Work Breakdown Structure

Download as docx, pdf, or txt
Download as docx, pdf, or txt
You are on page 1of 3
At a glance
Powered by AI
The document outlines the work breakdown structure (WBS) of a project which includes key stages like initiation, procurement, designing, production, logistics, monitoring and administration.

The main stages involved in the project are initiation, procurement, designing, production, logistics, monitoring and administration.

The tasks involved in the procurement stage include site acquisition, contracting workforce, acquiring suppliers and manufacturers, sourcing, preparing purchase orders.

BTMR4043 Project Management 2017/18 (Assignment)

WBS FIELDS
Est. Level
WBS # Task Description of Task Owners
of Effort
All task management and management
L-1 Initiation
activities
Assigning stakeholders involving in the Project
L-1.1 Assign Key Person
project Manager
Development of WBS, work package
identification, schedule formulation,
staffing projection, resource estimation.
Project
L-1.2 Prepare Project Plan Followed by development of a detail
Manager
project plan that list all the key resources,
task, milestones, dependencies, and
duration.
Meeting upon receiving Letter of Award Project
L-1.3 Kick-off Meeting
after completing tendering process Manager
Handling all purchasing and acquisition of
L-2 Procurement
properties
Project
Visit project location for surveying and Manager
L-2.1 Site Acquisition
value analysis Procurement
Mngr
Contracting Preparing labors and workforce needed to Procurement
L-2.3
Workforce run the project Mngr
Gathering information to supply and
Acquire Suppliers Procurement
L-2.4 manufacture the said products requested in
and Manufacturers Mngr
BOM from engineers
Finding the most efficient and reliable Procurement
L-2.5 Sourcing
source of materials Mngr
Preparing Purchase Procurement
L-2.6 Releasing purchase order to stakeholders
Order Mngr
L-3 Designing Design and product development stages
Selecting Choosing the right components and sub-
L-3.1 Mech Mngr
Components products involve in this projects
Rough quick design on the project's
L-3.2 Appearance Sketch Mech Mngr
product to be release for approval purpose
Allowing clients to check and revise the Project
L-3.2.1 Submission to Client
project's product first look Manager
Appearance Revise Project
L-3.2.2 Meeting on detailed revising information
Meeting Manager
Designing mechanical components
L-3.3 Mechanical Design Mech Mngr
involved in the product to develop
Low Level Control Designing the autonomous part of the
L-3.5 LLC Mngr
Design product
Designing electrical components involve
L-3.7 Electrical Design LLC Mngr
in the product
Interface Software Software user interface and experience
L-3.8 IT Mngr
Design designing (UI/UX)
Detailed Drawing Engineering drawings for manufacturers to
L-3.9 Mech Mngr
Submission/Approval product the assemblies
BTMR4043 Project Management 2017/18 (Assignment)

Develop Bill of Generate and release BOM to procurement Mech Mngr


L-3.10
Material (BOM) team LLC Mngr
Build and test first working unit of the Mech Mngr
L-3.11 Prototyping
product LLC Mngr
L-4 Production Producing the actual products
Product Specification Checking final specifications release by
L-4.1 Mech Mngr
Confirmation manufacturers to produce the product
Develop
Manufacturing Specify any specific process to be operate
L-4.2 Mech Mngr
Process Requirements by the manufactures
for Supplier
Involving engineers to check the produced
Preliminary Review
L-4.3 part at production floor to gauge the Mech Mngr
on Supplier Quality
quality produce by the manufacturers
Provide Purchase Releasing purchase order to Procurement
L-4.4
Order manufacturers/suppliers Mngr
Pre-assembly for Test Assemblies of sub-assemblies to examine
L-4.5 Mech Mngr
Fit the fit produced by manufacturers
In-House Quality In-house QA to ensure it passes certain
L-4.6 Mech Mngr
Check standards
L-5 Logistics Handle supply chain matters
Shipment of Raw Supply Chain
L-5.1 Handling container for product shipments
Materials Manager
L-5.2 Custom Clearance Resolve any matters regarding customs Port Manager
Supply Chain
L-5.3 Supply Chain Storage Handling warehouse matters
Manager
Prepare documents for customs or Supply Chain
L-5.4 Documentation
shipment purpose Manager
Support
Ensure safe packaging to reach the project
L-5.5 Packaging Services
location without damage
Manager
Operations
and
L-6 Monitoring Actual operating of the product
Maintenance
Manager
Operations
Install the product at the project location.
and
L-6.1 Installation Involving testing and commissioning the
Maintenance
products
Manager
Any prerequisite tasks to be done before
L-6.2 Site Preparation Site Manager
arrival and installation of products
General
L-7 Administrations Handle indirect tasks for the project N/A
Manager
Accounts
L-7.1 Accounting Handle financial matters on the projects N/A
Mngr
Performance outcome upon completion of General
L-7.2 Performance Test N/A
projects Manager
Public relation with stakeholders or
L-7.3 Human Resource HR N/A
involved individual
L-7.4 Travel Management Plan and prepare travel documents Admin N/A