and stability the grid system.
3-4
Renewable Energy Development Chapter 3 Capacity Development in the Planning, Design,
Final Report Construction, and O&M of a Grid-connected Solar PV System
As condition, when the RE, such as solar PV systems are increasingly interconnected
to the power grid system, EDLC equipment combining solar PV system is very
efficient to compensate output of solar PV system and stabilize the power grid.
(1) Premise
- Reverse power flow: Excess electricity flow back into the power system.
The KANSAI Electric Power Co., Inc. constructed a 10 MW solar PV system in Sakai
City, Osaka Prefecture, Japan (Sakai Mega Solar PV Power Station).
3-5
Chapter 3 Capacity Development in the Planning, Design, Renewable Energy Development
Construction, and O&M of a Grid-connected Solar PV System Final Report
Different types of solar panels have different conversion ratios. The area required to
install a 10MW solar panels depend on the type of panel. Even if the cost of solar
panel is lower, high land cost and high construction cost may result in rather
expensive total cost. Table 3.1-2 shows the relationship between type of solar panel
and occupied area for 10 MW and Fig. 3.1-5 shows relationship between cost and
efficiency of solar panel.
3-6
Renewable Energy Development Chapter 3 Capacity Development in the Planning, Design,
Final Report Construction, and O&M of a Grid-connected Solar PV System
Total cost
Cost
The value of solar PV system is comprehensively evaluated taking into account the
bid price and degradation ratio of PV panel in addition to predetermined system cost
and annual production.
System cost
Solar Panel Cost Cumulative total of
Unambiguously determined
Manufacturers bid + + land cost and
considering the conversion ratio and
price property tax
Evaluated value panels of solar battery
=
(yen/kWh) Degradation ratio
Annual energy Manufacturer's declared value
x x 20 years
production (20-year guarantee equivalent to
Western countries)
Fig. 3.1-6 Evaluated Value for the Solar PV System Cost
There is unequal sinking at the basement of the solar PV system and special
mounting hardware was developed for its countermeasure.
3-7
Chapter 3 Capacity Development in the Planning, Design, Renewable Energy Development
Construction, and O&M of a Grid-connected Solar PV System Final Report
1. Substructure
Conventional substructure: A steel platform supports the solar battery
panel frame. Solar battery
Solar battery
Hardware on the
Used metal 700t solar panel side
Hardware on the
Current substructure: directly fixed on the concrete concrete block side
foundation using mounting hardware
Backward concrete Hardware on the Rotation
foundation (50cm high) solar panel side Concrete block Lateral shear
Mounting hardware
Front concrete
Mitigate strain due to settlement by lateral shear and rotation.
foundation (20cm high)
Possible to correct shear following unequal shear.
2. Demonstration
test
Before After
settlement settlement
Rotation
Shear
Forced
stettlement
The mounting hardware can accommodate a 6 ~ 8cm unequal settlement without any problem
with its applicability.
Fig. 3.1-7 Countermeasure of Unequal Settlement
Compact basements of the solar PV panels can realize easy installation of the solar
PV panels.
3-8
Renewable Energy Development Chapter 3 Capacity Development in the Planning, Design,
Final Report Construction, and O&M of a Grid-connected Solar PV System
Although the fluctuation ratio of solar insolation at individual location points is rather
high, the averaged fluctuation becomes smaller due to off-setting effect. It is planned
to analyze the data to development of supply and demand control system.
Fluctuation
ratio
Kobe Substation Higashisumiyoshi
Office
Fluctuation ratio
ratio
Fluctuation
*Assuming 1000W/m2 solar
Fluctuation ratio averaged over 60 points
radiation as 100%
The measured solar radiation will be utilized to verify and improve the accuracy of the
method of prediction of PV output. Research programs are under progress on the
prediction of insolation by means of the weather forecasting system. With a high
level of errors in the prediction, it is necessary to develop new technologies to improve
the accuracy of prediction.
3-9
Chapter 3 Capacity Development in the Planning, Design, Renewable Energy Development
Construction, and O&M of a Grid-connected Solar PV System Final Report
[Numerical prediction]
Data on atmospheric pressure,
Attenuation by
temperature, wind transmitted
radiation
Amount of solar
atmosphere
from all over the world are
Atmospheric pathway
processed by the computer to
Amount of water vapor
predict future weather
Degree of air pollution
conditions.
Attenuation by clouds
Amount of upper clouds
Amount of mid-level
clouds
Amount of lower clouds 7 8 9 10 11 12
Water vapor
Comparing with the actual amount of solar radiation measured on the roof of
Kansais Research institute (one point), some predicted values deviate from
the measurement. It is planned to verify and improve the accuracy of
Ground observation data prediction based on the amount of solar radiation measured at several points.
Atmospheric pressure,
Satellite data temperature, wind
Visible image Amount of solar radiation
3 - 10
Renewable Energy Development Chapter 3 Capacity Development in the Planning, Design,
Final Report Construction, and O&M of a Grid-connected Solar PV System
Forest of co-
existing
Minato Sakai
Green Square
Sakai No.7-3
District
Sakai Mega Solar PV Power Station in the Demonstration project of KANSAI Electric
Power and there are several items to be verified shown in Table 3.1-1.
1) Construction cost is consist of several elements (solar panel cost, land cost, etc.)
Therefore to integrate those element costs and to evaluate total cost is essential.
2) Installation method which is variable due to the site condition also give influence
to the total construction cost. In Sakai case, special hardware which can fix the
PV panel easily to the concrete foundation and compact foundation were
developed.
3) Geographically spread PV systems make their total output fluctuation smaller than
each output fluctuation due to off-setting effect. For Qinghai Province, which has
vast area, geographical smoothing effect can possibly be an interesting option for
stabilization of total output of PV systems connected to the grid.
3 - 11
Chapter 3 Capacity Development in the Planning, Design, Renewable Energy Development
Construction, and O&M of a Grid-connected Solar PV System Final Report
Insolation Estimation
Insolation is automatically estimated using computer program of QBE. The input data
is gotten from meteorological neighboring observatories.
3 - 12
Renewable Energy Development Chapter 3 Capacity Development in the Planning, Design,
Final Report Construction, and O&M of a Grid-connected Solar PV System
Insolation value is very good, and if it is compared with other areas insolation,
Golmud site will be one of the best places to get insolation in the world.
Best tilt angel 36 is calculated by QBE.
Joint site reconnaissance of Golmud 10 MW Pilot Project Site was conducted with
QBE engineers and the Consultant in July 2011. Golmud is a vast barren area and
there seems to have little rain throughout the year by the data of neighboring
observatories. There is also NASAs data available for the region but the
precipitation is not known from satellite-image based on NASAs data.
Generally speaking, appropriate site conditions for PV power generation are listed
below;
1) Good insolation,
2) Sufficient flat land to install PV modules,
3 - 13
Chapter 3 Capacity Development in the Planning, Design, Renewable Energy Development
Construction, and O&M of a Grid-connected Solar PV System Final Report
Golmud site satisfies conditions 1) to 3) mentioned above. For the condition 4) a solar
PV system developer has to construct transmission line to the nearest substation at
his own responsibility. This is a standard procedure in PRC. For the condition 5) there
are no big rivers or high mountains on the way from main road to site that may hinder
the transportation of equipment, etc. For the condition 6) although there is no water
supply available at the site, some alternative measures, such as using water tank to
transport water to the site, is exist. For the condition 7) the meteorological data shows
that there is relatively strong wind from west. According to the design engineer of
QBE, there has not been reported that PV arrays of the existing solar PV power
stations were damaged by strong western wind in the past at the site. For the
condition 8), sandy wind at the site can be a matter of concern. In the maintenance
of solar PV power station, cleaning the accumulation of sandy dust on PV modules
can be a problematic issue.
Although there are some conditions at the site that are not favorable to solar PV
power generation, Golmud site is considered as very suitable site for solar PV power
generation.
(i) It is well known that solar PV system generates power not only by the direct
sunlight but also diffused sunlight from surroundings. However there is no
standard evaluation method of diffuse sunlight. There are many solar PV systems
which tilt angle of the solar panels is the same as the latitude of the site but the
diffused sunlight should be considered for power generation of the solar PV
system. If defused sunlight effect is counted into power generation of solar PV
system, it is better that the tilt angle of the solar panels is lower than the latitude.
(ii) Recommendation
Therefore it is recommended to have lower tilt angle of the solar panel for the
Golmud PV system to increase of power generation of the solar PV system.
Further, lower tilt angle of solar panel reduces the cost of support structure and
makes maintenance of solar panels easy. The lower tilt angle of solar panel helps
cleaning the surface of the solar panels.
3 - 14
Renewable Energy Development Chapter 3 Capacity Development in the Planning, Design,
Final Report Construction, and O&M of a Grid-connected Solar PV System
QBE provided the Consultant some drawings from their F/S report of 10MW Pilot
Project. The system configuration is shown Fig.3.2-2.
From operation and maintenance point of view, this configuration is clear and will not
cause misunderstanding, which is an important element in designing solar PV system
configuration.
3 - 15
Chapter 3 Capacity Development in the Planning, Design, Renewable Energy Development
Construction, and O&M of a Grid-connected Solar PV System Final Report
protection relay is placed at secondary side of the main transformer or each inverter
has one set of protection relay inside the inverter. The Consultant found that they
need to discuss with power utility company whether the islanding detector is
necessary or not, but there was no chance available to do so. The Consultant is of
the opinion that islanding phenomena would not happen in this solar PV system
configuration, because there are no loads between the solar PV system and the
substation which receive power from the solar PV system.
P
D1 D3
S/S
D2
P
D1 D3
S/S
D2
S/S
P: PV generation power
Fig. 3.2-3 Islanding Phenomena
D: Demand power by consumer
and Possibility of Occurrence
3 - 16
Renewable Energy Development Chapter 3 Capacity Development in the Planning, Design,
Final Report Construction, and O&M of a Grid-connected Solar PV System
10MW Pilot Project was designed to withstand the wind load of 0.45N/m2. This design
factor comes from the technical standard of PRC. Wind load was evaluated with
reference to the load code for the design of building structure. Design wind in the
code is for the extreme wind with recurrence period of 100 years.
PV array Switch
board
Switch Power
board conditioner Lower voltage
panel
Transformer
3 - 17
Chapter 3 Capacity Development in the Planning, Design, Renewable Energy Development
Construction, and O&M of a Grid-connected Solar PV System Final Report
It is designed that all the power generated by the pilot solar PV project is to be sold to
the grid and on the other hand the auxiliary power for the system is to be purchased
from the grid. This is because the power generated by pilot solar PV is sold to the grid
by higher tariff than the tariff of the power for auxiliary use is purchased from the grid.
Fig. 3.2-5 Electricity for Station Use at a Pilot 10MW Solar PV System
The resistance of national regulation for earthing requires less than 4 , and the
10MW pilot solar PV project will be 0.18 ~ 0.28 by their earthing design. It is very
satisfied because earthing value changes season by season. After the rain the
earthing resistance is decreased and in dry season it is increased. The earthing
resistance of the 10 MW solar PV system is satisfied in all season.
3 - 18
Renewable Energy Development Chapter 3 Capacity Development in the Planning, Design,
Final Report Construction, and O&M of a Grid-connected Solar PV System
3.2.4 Construction
Although the information on the organization for operation and maintenance of 10MW
Pilot PV Project has not been disclosed, the Consultant assumed that QBE acquired
sufficient operation and maintenance experiences and knowledge with their own 300
kW installation. Their experience and knowledge of operation and maintenance with
300kW plant were enough to operate and maintain a 10 MW pilot solar PV system. A
10MW pilot solar PV system demands more sustainability and efficiency. The
Consultant expects QBE accumulate more experience with larger solar PV system
and verify the performance of 10 MW Pilot Solar PV Project.
Design total loss before the inverter was 10%. Then the capacity of inverter could be
enough to have 90% of the capacity of the solar PV panels. Specifications of inverters
may be offered unilaterally by the inverter manufacturer; still it is important here that
the user engineers understand each item of the specifications. Users understanding
of the specifications of inverter should be at the same level as manufacturers
engineers. There are several steps to be taken to improve the knowledge of user
engineers.
3 - 19
Chapter 3 Capacity Development in the Planning, Design, Renewable Energy Development
Construction, and O&M of a Grid-connected Solar PV System Final Report
The life of a transformer is estimated based on the maximum utilization factor and the
load factor and the life measurement method of transformer is established at present.
Considering the fact that the utilization factor of the solar PV system in the night
period is zero, less than 90% of inverter capacity is good enough for the capacity of
the transformer. Generally speaking, a transformer has overloading capacity. It
depends on the insulator used in transformer, the load factor and ambient
temperature. Load factor of a transformer used for a grid-connected PV system will
be less than 0.3, and air temperature is not high in Golmud compared with Japans
case. It may be worth considering transformer capacity with smaller capacity than
PV system capacity. Of course there is a need to investigate how much the
maximum power is, how many hours the continuous operation is, and how often
appear in appropriate period.
Half life time period of Class F insulation transformer depends on every +8C rise.
3 - 20
Renewable Energy Development Chapter 3 Capacity Development in the Planning, Design,
Final Report Construction, and O&M of a Grid-connected Solar PV System
ln2
b= = 0.0866
8
H = k1.6 (o + g) + a
Under continuous operation at a rated load, the life time of transformer Y0 will be 20 ~
30 years. Life time of different load factor Y is expressed as below.
Y
= e-b(-145) = e-0.0866 (-145)
Y0
This is the result of continuous overloading condition. Using load factor 0.3,
transformer lifetime is estimated over 1000 years by this calculation. Purchasing a
transformer of this life time is not economical. Therefore, the size of the transformer
can be reduced, by allowing to have some over-loading situations.
3 - 21
Chapter 3 Capacity Development in the Planning, Design, Renewable Energy Development
Construction, and O&M of a Grid-connected Solar PV System Final Report
In case of fault occurred, the fault current is flown into the circuit breaker from not only
upper side of the power grid but also from other solar PV systems. It is necessary to
discuss with the reasonable power company about the short circuit capacity as the
short circuit current depends on the impedance of transmission lines.
The consultant considers that the lightning protection of 10MW Pilot Project has been
designed well. However, arresters should be carefully chosen.
Fig. 3.3-2 and Table 3.3-1 show the wave shapes of the test current which represent
direct lightning current and induced surge current.
3 - 22
Renewable Energy Development Chapter 3 Capacity Development in the Planning, Design,
Final Report Construction, and O&M of a Grid-connected Solar PV System
100kA
10/350s
8/20s
10s
t (s)
LPZ 0 LPZ 1
LPZ 2
LPZ 3
3 - 23
Chapter 3 Capacity Development in the Planning, Design, Renewable Energy Development
Construction, and O&M of a Grid-connected Solar PV System Final Report
LPZ 0 Zone where the threat is due to the unattenuated lightning electromagnetic field
and where the internal systems may be subjected to full or partial lightning surge
currents.
LPZ 1 Zone where the surge current is limited by current sharing and by SPDs 3 at the
boundary. Spatial shielding may attenuate the lightning electromagnetic field.
LPZ 2 Zone where the surge current may be further limited by current sharing and by
additional SPDs at the boundary. Additional special shielding may be used to
further attenuate the lightning electromagnetic field.
LPZ 3 Zone where the surge current may be further limited by current sharing and by
additional SPDs at the boundary. Additional spatial shielding may be used to
further attenuate the lightning electromagnetic field.
10 MW Pilot Project has been designed to be installed with SPD in each joint box.
This is an agreeable design in order to prevent PV arrays from lightning hazards.
Some array which was hit by lightning would spread the impact to other arrays.
Lightning strike
It might happen to flash over between frame and PV cell of PV arrays shown above.
Surge will be passed on to other PV arrays.
SPD
3 - 24
Renewable Energy Development Chapter 3 Capacity Development in the Planning, Design,
Final Report Construction, and O&M of a Grid-connected Solar PV System
For alterative current circuit, there are two kinds of power supply. One is effective
power and the other is reactive power. The PV system of 10MW Pilot Project will
supply only effective power, but transmission line needs reactive power because
there is line inductance and capacitance to the ground in transmission line. For this
reason, it is very appropriate to install SVC 4 in the substation to compensate the lack
of reactive power. For 10MW Pilot case, a SVC should be located at the transmission
line's end.
When the Consultant visited several solar PV plants in Golmud, wiring between
modules were not in good condition. Wiring is vibrating and rubbing against PV frame
because wiring was not firmly fixed. This condition damages the insolation of wiring.
Therefore, wiring needs some more length for setting to absorb vibration and to avoid
rubbing against PV frames..
PV system generates electric power with the total intensity of the sun light. Total
intensity consists of direct sun light and diffused light. The source of diffused light is
everywhere on the earth. Cloud is one of the major sources of diffused light. Fish
eye lens projection image can estimates cloud amount as solid angle of sky.
3 - 25
Chapter 3 Capacity Development in the Planning, Design, Renewable Energy Development
Construction, and O&M of a Grid-connected Solar PV System Final Report
Tilt angle of PV array was set at the same angle as site latitude for the 10MW Pilot
Project. This counts for direct sunlight only. But, to harness the total intensity of
sunlight which includes diffused light, the tilt angle may be set a little flatter. As
shown in Fig.3.3-7, solid angle of sky becomes larger as the tilt angle becomes
smaller, meaning PV modules catch more of diffused light. This design method was
developed in Japan about 10 years ago. In Fig.3.3-8, the relationship between
radiation of diffused sunlight and solid angle of cloud is shown.
The relationship between diffused light and other objects was investigated and there
is clear relation. Total radiation on PV modules is the sum of direct sunlight from the
sun and diffused sunlight from the sky. Diffused sunlight intensity is not so small to
be negligible as on a cloudy day PV system generates reasonable power.
diffusion light
Fig. 3.3-8 Relation between Diffusion Sunlight and Solid Angle of Cloud
3 - 26
Renewable Energy Development Chapter 3 Capacity Development in the Planning, Design,
Final Report Construction, and O&M of a Grid-connected Solar PV System
Observation of insolation with a few PV modules with different tilt angles, other things
be in equal. This observation should be continued for at least one year to obtain
reliable results.
senso
tilt angle 25
tilt angle 30
tilt angle 35
(8) DC Protection.
DC circuit generally needs insulation to the ground and some monitoring and
protection might be necessary.
However for PV system it is not clear how to apply insulation system because there is
no regulation in guidelines for solar PV system in Japan and in PRC as well.
270kV/350V
PV Transless Inverter
Transformer
Grounding
DC fault current
When grounding accident happens in the DC circuit of a solar PV system, the DC fault
current flows from PV array through transformer to the ground. DC fault current flows
in the transformer as shown in Fig.3.3-10. In this case the transformer may
experience insulation deterioration quickly by DC fault current which is dangerous for
maintenance people or other people working for solar PV systems. If someone
touches the wiring of DC circuit and the wiring does not have enough insulation,
electrical shock may happen to this person. Although there is no regulation in Japan,
3 - 27
Chapter 3 Capacity Development in the Planning, Design, Renewable Energy Development
Construction, and O&M of a Grid-connected Solar PV System Final Report
Even if the inverter does not have this function, it is possible to set this function
outside the inverter, such as DC OVGR 5.
In the case of short-circuited failure, the fault current will flows from not only
transformer but also other transmission lines that are connected to PV system.
Therefore, the capacity of circuit breaker should be designed to be large enough tp
handle the total current.
3 - 28
Renewable Energy Development Chapter 3 Capacity Development in the Planning, Design,
Final Report Construction, and O&M of a Grid-connected Solar PV System
Long term operation and maintenance requires not only human resources but also
spare parts, especially PV module and inverter parts. Long term maintenance
requires more skill in handling complex devices such as power conditioners.
Generally, a power conditioner has several electronics boards inside and replacing
such boards requires specific skills. If replacement of parts is conducted by
manufacturers engineer, we will have to allow for 2 or 3 days minimum before arrival
of engineers at the site. Unfortunately the skill of manufacturers engineer is a fruit of
special training, it would be the good chance to obtain the special training in the
guarantee period. Through the repeated discussions held between the Consultant
and QBEs engineers about operation and maintenance methods of PV systems, the
Consultant confirmed that the knowledge of engineers of QBE were significantly
increased.
When many PV modules with individual characteristics are connected in series, total
generation output becomes smaller than the output calculated in theory. This fact is
explained using the figures below.
50
40 Voc=90 V
Vop=70 V
30 Isc=50A
Current
Iop=40 A
Pmax=2800 W
20 FF=0.62
10
0
-10 10 30 50 70 90
Voltage
3 - 29
Chapter 3 Capacity Development in the Planning, Design, Renewable Energy Development
Construction, and O&M of a Grid-connected Solar PV System Final Report
Series connection of different Iops and Vops decrease total power generation shown
as the black curve in Fig. 3.3-13.
3000
2800
2600
2400
STADARD
POWER
2200 Vop + 5 %
2000 Iop +5 %
SERIES
1800
1600
1400
1200
CURRENT
This means that a PV array should consist of the modules with the same Vop and Iop
values. As a solar PV system is expected to be in operation for long time, we should
be careful when replacing PV modules with different model.
The quality of upstream manufacturing process of solar cell impacts upon its
conversion efficiency and long term reliability. The consultant team assessed the
upstream local manufacturing process and observed opportunity for further
improvement in its quality. It is difficult to avoid the yellow sand flies into the factory by
the nature of the locality in Qinghai, PRC. Therefore, appropriate countermeasure is
devised to prevent the yellow sand getting into the building, especially the cleaning
lab of materials and the pull-up lab of mono-crystalline silicon, and to keep the
factories as a whole cleaner. Required quality of mono-crystalline silicon necessary
for IC semiconductor and solar cell is different, but converting measure of
poly-crystalline silicon into mono-crystalline silicon is the same.
It is important to get more reliability of products and also to pay more attention to the
cleaner conditions of workers, equipment, facilities, etc. to improve the reliability of
the products.
3 - 30
Renewable Energy Development Chapter 3 Capacity Development in the Planning, Design,
Final Report Construction, and O&M of a Grid-connected Solar PV System
Employee Since one employee takes charge of 2 pots, one group to take
charge of whole pots consists of 642 = 32 employees/group.
Therefore, number of employees for pulling-up can be estimated as
64 employees for 2 groups, and 96 employees for 3 groups. It
seems that there are too many employees because process from
material to cleaning except for pull-up is conducted manually (by
MAN POWER).
Pull up with
rotating
Mono-
Ingot Wafer Crystalline
Cell
Polycrystalline
Silicon
Solid
Polycrystalline
Silicon Poly-
Ingot Wafer Crystalline
Cell
3 - 31
Chapter 3 Capacity Development in the Planning, Design, Renewable Energy Development
Construction, and O&M of a Grid-connected Solar PV System Final Report
MONOCRYSTALLINEINGOT POLYCRYSTALLINEINGOT
Fig. 3.4-2 Photos of Monocrystalline / Polycrystalline Ingots
Formation of Formation of
PN Junction Electrode Junction
Electro
Electro
3 - 32
Renewable Energy Development Chapter 3 Capacity Development in the Planning, Design,
Final Report Construction, and O&M of a Grid-connected Solar PV System
(3) PV Module
PV Module
Solar Cell
Following instructions and suggestions were provided to improve the production yield
of monocrystalline silicon.
3 - 33
Chapter 3 Capacity Development in the Planning, Design, Renewable Energy Development
Construction, and O&M of a Grid-connected Solar PV System Final Report
- It is required to remodel the laboratories such as material lab., drying lab, packaging
lab., filling lab., and pull-up lab. into clean rooms. It is also required to replace the
working wear in the laboratories with dustproof clothing.
Material
delivered Acid Pure
Virgin Polysilicon Cleaning Water PH Check Dry
HNOHF
Recycle Polysilicon Cleaning
for 1 minute OK
Pot Scrap NG PH67
As for pot scrap, it is PH6
subject to 24 hours
later after HF cleaning
<Current situation>
Pure water is discharged from above, so it is difficult to remove acid attached to
materials at the bottom.
<Proposal>
Pure water is discharged from below, so it enables to remove not only acid but other
contamination by overflow. (This method is adopted in Japan)
3 - 34
Renewable Energy Development Chapter 3 Capacity Development in the Planning, Design,
Final Report Construction, and O&M of a Grid-connected Solar PV System
Pull-up machines and carts are very dusty. The reasons of the pollution must be as
follows.
a) Yellow sand gets into the room because the windows are kept open due to hot
temperature inside the room. Sometimes the room temperature would be above
40C.
b) After opening the oven, dust of SiO and carbon occurs by cleaning the Lab.
c) By yellow sand and other dusts which are carried into the room through the
workers cloths make pollution.
[ Solution ]
3 - 35
Chapter 3 Capacity Development in the Planning, Design, Renewable Energy Development
Construction, and O&M of a Grid-connected Solar PV System Final Report
Material
Melting pot
Carbon pot
Melting pot
Carbon pot
Suction pad
Plane Figure
Fig. 3.4-6 Using a Vacuum Cleaner
- Method 2. A carbon pot is bundled by a band with a taper covering R-curve and
straight line to hang and set up by a crane or wire of pull-up pot.
3 - 36
Renewable Energy Development Chapter 3 Capacity Development in the Planning, Design,
Final Report Construction, and O&M of a Grid-connected Solar PV System
Carbonpot
Wirehook for
hangingbycrane
Meltingpot
Carbonpot
Band
Band
Plane Figure
Fig. 3.4-7 A Carbon Pot is bundled by a Band
- As for the issue b) it would be much improved by removing the carbon parts and
cleaning in another room after they cool down.
The Consultant concerned about the current situation of the factory that the products
and small silicon crystals which become products are placed directly on the floor, and
heated carbon parts taken out of the oven are put on a steel plate. The reason why
clean environment throughout the process from the materials to mono-crystalline
silicon pulled-up must largely affects the yield of mono-crystalline silicon. In fact, the
ratio of mono-crystallization is lower and loss time is longer due to contamination
which is visible in melted silicon.
1) Residue in a pot
3 - 37
Chapter 3 Capacity Development in the Planning, Design, Renewable Energy Development
Construction, and O&M of a Grid-connected Solar PV System Final Report
It should be conducted to confirm the validity of the current cleaning method and
occurrence of contamination from the equipment. The method of check out is as
follows. After usual cleaning, place a mirror glass inside of the quartz pot without
filling the material.
1) To vacuum the oven and confirm the contamination on the mirror glass
Vacuum
Confirm
Conditions of
usual cleaning
Contaminations
3 - 38
Renewable Energy Development Chapter 3 Capacity Development in the Planning, Design,
Final Report Construction, and O&M of a Grid-connected Solar PV System
2) Rising and falling the wire of the ingot and confirm the contamination on
the mirror glass
Check out whether metal particles fall on the mirror glass on wafer
Vacuum Riseandfall
thewireofthe
ingotto
confirm
MirrorglassorWafer
Fig. 3.4-11 Confirmation of the Contamination
This checking method has been already explained to the factory employees.
The route of contamination into the oven can be found by this checking method.
(1) As for the issues of pot scrap, deformation of ingot, and crack occurred when
ingot is detached, the engineer consulted about deformation of the pot since
June.
The cause of deformation is not found because the Consultant has not
experienced this before. The presumption of the cause is shown as below;
3 - 39
Chapter 3 Capacity Development in the Planning, Design, Renewable Energy Development
Construction, and O&M of a Grid-connected Solar PV System Final Report
Ba is applied on the surface of the pot thinly (0.5mm) inside and thickly (
2mm) outside. (5mm at the bottom). Ba was applied inside for the purpose of
preventing direct contact between quartz and contamination in the pot and also
applied outside.
(2) Refer to the following figures about the cause of deformation the Consultant
presumed. Thickness of Ba inside and outside of the pot shown in Fig. 3.4-13
was not measured accurately. Deformation in both of Fig. 3.4-13 and Fig. 3.4-14
does not occur throughout inside of a melting pot. It can be considered that air
hole shown in the Figures below occurred because of 90kW power. Outside of
the pot where heat-resistant material Ba was applied thickly, was not deformed.
For reference, comparison with solvent power in Japan is shown below.
Balayer
Transparentlayer
2
Translucentlayer
8
Balayer
Airhole
ItwascausedprobablybecauseBawas
notcompletelybondedonquartz.
Thickness ofBa0.5
Transparentlayer
Translucentlayer
3 - 40
Renewable Energy Development Chapter 3 Capacity Development in the Planning, Design,
Final Report Construction, and O&M of a Grid-connected Solar PV System
Air hole
It can be caused by
expansion of air bubble
Thick ness of
Ba2
Ba layer
Transparent layer
Translucent layer
Thickness of Ba
45 Ba layer
a) The gap was happened at strainer part of both pots (carbon pot and melting
pot) and direction was circular direction.
(4) The deformation occurred in 50% out of whole Bts (1,071 Bt = 1,071 pcs) in June,
and furthermore, deformation throughout circumference occurred in half of Bts.
In July, deformation was decreased but still occurred. Some of the pot did not fit
carbon pots at the corner, and it depends on manufacturers and Ba application.
It is assumed that his estimation is correct. Factory uses a carbon pot divided into
3 parts and thickness of the inside becomes thinner gradually during the usage.
Therefore, gap occurs accordingly at the place of contacting outside of the
carbon pot.
3 - 41
Chapter 3 Capacity Development in the Planning, Design, Renewable Energy Development
Construction, and O&M of a Grid-connected Solar PV System Final Report
A Newcarbonpot
B Mediumusage count
C Highusagetobe
Highusagecount
Lowusagecount Abouttobechanged
changed
(5) Factory should examine if usage count of carbon pots affect deformation of
melting pots or not. Therefore, the Consultant suggested that Factory prepare a
model of carbon pot for inspection when
they are delivered.
3 - 42
Renewable Energy Development Chapter 3 Capacity Development in the Planning, Design,
Final Report Construction, and O&M of a Grid-connected Solar PV System
diameter of a carbon pot, which keeps its shape without being deformed by
some influence.
2) If there is no gap between inside diameter of the model and outside diameter
of a carbon pot, the melting pot will pass the inspection.
3.4.5.5 What is required for Manufacturing Seed at their Own Factory in the Future?
(1) To utilize the existing factory is impossible to improve the quality of silicon ingot
because the present ingot production must not be stopped and it is necessary to
construct a new factory.
(2) At least the conditions mentioned below are necessary to construct the clean
factory.
Worker in the clean rooms must wear dust protection cap, dust protection
wears and shoes and when workers enter the clean room they need to have air
shower to eliminate the dust from the outside.
Raw material which is carried into the clean also needed to have air shower.
3 - 43
Chapter 3 Capacity Development in the Planning, Design, Renewable Energy Development
Construction, and O&M of a Grid-connected Solar PV System Final Report
from a manufacturer
2) Recycled material of
mono- crystal (A, B, C,
E) NGline
3) Pot scrap (D)
There are 2 types of pull-up specification for 0.5 ~ 3.0cm and 3~6cm.
When the Consultant asked the engineer if they have had two types of material, which
resistance was out of criteria, he replied engineers have never experienced that
resistance was out of criteria for 4 years since they started the operation. if the
engineer considers manufacturing IC semiconductors in the future the Consultant
suggests that they must improve process capability of resistance value by SPC6
management.
3 - 44
Renewable Energy Development Chapter 3 Capacity Development in the Planning, Design,
Final Report Construction, and O&M of a Grid-connected Solar PV System
The engineer showed inspection certificates of material. Purchase amount from each
manufacturer (A, B) is unknown.
Company A: N 300 cm (P 1000 cm)
Company B: N >40 cm (P > 200 cm)
According to the above value, abnormal resistance will not occur by using As material
in 60kg charge. On the other hand, resistance will be out of criteria by using Bs
material unless it is classified by resistance value.
(7) Effective Example for the Countermeasure of Crack Appearance at the Ingot in
Japan
(8) Suspended Contamination (Particle of Carbon, Particle of Quartz, SiC, Ba, etc.)
60kg/Bt(4kg + 3kg)
= 88.3%
60kg/Bt
3 - 45
Chapter 3 Capacity Development in the Planning, Design, Renewable Energy Development
Construction, and O&M of a Grid-connected Solar PV System Final Report
A+B=4kg
When crystal is pulled up after a part of crystal (6kg) which has contamination like
this is taken out of a pot
In both ways, "10%" yield loss will occur even when crystal can be pulled up to the
end as this figure. As for time loss, the employees make a calculation themselves to
understand about the impact on production by contamination, and work seriously to
look for the route that such contamination get into the pot.
3 - 46
Renewable Energy Development Chapter 4
Final Report Review of Grid Connectivity of MW Class Solar PV System
CHAPTER 4
1) For main transformers, two 63MVA transformers will be selected, and they will be
installed at one time;
2) There will be finally two 110kVA outgoing lines, one of which will be built to
connect to Golmud Substation and another line will be connected to the planned
110kV Nuomuhong Substation in the near future (no specific plan);
3) There will be finally eight 35kV outgoing lines (reserved for expansion), and four
will be built soon, with two connected to CPI and Longyuan each. The remaining
four lines are reserved for future expansion.
The incoming line to the combiner station was designed to be connected to the fifth
110kV bay from the south at the Golmud 330kV Substation. This is an exiting bay,
originally planned for Nachitai II outgoing line, and in this design, the associated
electrical equipment should be completed.
4-1
Chapter 4 Renewable Energy Development
Review of Grid Connectivity of MW Class Solar PV System Final Report
N 110kV
Golmud-Yushuihe
Reserved for Xiyu
Xiyu
Golmud-Qarham II
Golmud-Qarham I
Golmud-Baiyang I
Golmud-Nachitai
Golmud Gas-fired I
Reserved for Diantie
Golmud Gas-fired II
Golmud Plant
Golmud Refinery
original Nachitai II
Golmud Refinery II
Golmud-Baiyang II
Reserved for
Reserved for
PV Station
Fig. 4.1-1 Schematic Diagram of Arrangement of 110kV Outgoing Line Bays in 330kV
Golmud Substation
2) Calculation result
The breaking capacity of the existing circuit breaker in the area grid can meet the
requirements of safety operation of the system. As no short-circuit level of various
bus voltage levels in new substations will exceed the existing equipment level, they
can be selected from conventional equipment.
4-2
Renewable Energy Development Chapter 4
Final Report Review of Grid Connectivity of MW Class Solar PV System
A single loop 110kV power transmission line of Combiner Station ~ Golmud 220kV
Substation will be built, with a length of about 24km and conductor size 400mm2.
System configuration of the 10 MW Pilot Solar PV System was well designed in terms
of safety, reliability and cost effectiveness.
- One unit consists of two PV arrays and each unit has one transformer and one
circuit breaker,
- DC goes into one bus and after converted into AC, is stepped up to 31.5 kV. The
power is fed to 3.15 kV/220 kV substation.
(1) The specifications of DC convergence control box are shown in Table 4.1-2.
4-3
Chapter 4 Renewable Energy Development
Review of Grid Connectivity of MW Class Solar PV System Final Report
(2) The specifications of step-up transformer are shown in Table 4.1-3. In these
specifications the rated capacity of transformer seems too large, because it is
lager than PV array capacity (1000kW).
(3) The specifications of circuit breaker are shown in Table 4.1-4. These
specifications are adequate considering the local conditions of the substation.
Short circuit current on the primary side will not be as small as the secondary
short circuit current of substation transformer.
(4) Quantities of electric equipment are listed in Table 4.1-5. Lightning protection
was designed, and SPD seems to be very well chosen.
4-4
Renewable Energy Development Chapter 4
Final Report Review of Grid Connectivity of MW Class Solar PV System
4.1.3 Inverter
(1) The specifications of inverter in the feasibility study are shown in Table 4.1-6.
Inverter is as important a component as a PV module for grid connected PV
system.
4-5
Chapter 4 Renewable Energy Development
Review of Grid Connectivity of MW Class Solar PV System Final Report
(2) For No.10 item of the table above, the operating range (270 10%) is too low for
10MW system. Inverters manufactured in PRC produce output voltage either at
380V or 270V. 270V type inverter does not have insulation between DC and AC,
while 380V type does. It is necessary to raise the output voltage above 270V.
(4) Inverter input voltage should be carefully checked and balanced with PV array
voltage.
4.1.4 Control
Control system is one of the most important elements for the pilot solar PV system.
There should be two types of communication lines. One is to connect the system
with the electric utility by optic fiber, and the other is to connect the system to internet.
Electric utility has the authority to open or close the circuit breaker at the grid
connecting point. There are many PV projects in Golmud and the total output will
reportedly reach 2 GW. Therefore the stability of the grid will be the largest concern
of the utility, and there will have to be a means to control solar PV power stations in
the area. It will be necessary for the electric power utility to establish an absolute
control over the power stations in the area. Fig. 4.1-2 is the total control system for
the pilot solar PV system.
Diagram of monitoring system structure designed by QBE for the pilot solar PV
system is shown in Fig. 4.1-2.
4-6
Renewable Energy Development Chapter 4
Final Report Review of Grid Connectivity of MW Class Solar PV System
In order to realize monitoring work economically and effectively, the whole monitoring
system was designed to be made of three layers:
The second layer of the system is for data acquisition, communications and
networking. Network system was designed on the ISO model in which
transmission rate is 100M bps. Monitoring host is connected with spacer
equipment in order to achieve resource sharing. System backbone uses Fast
Ethernet: communication management unit, monitoring host, terminal server and
network printer are connected together by a network integrator.
4-7
Chapter 4 Renewable Energy Development
Review of Grid Connectivity of MW Class Solar PV System Final Report
All equipment needs space for configuration of the interval unit monitoring device,
environment detectors, metering equipments, grid inverters, intelligent
convergence boxes and other intelligent devices, which are transmitted to the
main networks, located in the central control room, among protection and
monitoring devices, measuring and other intelligent devices. Substation
automation technology is being developed rapidly. Intelligent devices are used
extensively. Data exchange between intelligent devices and systems is
becoming more and more important. Data communication equipment, which
connects equipment and systems and their management are necessary in
substation automation system.
Data acquisition
- Data of inverter: DC input current, voltage and power, three phase output
current change and voltage, AC input power, Frequency, Running, etc.
4-8
Renewable Energy Development Chapter 4
Final Report Review of Grid Connectivity of MW Class Solar PV System
2) Information necessary managing the pilot solar PV system will be collected and
analyzed.
For designing a solar PV system, cost effectiveness and efficiency of equipment (PV
module, inverters, circuit breaker, etc.) should be considered.
Loss of electric power at wiring and efficiency decrease due to temperature rise are
small, but must be considered to evaluate the cost effectiveness and efficiency of the
design of a solar PV system.
(1) Wiring
Local temperature of the site of the pilot solar PV system has large variation in a year.
The effect of temperature on generation efficiency of PV module is not negligible. It
should be carefully considered in the design.
4-9
Chapter 4 Renewable Energy Development
Review of Grid Connectivity of MW Class Solar PV System Final Report
Rated output power of PV module was estimated in QBEs F/S Report under the
standard condition. Here, monthly peak generation is reconsidered.
- Daily peak power appears when the ambient air temperature is at its peak,
- Wiring loss is 3%. From the QBEs design of 10MW Pilot Project.
4 - 10
Renewable Energy Development Chapter 4
Final Report Review of Grid Connectivity of MW Class Solar PV System
the inverter, as in 10 MW solar PV system case, input voltage is higher than output
voltage.
The capacity of the inverter is designed equal to the capacity of the solar PV panels.
In case of Golmud, maximum insolation appears from March to September and the
temperature of solar PV panel surface becomes 40 degree Celsius.
Then the capacity of inverter is enough to have 90 % of the capacity of the solar PV
panels. However over load is to be considered for the inverter but the inverter has
input restriction function to avoid over load for input power. In operational condition,
the inverter efficiency would be 90% or a little larger. The capacity of inverter can be a
little smaller than the rated output of PV modules connected to the inverter.
In most of cases the capacity of the transformer is designed as the same capacity of
the solar PV panels but it is too big capacity. In general transformer is designed to
resist against the short time over load capacity and it is standardized. Its capacity is
able to be reduced less than the capacity of the inverter. The life span of the
transformer is estimated based on the maximum utilization factor and the load factor
and the life measurement method of transformer is established at present.
Considering the utilization factor of the solar PV system in the night period is zero,
less than 90% of inverter capacity is good enough for the capacity of the transformer.
Then regarding breaking capacity of the circuit breaker, it should be considered much
more than the transformer. In case of fault occurred, the fault current is flown into
the circuit breaker from not only upper side of the power grid but also from other solar
PV systems. It is necessary to discuss with the area power company about the short
circuit capacity because the short circuit current is depends on the impedance of
4 - 11
Chapter 4 Renewable Energy Development
Review of Grid Connectivity of MW Class Solar PV System Final Report
transmission lines.
The Consultant identified other areas of improvement in the design of 10MW Pilot
Project.
a) and b) requires analysis on the operation data. The data collection interval should
be 10 minutes or less. a) can be measured at input point of inverter, and b) can be
measured at output of inverter.
When these factors are considered, simple inequality formula is made as follows.
DC generation > Inverter output > Transformer capacity
This kind of system arrangement is not peculiar, as the price of transformer is not that
high compared with that of other equipment. However, transformer loss is not
negligible, especially when the capacity of the transformer is large. There is also iron
loss even the system is not in operation and only charged by electricity.
The overview of the power system in Golmud, such as substations and transmission
lines, is described below.
Construction of new substations and transmission lines were ongoing and further
expansion being planned in the area. The grid will be reinforced and able to mitigate
the impacts of huge solar PV stations connected after these constructions.
Especially, 750kV transmission project and 400kV HVDC project should be in place to
ensure the stability of grid conditions. In addition to the above, application of smart
Grid Technology are envisaged being studied in PRC. The state grid companies are
4 - 12
Renewable Energy Development Chapter 4
Final Report Review of Grid Connectivity of MW Class Solar PV System
the hub authority of its development. The information is described in the website of the
state grid (http://www.sgcc.com.cn/ ztzl/newzndw/).
The power grid in Haixi is divided into central, eastern and western parts. The
central and eastern grid are supplied mainly by four 330kV substations at Ulan, Bayin,
Yanhu and Golmud, also by some local small hydropower and thermal power stations.
The western grid is further divided into three isolated supply grids, with power sources
mainly of local oil (gas) fired power stations, which are built, managed and used by
the enterprises themselves.
In the central part, Golmud area was connected with the main grid of Qinghai in 2001,
with 330kV Golmud substation as the main supply source. At present, the grid in the
area is connected with the main grid via the following 330kV transmission lines.
- Longyangxia-Ulan-Golmud
- Huangyuan-Mingzhu -Ulan-Bayin-Yanhu-Golmud
In 2009, the maximum power consumption in Haixi grid was 265.1MW, and it supplied
energy of 1,583 GWh, with sold electric energy of 1,524 GWh.
The grid associated with the pilot solar PV system is the Golmud grid in the central
part of Haixi. The Golmud grid was connected with the main grid of Qinghai at the end
of 2001, with 330kV Golmud substation as the main supply source, and assisted with
some local gas-fired power plants and small hydropower stations.
Substations and transmission lines associated with this project are described below.
- 330kV feeder : 2 outgoing lines (to Ulan substation and Yanhu substation)
(final: 6 outgoing lines)
4 - 13
Chapter 4 Renewable Energy Development
Review of Grid Connectivity of MW Class Solar PV System Final Report
Gas fired power plant II, Gas fired power plant I, Baiyang
substation, Qinghai Potassium Fertilizer power plant, Yushuihe
substation, Qarham I-II Ulan substation and Yanhu substation)
(final: 12 outgoing lines)
To supply power to the high purity magnesium oxide project and other planned
industrial projects in Kunlun Development Zone, it was planned to construct
Kunlun Development Zone 110kV substation (2 50MVA) in 2010, and one main
transformer will be installed in the initial period. The dedicated two transmission
lines will be installed from the 330kV Golmud substation.
4 - 14
Renewable Energy Development Chapter 4
Final Report Review of Grid Connectivity of MW Class Solar PV System
To meet the power demand along Golmud - Tuotuohe section of the Qinghai -
Tibet Railway and improve power supply reliability, it is planned to construct the
110kV Nachitai - Wudaoliang - Tuotuohe line II in 2012.
4 - 15
Chapter 4 Renewable Energy Development
Review of Grid Connectivity of MW Class Solar PV System Final Report
4.2.2 Demand Forecast and Power Balance (Supply-Demand Balance) in Golmud Area
Studies on demand forecast and power balance were carried out to check the
necessity of the PV power stations. The results of the studies are shown in Fig. 4.2-1,
Table 4.2-2, Table 4.2-3.
Demand will increase rapidly with construction of factories under the endorsement by
the government policy. The supply will be on the short side in near future if PV power
plants will not be installed even though some new hydro/thermal power plants will be
constructed. Therefore, the PV power plants should be constructed while power
balance is being kept.
2) The general demand in the area was forecast according to its development of
national economy with a certain growth rate,
4) A 600 kt/year methanol project is about 1km away from Baiyang substation, and it
will be supplied by this substation,
6) According to the regional grid plan, the 110KV Center substation and Kunlun
Development Zone substation will be constructed in the urban area of Golmud
around 2012, and by when completed, some load can be transferred from
Baiyang and Guangming substations to these new substation,
7) The PV power stations at the eastern and southern areas of Golmud are
incorporated to the 330kV Golmud grid. These PV stations as well as hydropower
and thermal power stations, which are under construction and planning, were
taken into account in this power balance,
8) The winter season has a peak demand period and the demand decreases during
summer season. On this situation, the forecast maximum demand is applied to
winter season and demand for summer season is decreased using the ratio
previously observed,
9) In summer season, generated power by all small hydro power plants is assumed
almost at rated capacity, and the number of operating generators of Golmud
Gas-fired power plant is decreased from two (2) to one (1) for economical
4 - 16
Renewable Energy Development Chapter 4
Final Report Review of Grid Connectivity of MW Class Solar PV System
consideration,
10) The two situations on the PV power plants are taken into account: one is no PV
output (PV power is included in supply side), and another is full PV output (PV
power is excluded from supply side).
[MW]
Legend
Power balance (Winter) [MW] Power balance (Summer)
Demand
Supply
(excluding PV
power)
Supply
(including PV
power)
No. Substation name 2009 2010 2011 2012 2013 2014 2015
1 Guangming Substation 22.0 24.0 26.0 27.0 29.0 32.0 36.0
2 Baiyang Substation 25.0 28.0 31.0 35.0 38.0 42.0 48.0
3 Qarham Substation 55.0 55.0 60.0 60.0 60.0 60.0 60.0
4 Lanke Substation 1.0 2.0 3.0 4.0 5.0 6.0 7.0
5 Beiletan Substation 3.0 4.0 5.0 6.0 7.0 8.0 8.0
6 Dongtai Substation 1.0 2.0 3.0 4.0 5.0 7.0 8.0
7 Yushuihe Substation 9.0 11.0 15.0 20.0 24.0 28.0 30.0
Zhongzhao Thermal Power
8 1.2 1.2 1.2 1.2 1.2 1.2 1.2
Substation
9 Gansen Substation 1.2 --- --- --- --- --- ---
Qinghai Potassium Fertilizer
10 15.5 15.5 15.5 15.5 15.5 15.5 15.5
Plant Substation
11 Golmud Refinery Substation 29.5 29.5 29.5 29.5 29.5 29.5 29.5
12 Xiyu Non-ferrous Substation 8.0 8.0 8.0 8.0 8.0 8.0 8.0
13 Nachtai Substation 1.5 1.5 1.5 1.5 1.5 1.5 1.5
14 Wudaoliang Substation 1.2 1.2 1.2 1.2 1.2 1.2 1.2
15 Tuotuohe Substation 1.2 1.2 1.2 1.2 1.2 1.2 1.2
Kun Development Zone
16 15.0 20.0 25.0 30.0 35.0
Substation
17 Central Substation 15.0 20.0 30.0 35.0
18 Guoxiang Substation 15.0 20.0 ---
19 Nuomuhong Substation 22.8 33.0 33.2 33.4 33.6
4 - 17
Chapter 4 Renewable Energy Development
Review of Grid Connectivity of MW Class Solar PV System Final Report
No. Project name 2009 2010 2011 2012 2013 2014 2015
I Max. power supply load in area 140.3 147.3 191.2 225.8 255.6 283.7 287.1
II Output from power plants in area 227.3 300.3 330.3 330.3 330.3 330.3 350.3
(I) Output from hydropower plants in area 92.3 92.3 102.3 102.3 102.3 102.3 102.3
1 Naijili Power Station 12.0 12.0 12.0 12.0 12.0 12.0 12.0
2 Dagangou Power Station 20.0 20.0 20.0 20.0 20.0 20.0 20.0
3 Xiaogangou Power Station 32.0 32.0 32.0 32.0 32.0 32.0 32.0
4 Yixiantian Stage I Power Station 7.5 7.5 7.5 7.5 7.5 7.5 7.5
5 Yixiantian Stage II Power Station 8.0 8.0 8.0 8.0 8.0 8.0 8.0
6 Nanshankou Stage I Power Station 12.0 12.0 12.0 12.0 12.0 12.0 12.0
7 Nanshankou Stage II Power Station 10.0 10.0 10.0 10.0 10.0
Nuomuhong Stages I and II Power
8 0.8 0.8 0.8 0.8 0.8 0.8 0.8
Stations
(II) Output from PV Station in area 73.0 93.0 93.0 93.0 93.0 113.0
1 Qinghai New Energy PV Station 10.0 10.0 10.0 10.0 10.0 30.0
2 Guodian Longyuan PV Station 10.0 20.0 20.0 20.0 20.0 20.0
3 Junshi Energy PV Station 10.0 10.0 10.0 10.0 10.0 10.0
4 Huaneng PV Station 10.0 10.0 10.0 10.0 10.0 10.0
5 CPI PV Station 10.0 20.0 20.0 20.0 20.0 20.0
6 QDI (Datang) PV Station 5.0 5.0 5.0 5.0 5.0 5.0
Yellow River Upstream Company PV
7 5.0 5.0 5.0 5.0 5.0 5.0
Station
8 Shenguang New Energy PV Station 3.0 3.0 3.0 3.0 3.0 3.0
9 Qinghai Baike 10.0 10.0 10.0 10.0 10.0 10.0
(III) Output from gas-fired station 135.0 135.0 135.0 135.0 135.0 135.0 135.0
1 Golmud Gas-fired Station 135.0 135.0 135.0 135.0 135.0 135.0 135.0
Power balance (no PV output)
87.0 80.0 46.1 11.5 -18.3 -46.4 -49.8
surplus (+) short (-)
III
Power balance (full PV output)
87.0 153.0 139.1 104.5 74.7 46.6 63.2
surplus (+) short (-)
4 - 18
Renewable Energy Development Chapter 4
Final Report Review of Grid Connectivity of MW Class Solar PV System
No. Project name 2009 2010 2011 2012 2013 2014 2015
I Max. power supply load in area 159.4 167.4 217.3 256.6 290.4 322.4 326.2
II Output from power plants in area 319.7 392.7 417.3 417.3 417.3 417.3 437.3
(I) Output from hydropower plants in area 49.7 49.7 54.3 54.3 54.3 54.3 54.3
1 Naijili Power Station 6.0 6.0 6.0 6.0 6.0 6.0 6.0
2 Dagangou Power Station 16.0 16.0 16.0 16.0 16.0 16.0 16.0
3 Xiaogangou Power Station 12.8 12.8 12.8 12.8 12.8 12.8 12.8
4 Yixiantian Stage I Power Station 3.2 3.2 3.2 3.2 3.2 3.2 3.2
5 Yixiantian Stage II Power Station 3.5 3.5 3.5 3.5 3.5 3.5 3.5
6 Nanshankou Stage I Power Station 6.6 6.6 6.6 6.6 6.6 6.6 6.6
7 Nanshankou Stage II Power Station 4.6 4.6 4.6 4.6 4.6
Nuomuhong Stages I and II Power
8 1.6 1.6 1.6 1.6 1.6 1.6 1.6
Stations
(II) Output from PV Station in area 73.0 93.0 93.0 93.0 93.0 113.0
1 Qinghai New Energy PV Station 10.0 10.0 10.0 10.0 10.0 30.0
2 Guodian Longyuan PV Station 10.0 20.0 20.0 20.0 20.0 20.0
3 Junshi Energy PV Station 10.0 10.0 10.0 10.0 10.0 10.0
4 Huaneng PV Station 10.0 10.0 10.0 10.0 10.0 10.0
5 CPI PV Station 10.0 20.0 20.0 20.0 20.0 20.0
6 QDI (Datang) PV Station 5.0 5.0 5.0 5.0 5.0 5.0
Yellow River Upstream Company PV
7 5.0 5.0 5.0 5.0 5.0 5.0
Station
8 Shenguang New Energy PV Station 3.0 3.0 3.0 3.0 3.0 3.0
9 Qinghai Baike 10.0 10.0 10.0 10.0 10.0 10.0
(III) Output from gas-fired station 270.0 270.0 270.0 270.0 270.0 270.0 270.0
1 Golmud Gas-fired Station 270.0 270.0 270.0 270.0 270.0 270.0 270.0
Power balance (no PV output)
160.3 152.3 107.0 67.7 33.9 1.9 -1.9
surplus (+) short (-)
III
Power balance (full PV output)
160.3 225.3 200.0 160.7 126.9 94.9 111.1
surplus (+) short (-)
4 - 19
Chapter 4 Renewable Energy Development
Review of Grid Connectivity of MW Class Solar PV System Final Report
Golmud Location
Golmud
Fig. 4.2-2
Only passed through
Map : Google
4 - 20
Site 1 : Qinghai New Energy, and Qinghai Junshi Energy (Junshi Energy)
Site 2 : Baike Solar Power (Baike SP) - China Science and Technology PV Power
Site 3 : China Longyuan Golmud New Energy Development (Guodian NED)
Final Report
Site 4 : SDIC Golmud Solar Power (SDIC) - CPI Huajing Power Holding
Site 5 : Xinguang New Energy Service (Xinguang NES)
Substation : East Golmud 110kV Collected Step-up Substation (110kV Substation) Huaneng International Power Development
Renewable Energy Development
Site 4
Site 2 AC750kV Substation
Substation
Site 1 DC400kV Converter Station
Site 3
Site 5
4 - 21
Map : Google Map
Chapter 4
Review of Grid Connectivity of MW Class Solar PV System
4 - 22
Emerson Network
Inverter Power,SSL0500 [*5]
Manufacturer -
[*4] (Made in China)
Oil Dry
Type Not Operate Not Operate Dyn11-dyn11 Dy11y11
Transformer for PV 5 Tap 5 tap
Rated Power [W] 1,000(500+500) 1,250
Rated Voltage [V] 38,500/380-380 35,000/270-270
110kV Substaion
Main Transformer 2 units, (110/38.5kV, 63,000kW, YNd11, 17tap)/1unit
110kV Bay 4 Bays (2 Line, 2 Transformers)
35kV Bay 17 Bays (10 Lines including 2 spear, 2 Transformers, 2 SVCs, 1 Bus section, 2 PTs)
SVC 2 units, 10,000kVar/1unit
*1 http://www.gs-solar.com/freefieldsolarfarm.html *2 http://www.yinglisolar.com/
*3 http://www.gdsolar.com/ *4 http://b2b.bjx.com.cn/8434505/product-199690.html
Renewable Energy Development
Final Report
*5 http://www.emersonnetwork.com.cn/Pages/Default.aspx
Renewable Energy Development Chapter 4
Final Report Review of Grid Connectivity of MW Class Solar PV System
The grid operation code (DL/T 1040 - 2007) and related regulations and standards
are applied to the PV power plants to be connected with the grids. There is no
stipulation and description on a PV power plant in the Grid Code while those of
hydro/thermal power plant are stated. For this reason, some technical stipulation on
hydro/thermal power plants was applied to PV power plants.
The following six (6) PV power plants are under planning or already operating in the
eastern area of Golmud City.
1) China Science and Technology Photovoltaic Power Holding Co., Ltd., 10MW
2) CPI Huajing Power Holding Co., Ltd., 20MW
3) Guodian Longyuan Golmud New Energy Development Company, 20MW
4) Qinghai New Energy Group Corporation, 10MW
5) Huaneng International Power Development Company, 10MW
6) Qinghai Junshi Energy Co., Ltd., 10MW
The 110kV substation, called Golmud East 110kV combiner station, has been
constructed to consolidate and step-up (35/110kV) the power from six (6) PV power
plants and to connect with the 110kV grid. The owners, construction and operation
scheme of the PV power plants and the 110kV combiner station are shown in Fig.
4.2-4.
The site of Qinghai New Energy Group (10MW) is on broad plain covered with dry
sand. There is no obstruction at the site. (The photos are shown in the Site Visit
Report.) Main load from the center of Golmud city to the construction site of the PV
power plant is large enough to transport the equipment. Access road from the main
load to the site has been constructed by neighbor PV power plants although its
surface is rough. A well with pumping equipment is necessary for construction work
and living. The authority surveyed and studied the availability of water in Golmud to
invite the PV power plants. They confirmed the large scale ground water flow to be
found as deep as 100 - 180 m. The electricity for construction work will be provided
from the 35 kV substation near the site as the same manner as other PV power
plants.
The Grid Code is applied at the connection point of the 110 kV lines and the combiner
station. The design of the combiner station was carried out by PV power companies
and it was reviewed and approved by the grid company. The monitoring and control
4 - 23
Chapter 4 Renewable Energy Development
Review of Grid Connectivity of MW Class Solar PV System Final Report
are implemented from the dispatch center of grid company, so only guardsman is
located at the substation. The operating information/data is transmitted to the dispatch
center via the substation using the optical fiber line.
The 35 kV switchgears are also operated by the grid company, and the grid company
informs switchgears operation to PV power plant by telephone before operation
except for emergency situation.
b. 110 kV Substation
110 kV Substation
(110/35kV Transformer)
c. 35 kV Transition lines
4 - 24
Renewable Energy Development Chapter 4
Final Report Review of Grid Connectivity of MW Class Solar PV System
Golmud East 110kV combiner station is connected with 330kV Golmud substation
through two 110kV transmission lines, and the configuration is as follows.
- 35kV Bay : 17 Bays (10 Lines including 2 spears, 2 Transformers, 2 SVCs, 1 Bus
section, 2 PTs)
The major facilities for the grid protection and operation, such as line protection relays,
recording facilities and remote automation facilities, are described in this item.
All facilities are designed in compliance with the Grid Code, Technical Code and
requirement of the grid operating company. For example, the protection system is
designed in compliance with GB14285-2006 Technical code for relaying protection
and security automatic equipment.
4 - 25
Chapter 4 Renewable Energy Development
Review of Grid Connectivity of MW Class Solar PV System Final Report
frequency and low voltage disconnection device is also installed at the Guodian
Longyuan and CPI (both PV power plants are already operated).
The station will be provided with a microcomputer fault wave recording device, to
record the faults of the 110kV line and the main transformer. It is required to have
the fault analysis, remote transmission and GPS satellite time calibration
functions.
4) Remote automation
a) Dispatching management
The remote operation host is connected to the power data net via data net
connection equipment, to send remote information to the provincial
dispatching center, with transmission rate no less than 2Mbps, and error
code rate not exceeding 10-7. The application level protocol is based on the
ministry issued standard DL476-92 and IEC60870-5-104, and TCP/IP be
adopted for network level protocol.
d) Miscellaneous
4 - 26
Renewable Energy Development Chapter 4
Final Report Review of Grid Connectivity of MW Class Solar PV System
5) Communication facilities
Optical fiber communication is applied between the combiner station and 330kV
Golmud substation, a 16-core OPGW optical cable and corresponding
communication equipment is used. The information from the combiner station is
transmitted via this channel to the Golmud substation, and then connected to the
existing power optical fiber net and then it is transmitted to the Qinghai Provincial
dispatching center and Haixi regional dispatching center.
The grid condition including power system and equipment of the 110kV combiner
station is in beside consideration mentioned above Section 4.1.2.5, items 1) to 5).
The FRT function which has already regulated in PRC (the voltage recover time is 2.0
Sec, remained voltage is 20 %) is not yet applied to the RE (wind, solar PV). However,
FRT function is essential to keep grid stability and it is to be applied to the wind/PV
power plant in other countries which have huge scale of wind/PV power plants, and
the grid operator in Qinghai also intends to do so.
4 - 27
Chapter 4 Renewable Energy Development
Review of Grid Connectivity of MW Class Solar PV System Final Report
setting value
[Sec]
0.0 1.0
Start time Time
of voltage drop
80
Within
1 Sec
80
Within
1 Sec
[Sec]
0.0 1.0
Voltage recovered Time
Start time
of voltage drop
4 - 28
Renewable Energy Development Chapter 4
Final Report Review of Grid Connectivity of MW Class Solar PV System
50.8
Frequency
50.0
0.06 [Sec]
(3 cycles) Time
Start time
of frequency rise
51.5
Frequency
50.0
Change rate of frequency: 2Hz/Sec
47.5
[Sec]
Time
Start time
of frequency rise
4 - 29
Chapter 4 Renewable Energy Development
Review of Grid Connectivity of MW Class Solar PV System Final Report
80
Within
1 Sec
remark
[Sec]
0.1
0.0 Time
Start time Voltage recovered
of voltage drop
80
Within
1 Sec
[Sec]
0.0 1.0
Voltage recovered Time
Start time
of voltage drop
Fig. 4.2-6 (a) Requirement on FRT Function in Japan (after April, 2017)
4 - 30
Renewable Energy Development Chapter 4
Final Report Review of Grid Connectivity of MW Class Solar PV System
50.8
Frequency
50.0
0.06 [Sec]
(3 cycles) Time
Start time
of frequency rise
51.5
Frequency
50.0
Change rate of frequency: 2Hz/Sec
47.5
[Sec]
Time
Start time
of frequency rise
The requirement on FRT function in PRC technical standard is shown in Fig. 4.2-7.
The differences of the requirements between PRC and Japan are stated in the above
Fig. 4.2-7 and shown below.
4 - 31
Chapter 4 Renewable Energy Development
Review of Grid Connectivity of MW Class Solar PV System Final Report
Although the requirement in PRC is appropriate, Further the voltage recovery time of
FRT will be modified from 2.0 Sec to 0.5 Sec in consideration of more stable operation
in immediate future.
80
Within
1 Sec
China
30
Japan
20
(before March, 2017)
Assessing the grid condition either it must be paralleled off or must be operated
continuously, is the key point to ensure safety operation of FRT function.
1) When a fault occurred in the connected transmission line, the PV power plant
must be paralleled off.
2) When a fault occurred in other transmission lines with voltage drop, the PV power
plant must be operated continuously.
The PV power plants in PRC should have a complete and efficient line protection in
compliance with the relevant Code and requirement by a grid company. This line
protection can catch a fault in the case of 1) above easily and quickly. The proposed
block diagram of the control system designed is shown in Fig. 4.2-8 and the result of
factory test is shown in Fig. 4.2-9. Grid protection circuit integrated in this block
diagram is designed to meet the requirements to connect with low voltage circuit
(6.6kV) without circuit breaker. Under this connection, control system of inverter must
have the grid protection.
4 - 32
Renewable Energy Development Chapter 4
Final Report Review of Grid Connectivity of MW Class Solar PV System
PV-Array Grid
Detection Circuit
Drive Circuit of
for Vout & Fout
Inverter
Grid Protection
Circuit
Control Control
for for
1
MPPT* Vout & Iout
Control
for
FRT Operation
Recovery operation
Continuous operation
by FRT function Usual operation
Grid voltage
Output current
of inverter
4 - 33
Renewable Energy Development Chapter 5
Final Report Economics of Solar PV Power Plant
CHAPTER 5
Financial assessment of the 10MW Pilot Project had been done by the project
proponent, QBE, in the feasibility study. The Consultant followed some of its basic
assumptions of analysis, while the Consultant also referred to a set of conditions
instructed by NDRC, to build a financial model.
As mentioned above, there had been a study carried out by QBE whose conditions do
not completely agree with the set of conditions shown by NDRC as a guideline for
prospective PV project investors. The settings of two methods are shown below.
2) Guideline of NDRC
NDRC published a set of conditions of financial analysis for those who wish to
apply for a license of PV projects as shown below.
5-1
Chapter 5 Renewable Energy Development
Economics of Solar PV Power Plant Final Report
Depreciation 20 years
Residual value of fixed assets 5%
Operation cost 7% of year's depreciation
VAT 17%
Income Tax 25%
Additional tax 8%
IRR of profit after tax 11 12%
Although QBEs feasibility study report does not specifically mention, their profit
and loss calculation includes "subsidy" in income, equivalent to CNY 0.09 per
kWh, limited for the period from the commencement of operation to the end of
12th year into operation. Aside from that, QBE's conditions are different from
Guideline's in many ways. Significant differences are; operation period, loan
conditions (repayment period, interest rate), depreciation period, etc.
In the following analysis, conditions set out by NDRC were used as they presented
tougher conditions on financial prospect of the project, except interest rate of domestic
commercial bank loan, which was revised upward in the analyses here, at 6.55% per
annum, referring to Peoples Bank of Chinas long-term loan interest rate. Also, an
alternative reference value for IRR on equity, 8% per annum, was considered as an
alternative, lower threshold in the following analyses.
1) Investment cost
5-2
Renewable Energy Development Chapter 5
Final Report Economics of Solar PV Power Plant
This investment cost estimate may not be quite up-to-date for the base year of
the analysis, 2011. The total CNY 166,722,100 is equivalent to US$24.6 million
and, in term of per-kW unit cost, US$ 2,460 per kW. This is quite low even when
compared with the international market price for the year 2012 1. However, in
PRC the price level of PV equipment has been falling drastically, and there is a
possibility that the investment cost for the Pilot Project could be lower than this
estimate. The effect of such a possibility was discussed in the later section.
2) O&M cost
O&M cost of this project are based on the instruction of NDRC. Each cost is
calculated as follows:
Taxes are VAT on sales 17%, sales additional tax 8% on VAT, and income tax
25%.
1 For example, National Renewable Energy Laboratory of the US reports in July 2012 that the average unit installation cost
($/kW) of PV projects with the size range of 1 to 10 MW is $3,383, while QBEs estimate in 2010 was $2,463.
2 Weighted Average Cost of Capital
5-3
Chapter 5 Renewable Energy Development
Economics of Solar PV Power Plant Final Report
Power generation was estimated in the study by QBE. Annual generated energy for
the first year is 17.85 GWh, subject to an annual deterioration of output at 0.8% for
years onward. The first year output corresponds to the capacity factor of the plant
20.4%. Annual decrease of output at the rate of 0.8% amounts to 8% in ten years and
15 % in twenty years.
On the other hand, the Consultants estimate of annual generated energy was a little
smaller than this, at 16.82 GWh annually, as shown in Chapter 2, Table 2.3-1. For the
purpose of the following analyses, the Consultants estimate was used.
Generated power is assumed to be sold to the provincial utility at CNY 1.15 per kWh,
which is a concession rate offered by the provincial government of Qinghai in July
2011 for those prospective PV power plant operators who would start power
generation by the end of 2011.
According to PRC's relevant laws for domestic power projects, equity to capital ratio
must be over 20%. NDRC also instructs to PV power plant proponents that the equity
has to be at least 40% of total capital requirement. Therefore, 40% of capital is
assumed to come from the proponents own finance (equity). The remaining finance
comes from domestic bank loan, whose conditions are as mentioned earlier.
(5) WACC
The WACC was calculated using the conditions mentioned above. The cost of equity
is assumed at 11.0%, interest rate of domestic bank loan 6.55%, income tax rate 25%,
all as instructed by NDRC except the interest rate. Inflation rate is assumed at 3.8%.
Thus WACC of 3.42% was obtained.
5-4
Renewable Energy Development Chapter 5
Final Report Economics of Solar PV Power Plant
(6) FIRR 3
Projection of revenue and cost are laid out for coming twenty years to calculate FIRR
(see the table below). FIRR obtained was 4.95%, higher than the calculated WACC
3.42%. Financial NPV calculated using the discount rate 3.42% was CNY 22 million.
However, we should not take this result at face value. This analysis method was
based on the assumption that the financial projection was valued in real terms: under
the inflationary condition, the interest rate of bank loan was converted to real terms
when WACC was calculated, and the O&M cost was considered to be constant in real
terms. One factor that does not go along is the income. The concession rate of power
purchase, CNY 1.15 per kWh, is likely to be inflexible upward in nominal terms, even
under very high inflation. Therefore, applying a constant concession rate in the
analysis for the whole project life may lead to overestimate of the income. One simple
approximation to avoid overvaluing of the result is to remove the inflation adjustment
in WACC, which leads to the WACC 7.35%. FIRR obtained, 4.95%, was much lower
than this, and Financial NPV would fall negative. Under the inflationary environment
with upward-inflexible price of main product, judgement on the result of the analysis is
not quite straightforward.
5-5
Chapter 5 Renewable Energy Development
Economics of Solar PV Power Plant Final Report
(7) FIRR/e 4
FIRR/e obtained for the same setting as in the preceding subsection was 4.46%. This
is much lower than NDRC Guideline value of 11% or the alternative lower threshold
8%. The project does not seem to be financially viable.
5-6
Renewable Energy Development Chapter 5
Final Report Economics of Solar PV Power Plant
The conditions of commercial bank loan were the same as before except that the
amount is now reduced to 10% of initial investment.
The result of the introduction of soft loan is shown below along with that for cases with
longer project life and additional income from CER.
Introduction of soft loan increases FIRR/e above the lower threshold value of 8%.
Extension of operation period for five years further improves FIRR/e. Combined with
the effect of additional income from CER, the Project will attain FIRR/e above 11%.
Preceding analyses were all based on the initial investment cost estimated by QBE in
2010. In a fast changing market environment of PV industry in PRC, this estimate may
no longer be relevant and the current cost level of PV equipment in PRC can be lower,
although QBEs estimate is much lower than the latest international market price level.
Examination was made to find the effect of smaller investment cost on project
financial performance, without resorting to such measures as introducing soft loans.
FIRR/es calculated for cases with lowered initial investment cost are shown below.
The additional income from CER was not considered here.
There are a few cases where FIRR/e is close enough to or exceeding the lower
threshold 8%. If the initial investment cost were 10 to 15% lower than QBEs estimate,
5-7
Chapter 5 Renewable Energy Development
Economics of Solar PV Power Plant Final Report
we may have the Pilot Project financially viable without the additional CER income,
although at least the project life would have to be extended to twenty-five years.
In the preceding section, the financial performance of the Pilot Project was assessed
with equity IRRs (FIRR/es) in nominal terms. The Pilot Project was found to give the
return lower than private investors expectations. Some measures for improvement
were considered; extending the project life to twenty-five years, securing additional
income from CER, and finally introducing softer loan in initial investment funding.
Each measure increases FIRR/e. But for the Pilot Project to attain FIRR/e larger than
11%, all of these measures should be employed.
In this subsection the result of the sensitivity analysis conducted for cases with
conditions shifting to adverse side. The base case is the case shown in Table 4.2-5,
using QBEs investment cost, with 50% of fund comes from a soft loan.
Income-increasing measures as an extension of the project life and additional income
from CER were handled as options.
Cases were considered for; (a) base case, (b) capital cost overrun by 10%, (c) benefit
(total revenue) lowered by 10%, (d) output of PV system deteriorate at faster rate at
1.5% per annum, (e) project implementation delayed for one year, (f) the CER income
reduced by 10%, (g) interest rates of loans increased by 10%, (h) combination of all
aforementioned conditions, (i) power conditioners needed an unscheduled whole
replacement (re-purchase) in 10th year, and (j) combination of d and i.
The most adverse conditions are represented by case (h), where FIRR/es in four
options fall to the lowest level but keep positive values. In case (e), the project
implementation was assumed delayed for one year, and the operation period
shortened. The second largest impact on FIRR/es was seen in the case.
5-8
Renewable Energy Development Chapter 5
Final Report Economics of Solar PV Power Plant
Having longer operation period surely increases the chance of better return. Problem
is that the Consultant do not know what may happen to Mega PV power plants after
ten to twenty years into operation, as the Consultant do not yet have many of such
cases. Such an option would bear extra risks related to time. Majority of such risks
may be attributable to deterioration of output and/or unexpected breakdown of
equipment. In base case the output of PV modules is assumed to fall by 0.8% every
year, corresponding to output falling to 92% in ten years and 85% in twenty years.
Considering the recent industrial standard of PV module manufacturers guarantee of
90% output for 10 years and 80% for twenty years, this assumption seems reasonable
but leaves some possibility of falling under more difficult situations. Such case was
considered in (d) where deterioration rate was set almost twice as fast. With 1.5%
deterioration rate, output will fall to 86% in ten years and 74% in twenty years, the
level that entitles the project owners to claim manufacturers guarantee. Further,
unexpected replacement of power conditioners in 10th year was considered in (i).
Combining (d) and (i), that is the case (j), FIRR/es in four options were shown to stay
above the level that seem not be very attractive, but not discouragingly low either, to
private investors.
Longer operation period may also raise a question of continuity of policy measures.
Qinghai Provinces July 2011 offer of CNY 1.15 per kWh is, although drastically lower
than offers for PV projects in the past few years, much more expensive than a
reference price for thermal power, CNY 0.35 per kWh in the country. The main
purpose of the high concession price for power purchase is to stimulate the market
and lower the cost of investment. Once this target is achieved, what would happen to
the policy measures while they are putting heavy burden on the budgets of the
5-9
Chapter 5 Renewable Energy Development
Economics of Solar PV Power Plant Final Report
Just to confirm the advantages of measures discussed above, another series of cases
was considered: for the concession tariff at CNY 1.0 per kWh. With the original
funding plan, FIRR/e fell to 2.01%. The results of sensitivity analysis are shown in the
table below. The lowered tariff at CNY 1.0 is 13% down from CNY 1.15, which gives
harsher condition than the case (c) in Table 5.1-7. For the cases where the project life
is set at twenty years, FIRR/e's all fall below the level of inflation if any of adverse
conditions comes to existence. And when all these conditions turn up together, FIRR/s
turns negative. However, with extended project life for twenty-five years, FIRR/e's all
stay above the inflation rate except in the case (h), and the project is unlikely to go
bankrupt.
Table 5.1-8 Sensitivity Analysis of FIRR/e with Soft Loan, tariff at CNY 1.0
FIRR/e
Change 20 years 25 years
w/o CER w/CER w/o CER w/CER
(a) Base case 5.18% 6.63% 7.59% 8.86%
(b) Capital cost overrun +10% 2.82% 4.24% 5.55% 6.78%
(c) Lower benefit -10% 2.58% 4.00% 5.34% 6.56%
(d) Faster deterioration -1.5% p.a. 3.79% 5.30% 6.31% 7.63%
(e) Delay of Construction 1 year 3.76% 4.88% 5.74% 6.78%
(f) CER income reduced -10% - 6.48% - 8.73%
(g) Higher Interest Rate +10% 4.76% 6.21% 7.21% 8.48%
(h) All of conditions above -1.93% -0.64% 0.00% 1.31%
Meanwhile, PV power generation also emits carbon dioxide in its lifecycle mostly
7 CO2 Emissions from Fuel Combustion Highlights, International Energy Agency 2011
5 - 10
Renewable Energy Development Chapter 5
Final Report Economics of Solar PV Power Plant
From the discussion above, we obtain a lifecycle reduction of CO2 emission due to PV
power plant operation to be 840 g-CO2 per kWh of generation.
Emissions of carbon dioxide and resulting climate change are considered to bring
about positive and/or negative changes to our lives and economic activities depending
on the regions and climate. And their net effect on global average is considered to be
negative. There are many efforts to evaluate the effect in monetary term, and IPCC 10
reported its finding from many researches estimates; the average of social cost of
CO2 emissions estimates to be US$ 12 per t-CO2 (the range from 100 estimates is
large (-$3 to $95/tCO2), and the net damage costs of climate change are projected to
be significant and to increase over time). Lifecycle reduction of social cost, in other
word social benefit, due to PV power plant operation is calculated to be 1.01 cent per
kWh of generation, that is CNY 0.068 per kWh.
As 10MW Pilot Project is just financially feasible at power selling rate of CNY 1.15 per
kWh, and this price is higher than the reference power production cost of CNY 0.35, it
is considered to pay CNY 0.8 extra cost to realize social benefit of CNY 0.068, which
is obviously very inefficient.
Whether the estimate of social cost of CO2 emission US$ 12 per t-CO2 is correct or
not, its magnitude will be larger in the future. The cost of fossil fuel and fossil fuel-fired
power production will be increasing as well. With decreasing PV generation cost, the
gap between expenditure on, and gain from the reduction of CO2 emissions will be
closing. For the time being, we could also narrow the gap, by choosing and investing
in better planned/designed PV projects, more efficiently operate and manage, and
extending life spans of working PV plants.
8 A guide to life-cycle greenhouse gas (GHG) emissions from electric supply Technologies, IAEA
9 As most of lifecycle emission of CO2 from PV power generation originates in PV cell production, the emission volumes should
be almost the same for 20 and 25 year operation. In this table, 6% of unit emission of coal-fired thermal power plant
emissions, that is 54 g-CO2/kWh, was used in both cases.
10 Fourth Assessment Report (AR4) of Intergovernmental Panel on Climate Change (IPCC), 2007
5 - 11
Chapter 5 Renewable Energy Development
Economics of Solar PV Power Plant Final Report
Now we look, from administrative perspective, at the adequacy of the concession tariff
CNY 1.15 per kWh for the PV projects connected to the grid by the end of 2011in
Qinghai Province. In order to support the concession tariffs for RE power development,
the Government has set an electricity price surtax of CNY 0.004 per kWh. The gap
between the reference power production cost of coal-thermal power plant (CNY 0.35
per kWh) and the concession tariff is approximately CNY 0.8 per kWh. This means
that to fill this gap, the power production and sales from coal-thermal power plants
connected to the Qinghai grid should be more than 200 times larger than the energy
sold by PV projects connected to the grid in 2011. In other words, PV produced
energy should be less than 0.5% of total energy consumption. The total electric
energy consumed in the Qinghai grid in twelve months from July 2010 to June 2011
was 47,944GWh. The expected annual production of energy by the Pilot Project is
16.8GWh, and assuming the same efficiency, PV projects of 2GW capacity in total
may produce 3,360GWh, which is 7% of energy consumed in the Qinghai grid. This
amount is 14 times larger than the level supportable (0.5%) by the collection of the
surtax. According to this simple calculation, the surtax will have to be raised to CNY
0.056 per kWh just to support the concession tariff for PV projects whose total
capacity is said to reach 2MW by the end of 2012.
5 - 12
Renewable Energy Development Chapter 5
Final Report Economics of Solar PV Power Plant
there were some measures to turn this around. Such measures shown effective
include; extending the project operation period from twenty years to twenty five years,
seeking additional income from CER, and as the most effective one, securing soft
loan for the fund for initial investment. For capital intensive PV projects, relieving the
burden of funding is crucial for the better financial performance. Investors will benefit
from access to foreign fund offering lower interest rates, longer repayment period and
grace period. At the moment, PV projects being promoted seem to have too many
uncertainties. For those new concession projects to prove themselves to be
creditworthy and bankable, disclosure of financial performance of preceding ongoing
projects can be effective and even necessary.
One measure found effective is to extend project life. Longer project life will not only
improve the financial performance of projects, but also contribute to the reduction of
carbon dioxide emission for most of carbon dioxide emission from PV power
generation comes from production and installation processes of the equipment.
Another effective and important measure is an introduction of soft loan in funding. For
capital intensive, expensive PV projects it is quite important to have funds available at
favourable, softer conditions. However, the financial conditions of ongoing PV projects
are not quite visible to outsiders, and international financial institutions may not see
them bankable. As these concession projects have been given tariffs way above the
tariffs for conventional power plants, by the fund collected from general users of
electricity, their basic financial position should be disclosed to public. The authorities
in charge of awarding concessions to projects may also benefit from monitoring the
financial performance of concession projects. Research on financial structures of
current PV projects will surely help formulate promotion policy for coming years.
Promotion policy may have to be revised as PV projects are expanding very rapidly.
The discussion is above points to a possibility of shortage of funds for concession
tariff. Although funds can be made available inter-province, the imbalance in Qinghai
Province is too large and may become unsustainable even nation-wide.
5 - 13
Renewable Energy Development Chapter 6
Final Report Policy Note, Key Findings, and Recommendation
CHAPTER 6
6.1 Outlook of Solar Energy Development in the PRC and the Qinghai Province
The government direction for the decarbonized power sector. The power sector
in the PRC has grown rapidly in tandem with the economic growth. Installed power
capacity has expanded by about 70% in the past five years alone. 1 Since the power
sector relies heavily on coal-fired power generation which accounts for more than
75% of total power, 2 the rapid expansion in capacity has caused large increase in
Carbon Dioxide (CO2), the major greenhouse gas (GHG) responsible for climate
change. 3 Promoting more diversified energy mix with higher share of renewable
energy is the core priority to decarbonize the countrys power sector to meet its
carbon intensity reduction target which is set at 40%-45% reduction by 2020
compared with 2005 levels. In 2005, the Renewable Energy Law of the PRC enacted
to kick start large scale renewable energy development in the country. It provides a
set of incentives to promote renewable technologies, specifies grid-feed in
requirements and standard procedures, and establishes supervisory measures. In
2007, the National Development and Reform Commission (NDRC) issued the
Medium and Long-Term Development Plan for Renewable Energy in the PRC, which
aims to increase the share of renewable energy in the total primary energy
consumption to 15% by 2020. 4 The Twelfth Five-Year Plan, 2011-2015, has set an
intermediate targets to increase share of renewable energy to 11.4% in 2015, and to
decrease carbon intensity by 17% by 2015 compared with 2005 levels to meet the
larger 2020 targets.
Huge solar PV production capacity and growing domestic market. The PRC is
the world largest solar cell producer with huge production capacity which shares
around 50% of 29.5 GW solar cell productions in the world as of 2011. Although the
worldwide solar cell market is estimated to be shrunk from 2012 and onward due to
aggressive cut feed-in-tariff (FIT) incentive in European countries, domestic huge
production capacity in PRC will continuously contribute to domestic solar PV market
expansion. With ambitious long term target in expanding solar energy install capacity,
and feed-in-tariff for solar energy project announced in 2011, the PRC has witnessed
a significant growth in domestic solar photovoltaic (PV) market where solar
photovoltaic (PV) installed capacity has surged by 2.9 GW from 0.9 GW in 2010.
During the Twelfth Five Year plan (2011 2015), the PRC has newly set a target for
1 National Energy Administration (2011) Report on Chinas Energy Development for 2011, Economic Science Press, Beijing.
2 National Energy Administration (2011) Report on Chinas Energy Development for 2011, Economic Science Press, Beijing.
3 GHG emission from energy sector in PRC accounts for 46.9% (or 3,376.7 MtCO2e) of total GHG emission.
4 Current installed capacity of renewable energy is 261 GW, which is 27% of total installed capacity or 18% of total power
generation in 2010. Targets of renewable energy install capacity by 2020 for wind, solar, hydro, and biomass are more than
150 GW, 20 GW, 380GW, and 30 GW respectively.
6-1
Chapter 6 Renewable Energy Development
Policy Note, Key Findings, and Recommendation Final Report
solar PV install capacity by 20 GW. As long as such surging trend continues, solar PV
market in PRC will be on rapid growth trajectory in high case scenario or be fallen
between Medium and high case scenario as in Fig.6.1-1.
Low plan
Medium plan
High plan
Grid parity for Solar PV and evolving off-take tariff level. Huge solar cell
production capacity and the expanding solar PV market in PRC will also enable solar
PV cost of energy to decline significantly. Though speed of decline in its cost of
energy depends on global and domestic solar PV market condition, and on the
presence of effective incentive policy for sustainable solar PV investment, solar PV
could still be competitive with thermal power plant and could reach CNY 0.6/kWh of
grid parity by 2020 as is in Fig. 6.1-2.
A decline in grid connected solar PV off-take tariff has been very impressive since
2007. Current CNY 1.0 per kWh of solar energy FIT is composed of benchmark tariff
(CNY 0.304/kWh) derived from thermal power plant off-take tariff and the government
subsidy (CNY 0.696/kWh) sourced from the renewable energy electricity price surtax.
In 2007 and 2008, National Development and Reform Commission (NDRC) approved
4 solar PV projects up to 1MW in two batches, including 2 in Shanghai and each in
Inner Mongolia and Ningxia, for which the electricity price to the grid of CNY 4.0 per
kWh was applied. In 2009, the government of PRC launched the first concession
bidding program for 10MW pilot grid-connected PV project in Gansu. The average bid
price from the 13 bidders was CNY 1.42 per kWh, and the awarded off-take price was
CNY 1.09 per kWh. The second batch concession bidding program for total 280 MW
in 2010 induced further decline in off-take price which was between CNY0.73 - 0.98
per kWh. In July 2011, the National Development and Reform Commission issued the
Circular on completing policies on electricity price to the grid for solar energy PV
power generation, which introduces a national unified benchmark off-take tariff to the
6-2
Renewable Energy Development Chapter 6
Final Report Policy Note, Key Findings, and Recommendation
grid connected PV. It specifies that, for PV projects approved for construction before
July 1, 2011 and able to complete before December 31, 2011, off-take tariff to the grid
of CNY 1.15 per kWh is applied, and for those not meeting the above conditions,
off-take tariff to the grid of CNY 1.0 per kWh would be adopted except for those in
Tibet.
Realize parity
price around
Qinghai province a major driver for solar energy development. Qinghai Province,
which is located in the northeastern part of the Qinghai-Xizang plateau in the western
part of PRC, has abundant mineral and natural resources, while its Gross Regional
Domestic Product (GRDP) is the second lowest of all the provinces in PRC. To
enhance economic development by utilizing these resources in environmentally
sustainable manner, the Qinghai Provincial Government has set a development
agenda for promoting solar energy, which would supply clean electricity to the load
centers in the eastern part of PRC, and for developing a solar PV-related supply-chain
industry, utilizing more than 20GW of solar power resource potential with around
2,000 kWh/day of solar irradiation resources and the rich silica deposits in the Qinghai
Province. The installed capacity of grid-connected solar PV systems in Qinghai
Province reached to 1,010MW by the end of 2011 which was 47.2% of total solar PV
installed capacity in PRC, and 1,000 MW additional solar PV power plants will be in
operation by the end of 2012. Qinghai provincial government plans to concentrate the
grid-connected solar energy power plants in Qaidam basin in Haixi prefecture to add
solar energy install capacity by 1,000 MW per year during the twelfth five-year plan
(2011-2015) period. By 2015, the planned solar energy install capacity will be 4,000
MW comprised of 3,500 MW of the grid-connected solar PV power plants, 300 MW of
the concentrating solar thermal power plants, and 200 MW of distributed solar PV
6-3
Chapter 6 Renewable Energy Development
Policy Note, Key Findings, and Recommendation Final Report
Qinghai province has been and will continuously be a major driver for solar energy
development in PRC. But challenges lie ahead, in view of grid-connectivity and
stability, electricity yield risk, financial viability, system quality assurance, and
development planning, to realize sizable grid connected MW and GW class solar PV
investment as planned in twelfth five-year plan (2011-2015) and onward till 2020.
6-4
Renewable Energy Development Chapter 6
Final Report Policy Note, Key Findings, and Recommendation
6.2.2 Upgrading Grid Code which requires FRT Function: Improving Grid Stability
and Safety
When a fault occurs in a grid, the voltage drops and frequency and power flow are
also disturbed. Under this disturbed grid condition, the conventional power plants
connected to the grid try to keep sending power to the grid, which helps the grid
recover from the disturbed condition. If it drops out of N-1 criteria, the interconnection
lines must be disconnected or the whole grid will corrupts at worst. The solar PV
systems do not have the modulation capability, and it stops operation (parallel off from
grid) when voltage drop and/or disturbed frequency observed. This parallel off is an
unexpected trip. When the total capacity of PV plants that have gone parallel off is too
large, the gird collapses. To solve this problem there is a technology developed which
is called Fault Ride Through (FRT) function. This function enables the inverters to
keep operations when an instant voltage drop and/or disturbed frequency
encountered. The FRT function is essential to avoid the unexpected trip and to keep
the grid stability. Since the grid code to date does not require FRT function for solar
PV power plants, upgrading the grid code in which FRT function is compulsory
requirement for grid connection is urgently needed. On top of it, as grid-connected
solar PV is expected to be sharply increasing even within a couple of years, low
voltage recovery time (LVRT) is also suggested to be shortened from 2.0 Sec to 0.5
Sec in immediate future for enhancing grid safety.
80
Within
1 Sec
China
30
20 Japan
(before March, 2017)
6-5
Chapter 6 Renewable Energy Development
Policy Note, Key Findings, and Recommendation Final Report
The micro grid system has small size power grid and controls supply and demand
power within the system. It connects multiple power-generating facilities and electrical
storage devices, including natural-energy sources such as solar power, thereby
ensuring a stable supply of electricity. The micro-grid system provides optimal control,
adjusting and maintaining the balance between demand and supply to ensure a stable
supply of electricity. The micro grid system is also effective to reduce the influence
caused by the fluctuation of the large solar PV system to the wide range power grid.
In case of micro-grid system in Los Alamos County in the United States which is up
and running in September 2012, solar PV power generation system and storage
batteries (1 MW of NAS batteries and 0.8 MW of lead batteries) are introduced to
compose micro grid system with around $37 million of initial investment cost.
Real-time price signal system from the Energy Management System (EMS) of the
power distribution lines is also designed to monitor solar PV power generation, power
storage volume in the secondary batteries, and electricity consumption inside the grid
system. In this micro grid system, clustered PV power generation system and storage
batteries that connect between the power distribution substation and the switchgear
are installed, and demonstrate the ability to control variations in solar radiation with
storage batteries. EMS for controlling the system is introduced and the smart
equipment on the power distribution lines
to simulate distribution lines with a high
PV power penetration into the grid is
operated. In case of Qinghai, the similar
concept of Los Alamos micro grid is
applicable. Golmud city could be the
candidate for the micro grid system as
the pilot testing location, using abundant
solar PV electricity supply capacity from
adjacent solar park and the natural gas
resources as back-up.
6-6
Renewable Energy Development Chapter 6
Final Report Policy Note, Key Findings, and Recommendation
inverter loss at DC-AC conversion, which will be resulted in a decline in overall plant
efficiency over time. Such possible quality deterioration in grid connected solar PV
performance will directly impact on electricity generation and economics of power
plant as a whole. Qinghai provincial government authority has made necessary
arrangement for grid connection and acceptance, water supply, access road, and
peak regulation. But, due to the absence of stringent and enforceable technical
specification standard, limited experience of developers, and very narrow construction
timeframe, a possible decline in the plant output over the times needs to be
anticipated without effective quality control measures.
In parallel, building technical guidance and supervision team under the provincial
government authority is also suggested to conduct technical evaluation of whole
project cycle including construction and operation, and strengthen supervision and
guidance for solar PV owners who fail to attain originally predicted annual power plant
output. Moreover, solar energy projects using unique and variety of technology such
as various type of concentrating solar thermal power (CSP), concentrating PV (CPV),
micro-grid are expected to be emerging in immediate future. As less down 50 MW
solar energy project is fallen in provincial government approving authority, continuous
capacity enhancement of such the provincial technical team and the local design
institute will also be essential to assure quality and performance of solar energy
projects in Qinghai.
Reliable solar irradiation data is essential to predict electricity yield throughout more
than 20 years of solar PV project life. Project site selection and electricity yield
forecasting are always based on historical solar irradiation data and changes in
weather patterns from year to year, and long term data are desirable for determining a
representative annual data set. Currently, solar irradiation forecasting uses the
approach (i) comparing locally measured ground data (at site and at metrological
station less than 10 km from the site) to the satellite-derived data for the same time
interval, and (ii) correcting any bias in the satellite data to generate the improved solar
irradiation data set. In Qinghai, only 3 out of 54 meteorological observatory stations in
6-7
Chapter 6 Renewable Energy Development
Policy Note, Key Findings, and Recommendation Final Report
operation have solar irradiation measurement function. But, in such a case, the solar
energy developer is likely to confront a lack of reliable solar irradiation and related
weather data sets due to limited number of metrological stations near by the potential
site, and short and discontinuous period of times of data sets. Ground measurement
data at the site over 12 months would not have good fit with satellite-derived data in
general due to short period of data accumulation and measurement error. Relaying
upon satellite-derived data is likely to cause more than 20% of high uncertainty in
solar irradiation forecasting, which will be resulted in the reduced electricity yield and
deteriorated financial performance of the project. Unreliable solar irradiation
forecasting will also disturb stable grid operation accordingly.
Considering the provincial government has set 20,000 MW of solar energy install
capacity by 2030 and has planned to concentrate solar energy power plant in Golmud,
enhancing metrological observatory system in Qinghai by (i) increasing number of
metrological observatory stations (one station in each 10 km mesh is desirable), and
(ii) accumulating continuous time series solar irradiation and related weather data set
will be a great help to gain developers and transmission operators confidence in
irradiation resource and electricity yield forecasting for sustainable solar PV
development in Golmud.
Financial assessment for the pilot 10 MW solar PV power plant indicates that financial
rate of return (FIRR) of 4.95% at base case scenario, which is higher than 3.42% of
weighted average cost of capital (WACC). Setting appropriate tariff level taking into
consideration latest static investment cost trend and leveraged cost of energy (LCOE)
will be essential for sustainable solar energy development. But, if credit enhancement
support will be in place, the project could become financially viable even with CNY 1.0
per kWh of off-take tariff level.
One approach found effective is to
extend loan tenor and project life
from 20 to 25 years. Longer loan
tenor and project life will not only
improve the financial performance
of projects, but also contribute to the
reduction of carbon dioxide
emission for most of carbon dioxide
emission from PV power generation
comes from production and installation processes of the equipment. Another effective
and important approach is an introduction of soft loan in funding plan. For capital
intensive, expensive PV projects it is quite important to have such funds having low
6-8
Renewable Energy Development Chapter 6
Final Report Policy Note, Key Findings, and Recommendation
cost and long term tenor terms. Given that (i) extension of loan tenor and project life
from 20 to 25 years, and (ii) 2.6% of interest rate with 25 years tenor (including 5
years grace period) are considered, the equity IRR improves to 7.59% from 2.01% in
the original case. If certified emission right (CER) is considered, the equity IRR further
improves 8.86%. Providing that all credit enhancement supports are accommodated
(2.6% interest of low cost and 25 years of long term loan with CER revenue),
sensitivity analysis shows that the equity IRR of the project would decrease to (i)
6.78% if there were a capital cost overrun 10%; (ii) 6.56% if revenue decreased by
10%; (iii) 7.63% if deterioration accelerated by -1.5%, (iv) 6.78% if there were 1-year
delay in construction; (v) 8.73% if CER price declined by 10%; and (vi) 8.48% if
interest rate hiked by 10%. The project is considered financially viable and
sustainable under various adverse scenarios. Credit enhancement support will greatly
improve the project financial performance.
6-9
Renewable Energy Development
Final Report Appendices
APPENDICES
Renewable Energy Development Appendix 1
Final Report Terms of Reference
APPENDIX 1
TERMS OF REFERENCE
Renewable Energy Development Appendix 1
Final Report Terms of Reference
TERMS OF REFERENCE
1. The technical assistance (TA) will be implemented over 14 months. The TA will require
the services of 16 person-months of international and 16 person-months of national
consultants.
2. Asian Development Bank (ADB) will recruit the consulting firm (including international
and national consultants) in accordance with its Guidelines on the Use of Consultants
(2010, as amended from time to time) through a quality- and cost-based selection
method to provide the services for implementation, management, and progress
monitoring of the TA. The terms of reference of the consulting services will include:
A. International Consultants
A1 - 1
Appendix 1 Renewable Energy Development
Terms of Reference Final Report
(i) assess the capacity and quality of the solar PV supply chain, including silicon solar
wafer and solar cell production;
(ii) provide technical guidance to develop a feasible solar PV supply chain for a
10-MW-class grid-connected solar PV system in Qinghai Province;
(iii) coordinate with the team leader to prepare technical guidance notes and a capacity
enhancement module, and to conduct capacity development training for relevant
counterpart staff, in consultation with the IA; and
(iv) coordinate with the team leader to prepare a policy note, including key findings and
recommendations based on activities under the TA.
A1 - 2
Renewable Energy Development Appendix 1
Final Report Terms of Reference
(i) introduce international best practices for grid protection design and system
configuration for a 10-MW-class grid-connected solar PV system;
(ii) assist the IA with liaising and discussing grid codes with grid operators, and with
identifying the required grid protection system design;
(iii) review the detailed design of the pilot 10-MW-class grid-connected solar PV system,
and provide technical guidance on grid protection system configuration and design;
(iv) coordinate with the team leader to prepare technical guidance notes and a capacity
enhancement module, and to conduct capacity development training for relevant
counterpart staff, in consultation with the IA; and
(v) coordinate with the team leader to prepare a policy note, including key findings and
recommendations based on the activities under the TA.
B. National Consultants
9. The national consultants will comprise (i) a deputy team leader and solar PV planner (4
person-months), (ii) a solar PV engineer (3 person-months), (iii) a solar PV system
designer (4 person-months), (iv) a solar PV supply-chain specialist (2 person-months),
(v) a transmission engineer (2 person-months), and (vi) a financial analyst (1
person-month). They will work with the corresponding international consultants. They will
also assist the international consultants in reviewing relevant reports, data, policies, and
regulations, and will translate relevant documents into English.
C. Reports
10. The consultant shall submit the following reports to ADB (in English) and to the EA and
IA (in Chinese):
A1 - 3
Appendix 1 Renewable Energy Development
Terms of Reference Final Report
(iii) Draft Final Report. It will be submitted within 12 months after commencement of
services. Upon submission of the draft final report, a final workshop will be held,
attended by relevant stakeholders, to get feedback on the report.
(iv) Final Report. It will be submitted within 1 month after receipt of comments from
ADB and the government on the draft final report. The final report shall take into
consideration the comments of ADB, EA, and IA. A summary report, of a maximum
of 10 pages, should be included in the final report.
A1 - 4
Renewable Energy Development Appendix 2
Final Report National Development Plan and Provincial Development Plan
APPENDIX 2
The Renewable Energy Law of China coming into effect on January 1, 2006 clearly
indicates the strategic significance of developing renewable energy, and put it clearly
that This law has been formulated with the purpose to promote the development and
utilization of renewable energy resources, increase energy supplies, improve energy
structure, safeguard energy security, protect the environment and realize the sustainable
development of economy and society. The Renewable Energy Law mainly establishes
the basic system framework, and the fundamental method to support the development of
renewable energy is compulsory supply to the grid, purchasing in total amount,
implementing categorized electricity price and distribute their costs over the whole grid".
After practice for a certain period of time, in December 2009, the NPC revised the
Renewable Energy Law, which mainly responds to some questions about operability in
local areas, in addition to its further completion.
The revised version clearly set forth the centralization of formulation of plan, review and
approval authority: the department in charge of energy under the State Council shall, in
conjunction with the national power regulatory authority and finance authority, determine
the proportion of renewable energy power generation in the total power generated that
should be introduced in the planned period according to the national program to develop
and utilize renewable energy resource, and also work out the specific methods to
dispatch in priority and purchase in total amount of the power generated utilizing
renewable energy by enterprises in the grid, and the department in charge of energy
under the State Council will supervise its implementation during the year in conjunction
with the national power regulatory authority. The peoples committees at all localities
shall prepare their own programs based on the national plan and the medium and
A2 - 1
Appendix 2 Renewable Energy Development
National Development Plan and Provincial Development Plan Final Report
long-term targets in the regions, and submit them to the department in charge of energy
management under the State Council and the national power regulatory authority for
filing, and organize their implementation. Technological development has been
emphasized and capital sources were specified. The state will set up renewable energy
development fund as governmental foundation, which will come from earmarked funds
arranged by the national finance for the year and the surtax for renewable energy
electricity price collected, and purchasing in full amount will be modified as guaranteed
purchasing in full amount.
By guarantee, it specifies clearly the responsibilities and obligations of the three parties
of grid enterprises, power generation enterprises and the government. The government
shall formulate programs and make administrative permission, the power generation
enterprises will obtain permission or make filing and supply electric energy complying
with standard according to the program and also ensure the safety for grids. Grid
enterprises purchase the power in full amount according to program, and permit and
strengthen grid construction.
Therefore, the Renewable Energy Law and its revised version have established the
basic system framework for renewable energy in China, including the total quantity target
system. The government is required to formulate development programs and put forth
total quantity targets, the fixed electricity price and cost amortizing system. It is required
to combine governmental pricing with electricity price determined by bidding, and the
extra cost be shared by all users; financial allowance system: allowance can be granted
by finance at both central and local levels, the central government can establish
renewable energy development fund and some local governments can also set up their
renewable energy development funds, and tax preferential system: preferential
conditions for VAT and income tax.
As the cost of photovoltaic power generation is far above the present purchasing price at
grid for hydropower and thermal power in China (CNY 0.35 -0.45 per kWh), and also
higher than the wind power generation cost (CNY 0.5-0.6 per kWh), after the
implementation of the Renewable Energy Law, the formulation and implementation of
specific policies on PV power generation in China now lags behind wind power and
biomass power, and is in the conditions of consultation on case by case basis.
The National Development and Reform Commission (NDRC) issued document Fagai
Jiage [2007] No. 44 Tentative measures for allocation of renewable energy electricity
price surtax income on January 17, 2007, which specifies that the allowance for
renewable energy electricity price will be paid from the renewable energy electricity price
surtax, which will be levied at CNY 0.002 per kWh in the whole country since June 2008
A2 - 2
Renewable Energy Development Appendix 2
Final Report National Development Plan and Provincial Development Plan
(now it has been raised to CNY 0.004 per kWh). It is specified in the document that the
later period operation and maintenance expenses for off-grid power generation system
constructed with state investment will also be paid from the renewable energy power
surtax. The concept of quota transaction was also put forth. The document defined the
bid electricity prices or government-determined prices for wind power (about CNY
0.4-0.6 per kWh), the benchmark electricity price for biomass will be increased by CNY
0.25 per kWh, slightly higher than that of wind power (CNY 0.5-0.7 per kWh), but the
document did not specify the electricity price for grid-connected PV power generation.
On August 31, 2007, document Fagai Nengyuan [2007] No. 2174 Medium and
long-term development program for renewable energy was issued, in which the planned
accumulated installed capacity of PV power generation was to be only 300MWp in 2010
and 1.6GWp in 2020. Now it is known that these targets were too low.
On November 22, 2007, document Fagai Nengyuan [2007] No. 2898 Circular on
relevant requirements on construction of large-scale grid-connected pilot PV power
stations was issued to 8 provinces and autonomous regions, which required that power
stations shall be constructed on non-cultivated land such as desert and Gobi, and their
size shall be no less than 5MW. The document specifies that electricity price to the grid
will be determined through bidding, and the cost exceeding the price can be shared
nationwide via the income of renewable energy electricity price surtax. This circular
started the prelude of constructing large-scale PV power stations in desert areas.
In 2007 and 2008, NDRC approved four PV power station projects up to 1MW in two
batches, including 2 in Shanghai and one each in Inner Mongolia and Ningxia, for which
the electricity price to the grid of CNY 4 per kWh would be applied, and the part above
the benchmark electricity price of local desulfurization coal-fired units will be shared
nationwide.
.
At the end of 2008, the National Energy Administration issued Zong Han [2008] No. 70
documents Reply letter from National Energy Administration for the construction of
10MW pilot grid-connected PV power generation project in June 2009 at Gansu
Dunhuan, launching the bid invitation for the project. The average price from the 13
bidders was CNY 1.42 per kWh, and the awarded electricity price to the grid for the two
10MW PV power stations approved in June 2009 was CNY 1.0928 per kWh.
In August 2010, bids were called for the concession right for the second batch of thirteen
ground PV power station projects totaling 280MWp, and the awarded electricity price to
the grid was between CNY0.7288 and 0.9791 per kWh.
During the same period, the electricity price to the grid of other administratively licensed
A2 - 3
Appendix 2 Renewable Energy Development
National Development Plan and Provincial Development Plan Final Report
In April 2011, in the circular for 930 Projects in Qinghai, the electricity price to the grid of
CNY 1.15 per kWh was adopted.
In July 2011, the NDRC issued the Circular on completing policies on electricity price to
the grid for solar energy PV power generation, deciding to adopt a national unified
benchmark electricity price to the grid for PV power generation, and it specifies that, for
PV power generation projects approved for construction before July 1, 2011 and able to
complete before December 31, 2011, an electricity price to the grid of CNY 1.15 per kWh
would be adopted, and for those not meeting the above conditions, an electricity price to
the grid of CNY 1 per kWh would be adopted except for those in Tibet, and this circular
also specifies that PV power generation projects for which owners are determined by
competitive bid for concession right would be given the bid awarding electricity price,
which shall not be higher than the above-mentioned benchmark electricity price.
On July 16, 2009, the Ministry of Finance, Ministry of Science and Technology and
National Energy Administration jointly issued Circular on implementing Golden Sun Pilot
Program, making clear that the central finance can provide some project funds from
earmarked funds for renewable energy, to support the pilot application of PV power
generation technologies in various fields and the industrialization of key technologies.
A2 - 4
Renewable Energy Development Appendix 2
Final Report National Development Plan and Provincial Development Plan
Table 1-1 Bid Prices for Large-scale Desert PV Power Stations in 2010
Installed Lowest price Next lowest Highest Average
Construction
capacity Bidder offer price offer price offer price offer
location
(MWp) (CNY//kWh) (CNY//kWh) (CNY//kWh) (CNY//kWh)
Yellow River Upper Reaches
Qinghai Gonghe 30 Hydropower Development Co., 0.7288 0.8595 1.2100 1.0227
Ltd.
Yellow River Upper Reaches
Qinghai Henan 20 Hydropower Development Co., 0.8286 0.8377 1.2000 1.0092
Ltd.
China Power International New
Gansu Baiyin 20 0.8265 0.8812 1.2000 1.0484
Energy
Gansu Jinchang 20 Huaneng New Energy Industry 0.7803 0.8010 1.0900 0.9128
Inner Mongolia Alxa 20 Inner Mongolia Guodian Energy 0.8847 0.8899 1.0600 0.9588
Ningxia Qingtongxia 30 Huaneng New Energy Industry 0.9791 1.0745 1.3500 1.1417
1.3 Planning for Renewable Energy during Twelfth Five-Year Plan Period
The year of 2011 is the first year to implement the "Twelfth Five-Year Plan for Economic
and Social Development in China. Although the Twelfth Five-Year Plan for renewable
energy has not yet been officially published, the total quantitative target of PV power
generation has been basically determined, i.e. the total installed capacity of PV power
generation in China will be 10GW by the end of 2015, and for long term, the planned
target is 50GW for the year 2020. These will be minimum figures. In the photovoltaic
development projection map of China prepared by some institutions, higher targets were
set as 15-20GW in 2015 and 100GW in 2020, which are realistic targets.
A2 - 5
Appendix 2 Renewable Energy Development
National Development Plan and Provincial Development Plan Final Report
Low plan
Medium plan
High plan
There are many reasons to make such estimation. First, the base quantity of installed
capacity on photovoltaic market in China is quite low, but the development momentum in
recent years has been strong. If an annual average growth rate of 62% can be
maintained, the target of high scenario among the plans above can be realized. As a
comparison, the global annual average growth rate of installed capacity of PV power
generation is 55.5% during the past decade, and is about 68% during the last 5 years.
Secondly, China has fairly good commercialized development experience for the off-grid
PV power generation, thus in the coming decade, the era of parity price to grid for PV
power generation will come, and marketization will progress rapidly.
Realize parity
price around 2021
Price of average PV Conventional power Residential Power Power for Industrial etc.
Fig. 1-2 Line Map for Parity Price to Grid for PV Power Generation in China
A2 - 6
Renewable Energy Development Appendix 2
Final Report National Development Plan and Provincial Development Plan
The above figure shows that, in China realization of parity price to grid can be expected
in around 2014 for industrial and commercial power (user side), around 2018 for
residents power (user side) and around 2021 for selling power to the grid (power
generation side).
A2 - 7
Appendix 2 Renewable Energy Development
National Development Plan and Provincial Development Plan Final Report
The year 2009 was the start of large scale application in the PV development in
China. Good achievements were obtained for PV technologies in power supply in
rural areas and commercial application in special fields, with fair market foundation,
the detailed rules for implementation for Renewable Energy Law were issued
before the end of 2008, and policy environment was basically established. In 2008,
four PV grid-connected projects obtained electricity price subsidy. The concession
right tendering for the first 10MWp PV power station in China was conducted at the
beginning of 2009, the photovoltaic building pilot program and Golden Sun pilot
program of the state were started in succession in 2009. In November 2009, the
surtax for renewable energy power was increased from 0.2 fen/kWh to 0.4 fen/kWh,
and many local governments issued various preferential policies and prepared the
PV industry development plans for the areas, promoting the PV application in larger
scale in China. Although most of the above-mentioned national programs were not
completed in 2009, apparent heat could be felt in PV market in 2009.
The installed capacity in 2009 in China reached 160.2 MWp, four times larger than
that of the previous year, and exceeding the total of previous years, bringing the total
installed capacity to 300MWp by the end of the year, and PV systems developed
were for grid-connected operation and large-scale ones. In 2009, large PV power
stations sized at 5MWp, 10MWp and 20MWp were completed starting its
generation.
The implementation of specific policies such as pilot of PV electricity price to the grid
and Golden Sun pilot program gave rise to expectation for larger scale PV
applications. In 2010, the added installed capacity reached 530MWp, including the
two 10MWp desert PV stations completed for operation as the first batch of
concession right tendering by the National Energy Administration and some PV
systems completed with national project support for initial investment, plus the PV
projects supported by local policies and the marketized PV applications.
A2 - 8
Renewable Energy Development Appendix 2
Final Report National Development Plan and Provincial Development Plan
Meanwhile, for the national pilot PV project in the form of subsidy for initial
investment, about 1030 MW was approved for construction during 2009-2010 and
about 800MW in 2011, as the specific final completion time was determined for
projects launched in batches, it is estimated that the installed capacity completed in
2011 will be about 800-900MW.
When other local projects and commercial projects are added, the increased PV
installed capacity in China in 2011 will at least exceed 1.5GWp, with high probability
to reach 2GWp.
A2 - 9
Appendix 2 Renewable Energy Development
National Development Plan and Provincial Development Plan Final Report
photovoltaic building pilot program and Golden Sun pilot program projects, PV
systems are developing for grid-connected operation and large-scale systems. At
the end of 2008, only several dozens of grid-connected power generation systems
were built, with installed power being several kW, and the 1.5MWp as the largest.
Most of them were PV power generation systems in conjunction with buildings.
These systems mostly were connected to grid at low voltage side, with anti-reverse
devices, for self-consumption of the power generated. In 2009, large sized ground
PV power stations of 5MWp and 10MWp were completed for operation, and the
20MWp PV power station at Xuzhou was put into operation at the end of the year,
which obtained support for electricity price to the grid by Jiangsu Province.
The implementation of specific policies such as pilot of PV electricity price to the grid
and Golden Sun pilot program gave rise to expectation for larger scale PV
applications. In 2010, the added installed capacity reached 530MWp, including the
two 10MWp desert stations completed for operation as the first batch of concession
right tendering by the National Energy Administration and some PV systems
completed with national project allowance in initial investment, plus the PV projects
supported by local policies and the marketized PV applications, and this brought the
total installed capacity to 830MWp.
2 10MWp desert
First concession Mar. ~ May Gansu
grid-connected About 1.9-2.1 1.0928 CNY/kWh
right tendering 2009 Dunhuang
stations
2 30MWp and 11
Second 6 western
June ~ 20MWp desert
concession right provinces and About 2.0 0.7288-0.9791 CNY/kWh
Sept. 2010 grid-connected
tendering regions
stations
5MWp; 10MWp Built by power
Pilot project 2009 Ningxia etc. desert grid-connected generation 1.15 CNY/kWh
stations enterprise
A2 - 10
Renewable Energy Development Appendix 2
Final Report National Development Plan and Provincial Development Plan
With the continuous increase of capacity of PV systems, the PV market in China has
been transiting gradually from off-grid systems to grid-connected systems as the
main. In 2008, although the electricity price to the grid and grid purchasing price
were basically not opened, installed capacity of PV grid-connected systems
increased substantially, with the proportion rising from 10% in previous year to about
47%. The share of accumulated installed capacity also reached 17.8%, and in 2009,
grid-connected systems accounted for about 85% of the annual total, with
accumulated share exceeding 50%. In 2011, grid-connected systems have become
further dominated.
Off-grid Grid-tied
142.0
InstallationMW
150.0
100.0
50.0 21.0
17.8 19.0 18.0
8.8 1.2 7.4 1.5 9.0 1.0 2.2
0.0
2004 2005 2006 2007 2008 2009
Year
(3) Substantial Decrease of Initial Investment Cost and Power Generation Cost
The electricity price to the grid for the four PV systems for connection to grid
approved by the state in 2008 was CNY 4 per kWh. Affected by the financial crisis
originated in the USA, the prices of PV products dropped substantially at the end of
2008 and beginning of 2009, greatly reducing the initial investment cost for
constructing PV power stations. According to estimation at the time, in some areas
with good radiation and land conditions in western China, the unit initial investment
cost for constructing PV power stations could be about CNY 20000~25000 per kWp,
and the reasonable electricity price to the grid should be in the range of RM 1.2-1.6
per kWh.
In March 2009, in the concession right tendering launched by the National Energy
Administration, a bidding electricity price to the grid of CNY 1.0928 per kWh was
A2 - 11
Appendix 2 Renewable Energy Development
National Development Plan and Provincial Development Plan Final Report
appeared. No matter how this price really reflected the original intention for
sustainable development reasonable cost plus reasonable profit, the fact that the
unit investment cost for PV systems and power generation cost have decreased
substantially is worth to be noted. The two 10MWp projects in Dunhuang were
connected to grid for power generation in 2010.
After the financial crisis, the global PV market restored quickly, and the market price
of PV products rose slightly. Although PV modules have been in short supply for
demand since mid 2009 as driven by the international market, their prices remained
at the level slightly above the price that at the beginning of 2009 (for which
expanded production and technological progress played major roles, and if the tight
supply of silicon materials could be lessened, the price of PV modules would
decrease further). In the ground PV power stations subsequently approved with
consultation case by case, electricity price to the grid of CNY 1.15 or 1.12 per kWh
was given, and in some provinces with relatively inferior resources conditions,
electricity price to the grid of about CNY 1.7 per kWh was offered. In 2010, in the 13
projects sized 20-30MWp in western provinces and regions in the second batch of
concession right tendering launched by National Energy Administration, electricity
price of CNY 0.7288-0.9791 per kWh was awarded under the principle of awarding
with lowest price.
Since the state launched the concession right tendering for construction of
large-scale PV power stations, state and local power companies and energy
investment groups including the five major power groups all show great attention to
the realistic and potential market of PV power generation and are actively participate
in it. The concession right tendering results and the investment and construction of
large-scale desert PV power stations show that these large-scale state-owned
enterprises have absolute adavantage. Large-scale power enterprises not having
been awarded with contract are in active work to build bases in areas with good
resources conditions, and most power enterprises have formed specialized solar
energy companies to construct pilot and research projects of different sizes, to pave
A2 - 12
Renewable Energy Development Appendix 2
Final Report National Development Plan and Provincial Development Plan
the way for future development. Before the national benchmark electricity price was
issued, a number of large-scale projects have been completed. For example, the
Solar Energy Company of CGNPC has built a 10MWp PV power station at Gansu
Dunhuang (with concession right bidding) and Qinghai Xitieshan, and it also has
projects of 70MWp under construction. Ningdian Group also built some 5MWp and
10MWp PV power stations at Shizuishan and Taiyangshan, and is building
upstream industries. Guodian Longyuan, Huaneng, Huadian and Datang Power
have also constructed some 5-40MW PV power stations, which are now in trial
operation.
Crystal silicon solar cells remain the mainstream product in market application, and
in addition to the traditional fixed inclined mounting method which is still being widely
adopted, plate tracking systems with double shafts, flat single shaft and inclined
single shaft are also been applied in many projects. Due to gradual improvement of
sun tracking technology, tracking precision and reliability indicators have been
improved, high multiple concentrating photovoltaic system (CPV) is been gradually
marketed, and in some enterprises, gallium arsenide high multiple (available in 300,
500 and 1000X) concentrating modules and systems are being made and installed.
Great progress was also achieved for the market application of film solar cells in
2009, and silicon based film cells and CIGS cells have gained more applications in
building integrated PV (BIPV). Some practical BIPV projects with different features
have been completed by some companies.
A2 - 13
Appendix 2 Renewable Energy Development
National Development Plan and Provincial Development Plan Final Report
installed in the country. In 2010, PV modules exported exceeded 8GWp, while about
0.53GWp were installed in the country, accounting for only about 6%. In 2011, the
PV export will possibly reach 10GWp, and proportion of domestic installation will
possibly increase to 15%-20%, with installed capacity of 1.5 - 2GWp during the year.
Qinghai Province is located in the western China, with very rich solar energy and land
resources, and ready conditions to build large-scale PV power stations. In the design and
construction of large-scale photovoltaic power generation projects, the power generation
efficiency is low in many projects in China in general. With the power generation cost
higher than that of traditional forms of power generation, increasing the efficiency of the
whole system will be the main issue to cut power generation cost. In this research
subject, the local policies and grid conditions will be expounded in conjunction with the
actual local conditions, and policy notes and suggestions on design of photovoltaic
system are proposed.
Over a long time, due to investment by the state in power supply projects to areas
previously no access to electricity and the support to commercialized development of
photovoltaic products in rural and pasture areas, China has achieved fairly substantial
A2 - 14
Renewable Energy Development Appendix 2
Final Report National Development Plan and Provincial Development Plan
Before the national unified benchmark electricity price was issued, some provinces and
regions formulated policies to encourage PV application projects, to push the
implementation of PV projects in local areas. Among them, Jiangsu, Zhejiang and
Shandong with good economic conditions and concentrated PV enterprises formulated
specific policies on PV electricity price to the grid, therefore, some PV power stations
connected to the grid were constructed during 2009 to 2011 in these provinces, with the
maximum single station size being 20GWp. However, not many projects were approved
due to the limitation of available subsidy for capital requirements offered by local
governments.
Ningxia Hui Autonomous Region obtained the approval of specially licensed temporary
electricity price to the grid from the NDRC in 2009, and built a number of PV power
stations, with total installed capacity of 50MWp.
Projects of Golden Sun pilot program and photovoltaic building pilot program that
encourage connection to grid on user side (low voltage side) and self-consumption are
distributed throughout the country.
As there are richer solar energy and land resources in the western part of China, more
electric power can be obtained in these areas with PV systems with the same size,
therefore investors for large-scale PV power stations started to concentrate their
attention to the west. The state selected Dunhuang of Gansu Province for the first
concession right tendering for construction of PV power stations, and selected 6
A2 - 15
Appendix 2 Renewable Energy Development
National Development Plan and Provincial Development Plan Final Report
provinces and regions of Qinghai, Gansu, Shaanxi, Inner Mongolia, Xinjiang and Ningxia
for the second concession right tendering.
Table 2-1 Comparison of PV Electricity Price to the Grid by Provinces and Regions
with State Electricity Price Policy
Electricity price to the grid Target
Region Year (CNY/kWh) installed Remarks
Ground Roof BIPV capacity
Concession 2007 - Shanghai, Inner Mongolia,
4.0
electricity price 2008 Ningxia, etc.
Jiangsu 2009 2.15 3.7 4.3 400MWp
2010 1.7 3 3.5
2011 1.4 2.4 2.9
Zhejiang 2010 1.16 50MWp
2011 -
1.43
2012
Shandong 2010 1.7 10/Wp 150MWp
2011 1.4
2012 1.2
Ningxia Concession temporary electricity
2009 -
autonomous 1.15 50MWp price to the grid
2010
region
Qinghai 900MWp To be completed before 2011
2011 1.15 already Dec.31 (previously scheduled to
approved complete before 2011 Sep.30)
Concession right Gansu Dunhuang
2009 1.0928 20MWp
tendering 1
Concession right 0.7288 - 13 projects in Gansu, Qinghai,
2010 280MWp
tendering 2 0.9791 Ningxia and Inner Mongolia
National unified Those approved before 2011.07.
2011 1.15
benchmark 01 and completed before Dec 31
electricity price Electricity price of 1.15 CNY/kWh
2012 1.0 will still be applied in Tibet
Starting in 2008, many PV power station investors saw the good prospects of solar
energy and land resources for construction and the grid and power transmission and
transformation conditions of Qinghai Province, believing that it is the best area in
comprehensive conditions to construct large-scale PV power stations in China. They
came one after another to Haixi Prefecture and other areas with good conditions in
Qinghai to sign letter of intent for cooperation, and started registering power generation
companies and securing land for construction, to start construction of PV power stations
at appropriate time.
A2 - 16
Renewable Energy Development Appendix 2
Final Report National Development Plan and Provincial Development Plan
1900 1800
2000
1700
2000
A2 - 17
Appendix 2 Renewable Energy Development
National Development Plan and Provincial Development Plan Final Report
Though the government has not issued supporting policies for electricity price to the grid
for PV power generation, investing enterprises were active in preparing for start of works.
However, large-scale construction action could not be started, and only some companies
started research projects. In May 2011 when Qinghai Province notified project
companies locally registered and approved that projects completed before September 30,
2011 could enjoy the electricity price to the grid of CNY 1.15 per kWh, 26 (now 27)
enterprises submitted applications and obtained approval. These projects were the
Qinghai 930 projects as referred to by outsiders.
Table 2-3 Registered Companies and Applied Projects of Qinghai 930 Projects
in Haixi Prefecture
Planned
New Project for 1.15 electricity
No. Project owner total Location
capacity price
capacity
1 Longyuan Golmud New Energy Development Co., Ltd. 30 200 20 + 30 = 50 Golmud
2 Yellow River Upper Reaches Hydropower
200 1000 200 Golmud
Development Co., Ltd.
3 Guodian Power Qinghai New Energy Project
10 200 10 Golmud
Preparatory Office
4 China Three-gorge New Energy 5 10 5 Golmud
5 Beijing Beikong Green Science and Technology
20 50 20 Golmud
Industrial Co., Ltd.
6 Qinghai Water Conservation and Hydropower Group 10 20 10 Golmud
7 CPI Golmud Photovoltaic Power Generation Co., Ltd. 30 200 20 + 30 = 50 Golmud
8 Jinzhou Sunshine Energy 20 20 20 Golmud
9 Qinghai Project Preparatory Office of Datang
20 20 20 Golmud
Shandong Branch
10 Huaneng Golmud Photovoltaic Power Generation Co.,
30 200 30 Golmud
Ltd.
11 Qinghai Baike Photoelectrical Co., Ltd. 8 10 2 + 8 = 10 Golmud
12 China Huadian Photovoltaic Power Generation Co.,
10 10 10 Golmud
Ltd.
13 Zhejiang Zhengtai Solar Energy Science and
20 20 20 Golmud
Technology Co., Ltd.
14 Qinghai Jingneng Construction Investment Co., Ltd. 20 100 20 Golmud
15 Shengguang New Energy Co., Ltd. 2 20 1+2=3 Golmud
16 Qinghai Datang International Energy Project
20 20 20 Golmud
Preparatory Office
17 Qinghai New Energy Group Corporation 10 10 10 Golmud
18 Qinghai Junshi Energy Co., Ltd. 8 10 2 + 8 = 10 Golmud
19 Qinghai Provincial Development and Investment Co.,
2 2 2 Golmud
Ltd.
20 Yellow River Upper Reaches Hydropower
30 50 30 Ulan
Development Co., Ltd.
21 CEC Solar Energy Co., Ltd. Da
10 10 10
Qaidam
22 Guodian Qinghai Branch 20 20 20 Delingha
23 Qinghai Linuo Solar Energy Power Co., Ltd. 30 30 30 Delingha
24 China Wind Power Group 30 50 30 Delingha
25 CEC Solar Energy 20 200 20 Xitieshan
26 CGNPC Solar Energy Development Co., Ltd. 90 100 10 + 90 = 100 Xitieshan
760
(including 45MW at
Total 705 2582 Golmud and 10MW at
Xitieshan already
connected to grid)
A2 - 18
Renewable Energy Development Appendix 2
Final Report National Development Plan and Provincial Development Plan
In fact, after NDRC issued the national unified PV benchmark electricity price in Aug.
2011, all Qinghai 930 projects were covered, and their completion date was naturally
extended to Dec. 31, 2011. Because they were started early, Qinghai Province got the
first priority in the construction of this round of PV projects, becoming the area with most
concentrated PV power stations being constructed in China. On September 16, 2011 at
the PV development conference called for by the Qinghai Provincial Government,
officials of the provincial government declared that in 2011, it would be ensured that PV
power generation systems of 0.9GW should be completed for production by the end of
the year, and further efforts would be made to realize a higher target of 1GW.
In early July 2011 when statistics were started for this study, PV power stations of
Longyuan with 20MW, CPI Golmud with 20MW, Baike with 2MW and Shenguang (CPV)
with 1MW at Golmud had been connected to grid, with 45MW already connected to grid
in Golmud, and the 10MW project at Xitieshan was also connected to grid. If the new
projects of 705MW could be completed on schedule, the installed capacity in Haixi
Prefecture during the year will be 760MW. With projects in other places of Qinghai
Province, the applied installed capacity of 930 projects in the province will be about
900MW. However, as investing enterprises doubted whether Qinghai Province would
finally make good the promise of CNY 1.15 per kWh electricity price to the grid, and also
the schedule to complete by September 30, 2011 was too tight, we estimate that only
about 500MW can be completed out of 930 projects. The issuance of the state
benchmark electricity price eliminated the doubt of investors and granted additional 3
months as construction schedule, so large-scale construction of PV power stations
immediately went into full swing in Qinghai Province. In the present progress of
construction, there is a high possibility that PV power stations completed and connected
to grid for power generation by the end of the year reach 0.9GW in Qinghai Province.
Although the electricity price to the grid in 2012 will possibly decrease to CNY 1 per kWh
(if no extra subsidy is provided by local governments), investing enterprises are still at
high initiative for subsequent construction. By now, Qinghai Provincial Energy Bureau
has received project application reports for a total of 4GW, and it plans to approve
projects of about 1GW out of 4GW to be constructed in 2012. Therefore, the installed
capacity of PV power station in Qinghai Province will reach 2GW by the end of 2012.
A2 - 19
Appendix 2 Renewable Energy Development
National Development Plan and Provincial Development Plan Final Report
Table 3-1 Summary of Projects under Construction and Proposed in Qinghai Province
Installed
Description of project capacity Origin of project Owner
(MWp)
PV power station in Gonghe Yellow River Upper Reaches
30 Concession right tendering
County of Hainan Prefecture Hydropower Group
PV power station in Henan Yellow River Upper Reaches
20 Concession right tendering
County of Huangnan Prefecture Hydropower Group
Approved by Qinghai
2011 benchmark electricity price 900 Investing enterprises
Provincial Energy Bureau
To be approved by Qinghai
1,000 Investing enterprises
Provincial Energy Bureau
Photoelectrical building pilot
2012 benchmark electricity price
program
Total 1,950
First, to concurrently implement many projects in a short period of time with tight
schedule and heavy work tasks, investing enterprises will subject to pressure from
aspects of materials procurement, transport, supply of labor, construction organization
and cost control. Second, as construction standards, project specifications and quality
acceptance standards have not been unified, some projects were started in haste to
catch up with schedule, and working in winter, there will be some hidden perils to project
quality.
Although Qinghai Province has make arrangement on preparation for connection, grid
acceptance ability, peak regulation method and total quantity target control, due to tight
schedule, large amount of work and insufficient experience, unexpected problems will
possibly occur when large number of power stations are connected to the grid almost at
the same time. Therefore, countermeasures have to be worked out in advance.
A2 - 20
Renewable Energy Development Appendix 2
Final Report National Development Plan and Provincial Development Plan
At present, all existing technical plans, installation methods and PV modules can be
found in the projects in Qinghai. As prior tests and evaluation data are lacking, it should
be verified if the expected technical and economic indicators can be reached. If they can
be operated reliably for long time after completion, this will bring some risks to investing
enterprises.
In early July, 2011 when statistics were started for this research program, PV power
stations of Longyuan with 20MW, CPI Golmud with 20MW, Baike with 2MW and
Shenguang (CPV) with 1MW at Golmud had been connected to grid, with 45MW already
connected to grid in Golmud, and the 10MW project at Xitieshan was also connected to
grid. If the new projects of 705MW can be completed on schedule, the installed capacity
in Haixi Prefecture during the year will be 760MW. With projects in other places of
Qinghai Province, the applied installed capacity of 930 projects in the province will be
about 900MW. However, as investing enterprises doubted whether Qinghai Province
would finally make good the promise of 1.15 yuan/kWh electricity price to the grid, and
also the schedule to complete by Sept. 30 was too tight, we estimate that only about
500MW can be completed in 930 projects. The issuance of the state benchmark
electricity price eliminated the doubt of investors and granted additional 3 months as
construction schedule, so large-scale construction of PV power stations immediately
went into full swing in Qinghai Province. In the present progress of construction, there is
a high possibility that PV power stations completed and connected to grid for power
generation by the end of the year 2011 reach 0.9GW in Qinghai Province.
Although the electricity price to the grid in 2012 will possibly decrease to 1 CNY/kWh (if
no extra allowance is provided by local governments), investing enterprises are still at
high initiative for subsequent construction. By now, Qinghai Provincial Energy Bureau
has received project application reports for a total of 4GW, and it plans to approve project
of about 1GW out of 4GW to be constructed in 2012. So, the installed capacity of PV
power station in Qinghai Province will reach 2GW by the end of 2012.
A2 - 21
Appendix 2 Renewable Energy Development
National Development Plan and Provincial Development Plan Final Report
Table 5-1 Summary of Projects under Construction and Proposed in Qinghai Province
Installed
Description of project Origin of project Owner
capacity (MWp)
PV power station in Gonghe 30 Concession right tendering Yellow River Upper Reaches
County of Hainan Prefecture Hydropower Group
PV power station in Henan 20 Concession right tendering Yellow River Upper Reaches
County of Huangnan Hydropower Group
Prefecture
2011 benchmark electricity 900 Approved by Qinghai Investing enterprises
price Provincial Energy Bureau
1000 To be approved by Qinghai Investing enterprises
Provincial Energy Bureau
2012 benchmark electricity
Photoelectrical building pilot
price
program
Golden Sun pilot program
Total
A2 - 22
Renewable Energy Development Appendix 3
Final Report Capacity Development Training
APPENDIX 3
1. Schedule
A3 - 1
Appendix 3 Renewable Energy Development
Capacity Development Training Final Report
Then they gave technical assistant to QBE regarding planning, construction and
O&M of a solar PV system, and gave technical guidance on their 10 MW class
grid-connected solar PV system.
A3 - 2
Renewable Energy Development Appendix 3
Final Report Capacity Development Training
A3 - 3
Renewable Energy Development Appendix 4
Final Report Presentation Materials
APPENDIX 4
PRESENTATION MATERIALS
Renewable Energy Development Appendix 4 : Presentation Materials
Final Report Appendix 4-1 : Seminar
April 27,2011
Yukao TANAKA
NEWJEC Inc.
1
Todays Topic
A4-1 - 1
2
Background of the Project
-- Outline of system -- 3
Compensating the PV Power Fluctuation by Capacitor
with Rationalized PV system
Purpose of the Project 10kV Line
Indicator of power frustration:
frustration:
Compensation of PV Power fluctuation
Project System Faster interconnection of PV system
A4-1 - 2
4
Project Schedule
2010
2007 2008 2009 (up to
March)
Feasibility Study
Site survey and Specification study
300kW PV Plant
166m 60
Site Layout
T Branch from 10kV distribution line
A4-1 - 3
-- Site Layout/ System Layout -- 6
Photovoltaic Module / 14 series and 108 circuits
P.C.BOX
60m Low voltage
High voltage
Sub-Array
10kV Line
B D
Number of PV module
module1,512
1 512 pcs.
pcs A C
Component of circuit:14
circuit:14 module (series)/circuit Component of sub
> Num. of Circuit:108 circuit array
Component of sub array :4(2)circuit/sub array
> Num. of Sub array:28 sub array
Component of P.C.BOX:4-
P.C.BOX:4-5 sub array / P.C.BOX(16
P.C.BOX(16
20
circuit/P.B.BOX) > Num. of P.B.BOX: 6 units
PV Sub Array Capacity of PV system: about 300kW
108 Circuits
A4-1 - 4
-- Configuration of major equipment -- 8
Electric Double Layer Capacitor (EDLC) System
EDLC modules is composed of 5 series 5 parallels, 2 sets
To DC/DC Converter for EDLC Panel
-
Control functions
a) Constant-voltage control (DC 280V) and power factor 1 control
b) Constant reactive power control
A4-1 - 5
10
Typical Daily Operation Pattern
- Small change in PV output (on a fine day) -
Freqquency(F)
PV OUTPUT(kW)
TimeH)
Voltage
Voltage
V)
TIME (H) TimeH)
11
Typical Daily Operation Pattern
- Sharp Changed in PV Generation -
TIME (H)
Voltage
Voltage
V)
A4-1 - 6
12
Typical Daily Operation Pattern
- Cloudy Day -
Output of PV Generation
Frequency
Freequency(F)
PV OUTPUT(kW)
TIME (H)
Voltage
Voltage
V)
TIME (H) TIME (H)
Summary of Maximum and Minimum Averages
Min. Max. Ave.
PV generation (kW) 0 15.15 112
Frequency (Hz) 49.93 50.00 50.05
Low voltage on AC side (V) 375.7 380.6 384.7
Date10 July,2009
-- Compensation by Capacitor -- 13
Power System
EDLC Power out put
Power
Stabilizing Control
Equipment
Time
A4-1 - 7
-- Fast Operation of PV System -- 14
Development of Inventor Control Method
for Faster Restarting of PV Operation
Distribution Image for Restart of PV Power Generation
System
Accident
Around 2 second
Faster Deviation Detection of Voltage and Phase
Development for fast restart of PV Operation
-- Achievements
Achievements-- 15
Development of Power Stabilization Control
Case: 1Hz fluctuation of DC/DC Converter for PV System
System
100
100
Power (kW)
W)
W)
Power (kW)
50
50
0
0
CNV EDLC
-50
-50
-100
EDLC
-100 0.0 0.5 1.0 1.5 2.0 2.5 3.0 3.5 4.0 4.5 5.0
0.0 0.5 1.0 1.5 2.0 2.5 3.0 3.5 4.0 4.5 5.0 sec)
sec)
Frequency (Hz)
Output power variations per second (1 Hz) were reduced to 1/10 for
the capacity of the output power stabilization system
A4-1 - 8
-- Achievements
Achievements-- 16
Development of Power Stabilization Control
(Case: PV output makes a sharp change (270 kW to 0 kW))
PV Output
PV Output
DC Voltage
DC Voltage
Enlarge
-- Achievements
Achievements-- 17
Development of Inventor Control Method
for Faster Restarting of PV Operation
Time axis: 50 ms/div.
Restart time: 1.14s
We could achieve the target with the fastest time of 1.14 seconds.
A4-1 - 9
18
Training for Operation and Maintenance
Training to operator
Preparation of operation manual (Chinese
Chinese version
version)
On the Job training using real equipment at site
Report system to Japan when trouble happened
Making daily repot by operators
Workshop
Enlightenment of Photovoltaic
generation technology
Operation Manual
Chinese version)
(Chinese version
19
Training for Operation and Maintenance
(On the Job training using real equipment at site)
A4-1 - 10
20
THE END
A4-1 - 11
Construction Project of Sakai Mega Solar
Power Generation Plant
Takao Shiraishi
NEWJEC Inc.
Table of Contents 2
A4-1 - 12
Outline of Electric Power Facilities 3
Electricity generated by a power plant is distributed via intermediate/distributing substations after being fed
through transmission lines to ultrahigh voltage/primary substations where its voltage is gradually reduced.
Before being supplied to customers, the voltage is furthermore reduced to 100200V by pole transformers.
Ultrahigh voltage substation Primary substation Intermediate substation Distributing substation Pole transformer
Nuclear power station
Rail substation
Building, mid-scale factory
Housing
Thermal power station
A4-1 - 13
Table of Contents 5
Fluctuation
Demand Demand
Excess electricity is As power generation depends on the
Pumped hydropower generated.
Minimum thermal power Minimum thermal power
weather condition, large scale
Pumped
Pumped hydropower
Solar power
Pumped hydropower Solar power
hydropower introduction of solar power
electricity
Thermal power
electricity
generation may lead to excess
Surplus Thermal power
electricity through the entire power
Wind power
Wind power
Hydropower Hydropower
system.
Nuclear power
Nuclear power
Electricity
Excess
electricity
Reverse power Solar panel
flow
Consumption Generated
electricity
Reverse
power flow
A4-1 - 14
Fluctuation in Solar Power Generation 7
Sunny (November 4)
As it depends on the weather condition,
the adjustment of power output is Occasionally cloudy (November 23)
difficult.
Occasionally rainy (November 22)
Power
output (kW)
Clock time
Solar power generation can provide stable power on sunny days. However, on cloudy or
rainy days, a high level or stable output cannot be expected.
Fluctuations in solar power generation are compensated by increasing/decreasing the power output of adjustable
electric sources (thermal power generation, etc.). Large-scale introduction of solar power generation may lead to an
extended fluctuation, resulting in lack of frequency balance.
Demand
Demand Supply
Power Electricity generated
generation by solar power Supply
Demand Supply
Existing
electricity
Increasing power output
by adjustable power
sources
Adjustable power
sources (thermal Decrease in
power, etc.) frequency
Supply
Demand Supply
A4-1 - 15
Expected Supply & Demand Balance after Full-Scale
Introduction of Solar Power Generation 9
Unit: 10MW
Summer
Hydropower generation
(Hour)
During lightly loaded periods, such as an off-peak month, the electricity generated by base loads and solar power may exceed the demand,
resulting in excess electricity.
Excess
electricity
Electricity demand
(Hour)
A4-1 - 16
Increase in Distribution Voltage 11
As the distribution voltage increases due to a reverse flow of solar power, output control of solar
power generation occurs.
Flow of electricity Reverse flow of solar power
T
Transformer
f Not allowed to generate
Distributing substation
power even if it is sunny.
Solar panel
Power
Exceeds 107V.
Range of app
control
As the distribution voltage increases due to a reverse flow of solar power, output control of
solar power generation occurs.
As solar power generation increases, the frequency of controlling reverse power flow increases,
which results in an increase in claims from customers.
Contents 12
A4-1 - 17
Outline of Sakai Mega Solar Power Generation Plant 13
Operator: Jointly operated by Sakai city and Kansai Electric (public relations: Sakai city,
construction & operation: Kansai Electric)
Location: Industrial waste landfill in Sakai No. 7-3 District
Area: approx. 20ha
Power output: 10MW (10,000kW)
Generated electricity: approx. 11million kWh/year
Installation: on ground
Operation schedule: partially started on October 5, 2010 (approx. 2.85MW)
planned to fully start on October 2011
Forest of co-existing
Minato Sakai
Green Square
Sakai No.7-3
District
A4-1 - 18
Verification Items for Sakai Mega Solar Power Generation
15
Plant
Item Verification
Drop out of all Verification of voltage decrease rate due to a failure at the upper voltage system
generators and the range of continuous operation of power conditioner
Assurance of transparency (taking a fair Selection of solar batteries considering the land cost,
procedure) and economic efficiency (optimized construction cost, power output and other factors
procurement) as a subsidized project* comprehensively.
Placing orders for material and construction work separately based on
the internal design
design.
Construction of a plant at the industrial waste landfill (a Setting the geometry of the substructure which does not require
land impossible to be excavated, possibility of future excavation.
unequal settlement) Design of a plant which can address future unequal settlement
Besides the above technical issues, it is necessary to consider and take the following measures:
To meet the disaster prevention and safety criteria considering harsh weather conditions expected in the waterfront
area (earthquake resistance, lightning protection, measures against high tide and Tsunami, salt resistant design, etc.)
To provide functions which can help the verification of the influence on the power system
(PCS functions to enable/disable control, and necessary instrumentation systems, etc.)
A4-1 - 19
Structure of Sakai Mega Solar Power Generation
Plant Facilities 17
interconnection
Total cost
Cost
<Example>
Type of solar Conversion ratio Occupied area for Cost of solar batteries
battery 10MW (as more expensive as higher
efficiency)
Crystal system Approx. 15% Approx. 70,000m2
Land and construction work cost
(As less expensive as higher
Thin-film system Approx 8%
Approx. 130 000m2
Approx 130,000m
Approx. efficiency)
Even if the cost of solar batteries is lower, a lower conversion ratio will lead to a high land and
construction work cost, which may result in a rather expensive total cost.
A4-1 - 20
Comprehensive Evaluation in Selecting the Type of Solar 19
Battery
The value of solar battery is comprehensively evaluated taking into account the bid price and
degradation ratio in addition to the predetermined system cost and annual energy production.
Fixing bracket
Concrete placement using Installing formwork after positioning Mounting solar battery panels on the
formwork using the fixing bracket. substructure using the mounting
hardware.
A test installation was conducted prior to the actual construction work in order to improve the work
quality and efficiency.
A4-1 - 21
Development of Mounting Hardware Which Can 21
Accommodate Unequal Settlement
1. Substructure
Conventional substructure: A steel platform supports the solar battery panel
frame. Solar battery
Solar battery
Hardware on the
Used metal 700t solar panel side
Hardware on the
Current substructure: directly fixed on the concrete foundation concrete block side
usingg mountingg hardware
Backward concrete Hardware on the Rotation
foundation (50cm high) solar panel side Concrete block Lateral shear
Mounting hardware
Front concrete foundation
Mitigate strain due to settlement by lateral shear and rotation.
(20cm high)
Possible to correct shear following unequal shear.
2. Demonstration
test
Before After
settlement settlement
Rotation
Shear
Forced
stettlement
The mounting hardware can accommodate a 68cm unequal settlement without any problem with its
applicability.
Formwork
A4-1 - 22
Installation of Solar Battery Panels 23
August 2010
Substation 24
August 2010
A4-1 - 23
Arrayed Solar Battery Panels 25
August 2010
No 2 zone
No.2
Approx. 3,450kW
(planned to start operation this
spring)
No.3 zone
Under construction (approx. 3,700kW)
(planned to start operation this fall)
No.1 zone
Started operation on October 5, 2010
(output: approx. 2,850kW)
A4-1 - 24
Visitor Center 27
Looking at the plant site from above the Looking at the plant site from underneath the
observation deck observation deck
A4-1 - 25
Table of Contents 29
Cloudy, temporarily fine Cloudy, occasionally Fine with intermittent Fine Clear and sunny Cloudy with intermittent Cloudy
Weather
It is planned to accumulate data to evaluate the influence of solar power generation on the power
generation system.
A4-1 - 26
Verification of Influence on Power Systems 31
Function to adjust
reactive power
Solar radiation Solar power from Sakai
Plant
Frequency fluctuation
Analysis of output fluctuations of mega solar power generation
Analysis of voltage fluctuations in the normal system at a mega solar power generation
Voltage fluctuation
Verification of effectiveness of the measures against normal system voltage fluctuations
Control of reactive power by means of power conditioners, etc.
Harmonic Verification of harmonic (waveform strain) occurrence levels due to the interconnection of multiple inverters
(power conditioners)
Atmospheric
temperature
The amount of solar radiation on the inclined surface and the electricity
generated by solar power are locally measured.
Pyranometer installed on the roof of Kansai Electric
Human Resource Development Center
A4-1 - 27
Measured Solar Radiation (Example) 33
Fluctuation
ratio
atio
n
Kobe Substation Higashisumiyoshi Office
Fluctuation ratio
ratio
Fluctuation
*Assuming 1000W/m2 solar radiation
Fluctuation ratio averaged over 60 points
as 100%
Although the fluctuation ratio of solar radiation* at individual points is rather high, the averaged fluctuation ration
becomes smaller due to off-setting effect.
It is planned to accumulate and analyze data to contribute to the development of supply and demand
control system.
[Numerical prediction]
Data on atmospheric pressure,
Attenuation by
radiation
Amount of solar
Attenuation by clouds
Amount of upper clouds
Amount of mid-level clouds
Amount of lower clouds
Water vapor
Comparing with the actual amount of solar radiation measured on the roof of
Kansais Research institute (one point), some predicted values deviate from the
measurement. It is planned to verify and improve the accuracy of prediction based
Ground observation data on the amount of solar radiation measured at several points.
Atmospheric pressure,
Satellite data
temperature, wind
Visible image
Amount of solar radiation
Research programs are under progress on the prediction of solar radiation by means of the weather forecasting system. With
a high level of errors in the prediction, it is necessary to develop new technologies to improve the accuracy of prediction.
A4-1 - 28
Research on Power Supply & Demand Control System 35
Utilizing Batteries
A research is being conducted on the possibility of connecting nickel hydride batteries to the power system at Ishizugawa
substation to which Sakai Mega Power Generation Plant is interconnected.
Generation Plant
Active power Active power
22 kV power system 6.6kV power system
Inverter
Plant
Nickel hydride battery
Ishizugawa
substation
Specification of nickel hydride battery
Research subjects Nickel hydride battery stack
Supply & demand control system which Number of stacks
allows mass introduction of solar power
Rated voltage
generation
Service life evaluation and applicability Rated capacity
assessment of batteries as the supply and Energy capacity
demand control tool.
Power output
*Power output as the supply and demand control system being
interconnected to inverters
36
Improvement of thermal
efficiency of thermal plants
Promoting diffusion of
electric vehicles
A4-1 - 29
1
April
p 27,2011
,
Takashi NAKAZAWA
NEWJEC Inc.
2
Todays Topic
A4-1 - 30
3
1. Basis of Sunlight
The Earths Axis
Solar Position
The earths axis declines
23 4from
23.4 from the sunlight
sunlight.
The Equator
Summer Spring
Solar tracking Winter
IIn winter
i t the
th altitude
ltit d off
meridian passage is the lowest, North South
and in summer it is the highest
in the year. West
4
1-1 Solar Constant
Io =Isc[1+0.0033 cos{360(n2)/365}]
Isc=1.382 kW/ Solar constant
n a calendar day
A4-1 - 31
5
1-2 Atmospheric Transmittance
Atmospheric transmittance
The sunlight reduces for the sake of scattering and absorption by
many molecules and clouds.
Some amount of greenhouse gas is
necessary for keeping temperature not
so low.
Much amount of them causes global
Greenhouse Gas hot.
O observation
Our b i off atmospheric
h i
transmittance is about 0.5 at Kansai
area in Japan.
In Timor island (Indonesia) 0.50.65
is observed.
6
1-3 Air Mass
A4-1 - 32
7
1-4 Solar Spectrum
outside atmosphere
1.38kW/ The sunbeam is partially
blocked by molecules and
at sea level (AM=1.5) debris.
Molecules such as H2O,
1kW/ CO2, O2, etc. absorb
energy and scatter the light.
8
1-5 Spectral Characteristic of PV
c-Si
a-Si
A4-1 - 33
9
1-6 Direct Light and Scattered Light
10
1-7 Solar Radiation Intensity
A4-1 - 34
11
1-8 Daily Solar Radiation Intensity Curve
1.00
Fine
INTENSITYW/
0.50
Cloudy
Rainy
0.00
6 12 18
TIME
In case of grid connected PV system the power conditioner will operate more than 0.05kW/
. So the system will not operate in rainy days efficiently. In cloudy day power conditioner
will repeat start and shut down.
12
2-1 V-I Characteristic of PV
Pm
Which one is the hottest
Volt.
on a PV surfase?
Vpm Voc
Case 1: short circuit
Isc : short circuit current
Case 2: open circuit
Ipm : current for maximum power
Case 3: power supply
Voc : open circuit voltage
power to some
Vpm: voltage for maximum power
Pm : maximum power
A4-1 - 35
13
2-2 Generation
Generation--Radiation Intensity Characteristic
As radiation intensity
increase,, ppower output
p
increase.
At the same temperature
PV power is linear to
intensity.
PV module is tested
under the condition as
b l
below.
Irradiation: 1kW/
temperature: 25
AM: 1.5
14
2-3 Temperature Characteristic
Pm(25)
Power
Pm(75
Voltage
A4-1 - 36
15
3. Power Increase Method
Weather condition
Strong solar radiation intensity
Low air temperature
PV array
High efficiency PV module
Array should be installed by same characteristics PV modules.
High voltage PV array and low loss wiring
Power conditioner
High efficiency
MPPT control (with PV array)
Lower loss of transformer
Circumstance
No shadow
16
4. Fish Eye Lens and Camera
A4-1 - 37
17
4-1 Feature of Using Fisheye Lens
18
4-2 Difference
south
north
east west
east west
south
A4-1 - 38
19
4-3 Solar Orbit Image
20
4-4 Layering Solar Orbit Image Over Picture
obstacles
A4-1 - 39
21
4-5 Estimation of Obstacles
and the Scattered Light
North
In summer direct light will
reach for 12 hours.
In spring and autumn direct
light will reach for 10 hours.
In winter direct light will
reach for 8 hours.
East West
g from cloud
Scattered light
is estimated as solid angle
of the sky.
South
22
4-6 Estimation of Generation by PV System
Condition
Capacity: 100kW,
100kW
Location: Osaka Japan
Air temp.: data from Osaka Meteorological Observatory
A4-1 - 40
23
THE END
A4-1 - 41
Financial Assessment of
PV Power Station
April 2009
Masaru NISHIDA
NEWJEC Inc.
1
Contents
A4-1 - 42
2
1. Purpose of Financial Assessment
A4-1 - 43
4
3. Economic Assessment vs Financial Assessment
Financial assessment:
estimating the profits (revenue minus expenditures) accruing
to project owner (implementing/operating
agencies/companies)
Economic assessment:
estimating the effects of the project on the national economy
5
3. Economic Assessment vs Financial Assessment
A4-1 - 44
6
3. Economic Assessment vs Financial Assessment
7
3. Economic Assessment vs Financial Assessment
A4-1 - 45
8
3. Economic Assessment vs Financial Assessment
Mechanism such as
- CDM,
- Carbon Credit Market, etc.
Additional Income
(Financial Value)
9
4. Procedure of Financial Assessment of Project
Identify project
Define services to be provided by the project
Find demand and prices for the services
Design physical and organizational components of the project
Schedule construction and operation and maintenance of the project
Estimate project costs in financial terms with the level of detail required
for financial analysis.
Define financial resources (own fund, equities, loans, etc.) available and
their conditions
Calculate streams of expenditures and incomes
Calculate indicators of financial viabilities
A4-1 - 46
10
5. Elements of costs and benefits to be considered
11
5. Elements of costs and benefits to be considered
COST
b)) Recurrent Costs
operation and maintenance costs (salaries of OM staff, fuel, consumables)
replacement costs of worn-
worn-out parts
others
A4-1 - 47
12
5. Elements of costs and benefits to be considered
13
6. Source of Financing the Project
own fund
= project owner's
owner s money
equities
= money collected from shareholders expecting dividends
loans
= money borrowed from banks to be repaid on rigid conditions
A4-1 - 48
14
7. Other Factors related to Costs and Benefits
FIT :
Power generators using renewable technologies are paid a
premium price for electricity they produce.
Electric grid utilities are obligated to take the electricity and
pay them at the premium price.
15
8. Method of Assessment
Cash flow analysis = profit and loss projected for project life
I di
Indicators off Fi
Financial
i l Viabilities
Vi bili i : FIRR = return on the
h
money you spent for the investment
Criteria of viability
The internal rate of return (FIRR) must be larger than the
cost of capital of the project owner (WACC).
If not, you have better way to spend your money than in the
project in question.
A4-1 - 49
16
8. Method of Assessment
17
8. Method of Assessment
unit 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027
Gross Generation GWh 0.00 0.00 0.00 659.40 659.40 659.4 659.4 659.4 659.4 659.4 659.4 659.4 659.4 659.4 659.4 659.4
Salable Energy GWh 0.00 0.00 0.00 587.50 587.50 587.5 587.5 587.5 587.5 587.5 587.5 587.5 587.5 587.5 587.5 587.5
Power Tariff c/kWh 8.26 8.35 8.43 8.51 8.60 8.684 8.771 8.859 8.947 9.037 9.127 9.219 9.311 9.404 9.498 9.593
Sales Revenue M.US$ 0.00 0.00 0.00 50.00 50.50 51 51.5 52 52.6 53.1 53.6 54.2 54.7 55.2 55.8 56.4
Fuel Cost M.US$ 0.00 0.00 0.00 -37.20 -37.20 -37.2 -37.2 -37.2 -37.2 -37.2 -37.2 -37.2 -37.2 -37.2 -37.2 -37.2
Fixed O/M Cost M.US$ 0.00 0.00 0.00 -0.68 -0.68 -0.68 -0.68 -0.68 -0.68 -0.68 -0.68 -0.68 -0.68 -0.68 -0.68 -0.68
Earning after operation M.US$ 0.00 0.00 0.00 11.12 11.62 12.12 12.62 13.12 13.72 14.22 14.72 15.32 15.82 16.32 16.92 17.52
Depreciation M.US$ 0.00 0.00 0.00 -6.10 -6.10 -6.1 -6.1 -6.1 -6.1 -6.1 -6.1 -6.1 -6.1 -6.1 -6.1 -6.1
Interest Payment M.US$ 0.00 0.00 0.00 -2.00 -2.00 -2 -2 -2 -2 -2 -1.9 -1.8 -1.8 -1.7 -1.6 -1.6
Principal Repayment M.US$ 0.00 0.00 0.00 0.00 0.00 0 0 0 0 3.4 3.4 3.4 3.4 3.4 3.4 3.4
Earning before Tax M.US$ 0.00 0.00 0.00 3.02 3.52 4.02 4.52 5.02 5.62 6.12 6.72 7.42 7.92 8.52 9.22 9.82
Corporative Income Tax M.US$ 0.0 0.0 0.0 -2.2 -2.3 -2.4 -2.5 -2.6 -2.7 -2.8 -2.9 -3.1 -3.2 -3.3 -3.4 -3.5
Project Cash flow M.US$ -57.4 -62.8 0.0 8.9 9.3 9.7 10.1 10.5 11.0 11.4 11.8 12.2 12.6 13.0 13.5 14.0
A4-1 - 50
18
9. Uncertainty = Risks and Sensitivity Analysis
Project variables
Demand (volume, price), Costs of inputs, construction, etc
19
THE END
A4-1 - 51
Renewable Energy Development Appendix 4 : Presentation Materials
Final Report Appendix 4-2 : Interim Workshop
December 7, 2011
Renewable
R bl EEnergy D
Development
l t iin Qi
Qinghai,
h i
Peoples Republic of China
Project Director
Yukao Tanaka
2
Estimation of PV site in Golmud
North
PV site in Golmud will be
one of the most suitable
place
l for
f PV generation
ti
system.
East West
There is no obstacles to
obstruct the sun shine.
South
Golmud is highland, and
seems to have little rain.
A4-2 - 1
3
Estimation of PV system design
4
Proposal to observe insolation
Insolation sensor
PV arrays will be installed having tilt angle as the same as latitude of Golmud
This method will count on direct sun light mainly.
PV system generates power not only direct light but also diffusion light.
Diffusion light intensity will be larger in smaller tilt angle.
It will be worth to measure insolation by different tilt angle to generate more power.
A4-2 - 2
5
Owner, Construction and Operation Scheme
Haixi Grid 110kV Lines or Substation
b 110 kV Substation
b. S b i
110 kV Substation
(110/35kV Transformer) c. 35 kV Transition lines
6
Outline of 110/35kV Substation
-110kV Line x 2Feeders
-35kV Income Line x 8 Feeders
-110/35kV, 63MVA Transformer x 2 units
North
110kV Lines 110kV 10MV
-110kV, 10MVar SVC x 2 units
i
35kV Lines
A4-2 - 3
7
Outline of 110/35kV Substation
Generated Power by PV and other power plants is transmitted to
Tibet and East area through DC 400kV and AC 750kV System
AC 750kV Lines
Direction : East (Wulan - Riyue, Qinghai) DC 400kV Area
AC 750kV Area
8
Information on the Electric Grid
The following technical maters are concerned and studied by Gird
company to keep stability of the grid and to enhance the development
of clear energy.
A4-2 - 4
9
Financial Study Framework
10
Financial Study - Results & Sensitivity Analysis
- For Base case, Project is just good enough with financial return
(FIRR) slightly over the requirement (WACC)
25yr Project may be more susceptible to problems arise in the long run:
-equipment problems, policy change, etc.
A4-2 - 5
2
Financial Study Tentative Conclusions
PV Technology in Japan 11
- for Reference -
Current Status of
Photovoltaic Power Generation
Technology Development
in Japan
p
A4-2 - 6
NEDO PV2030+ Roadmap 12
Introduction of Inexpensive PV System)
50/kWh
Advancing technology
30/kWh development assuming
Powe
Equivalent to home electric Equivalent to office electric Equivalent to industrial Utilization as general-purpose
Generation cost
power (23/kWh) power (14/kWh) electric power (7/kWh) electricity 7/kWH or less)
Module conversion efficiency Practical module: 16% Practical module: 20% Practical module: 25%
Super efficient module: 40%
(research level) (Research cell: 20%) (Research cell: 250%) (Research cell: 30%)
Before 2000
Development of power system interconnection technologies on an assumption of introducing new
energy on a single-unit basis
20002010
Research and demonstration of p
power system
y interconnection technologies
g for mass new energy
gy
on a multiple-unit basis
A4-2 - 7
Power System Interconnection Projects 14
L
Location:
i Josai-no-Mori
J i M i residential
id i l complex,
l O Ota city,
i G Gunma prefecture
f
Photovoltaic panels are installed on the roof of 553 houses generating total 2,129kW
electricity.
A 6kWh lead battery is installed at each house. An experiment to avoid the possibility of
reverse power flow by charging the batteries is conducted.
An effort is being made to develop a function capable of shutting down dispersed power
sources while generated electricity and demand is balanced even if the power system is
shut down in case of a malfunction in the power system (i.e., islanding detection system).
A4-2 - 8
Demonstration of Clustered Photovoltaic Power Generation 16
Systems2
A4-2 - 9
Demonstration of Stabilized PV Power System for Mega 18
Electricity Supply
Wakkanai site
Hokuto site Module type 10 types of modules mainly 26 types of modules mainly consisting
consisting of crystal system cells of advanced cells (including 2 types of
tracking cells)
Power storage
P t N Sb
NaS battery:
tt 1
1.5MW-11.8MWh
5MW 11 8MWh -
system
Power 250kW (commercial type) 400kW (newly developed PC: reactive
conditioning Introducing a large PCS with a power compensation, fault ride
1000MW capacity through function, harmonic power
system control function)
Smart grid
The smart grid is an interconnected system of electricity generation by introducing instrumentation
and control based on information and communication technologies. Generally, it means making the
system between a utilitys power generation plant and a customers meter smart. It may include the
demand side management, electric vehicle battery charging and control of customers PV system from
the utility.
Smart community
The smart community covers a wide range of public infrastructures including heat supply, water
supply and sewerage system, transportation, communication system as well as electricity. The
community means a specified range of area.
Smart city
The smart city
y has a similar meaningg to the smart community.
y The smart city
y is a sort of smart
community as a unit of municipality.
Smart society
The smart society is an extended concept of smart community. As it applies to a wide range, various
types of technologies in different generations will co-exist in the smart society.
A4-2 - 10
20
Concept of Smart Grid
Europe
Lyon, France
Malaga, Spain (already
Malaga Chi
China
adopted) Gongqngcheng : under public
Germany and UK: under invitation
investigation Yanqing, Beijing : basic survey
U.S.
New Mexico: under progress 8
Hawaii: adopted
A4-2 - 11
General Research Regarding Smart Grid 22
Cyber security
Summarizing the results of smart
grid demonstration projects
Data management
Modeling
Analyzing the data obtained from verification projects to determine the effectiveness of introducing the smart
grid.
Conducting research aiming at the standardization of cyber security and power system interconnection
technologies.
Analyzing the influence of the location where new energy power systems are installed.
A4-2 - 12
PV Industrys Trend and Market Prospective in
China
07/12/2011 QINGHAI
Contents
2. China's PV incentives
A4-2 - 13
1 Development of China's
1. China s PV products
manufacturing
Multi-crystal
PV modules power generation
Solar wafer Solar cells
silicon system
A4-2 - 14
The manufacturing capacity of PV products expanded quickly
Polysilicon
produc
ction capacity of 2011
Solar Wafer
Solar
Battery
PV Modules China
producttion capacity of 2009
Polysilicon
Asia
Solar Wafer
Global
Solar
Battery
PV Modules
0 20 40 60 80 100 %
The investments of large enterprise tend to the both ends of industry chain
Suntech
Trina
LDK
Hanwha
Jinko
CSI
DAQO
GCL
Renesola
JA SOLAR
CSUN
A4-2 - 15
The output of Solar cell production is high but the domestic
installation is low in China
Year
Shipments (MWp)
Installed capacity
Export
Export proportion
Domestic Installation
Domestic Export
49%of global
shipments in 2010
2.8%of global
installation in 2010
PV module production accounts for about 50% of global PV market and the market
continues to expanding but the volumes is small compared to the world.
The investment in photovoltaic module and solar cells maintain boom and the solar
design capacity is more than 20GW at the end of 2011.
A4-2 - 16
The contradiction between the volatility of Market expansion and productivity growth
40%
GrosssMargin%
30%
20%
10%
0%
EPC/Developer
Module
Inverter
Polysilicon
Integrated
Wafer
BoS
Cell
isuppli2011103
2China's PV incentives
A4-2 - 17
China's PV incentives
A4-2 - 18
China photovoltaic system initial investment subsidies
1.74GWp
MWp
Annual Installed capacity MWp
Accumulated Installed
(MWp) capacity (MWp)
2500
After the
Benchmarking
2000 electricity price
500 International
support
0
2000 2001 2002 2003 2004 2005 2006 2007 2008 2009 2010 2011E
A4-2 - 19
3 PV market development in China
3.
By iSuppli
A4-2 - 20
Installed capacity in Europe will decline in
2012?
0.81
0.8
/kWh
0.6
6%
0.54
/kWh
0.4 Sales of electricity to
0.34 the grid parity in 2021
/kWh
0.2 PV on-grid power Conventional power Residential power average Industrial power average
PV
average tariffs
average price price price
0
2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023
A4-2 - 21
China is close to Grid Parity
100GW
Low Goal
Intended Goal
High Goal
38.0%
10GW 20GW
0.8GW
Intended Goal may be used as the photovoltaic power target of China New Energy
Development.
A4-2 - 22
The photovoltaic market trend of China
The growth of China solar power will mainly be affected by policy and
subsidies
The large-scale PV power plants onshore will develop rapidly after the introduction
of benchmark on-grid tariff.
Distributed power generation will take the lead in "grid parity" although its difficult
to achieve the feed-in tariff tentatively.
China's PV market has great potential, but there are huge disparity
compared with Europe, America, Japan and other developed countries.
The development of solar industry will stimulate both the commercial
market and the projects with national capital subsidy. With the narrow of
price difference, China PV system installation in next five years is
expected to be more than the total above the target .
Thank You!
wu dacheng@163 com
wu.dacheng@163.com
A4-2 - 23
Design of Large Scale Integrated PV
Plants in Qinghai Province Evaluation
off PV System
in Golmud
December 7, 2011
Renewable Energygy Development
p in Q
Qinghai,
g ,
Peoples Republic of China
Project Engineer
Takashi Nakazawa
A4-2 - 24
1-1 Golmud site still picture
There is a tower
tower which distance
will be over 100m.
And there is
mountains far
Away, from PV
site.
site
Picture was taken at
south-west corner of
site.
2011/07/12
A4-2 - 25
1-3 Solar orbit
Solar orbit at PV site is
shown as left figure.
Day length in winter,
spring and summer are 8,
12, 12 hours.
In summer day length is
14 hours or so, but
sunrise and sunset time
direct light from the sun
will irradiate backside of
Sun is under module because of its
horizon. tilt angle.
A4-2 - 26
1-4 (2) Estimation of Golmud site
Golmud site might be one of the best place for
PV generation.
Power supply by PV system is effective power
only. Although AC circuit needs reactive power
to stabilize circuit, SVC in substation is to
supply or absorb reactive power by electric
utility company control. This concept is very
good.
After completion of every PV site, problem of
sand will be conquered.
Diffusion light
Tilt angle<latitude
A4-2 - 27
Solid angle of sky by the difference of tilt angle
Lon 94 Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
< 10% @0 n/a n/a n/a 30.1 24 26.8 30.2 34.4 n/a n/a n/a n/a
< 10% @3 28.7 16.8 12.7 21 19.3 24.7 27.1 31.6 31.8 26.2 33.4 26.6
< 10% @6 18 14.4 12.1 17.2 14.6 14.5 18.4 27.1 29.5 29.4 29.5 27.2
< 10% @9 12 8 03
8.03 63
6.3 9 55
9.55 10 4
10.4 15 6
15.6 16 1
16.1 24 1
24.1 25 20 8
20.8 27 1
27.1 18 4
18.4
< 10% @12 n/a n/a n/a n/a n/a n/a n/a n/a n/a n/a n/a n/a
Mon th ly Ave rage d Fre qu e n c y O f B ro ke n - c lou d Skie s At In dic ate d GMT Time s ( % )
Lon 94 Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
10 - 70% @0 n/a n/a n/a 30.6 29.3 19.7 20.9 22.6 n/a n/a n/a n/a
10 - 70% @3 43.8 42.6 29.6 24 27.4 16.3 21.4 20.9 20 33.5 43.3 42.2
10 - 70% @6 44.1 36.1 26.5 20.3 19.3 18.9 18.7 21.4 22.8 34.3 42.1 39.1
10 - 70% @9 40.1 32.6 21.7 20.4 15.8 17.7 18.3 20.8 25.9 37.5 37.4 38.5
10 - 70% @12 n/a n/a n/a n/a n/a n/a n/a n/a n/a n/a n/a n/a
Mo n th ly Ave rage d Fre qu e n c y O f N e ar- o ve rc ast Skie s At I n dic ate d GMT Time s ( % )
Lon 94 Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
>= 70% @0 n/a n/a n/a 39.2 46.6 53.4 48.8 42.9 n/a n/a n/a n/a
>= 70% @3 27.4 40.5 57.6 54.8 53.2 58.9 51.4 47.3 48.1 40.1 23.1 31
>= 70% @6 37.8 49.3 61.2 62.4 65.9 66.5 62.7 51.4 47.5 36.2 28.3 33.5
>= 70% @9 47.8 59.3 71.9 70 73.7 66.6 65.5 54.9 49 41.6 35.4 42.9
>= 70% @12 n/a n/a n/a n/a n/a n/a n/a n/a n/a n/a n/a n/a
A4-2 - 28
1-7 Diffusion light in Golmud
Cloud amount in
Golmud is not so low
according to NASA
data. Actually left
picture shows much
cloud in the sky.
This seems tilt angle
of PV array should
b better
be b tt tto iinstall
t ll
smaller than latitude.
This is noting but one
assumption.
2011/07/12
Insolation sensor
A4-2 - 29
1-6 Generation by weather condition
Month 1 2 3 4 5 6 7 8 9 10 11 12
Fine 12.18
12 18 12.61
12 61 13.06
13 06 12.34
12 34 11.42
11 42 10.79
10 79 11.08
11 08 11.9
11 9 12.72
12 72 12 8
12.8 12.19
12 19 11.98
11 98
Cloudy 2.64 3.52 4.45 5.04 5.17 5.13 5.13 5.07 4.67 3.82 2.87 2.36
Rainy 1.41 2.17 2.98 3.56 3.73 3.73 3.71 3.61 3.21 2.43 1.6 1.2
Month 1 2 3 4 5 6 7 8 9 10 11 12
Fine 933 941 961 907 793 731 776 796 887 891 862 888
Cloudy 231 300 367 408 404 393 387 385 366 308 240 204
Rainy 231 300 367 408 404 393 387 385 366 308 240 204
1-9 Others
Inspection of other site
Wiring
Module Module
A4-2 - 30
2. Design of PV system
10 MW PV system consists of 101MW systems. From the
view point of reliability, when some trouble happens total PV
system have a little impact on generation.
Each equipment is specified in detail.
Grid system is constructed for large scale of PV systems.
Lightning protection system will be installed as a vest design.
Some specifications seems to be penetrated into detail.
Transformer capacity is lager than PV array capacity.
Irelanding protective function is installed in each
inverter.
Some protection seems necessary on DC side for safety.
Lightning protection
LPZ 1
standard is authorized
LPZ 0
LPZ 2
in IEC62305-14.
LPZ 3
8 / 2 0
1 0
t( )
Fig . T e s t Wave
A4-2 - 31
Lightning protection in PV system
External and internal protection method
SPD
100% 12%
A4-2 - 32
2-2 (2)Transformer capacity
AC generation by PV system might not so large.
Inverter does not convey over rated power continuously.
Transformer has some overloading ability.
And that there is not necessary case, when active power and
reactive are not balance between supply and receive side.
A4-2 - 33
2-4 DC circuit protection
Recent power conditioner will be designed to protect DC current
flow into AC circuit.
B
Over current flows in transformer.
Over current
DC wiring
If someone touched another wire of
DC circuit, electric shock will
happen.
A4-2 - 34
Financial Study of PV Development
- A case of 10MW Pilot
il Project
j -
December 7, 2011
Renewable Energy Development in Qinghai,
Qinghai
Peoples Republic of China
Economist
Masaru NISHIDA
NEWJEC
1
Contents
1. Purpose
p of Financial Study
y
2. Method of Financial Analysis
3. Results and Sensitivity Analysis
4. Lifecycle analysis and Cost effectiveness
5. Tentative Conclusions
A4-2 - 35
2
1. Purpose of Financial Study
3
2. Method of Financial Analysis Procedure
Identify project
Define services to be provided by the project
Find demand and prices for the services
Design physical and organizational components of the project
Schedule construction and operation and maintenance of the project
Estimate project costs in financial terms with the level of detail required
for financial analysis.
Define financial resources (own fund, equities, loans, etc.) available and
their conditions
Calculate streams of expenditures and incomes
Calculate indicators of financial viabilities
A4-2 - 36
4
2. Method of Financial Analysis Indicators
5
2. Method of Financial Analysis Indicators
WACC
= Returns that Project has to achieve to satisfy financiers
A4-2 - 37
6
2. Method of Financial Analysis Framework
7
2. Method of Financial Analysis Conditions
NDRC Instruction
Loan Proportion
p 60%
Repayment Period 15 years
Interest of Loan 6.12%
Operation period 20 years
Depreciation 20 years, 5% Residual value
Operation cost 7% of depreciation
Value added tax 17%
Income Tax 25%
Additional tax 8%
IRR of profit after tax 11 12%
A4-2 - 38
8
2. Method of Financial Analysis Calculation
year Electricity Capital Cost O&M and Sales Income Tax Total Revenue Net Revenue (after
Generated Tax tax)
(GWH)
2011 (166.722) (166.722)
2012 17.851 4.292 2.089 20.529 14.148
2013 1 08
17.708 4.266
266 20
2.054 20 36
20.365 1 0
14.044
2014 17.567 4.241 2.020 20.202 13.941
2015 17.426 4.216 1.986 20.040 13.839
2016 17.287 4.190 1.952 19.880 13.737
2017 17.148 4.165 1.919 19.721 13.637
2018 17.011 4.141 1.885 19.563 13.537
2019 16.875 4.116 1.852 19.406 13.438
2020 16.740 4.092 1.820 19.251 13.340
2021 16.606 4.068 1.787 19.097 13.242
2022 16.473 4.044 1.755 18.944 13.146
2023 16 342
16.342 4 020
4.020 1 723
1.723 18 793
18.793 13 050
13.050
2024 16.211 3.996 1.691 18.643 12.955
2025 16.081 3.973 1.660 18.493 12.861
2026 15.953 3.950 1.629 18.345 12.767
2027 15.825 3.927 1.598 18.199 12.674
2028 15.698 3.904 1.567 18.053 12.582
2029 15.573 3.881 1.537 17.909 12.491
2030 15.448 3.859 1.506 17.765 12.400
2031 15.325 3.836 1.477 17.623 12.311
9
3. Results and Sensitivity Analysis Results
FIRR
change 20 years 25 years
(a) Base case 4.99% 5.97%
(b) Capital cost overrun 10% 3.99% 5.04%
(c) Lower benefit -10% 3.86% 4.91%
(d) Faster deterioration -1.5% p.a. 4.39% 5.33%
( ) Renew
(e) R power conditioners
diti 4 21%
4.21% 5 32%
5.32%
(f) Combination of (b) and (c) 2.93% 4.03%
(g) Combination of (d) and (e) 3.57% 4.64%
WACC = 4.44%
A4-2 - 39
10
3. Result and Sensitivity Analysis Sensitivity
11
4. Lifecycle analysis and Cost effectiveness
A4-2 - 40
12
Lifecycle analysis and Cost effectiveness
13
Lifecycle analysis and Cost effectiveness
A4-2 - 41
14
4. Lifecycle analysis and Cost effectiveness
15
4. Lifecycle analysis and Cost effectiveness
A4-2 - 42
16
4. Lifecycle analysis and Cost effectiveness
17
5. Tentative Conclusions
- Pre
Pre--FS level 10MW Pilot Project can be financially viable at power
purchase rate 1.15 / kWh, but vulnerable to adverse conditions.
p
(Would like to discuss more in Final Report)
A4-2 - 43
18
THE END
A4-2 - 44
96.5%
2012
A4-2 - 45
250kW
100kW,
2009 250kW
250kW
100kW 250kW
SOLARPACK
500kW
A4-2 - 46
W
100kW 250kW
94.5%100% 96.8%100%
95.3% 70% 96.9% 70%
94.0% 30% 96.5% 30%
97 0% (
97.0% 97 8% (
97.8%
4%2.5%
PWM
-10~4090%
A4-2 - 47
(
98.00
97.00
96.00
95.00
94.00
93.00
92.00
91.00
90.00
89.00
88.00
0 20 40 60 80 100
A4-2 - 48
W
TR,3,550kVA
250kWPV
MCCB MCTT MCCB 270V11kV
LBS LBS VCB DS PAS
250kWPV
33W
50Hz,11kV
DC1000V
KW
TR,3,550kVA
270V11kV
500kWPV 500kWPCS
MCTT MCCB LBS LBS VCB DS PAS
MCCB
33W
50Hz,11kV
270Vac 11kVac
500kWPCS
High Voltage
4 sets of 500kWPCS Power Grid
500kWPCS
A4-2 - 49
Out Door Packaging Image for 1MW System
Tentative Plan
Top view
550kVA
500kW 500kW
CS CS
550kVA
Air Air
Conditioner Conditioner
Door
Height
2700mm
Air conditioner
(Outdoor unit)
A4-2 - 50
A4-2 - 51
A4-2 - 52
(
98.00
97.00
96.00
95.00
94.00
93.00
92.00
91.00
90.00
89.00
88.00
0 20 40 60 80 100
Solution1
kVar
Mode
Mode
Mode
Solution
Cos0 85
Cos0.85 0 851
0.851
Mode
kW
Solution
0.85,
A4-2 - 53
P,Q
Vs
Vs+Vs Vs
1
s
s
s
FRT
A4-2 - 54
FRT
FRT
V V
66kV 6.6 kV
PV
PCS
1.0p.u.
Precover0.8pu)
V recovery (0.8 p.u.)
V min
0 T1 T2
Vmin0.2puT1=1,T2-T10.1(Vmin>0.2pu,0.2(Vmin<0.2pu
A4-2 - 55
RS-485
RS-
485
FRT
FRT
(275 3LS(0.2 66kV 6.6kV 110WPV-PCS
10W
2km
-PCS
2km 5
3MVar CL
1MW
10 500
500
A4-2 - 56
FRT
FRT
0.2sec
(100%
3LS
Benesse BL
BL
o.1
o.1
1
2010
2010 2
720kW
720kW 3456
3456
100kW
100kW
7
A4-2 - 57
110kW
100kW 10kW
100kW PCS
100kW
100kW 480
480
10kW
10kW
10kW
55 55
100kW
100kW
110kW
10kW
1
100kW
100kW
5 498kW
45
80kW 20kW
20kW
A4-2 - 58
2012 50075MW/
2011 30060MW/
2010
2010 100
00
13MW
13MW//
2009
2009 20
203MW
3MW//
2013
2013
1000
1000 00MW
00MW
2012
2012
720
720 300MW
300MW
2011
2011
200
200
20MW
20MW
A4-2 - 59
2011
MPPT
A4-2 - 60
A4-2 - 61
1.
2.
3.
4. MPPT
5.
6. ( )
1-1
1-1boost
98%
boost
A4-2 - 62
Boost
1-2
1-2Boost
1
1
2
3
4
5
1-3
1-3boost
99%
A4-2 - 63
3
1-4
1-4
96%
1-5
1-5
96%
A4-2 - 64
5
-1-6
1-6
440V 900V
440V 4400 612 270V
4400.612
270V/10KV
6MPPT
DC-DCMPPT
DC DCMPPT
3%-10%
A4-2 - 65
7
()
BIPV5%
A4-2 - 66
1
2
3
97%~98%
MPPT
A4-2 - 67
1
2
3
4
A4-2 - 68
1 ( )
2
3
4
5
2-2 MPPT
MPPT
2-2
A4-2 - 69
MPPT
2-1
2-1
Labcde
ab c
d e
1
0.35% 0.45%
A4-2 - 70
MPPT
MPPTMax Power Pointer Tracking
U-I
MPPT
MPPT
(Incremental Conductance Algorithms)
P&OPerturb&Observe Algorithms
MPPT
P-U
Pmax
MPPT
99%
MPPT
A4-2 - 71
A4-2 - 72
LVRT
A4-2 - 73
LVRT
2008.4
2011.2.24
16598
2011.4.25
A4-2 - 74
CGC/GS004:2011
5.5.1.2
10/
A4-2 - 75
CGC/GS004:2011
A4-2 - 76
20%5%
10%
20ms
1%2%
A4-2 - 77
1 500KW
A4-2 - 78
2
1)
1.1 IGBT
infineon
1.2
A4-2 - 79
1.3
1.4
A4-2 - 80
1.5
10
1.6
IGBT
PN
A4-2 - 81
1.7
1.8 DSP
32CPU(DSP)SPWM
MPPT>99.99%
A4-2 - 82
1 400V
1400V
2
3
4
5
6
6
7
A4-2 - 83
A4-2 - 84
1
PCB
A4-2 - 85
3
30%
30%
A4-2 - 86
5
3%
30%
A4-2 - 87
A4-2 - 88
11
A4-2 - 89
3
A4-2 - 90
A4-2 - 91
200111
501.5290
9011
8633
2011500MW2012800MW2013
2GW20143.5GW20155GW
20114
7000130
20127
2012
863
CGF
A4-2 - 92
2011 8
2010
2009 500KW
2007 15000
2006
2002
20014
1.5kW~5kW 1.5kW~5kW
A4-2 - 93
12KW17KW22.5 KW
50KW-1000KW
A4-2 - 94
500kW
GSG-500KTT-LV
630kW
GSG-630KTT-LV
A4-2 - 95
1MW
GSG-1000KTT-LV
UPS
A4-2 - 96
10%
3837
11
A4-2 - 97
ISO90012008
RoHs
6S
QCC
A4-2 - 98
200MWp30MW
20MWp
20MWp
20MWp
10MWp
10MWp
10MWp
30MWP
7.5MWp
9.8MWp
10MW
10MW
10MW
10MWp
9.3MW
/7.5MWp
5MWp
3.37MWp
3MW
10MW 30MW6MW
10MW 0.5MW
A4-2 - 99
200MWp
30MW
0.5MW
60MW
201180788
61162
6094
6094
7438
A4-2 - 100
/1000KW
35GW
A4-2 - 101
TUV AS4777
A4-2 - 102
18
A4-2 - 103
Renewable Energy Development Appendix 4 : Presentation Materials
Final Report Appendix 4-3 : Final Workshop
1) Final Report
2) 10MW Integrated PV Station of Golmud City
3) Speech on the Final Workshop and Outcome Extension
ADB TA Qinghai Renewable Energy Development Project
4) Prospect of ADB TA Haixi Renewable Energy
Development Project
RENEWABLE ENERGY DEVELOPMENT IN QINGHAI
PEOPLES REPUBLIC OF CHINA
PREPARED FOR
SEPTEMBER,2012
1
A4-3 - 1
History of Technical Assistance
1. Training
(1) The First Training April 25 to April 28, 2011 4 days
(2) The Second Training
July 04 to July 30, 2011 27 days
(3) Overseas Training in Japan
October 24 to October 30, 2011 7 days
1. Background
2 Advanced Technology for Grid
2. Grid-connected
connected Solar PV
System
3. Capacity Development
4. Review Design of a Pilot Grid-connected Solar PV
System
5. Knowledge Dissemination on Grid-connected Solar
PV Systems
A4-3 - 2
1. Background
A4-3 - 3
Renewable Energy (RE) such as solar, wind, biomass and so on,
has being introduced rapidly into the power system towards
environmental protection for the production of gases such as SOx,
NOx and carbon dioxide.
In Golmud district of PRC, power supply would exceed the demand and surplus power
would be generated when a solar PV system is installed. Following measures can be
considered;
1) Output control of the solar PV power system,
2) Expansion of transmission lines
8
A4-3 - 4
It still remains some issues to realize stable operation of the power
grid. As countermeasures against this issue, it is required to collect
and store the real-time operation data and continuous operation
record of the solar PV power system. Therefore, the facility that
transmits such information is required to be installed in the solar PV
system.
A4-3 - 5
(2) Impacts on Grid Stability and Measures
Table 2-2 Impacts on the Grid and Measures
Impact Measures
Supply - Impact-1 Power reducing operation of the renewable source power plants.
demand Excessive supply generated by the (Spain)
balance renewable source power plants Storage the generated power by battery, pumped storage power
plant,, etc.,, because the g
p generated p
power byy the renewable source
power plants must be supplied without power reducing operation
comply with government policy. (Germany)
Grid Impact-2 Power flow operation with/without neighbor TSOs grid operation.
stability The heavy power flow causes critical At emergency condition, power reducing operation of the
grid condition with small margin of N-1 renewable source power plants. (Germany)
criteria frequently. Power reducing operation of the renewable source power plants.
(Spain)
Impact-3 Stability analysis studies are carried out by organization set up by
Unexpected power flow caused by the related TSOs.
concentrated wind p power p plants ((Germany) y)
increases around Germanys grid.
Impact-4 Specified organization for renewable source power plants is
Misgiving of emergency trip at the established to control these plants. (Spain)
inter-connection lines caused by the A renewable power plant is obligated to equip FRT function.
unexpected trips of a large number of Requirement of FRT function is prescribed in Grid Code.
the wind power plants.
12
A4-3 - 6
2.2 Power Conditioner
13
14
A4-3 - 7
2.3.2 Smart Grid Technology
15
Substation Transformer
A4-3 - 8
(2) Verification of Grid Stabilization with Large-scale PV Power Generation
Systems
It will be required to evaluate the influence of interconnection of large scale
PV power generation to power grid on power quality such as fluctuations in
voltage and frequency, and apply output control technologies using a power
storage system for power grid stabilization.
17
5000 100
Remaining capacity of battery PV output
Remaining capacityy [%]
4000
W]
80
Power output [kW
3000
60
2000 Power plant output
1000 40
0
NAS output 20
-1000
-2000 0
4:00 6:00 8:00 10:00 12:00 14:00 16:00 18:00 20:00
A4-3 - 9
2.4 Assessment Tools
19
FishEyelensandCamera
20
A4-3 - 10
This estimation was compared with that derived with other methods,
one was NASAs and the other is QBEs Feasibility Study results.
Estimation of insolation for the site for 10 MW Pilot Project by QBE
was presented in their Feasibility Study Report whose excerpts
were p
provided to the Consultant.
Jan. Feb. Mar. Apr. May Jun. Jul. Aug. Sep. Oct. Nov. Dec. Total
QBE site 145.3 147.2 179.7 201.8 214.5 199.4 201.7 210.1 193.0 195.6 165.2 143.3 2197
NASA 176.7 168.3 196.9 193.8 186.3 167.4 170.5 172.1 168.0 198.4 179.1 169.0 2146
fish-eye 135.2 129.9 169.6 183.6 189.7 173.4 197.8 222.0 221.7 209.3 179.4 147.9 2159
21
22
A4-3 - 11
2.4.2 Technical Application of the large Capacity Solar PV
System connected to the Power Grid
There are two issues by the fluctuation for the grid-connected solar PV
system as follows;
23
(2) Countermeasures
1) Restrain of fluctuation voltage
For restrain of fluctuation voltage it is effective to control the voltage
fluctuation at the connection point to the power grid and fix the grid
voltage within specified value according to control reactive power and
install SVC (Static Var Compensator) at the connection point to the
power grid.
id
2) Supply and demand power control
It is necessary to keep the frequency stability at the appropriate level
for supply and demand power control of the power grid connected to
the large solar PV system.
As the counter measure of this difficulty, micro grid technology is
being developed.
In case of the solar PV system, insolation prediction is related to the
prediction of the solar PV system and it is also necessary to consider
the prediction of power generation which changes every hour.
A4-3 - 12
Table 2-6 Prediction Method of Insolation and Quick Demand/Supply
Control Method in Japan
Control
Outline of prediction method and control method Source
interval
Prediction method that based on the weather data
supplied by Europe Center of Meteorological Weather IEEEJournalVol.2, No.1, pp2-
Forecast ((ECMWF),), solar PV p
power output
p is p predicted 10 ((2008))
every one hour.
Generation The insolation data of the next day is predicted every
IEEJ Annual Meeting, 2009,
Plan 30 minutes by the territorial data of the Japan
No.7-049 (2009)
Meteorological Agency.
The insolation data of the specific time is predicted
IEEJ Trans. PE, Vol. 127, No.
based on the area weather forecast of every three
11, pp.1219-1225 (2007)
hours of the Japan Meteorological Agency.
Long interval
control 5 to 15minutes interval insolation prediction is tested IEEJ Technical Meeting on
(1 to
t severall b
basedd on the
th data
d t base
b off the
th pastt weather
th forecast
f t Power
P S t
System E i
Engineering,
i
minutes and the area weather forecast in rather short time. PSE-11-17 (2011-01)
interval)
Short interval IEEJ Trans. PE, Vol. 127, No.
The power storage system which quickly responds to
control 3, pp.451-458 (2007)
fluctuation of the Grid power for compensation of active
(second level IEEJ Trans. PE, Vol. 129, No.
power is applied.
interval) 12, pp.1553-1559 (2009)
25
Solar PV system generates electricity by direct and diffused sunlight and the
g of direct sunlight
strength g is several times stronger
g than the diffused sunlight
g
1) Macro Prediction
for a few hours or for a few days in a macro view
2) Micro Prediction
on the satellite photo
26
A4-3 - 13
2.4.4 Simulation Tools
27
Enables
E bl assessmentt off possible
ibl projects
j t att low
l costt
Free-of-charge to users around the world via the Internet &
CD-ROM
Training & technical support available via an international
network of RETScreen Trainers
IIndustry
d t products
d t & services
i accessible
ibl via
i an Internet
I t t
Marketplace
28
A4-3 - 14
3. Capacity Development
3.1 Performance Assessment of the Selected Grid-connected
Solar PV System
30
A4-3 - 15
(3) Evaluation of Site Analysis
32
A4-3 - 16
3.2 Capacity Assessment of 10MW PV System
33
The Consultant visited the ingot factory of Qinghai China Silicon Energy
Co. several times and received brief explanations on how the production
process was managed.
- It is considered very difficult to avoid the yellow sand intrusion into the
factory by the nature of the locality in Qinghai, China. Therefore,
appropriate countermeasure is required to prevent the yellow sand
getting into the building.
34
A4-3 - 17
3.4 Technical Guidance Note and Capacity Enhancement
Module
35
The result of continuous overloading condition is shown in the Table 3.3. If the
load factor is assumed to be around 0.3, the expected transformer lifetime for the
model chosen by QBE engineers would be over 1000 years. The size of the
transformer can be reduced, by allowing to have some over-loading situations.
05
105 155
55 0.421
0
36
A4-3 - 18
(4) Wiring between Modules
Wiring needs more length for setting to absorb vibration and to avoid
rubbing against PV frame.
37
Tilt angle of PV array was set at the same angle as site latitude for the 10MW
Pilot Project. This counts for direct sunlight only. As shown in Fig.3.2, solid angle
of sky becomes larger as the tilt angle becomes smaller, meaning PV modules
catch more of diffused light.
A4-3 - 19
(6) Direct Current Protection
270kV/350V
PV Transless Inverter
Transformer
Grounding
DC fault current
39
In the case of short-circuited failure, the fault current will flows from not only
transformer but also other transmission lines that are connected PV system.
Therefore, the capacity of circuit breaker should be designed to have enough
endurance of those total current.
A4-3 - 20
4. Review Design of a Pilot Grid-connected
Solar PV System
4.1 Review Design of a Pilot Grid-connected Solar PV System
411 R
4.1.1 Review
i D
Design
i anddT
Technical
h i lG Guidance
id on a Pil
Pilot G
Grid-
id
connected Solar PV System
Jan. Feb. Mar. Apr. May Jun. Jul. Aug. Sep. Oct. Nov. Dec. Total
QBE site 145.3 147.2 179.7 201.8 214.5 199.4 201.7 210.1 193.0 195.6 165.2 143.3 2197
NASA 176.7 168.3 196.9 193.8 186.3 167.4 170.5 172.1 168.0 198.4 179.1 169.0 2146
fish-eye 135.2 129.9 169.6 183.6 189.7 173.4 197.8 222.0 221.7 209.3 179.4 147.9 2159
41
(4) Inverter
It is important here that the user engineers understand each item of the
specifications. Users understanding of the specifications of inverter
should be at the same level as manufacturers engineers.
42
A4-3 - 21
(5) Control
There are many PV projects in Golmud and the total output will
reported to reach 200 MW. Therefore the stability of the grid will be the
largest concern of the utility,
utility and there will have to be a means to
control solar PV power plants in the area.
43
Legend
[MW] Power balance [MW] Power balance
Demand
Supply
(excluding PV power)
Supply
(including PV power)
Winte Summer
A4-3 - 22
(2) PV Power Plant
1) China Science and Technology Photovoltaic Power Holding Co., Ltd., 10MW
2) CPI Huajing Power Holding Co., Ltd., 20MW
3) Guodian Longyuan Golmud New Energy Development Company, 20MW
4) Qinghai New Energy Group Corporation, 10MW
5) Huaneng International Power Development Company, 10MW
6)) Qinghai
Q g Junshi Energy
gy Co.,, Ltd.,, 10MW
Haixi Grid 110kV Lines or Substation
Fig.4-2
Owner, Construction and b. 110 kV Substation
110 kV Substation
Operation Scheme
(110/35kV Transformer)
T f )
c. 35 kV Transition lines
90
power plant in the 80
Within
countries, which have 1 Sec
huge scale of wind/PV
power plants, and grid China
30
operator in Qinghai 20
Japan
(before March, 2017)
also intends to do so.
0 0 0.5
0.0 05 2.0 [Sec]
Voltage recovered Time
Start time
of voltage drop
*1 LVRT: Low Voltage Ride Though = Fault Ride Through,
Value of remained voltage to be continuous operation
A4-3 - 23
Recovery operation
Continuous operation
by FRT function Usual operation
Grid voltage
Output current
of inverter
48
A4-3 - 24
Result of Analysis financially unviable (FIRR/e=4.46%)
income-increasing/
expense decreasing measures required
49
change FIRR/e
Other implications
1) Concessional Tariff may not be sustainable.
2) Projects need access to foreign funds.
3) Disclosure of information is desirable.
50
A4-3 - 25
5. Knowledge Dissemination on Grid-connected
Solar PV Systems
51
5.1 N ti
National
lDDevelopment
l t Pl
Plan
51
The total installed capacity of PV power generation in China will be 10GW by the
end of 2015, 50GW for the year 2020 higher targets were set as 15-20GW in
2015 and 100GW in 2020, which are not impossible to realize.
Low plan
Medium plan
High plan
A4-3 - 26
(3) Production of Grid-connected Power Generation
Off-grid Grid-tied
142.0
W
150.0
InstallationMW
100.0
50.0 21.0
17.8 19.0 18.0
8.8 7.4 1.5 9.0 2.2
1.2 1.0
0.0
2004 2005 2006 2007 2008 2009
Year
53
54
A4-3 - 27
Table 5-3 Registered Companies and Applied Projects of Qinghai
930 Projects in Haixi Prefecture
Planned total
No. Project owner New capacity Project for 1.15 electricity price Location
capacity
1 Longyuan Golmud New Energy Development Co., Ltd. 30 200 20 + 30 = 50 Golmud
2 Yellow River Upper Reaches Hydropower Development Co., Ltd. 200 1000 200 Golmud
3 Guodian Power Qinghai New Energy Project Preparatory Office 10 200 10 Golmud
4 China Three-gorge New Energy 5 10 5 Golmud
5 Beijing Beikong Green Science and Technology Industrial Co., Ltd. 20 50 20 Golmud
6 Qinghai Water Conservation and Hydropower Group 10 20 10 Golmud
7 CPI Golmud Photovoltaic Power Generation Co., Ltd. 30 200 20 + 30 = 50 Golmud
8 Jinzhou Sunshine Energy 20 20 20 Golmud
9 Qinghai Project Preparatory Office of Datang Shandong Branch 20 20 20 Golmud
10 Huaneng Golmud Photovoltaic Power Generation Co., Ltd. 30 200 30 Golmud
11 Qinghai Baike Photoelectrical Co., Ltd. 8 10 2 + 8 = 10 Golmud
12 China Huadian Photovoltaic Power Generation Co., Ltd. 10 10 10 Golmud
13 Zhejiang Zhengtai Solar Energy Science and Technology Co., Ltd. 20 20 20 Golmud
14 Qinghai Jingneng Construction Investment Co., Ltd. 20 100 20 Golmud
15 Shengguang New Energy Co., Ltd. 2 20 1+2=3 Golmud
16 Qinghai Datang International Energy Project Preparatory Office 20 20 20 Golmud
17 Qinghai New Energy Group Corporation 10 10 10 Golmud
18 Qinghai Junshi Energy Co., Ltd. 8 10 2 + 8 = 10 Golmud
19 Qinghai Provincial Development and Investment Co., Ltd. 2 2 2 Golmud
20 Y ll
Yellow Ri
River U
Upper R
Reaches
h Hydropower
H d D
Development
l t Co.,
C Ltd.
Ltd 30 50 30 Ul
Ulan
21 CEC Solar Energy Co., Ltd. 10 10 10 Da Qaidam
22 Guodian Qinghai Branch 20 20 20 Delingha
23 Qinghai Linuo Solar Energy Power Co., Ltd. 30 30 30 Delingha
24 China Wind Power Group 30 50 30 Delingha
25 CEC Solar Energy 20 200 20 Xitieshan
26 CGNPC Solar Energy Development Co., Ltd. 90 100 10 + 90 = 100 Xitieshan
760
(including 45MW at Golmud
Total 705 2582
and 10MW at Xitieshan already
connected to grid)
55
56
A4-3 - 28
2) The financial exercises in Chapter 4 suggest that, for a PV project to be
financially viable, or the investors can sit comfortable when faced with adverse
conditions, there should be some measures taken to improve the cash flow for
a concession tariff of CNY 1.15 per kWh.
3) One measure found effective is to extend project life. Longer project life will not
only
l improve
i th financial
the fi i l performance
f off projects,
j t butb t also
l contribute
t ib t tot the
th
reduction of carbon dioxide emission for most of carbon dioxide emission from
PV power generation comes from production and installation processes of the
equipment.
57
- Fluctuation of the grid voltage caused by the reverse power flow to the
power grid from the solar PV system
58
A4-3 - 29
(2) Countermeasures
1) Reactive power control of the power conditioner for the grid connected
solar PV system and SVC (Statistic Var Compensator) installed at the
connection point of the solar PV system for reactive power control are
effective.
effective
2) Micro grid technology, namely to construct small size power grid and to
control supply and demand power of that power grid is essential to
reduce the influence caused by the fluctuation of the large solar PV
system to the wide range power grid.
59
(3) Recommendation
60
A4-3 - 30
5.5 Optimal System Configuration
61
62
A4-3 - 31
10MW Integrated PV Station
of Golmud City
Introduction
Contents
Chapter 1 Outline
Chapter 2 General Plan
Chapter 3 Electrical Design
Chapter 4 Civil engineer
Chapter 5 Fire protection
Chapter 6 Environmental Protection
A4-3 - 32
Chapter 1 Outline
1. Summary
A4-3 - 33
2. Scale of construction and Designing Scope
Scale of Construction
No. Item
2 PV
V Module
odu e 220wp
0wp 45600
5600
Designing Scope
2. Site introduction
2.1 Natural condition
The PV station is located in the east exit of Golmud City, 11 KM
away from Golmud City. National highway No. 109 pass through
the site with convenient transportation.
p The terrain is pplain and
open in general. Geographic environment is good. Situated in the
south side of the Chaidamu Basin, which is defined as Gobi
Desert with a stable geographic strike. The site is 562 meters long
from east to west, 503 meters wide from south to north, with the
total area of 282686 square meters. According to the 30 years
statistics recorded by the weather station ranged from 1971 to
2000, the total radiation of this area could reach to 1806
1806
2077kWh/square
q meters,, the average
g annual radiation could reach
to 1944.5kWh/m2.
A4-3 - 34
2.2 Engineering geology
The site is located in the flood alluvial plain of Kunlun Mountain. The ground elevation is 2862.19
2862.19
2874.47m, relative elevation is 12.28m,high in west and low in east.
2.2.1 Above the site 0.3~0.5m, it is the loose eolian
eolian--sand which should be removed.
2.2.2 sand soil spread in the site with good mechanic property, could be used as the bearing layer. And
around No. 78, 112,113
112,113144 holes, the round sand could be used as the bearing layer. We suggest the
base of the facility should use the independent base . The associated equipment house could use strip
shaped base.
2.2.3 Due to the pretty deep location of the underground water , the impact could be neglected.
2.2.4 The seismic resistance is 7 degree, categorized to group 3. The designed basic seismic added value
is 0.10g, categorized to group
group, the designed characteristic cycle value is 0.45s. No earthquake in the
site happened. Breaking and factors influence the stability of the rock exists, belonging to ordinary site
for the construction.
2.2.5 The standard freezing depth in Golmud area is 1.05m, according to the result of analysis to the soil
sample taken from the site, the moisture content is 4.7~6.1%, averagely 5.4%. The minimum distance
between underground water to freezing ground is is1.50m, average frozen heave factor is1, belong
to the grade 1 as non
non--froze layer
2.2.6 Resistivity of the site soil is 58~163m
58~163m
2 2 7 Sand storm happens in the site
2.2.7 site, which need the active protection from wind storm and sand storm
storm.
A4-3 - 35
2.3 Solar energy
Table 1-3 Main meteorological elements table of Golmud City (normal value of accumulated year)
A4-3 - 36
Chapter 2 General Plan
1. Briefing of the site
The site is located in Golmud City, 11 km away from the east toll gate, and 2 km away from the
national road with a convenient transportation. The total capacity is 10MWp. Generally, it is a matrix
layout. The station is composed with two parts of production area and management area. The entrance
and exit of the station is designed at the west and south side of the station, and connected with the road
outside. The management
g area is in the southwest. The total area of the station is 0.283k
0.283k, the area
for the management area is15824
is15824
2. General layout
On the basis of full consideration of the site and condition, newly built comprehensive building is
located in the southwest of the site, adjacent to the distribution central control room in the west. The
comprehensive building is linked with the distribution central control room by the corridor. The
comprehensive
3. Vertical design
The superficial standard height is 2862.19
2862.192874.47m, relative height is 12.28m, high in west and
low in east. Generally , the site is plain and broad. There are rise and fall in part of the area. On the
basis of the, road standard height refers to the current standard height of the site. The newly built
comprehensive building is 450mm higher than the surface outside of the building.
building
4. Transportation
The transportation system is a loop line with the array as the main part, connected with all buildings.
The average width of the road is 4 m, the minimum turning radius is 6 m.. It is a complete traffic
network with fire ring.
A4-3 - 37
Chapter 3 Electrical Design
1. PV site design
A4-3 - 38
1.2 PV array framework
Fixed support. The bearing angle of the array is south with the best
angle roll of 33 degree
1 3 PV array design
1.3
2 groups of solar energy group string (20 pieces of each string),
vertically settled and form them to 2 lines and 20 columns, i. e. 40
pieces of solar cell module is formed as an array.
Technical requirement
1. Module type BEST-220P-20, 40 pieces for each subarry
A4-3 - 39
Installation Diagram of PV Array Framework
Installation requirement:
Straightening the connecting rod before installation
All connecting parts need to be well ready and connection needs to be reliable.
The back up plates will be requirement between the connection points for any necessary moment.
The material listed in the sheet are for one subarray (40 modules form for one subarray)
Strengthening brace is installed in the first shelves and sixth shelve, and fastened by the M16 bolt.
The beam is formed with the 6 C type steel numbered as IIIIIIIVVVI, Connection need to be
carried out orderly.
A4-3 - 40
According to the calculation, the power generation of the first year could reach to 17
17,,8658
million kWh, 20%
20% declining for 25 use of the system, the total output of 25 years could
reach to 406
406,,285 million kWh, the average output each year is 16 16,,2514 million kWh, the
output of 25 years is as following
following::
A4-3 - 41
2.1.2 Choice of Booster Station Site
A4-3 - 42
Floor Plan of Booster Station
A4-3 - 43
Unit Transformer
American box transformer substation, outdoor installation.
35kV Switchboard
35kV switchboard takes KYN61-
KYN61-40.5GY Armoured removal AC closed high
tension switchgear. ZN85GY(VEM)-
ZN85GY(VEM)-40.5 vacuum cutout switch is inside with 25
ka drop
drop--out current. Metering point is settled in 35 kv metering cabinet of the
newly built 35 kv high tension switchgear. The metering point of the pass is
settled on the end of the line side. 2 inlet wire switch cabinets, 1 incoming cabinet,
1 capacitor box 1 voltage transformer cabinet will be
A4-3 - 44
Function Needed for Electricity and Electric Power Collection
To meet requirement of commercial operation of grid, the following function will be needed:
aSystem could receive and process the electricity quantity data and non
non--electricity quantity data sent
by pass or collection terminals.
bThe data pool could store more than 1 year of electric data period by period with the time mark:
including original data,
data partial middle result,
result the processing capability should be no less than 200 points.
points To
form the report sheet according to the requirement and printing or storing in other media.
cSecurity and confidentiality, especially for the store and access data, the mode setting and remode of the
parameters, user permission and access condition, to prevent the illegal access.
dFile all operation from operators.
eGood manman--computer interaction like warning , display of report sheet, timing, call print etc.
fSupervision and automatic warning on the inefficiency of pass measurement and electric quantity
intervals and print the result.
gAutomatic recording when the phone is busy, breakdown of the passageway, wrong report and
transmission etc and could be displayed and checked on CRT.
hSupport application development.
iInterface requirement should be available. When 4 wire line channel adopted, the modem should be
equipped.
The measuring point will be settled in the 35kV measurement cabinet. The measurement loop
concludes 2 three phase automatic electric meters of 0.2 s class and 1 pressure loss timer. The CT
measurement adopts class 0.2s, 0.2 class for PT. The variable voltage measuring two loop is equipped
with 1 three phase four wire low voltage automatic electric meter of class 0.2s. Measuring CT adopts
class 0.2s, and installed in the cabinet of the secondary electric equipment. Cabinet.
a) The comprehensive automation system and interface circuit of the secondary electric equipment: the
abnormal signal of protection, automatic equipment, direct current of the equipment will both send
teleindication and display in the screen of each . The indication panel will not be installed in the
substation. If needed, the automation system could be available.
b) telecommunication and interface: the station control layer adopts Ethernet. The layer has a good
openness. Interval layer adopts industrial control network, which owns the enough transmission speed
and high efficiency. Each interval layer could telecommunicate directly. Network topology should adopts
bus type, ring type or star type, the physical connection between station control layer and interval layer
should adopt star.
c) Control voltage and reactive power regulation: Circuit breaker and all electric isolation switch could
be remote controlled. Voltage and reactive power could be remote controlled by hand; The reactive
power compensation equipment could automatically adjusted; The remote cast and reset, amendment of
protection constant value could be used for the protection equipment. The control way could be switched
and closed automatically.
d) Man
Man--computer interaction: The local monitoring host, display, panel and printer, data storage etc
could
ld be
b installed
i ll d in
i the
h substation
b i for f the
h convenient
i operation.
i
e) Other function like self
self--diagnosis and management etc.
A4-3 - 45
2.2 Configures of computer supervisory system
Computer supervisory system is composed with station control layer and interval control layer.
1) Station control layer
Substation takes single network structure, station control layer is directly connected with the interval
layer, mainly, includes 1 engineer working station, 1 telecontrol master station, 1 warning system, 1
printer and 1 set of timer, network system
Host computer and operators working station adopts the man man--computer interface of station control
layer to collect, process, store the data , and to record report sheet, event and warning display as well as
checking guiding,
checking, guiding explaining and transmitting the control orders.
orders
Telecontrol station directly receive data of I/0, and establish the data pool, and according to the
protocol of dispatch center, through special channel to connect to the equipment and transmits the
telecontrol information.
Station control layer is connected with the equipments by Ethernet, , station control layer will be set
screen and installed in the secondary electric equipment cabinet.
2) Interval control layer
Telemetry, teleindiation and remote control function could be conducted by the special measurement
and control equipment
equipmentI/O measuring and controlling unit), which has the function of LED
measurement, Synchronous detection, emergent operation of on spot breaker and display of the
measurement figure etc. Each interval layer is independent, mainly used to collect , transfer, process
and
d transmits
i the
h iinformation
f i off theh equipment.
i
I/O measuring and controlling unit collect the real time data and upload to Ethernet which transmits
them to station control layer, at the same time, transmits the remote control , teleindication orders to
each I/O.
Station control layer is connected with interval control layer by LAN.
A4-3 - 46
2.3 Relay Protection and Automatic Device
2.3.1 Designing principle
On the basis of Technical Regulation of Relay Protection and Automatic Devices
GB14285--2006, with micro
GB14285 micro--computer
2.3.2 Deploy of relay protection and safety automatic device
a 35kV line protection
b Unit transformer protection
c SVG outline protection
d Stability control system
e wave recorder of breakdown of micro
micro--computer
f inverter protection
A4-3 - 47
3 Station power
Load of the station includes the life power, lighting electricity of the
control room, operational power of all devices. According to the
statistics of the PV power loading, the transformer of the station is
250kVA, which is supplied with 0.4kV, which could meet the
requirement of the technical regulation. Duplicate supply will be
adopted for the power station, the main power supply is from T
connection of 35 KV line nearby, the backup power supply is from
35 KV generating line of the PV station
station.
A4-3 - 48
5. Lightening protection grounding
5.1 PV array
5.2 Booster overvoltage protection
5.3 Grounding system
A4-3 - 49
2. General layout
In general, the building is integrated with the surrounding and coherent with other buildings, with the
main building facing a good direction.
3. Single building designing
1Office: 460m square
The office is located in the southwest of site, east of central control cabinet with one floor. F6
dormitories, 3 offices, lobby, anteroom, corridor, dining room, operation room, storage room and
bathroom.
2Central Control Room: 413 m squareq
The central control room is located in the southwest of the site, west side of the office with one floor.
SGV compensation room, 35 kv switching room, transformer room, central control room and passage.
4. Architectural section
1Office : Story height is 3.3 meters
First Floor
Floor 3.3 meters
Height dispersion between inside and outside room: 0.45 meters
Total height: 3.75meters
2Central control room: story height is 4.8 meters (eaves height)
First floor: 4.8 meters (eaves height)
Height dispersion is 0.30
0 30 meters
Total height is 5.10 meters (eaves height)
5. Energy saving
160 layer of extrusion
extrusion molding warmth keeping boards is put on the exterior wall above the floor.
2Good air tightness energy saving hollow glass is adopted in the exterior wall.
3Natural illumination is adopted for the main buildings.
4Door bucket is adopted for the main entrance
A4-3 - 50
Floor Plan of First Floor of Central Control Room and Distribution Room
3. Structure designing
2Natural condition
Table 3-2 Parametric loading of wind and snow
A4-3 - 51
3Designing evidence and requirement
Table 3-4 Standard, rules, regulations and procedures of the designing of the site
4Structure type
Vertical structure system: single story building with the steel structure. The exterior wall is coal gangue
porous brick masonry
Roofing system
systemsandwich steel panel
Structure analysis
A overall analysis
Calculation and Drawing on Steel Concrete frame, Bent and Continuous Beam of Architecture
Science Institute of China is adopted. 2010 2010
B Calculation of the foundation
JCCAD Software on Foundation,
Foundation Strip Foundation
Foundation, Steel and Concrete Foundation Beam
Beam, Pile
Foundation and Raft Foundation of Architecture Science Institute of China is adopted.
5Main structure material
Concrete earth Table 3-6 Density level of concrete component
Environment category
categoryUnder earth belongs to category B; the rest belongs to Category A.
Steel:
ASteel for concrete structure
Concrete iron: is HPB300 concrete iron ,is HRB335 concrete iron
Steel: Q235B
Q235B
Wall material: MU10coal gangue porous brick , mortar is M5 fixed mortar
A4-3 - 52
2. Briefing about office
Marshalling structure with total area of 460m2
460m2
1Security level and service life
Table 3-7 ecurity level of building and designed service life
2Nature condition
Table 3-8 Parametric loading of wind and snow
Basic wind pressure Toughness of ground surface Basic snow pressure
Wo0.40kN/m Category B So0.20kN/m
A4-3 - 53
4 Structure type
vertical structure system: single story building with marshalling structure
roofing system: The cast-
cast-in-
in-place reinforced concrete roofing system
structure analysis
A. overall analysis
Based on Software of Calculation and Drawing of Steel Reinforced Concrete Frame, Bent, and
Continuous Beam of PK. PMCAD Engineering Department of China Architecture Science Institute
(2010)
B Calculation of the foundation
JCCAD Software on Foundation, Strip Foundation, Steel and Concrete Foundation Beam, Pile
Foundation and Raft Foundation of Architecture Science Institute of China is adopted
5Main structure material
concrete
A. Intensity level of concrete member
No Name and range of component Density level of concrete Note
A4-3 - 54
4.4.3 Designing Scope
The designing includes: water supply and drainage system, indoor fire hydrant system,
outdoor hydrant system, extinguisher system of building
Drainage system is diversion of rain and sewage
1sewage: after processing in the digestion tank, it will be led to the absorbing well
which owns the diameter of DN300
DN300
Pipe material and interface: indoor pipe is UPVC spiral silent drainage pipe. The outdoor
drainage pipe is double wall corrupted pipe with rubber interface.
2Rain: The rain will be drained to outdoor manhole, together with the rain outside , flow
to rain pipe network of the site.
3) Pipe deployment: The geology is Grade 2 self weight collapsibility loess. The pipe
within 6 meters of prevention distance will be deployed in the leak detection pipe ditch
which is mortared with the type C brick.
A4-3 - 55
4.5.4 Designing of heating and ventilation
1Heat radiator
We adopt antiseptic LXGL
LXGL--X/202-
X/202-600Steel aluminum composite radiator. (Under the
standard condition, the heating radiation is 130W/piece)
2Heating pipe
Welded steel ppipe
p with the diameter of DN32, connected with flange,
g when diameter is
DN32, connected with wire.
3Mechanical recycling heating radiation system
4Mechanical exhaust for deficiency of natural exhaust
5Mechanical ventilation system for deficiency of natural exhaust
6Mechanical ventilation for the bathroom
A4-3 - 56
4.6.2 Designing scope: the following electric equipment is included:
10/0.4kv distribution system, low voltage distribution system, illumination system, telephone, TV,
network, lightening protection, grounding system and other safety measurements.
4.6.3 Distribution system:
1Load rating: the illumination load is rate 3. Emergency lighting and escape lighting use storage
battery, the emergency hours is no less than 30 mins.
2Energy measurement: total measurement will be deployed at the side of high voltage
distribution system, meters set will be deployed at the side of high voltage system to measure the
power.
3 Cable of 0.4kv line led the power source to building is YJV22 YJV22--1kv. Cable for low voltage is
directly buried underground.
4.6.4 Low voltage distribution system :
1Power source of the building are all connected by the AC screen of distribution cabinet of
central control office , in the way of radiation or trunk type , and lead to distribution closet of floor or
end distribution closet. Return circuit of lighting is protected by the circuit breaker. Outlet circuit is
protected by the leaking circuit breaker.
2Distribution system inside of the building adopts BV BV--0.5kv type cable
cable
3) Panel switch, outlet adopt 86 series product. The wall is concealed installed. Distribution closet,
control closet, outlet closet all adopt ZJPR type or PZ30 type product. The wall is concealed installed.
44.6.6
6 6 Telephone,
Telephone TV and computer network system
Telephone circuit is connected with the public telephone, and distributed to single machine by telephone cable
box set .
Signal line of TV is connected with regional cable television network, and transfer, distribute to terminal users.
LAN system is set up in the office building, and is connected with the civil network. Network interface
according to the requirement of the clients is deployed in the office. Backbone network is optical one, the
branch uses 4 pairs of twisted copper cable of super category 5.
The weak line is all led to through the cement pipe outdoor, and KBG metal pipe indoor.
4.6.7 Lightening prevention, grounding and safety measurement
1Category 3 lightening prevention and protection of the building.
2Integrative grounding of lightening prevention and protection for all single building
3General equipotential connection is set up in all single building, including all metal protective cover,
metal cuticle, heating pipe, underground line etc.
4All kinds of strong or weak line led to the building will be set up a SPD at the end of the line.
A4-3 - 57
Chapter 5 Fire Protection
5.1 Designing evidence
Typical Fire Protection Rules of Electric Equipment DL5027
DL5027--93
Fire Protection of Thermal Power Plant and Substation Designing GB50229
GB50229--2010
Regulation on Fire Protection of Building GB50016
GB50016--2010
Designing Rules of Extinguisher of Building GBJ140
GBJ140--90
6.2 Water
We take water from the well, the amount of the life water is very less, so it will not
bring any negative impact to the underground water.
The sewage amount is 0.6m/d( 219m/a), the floor dust, together with the waste will
be disposed and filled in the landfill site regularly. The panel will be cleaned by the
wet cloth without and addictives once every month, except in winter. The cleaning
water is 60 m3/a, which could be used for the plants and floor.
6.3 Noise
A4-3 - 58
You
Thank You
A4-3 - 59
Speech on the Final Workshop and
Outcome Extension of ADB TA
Qinghai Renewable Energy
Development Project
Distinguished guests,
Ladies and gentlemen,
A4-3 - 60
In recent years, in the face of international
financial crisis, euro crisis and high fossil fuel
energy price,
price all nations are adjusting their
energy development strategies. We should step
up the efforts on renewable energy development,
vigorously promote energy conservation and
pollution reduction, increase energy efficiency,
andd enhance
h iinternational
t ti l energy cooperation
ti
for a green and low-carbon development.
A4-3 - 61
Qinghai is the best place for solar power
generation in the world. Qaidam region has a
large amount of desertified land and plenty of
sunshine for solar power generation, good grid
connection and transmission conditions and
con enient transportation
convenient transportation.
A4-3 - 62
Inlight of present development, we can
summarize the characteristics of solar PV
generation as follows: 1, diversified technology
and developing trends. Different technologies
are competing with each other and this will help
drop the cost. 2, growing economic advantages.
A4-3 - 63
3, solar power generation will gradually change
its role from supplementary energy to alternative
energy. With its growing economic and
technological advantages, solar power
generation will enter the phase of large-scale
development and become another important
way off power generation
ti after
ft hhydropower,
d
thermal power and wind power generation.
A4-3 - 64
At present, solar power generation is faced with the
problems of large-scale grid connection and operation.
Technologygy and standards on g grid connection of new
energy power still need further study. We hope that
ADB will give us concern and support as always and
Chinese enterprises will actively participate in the R&D
and cooperation on international energy technology to
promote the sound and sustainable development of
renewable
bl energy. AAndd fifinally,
ll I wishi h th
thatt th
the workshop
k h
can attain the results expected.
Thank you!
A4-3 - 65
Prospect of ADB TA Haixi Renewable
Energy Development Project
Contents
A4-3 - 66
I. Overview of Haixi Prefecture
H i i Mongol
Haixi M l andd Tibetan
Tib t Autonomous
A t P
Prefecture
f t li
lies att th
the north
th off th
the Qi
Qinghai-Tibet
h i Tib t Plateau
Pl t andd eastt off Qinghai
Qi h i
province. It is the largest ethnic autonomous prefecture in Qinghai with an area of 300,900 k, covering 41.7% of the
total area of the province. It is named Haixi because its location on the west of Qinghai Lake. The major part of its
land is the Qaidam Basin, one of the four largest basins in China, therefore, Qaidam is used to refer to Haixi Mongol
A4-3 - 67
Map off Key Function
i Zones in
i Qinghai
Qi i Province
i
Haixi Prefecture is important for the economic development of Qinghai province. Supported by
the circular economic pilot zone and its superior resources, Haixi strives for the leap-forward
development of economic and social transformation and greater contribution to the development
of Qinghai by achieving three-leads and three-breakthroughs in the province.
A4-3 - 68
Qaidam circular economy pilot zone is the
largest among the first 13 circular
economy pilot industrial parks in China. It
is the key area in Qinghais strategy of
promoting new type of industrialization,
the characteristic and competitive
industrial base for the Great Western
Development and one of the national
sustainable development experimental
zones.
In the first half of 2012, the prefecture has
achieved a total economic output of 25.79
billion yuan with a year-on-year growth of
16.3%. In the first 7 months, it has
achieved an industrial added value of
24.04 billion yuan with a growth of 17.6%,
and a total investment in fixed assets of
25.64 billion yuan with a growth of 100%.
Haixi prefecture has rich energy resources, including hydro power, wind power, and solar
power resources. Its average altitude is about 3,000 m and it has an unique climate with not
distinct four seasons, strong insolation , dramatic daily temperature swings and perennial
drousght, wind and small rainfall. It belongs to the typical plateau continental climate with its
annual average temperature of -5.65.2, annual average rainfall 16.7487.7 mm and
annual average evaporation 1353.93526.1 mm.
A4-3 - 69
Hydro power
Haixi has a total of over 160
rivers that cover about 500
k and about 40 rivers have
water throughout the year.
Th volume
The l off water
t
resources is 11.655 billion m,
among which 5.269 m comes
from the pilot zone.
Wind power
Haixi has relatively rich wind power. Influenced by land forms and altitudes,
the average wind speed inside the basin is 3m/s4m/s, and the average wind
speed in hilly area is above 4m/s. There are 12-168 days that have high wind
above level 6.
A4-3 - 70
Qaidam basin is the area with the richest solar resources in Qinghai province and Lenghu, Magnnai and Golmud
are the areas with the richest resources in Haixi prefecture.
A4-3 - 71
In 2011, 44 new energy projects with a total installed capacity of 1118.5
MW were under construction in Haixi prefecture, among which 40 were
PV projects, 3 wind power projects, and 1 photo-thermal project. 40 PV
power ggeneration p
p projects
j were completed
p with an installed capacity
p y of
913 MW and a fixed investment of 12.6 billion yuan. The estimated
annual average power generation is 1.5 billion KWHs, saving 525,000
tons of standard coals that are equivalent to reducing 15.3 million tons of
CO and 58.8 tons of SO.
Within only one year, Haixi claimed the title of five first in the world:
the area with the most concentrated solar PV installed capacity, the
largest PV power station under construction, the largest installed
capacity of PV power stations within a short period in the same area, the
largest on-grid PV system under construction and the first million KW
class on-grid PV power station in the world.
A4-3 - 72
IV. Prospect of ADB TA Haixi Renewable Energy
Development Project
A4-3 - 73
Program for Haixi Renewable Energy
Development
2010-
2010-2020
2020
Solar Power
According to the principles of overall planning and all-round consideration,
appropriate concentration, reasonable distribution, step implementation and
conduciveness to the long-term development and in accordance with the National
Renewable Energy Law, National Program for the Medium and Long Term
Development of Renewable Energy, Report of the Planning of the Ten Million
Kilowatts Class PV Power Base in Qaidam Basin of Qinghai Province, and the
Planning of the Solar Power Generation Base in Qaidam Basin of Qinghai
Province 31 on-grid PV power stations are planned to be built with a fixed
Province,
investment of 62 billion yuan and a total installed capacity of 20,000 MW,
accounting for 7 of the theoretically explorable installed capacity in Qaidam
basin and covering 1,817 k. It is planned the total installed capacity of solar
power generation base in Qaidam basin will reach 4,000 MW by 2015, 10,000
MW by 2020, and 20,000 MW by 2030.
A4-3 - 74
Objectives of Development of Renewable Energy in
Haixi Prefecture
Duringg the 12th Five Year Plan pperiod,, Haixi pprefecture will
continue to depend on its rich solar energy and land resources, seize the
opportunity to develop new energy with national and provincial support,
and speed up the construction of solar power projects to build Qaidam into
the largest solar power generation base in China with a total installed
capacity of 4,000 MW by the end of the 12th Five Year Plan period.
During this period, Haixi will continue to speed up the utilization of wind
power, seize the opportunity to develop new energy with national and
provincial
i i l supportt andd steadily
t dil promote t the
th construction
t ti off wind i d power
projects to achieve a total installed capacity of 650 MW of wind power
projects by the end of the period.
Conclusion
A4-3 - 75
Thank you!
A4-3 - 76
Renewable Energy Development Appendix 5
Final Report Seminar and Workshops
APPENDIX 5
1. Seminar
(1) Schedule
April 27, 2011 and April 28, 2011, in Xining, Qinghai Province, PRC.
(2) Program
28 April, 2011
Time Details Speaker
09:00 - 09:30 Transportation to the Site -
09:30 - 11:30 Site Visit (300kW PV System) NEWJEC (Mr.Tanaka/Mr.Yagi)
11:30 - 12:00 Transportation -
12:00 - 13:00 Closing and Lunch -
A5 - 1
Appendix 5 Renewable Energy Development
Seminar and Workshops Final Report
2. Interim Workshop
(1) Schedule
(2) Program
A5 - 2
Renewable Energy Development Appendix 5
Final Report Seminar and Workshops
3. Final Workshop
(1) Schedule
A5 - 3
Appendix 5 Renewable Energy Development
Seminar and Workshops Final Report
(2) Program
Concerning the Panel Discussion, the speakers and panelists will consist of two
moderators, two experts from ADB, one panelist from Energy Bureau, one
panelist from Electric Company, one panelist from EA, one panelist from IA and
two panelists from the Consultant.
A5 - 4
Renewable Energy Development Appendix 6 Registered Companies and Applied Projects of
Final Report Qinghai 930 Projects in Haixi Prefecture
APPENDIX 6
Planned total
No. Project owner New capacity Project f or 1.15 electricity price Location
capacity
1 Longyuan Golmud New Energy Development Co., Ltd. 30 200 20 + 30 = 50 Golmud
2 Yellow River Upper Reaches Hydropower Development Co., Ltd. 200 1000 200 Golmud
3 Guodian Power Qinghai New Energy Project Preparatory Of f ice 10 200 10 Golmud
Renewable Energy Development
A6 - 1
14 Qinghai Jingneng Construction Investment Co., Ltd. 20 100 20 Golmud
15 Shengguang New Energy Co., Ltd. 2 20 1+2 = 3 Golmud
16 Qinghai Datang International Energy Project Preparatory Of f ice 20 20 20 Golmud
Appendix 6