1122 - 02 Tech Spec Vol 2B - WT SAC PDF
1122 - 02 Tech Spec Vol 2B - WT SAC PDF
1122 - 02 Tech Spec Vol 2B - WT SAC PDF
NRO/CON/WT/533
CONTENTS
1. Cover page
3. Scope of Supply
11. Spares
GENERAL
(iii) Type and quantity of oil, lubricants & consumables for initial fill till successful
commissioning of equipment.
(iv) List of Commissioning spares and start-up spares with unit rates.
(v) List with unit rates of special tools and tackles, if any required.
(vi) Price Schedule for equipment & erection work as per the format enclosed.
(vii) List of recommended spare parts for 3 years trouble free operation and
maintenance alongwith unit rates as per the format enclosed in price schedule.
(viii) Technical Data sheets duly filled by the vendor (blank data sheets enclosed).
(xii) Reference list of your Customers for the similar supply of items.
(xv) Wagon Tippler - PLC interface details for communication with main plant PLC.
(i) Complete wagon tippler with side arm charger as per the details given in
the specifications except civil works.
(ii) Consumables like first fill of lubricating oils etc. for the initial operation of
the equipment till handing over.
(iii) Commissioning spares and start-up spare parts.
(iv) Special tools & tackles, if any required.
(v) Recommended spare parts for (3) three years trouble free operation and
maintenance.
(vi) Painting of complete equipment (including final painting before handing over
to the Employer).
(vii) Supervision of Installation, testing & commissioning at site.
(viii) All drawings / documents along with operation and maintenance manuals as
per requirement mentioned elsewhere in the tender document.
(ix) Getting approval of design/drawings and any other design calculation
related to the equipment from BSPI / MECON / EPI.
(x) Power supply at 415V+10%, 50Hz 5% and combined voltage & frequency
variation 10% shall be provided at vendors Main Panel / control desk and
equipment JBs only. However supply of MCC and control as required shall
be in vendors scope. .
(xi) Trailing / Flexible Cables as required for the complete system shall be in
vendors scope.
MECHANICAL
(A) GENERAL
(1) One no. Side Arm Charger to pull or push a rake of 59 loaded
wagons as per IS:10095 1982, Reaffirmed-2001. The Side
Arm Charger shall be complete with
- Trolley with wheels and side guide roller, universal coupling arm
along with hydraulic system for luffing.
- End stops, Festoon Cable & Trolley with heavy duty carriage and
supporting structures.
- Tippler Table with rails, end frame with necessary rack segments,
side beam with rubber pads.
- Control Cabin where from the Wagon tippler and Side Arm
Charger can be operated jointly or independently.
(4) Dust suppression system. Suitable House/ Canopy for centrifugal fan of
Wagon tippler tunnel shall be in bidders scope
(6) Supply of Side Arm Charger and Wagon Tippler shall be complete with
its structural, mechanical and electrical components and standard
accessories mentioned in the T.S.
(7) 25T wagon axle load and 110T gross weight of wagons (BOX / BOXN / BOXN
HA / BOXN HS / BOXN EL / BOYEL / BOBSN / BOBRN) to be considered for
design of wagon tippler and track hopper.
a) Application
The Side Arm Charger (SAC) shall be used for wagon positioning at the
wagon tippler for unloading of materials. It shall be used for
pushing / pulling a rake of 59 wagons as per IS:10095 1982, Reaffirmed-
2001 and locating wagons one by one on tippler.
b) Working
c) Specification
The supply includes Side Arm Charger with hydraulic power pack, power
supply system, supports, electrics, buffer stop, rack & pinion, control
cabin, automatic coupler/decoupler etc. The Side Arm Charger shall run on
its own track parallel to the main track. It shall have a stroke of
suitable length from a point on the inhaul side of tippler to a point on the
out haul side.
It shall be fitted with an arm pivoted at right angles and operated through
a hydraulic system for raising and lowering. The arm shall have an
automatic coupler to couple/decouple the wagons.
The charger shall run on four steel wheels mounted on spherical roller
bearings.
To resist the moment reaction of the pushing force, two pairs of steel
side guide rollers shall be fitted. They shall be fitted on spherical roller
bearings and shall have a simple lockable adjustment for true running
and to take up wear. The side guide rollers shall run on the sides of the
rail heads of the charger running track.
The charger shall have adequate power for pushing a train load of a full rake
of 59 wagons as per IS:10095 1982,Reaffirmed-2001. It shall be
hydraulically driven through rack and pinion arrangement.
The charger shall be electrically interlocked with tippler for proper sequential
d) Technical parameters
Quantity : One
a) Application
The wagon tippler shall be fed with loaded wagons one by one by a Side
Arm Charger. Tippled empty wagons shall be collected on the empty
side by ejection through side arm charger while placing loaded wagons on
the tippler. The wagon tippler shall unload the materials into receiving
hoppers for onward transportation to stock yard.
b) Specification
- The drive design shall incorporate controlled hydraulic drive and shall
be controlled from remote control post.
- The bearing shall be of antifriction type and equipped with dust seal.
Adequate platforms shall be provided around tippler for ease of
maintenance.
- The tippler shall be interlocked electrically with side arm charger and
succeeding equipment (feeders, conveyers etc.) with respect
to operational and safety requirements.
c) Technical Parameter
The execution of the work covered under this specification shall conform to the
latest Indian Standards specification where the same are available or the
reputed standards acceptable to the owner / consultant. In case such
specifications are not available, the work shall be according to good engineering
practice and norms acceptable to owner / consultant.
(1) Work zone dust concentration shall be less than 5 mg/Nm3 (at 5m to 7 m
distance from source) above ambient level .
(2) Water line velocity shall be maintained less than 1.5 m/sec. Water pipe line
shall be supported at regular interval. Make-up water, quick fill, drains and
overflow connection shall be included at pump station tank. Duplex strainer
shall be included at inlet to dust suppression system pumps. IS-1239 heavy
class, ERW, G.I pipe line ( for size up to 150 NB) shall be used in the water line.
The pipes above 150 NB shall be MS, spirally welded, 6 mm thick & conforming
to IS:3589. Water pipe line shall be preferably be laid over ground along
conveyor gallery. In case of non-availability of same suitable supporting
scheme shall be provided to suit site. Underground pipeline (wherever
provided) shall have wrapping and coating as per IS 10221 (preferably
wrapping coating shall be coal tar based). Hume pipe protection shall be laid at
road crossing area.
(3) IS-1239 heavy class, ERW, G.I pipe line shall be used in the compressed air
line. Compressed air pipeline network over ground laying shall be preferred
with a minimum slope of 10 mm in 1m (1: 100) along flow and moisture trap
with drain provision at regular interval. Compressed air pipeline shall be
preferably laid along conveyor gallery or can be supported from building
supporting structure. In case of non-availability of same suitable supporting
scheme to be developed by the Bidder to suit site.
(4) In wagon tippler , spray nozzles shall be arranged in three rows, at both side of
hopper and top of hopper to cover the entire hopper. Water spray in each group
of nozzles shall be through solenoid valve. The operation (open/ close) of
solenoid valves shall be linked with the wagon tippler rotation, i.e wagon tippler
position switches and timers rotation. There shall be two water pumps (one
working and one reserve).
(5) Compressed air station shall be provided for DFDS systems. Standby
compressor shall be provided.
(6) At each pump station air receiver capacity shall be considered @ 16% of the
compressed air consumption in m3/min or 2 m3 capacity, whichever is higher.
(7) Adjacent to pump station of wagon tippler dust suppression system, MS tank of
5 mm thick with stiffener for 1-hour storage capacity shall be provided by the
Bidder. The inside surface of MS tank shall be epoxy painted.
(8) The Bidder shall provide plat form, walkway, stair case adequate for the
necessary approach to the equipment for operation & maintenance point of
view.
(9) Duplex strainer with SS filter element shall be provided at inlet to dust
suppression system pumps to remove all suspended particles exceeding 100
micron
(10) Monorail with chain pulley block shall be provided for handling of equipment of
weight more than 300 Kg
The equipment for "DFDS" dust control system is grouped into two main
categories.
The main equipment shall include spray bar assemblies fitted with dual-fluid air
driven acoustic oscillator atomizing nozzles, pressure regulating units, and flow
activation stations for ON-OFF control of the system and instrumentation for
auto operation.
The spray bar assemblies shall be manufactured from stainless steel tubing
drilled and tapped for connection of nozzle adapters. A specially designed and
selected dual fluid atomizing nozzle shall be fitted into each of the adapters.
These nozzles are fitted with acoustic oscillators for atomizing the water into
droplets of micronic size by passing them through a field of high frequency
sound waves. The nozzles shall be of stainless steel while the adaptors shall be
of brass. Each spray bar shall be provided with mounting brackets and flexible
hoses for connection to the air & water pipeline.
The performance of "Dry Fog" type dust control system is critically related to
the size of water droplets. The nature and particle size of dust generated in the
material handling system changes with change in size and characteristic of the
material. In practice, the sizes of the dust particles have a very wide spectrum
(1-800 microns).
A careful control of air and water flow & pressure is therefore necessary to
obtain optimum dust suppression results. For this purpose, pressure regulating
units shall be provided in the system. The pressure regulating unit shall consist
of diaphragm type pressure regulator with pressure gauge and ball valve for
isolation of air and water line. The operator can adjust both the air and water
pressures independently to change the fog characteristics to obtain optimum
dust suppression results vis-a-vis the site requirements. The pressure
regulators shall be installed in a metallic enclosure with inspection door with
rubber sealing arrangement. Flexible hose shall be provided for connection of
PRU to the air & water pipeline.
The number of pressure regulating units shall depend upon the position /
elevation of spray bars. Generally independent pressure regulating units shall
be provided when the elevation of spray bars exceeds 3 m. Further the number
of nozzles operating from one PRU should not exceed 6 ~ 8.
The flow activation station shall consist of solenoid valves in air & water line,
pressure switch in the airline, selector switch, and indication lamps. Isolation
ball valves shall be provided in the air & water line. All the equipment shall be
installed in a metallic enclosure with inspection door with rubber sealing
arrangement. Flexible hoses shall be provided with each FAS for connection to
air and water pipeline.
The "ON - OFF" control of the fogging system shall be through the flow
activation stations with facility for both manual and auto mode. A three position
selector switch shall be provided to select the mode of operation. The switch
when energized shall open the electric solenoid valves, which shall permit
compressed air and water to enter into the pressure regulating units and spray
bars.
In addition, a pressure switch shall be installed in the airline to ensure that air
and water solenoid valves are energized only when sufficient air pressure is
available in the line. This shall ensure that the system cannot operate without
sufficient air pressure to the nozzles and reduces the chance of un-atomized
water to pour into the dust source. Flow activation shall have indication for: -
- System ON
- System OFF due to lower air pressure
The flow activation stations shall have provision for both manual and automatic
operation. For manual operation, the system shall become operational with
selector switch in manual mode and in auto mode, the fogging operation starts
on receiving a signal either from a speed switch cum belt load monitor or limit
switches installed at a strategic location in the material conveying line or
potential free Tender from the drive motor of equipment as per requirements.
Each dust suppression system location shall be provided with requisite number
of spray bar assemblies with DFDS atomizing nozzles. Pressure regulating units
shall be provided at each location to regulate the pressure of compressed air
and water.
The dust suppression system shall be divided into independent circuits taking
into account the flow diagram, operational requirements, distances between
dust suppression locations etc. Flow activation stations with instruments for
auto operation are provided for each circuit for ON/OFF control of the dust
suppression system.
Horizontal back pull out pump shall be provided. Pump casing shall be vertically
split type. Impeller rpm shall generally not exceed 1450. However, for pumps
with low capacity & high head may be provided with 2900 rpm. Pump shall be
coupled to motor with flexible coupling. Spacer type coupling shall be provided.
Pump shall conform to IS: 1520.
Pump shall give satisfactory performance at any point on the H-Q curve over a
range of 40% of rated flow to 120% of the rated flow. The maximum efficiency
shall preferably be within 10% of the rated design flow. The total head -
capacity curve shall be continuous rising towards the shut off without any zone
of instability and with a minimum shut-off head of 15% more than the design
head.
Pumps shall have shaft seal by gland packing. Pump shall be fitted with double
wearing rings , one is fitted in the front of the impeller on the casing and the
other is fitted in the back of the impeller on the impeller itself.
Common base plate for pump & motor shall be in one piece & made of welded
steel construction. Adequate space shall be provided between pump drain
connection and base plate for installation of minimum 15 mm drain piping.
Pumps shall be supplied with suitable drain pans or drain rim type base plates
with tapped drain connections.
Critical speed of the shaft shall be at least 30 percent above the operating
speed.
Water piping up to 150 mm NB size shall be GI, ERW, heavy class and
conforming to IS-1239 Part- 1 . The pipes above 150 NB shall be MS, spirally
welded , 6 mm thick and conforming to IS:3589. Pipe ends shall be beveled.
Pipe fittings shall be as per IS 1239, Part -2 for pipes of size up to 150 NB.
Fabricated fittings manufactured from the pipes may be provided for pipes of
sizes 200 NB & above.
Pipes shall be of welded joints. Welding (manual metal arc welding) shall be as
per relevant IS code and only certified welders shall be employed.
All piping systems shall be hydro tested at 1.5 times the design pressure.
Auto air venting valves shall be provided at highest point of the pipe lines &
drain valves shall be provided at lowest points of the pipelines in different
segments.
Pipe supports comprising pipe shoes, saddles, base plate, clamps & structural
members like channels, angles etc. shall be provided
(7) Valves
Butterfly Valves shall be provided in water line of size 65 NB and above and ball
valve shall be provided for pipe size below 65 NB. However, ball valve shall be
provided in the pipe line (irrespective of sizes) when flow control is required.
The valves shall be provided with integrally moulded & bonded body liner to
provide perfect seating and complete isolation of body material from fluid. The
body liner shall provide the seating to valve disc, primary seal to the stem &
gasket joint with mating pipe flanges. Valves shall be provided with self locking
lever operation from open to fully closed position with intermediate positions
marked on the indicator plate mounted on the top flange. The valves shall
conform to BS : 5155 / IS : 13095. Extended valve shaft shall be provided so
that the lever can be operated without any obstruction on the insulated pipes.
Gear operated valves shall be provided for sizes more than 250 NB.
Vertical self supporting in cylindrical design with dished end at both ends
having minimum capacity of 2 m3 volume. The air receiver shall be designed
for a working pressure of 8 kg/cm2 g. Design, manufacture, inspection and
testing of air receiver shall be in accordance with IS:7938 and IS : 2825 -1969
(RA 1984), Class-2, Dished ends IS:4049 Part-I, 1979 (RA 1991). Material of
construction shall be as follows:
5.0 HYDRAULICS
Hydraulic power pack shall be installed in room where adequate provisions are
made to keep ambient air free from dust, moisture and ambient temperature
shall be kept below 350C.
Adequate illumination.
Adequate fire alarms, fire protection system and fire fighting facilities.
Design of floor shall be such that spilled oil / leakage oil, if any is collected into
drain pit and from there, arrangement shall be provided for collection and
disposal of leakage oil into oil barrels for reclamation purpose.
(B) Whatever Servo / Proportional Valves are used in the system, supplier shall
supply Servo Valve flushing facility and test kits for Servo and Proportional
Valves.
(C) For hydraulic systems with conventional valves, the supply voltage to various
controls shall be 24 DC.
(E) Mineral oil shall be used in hydraulic systems until otherwise agreed upon by
BSP.
(F) All the pipes and fittings used in hydraulic systems of critical production units
shall be stainless steel until otherwise agreed up on by BSP.
(G) Filters shall be provided for continuous removal of contaminants from the
hydraulic fluid, which are likely to cause malfunction of pumps, valves and
actuators and maintain desired cleanliness level of hydraulic fluid. Adequate
filtration shall be provided for each system considering the ingress rate of
contaminants in each applications.
(H) All the pressure line, return line and circulation filters shall be of absolute
filtration design with B (x) ratio greater than or equal to 200. Total delta p across
filters shall not exceed 0.5 bar with filter element in clean condition. (Total p
means pressure drop across clean filter element plus pressure drop filter
housing).
(I) All the hydraulic system shall be provided with dedicated oil purifier. The oil
purifier (vacuum dehydrator type) shall be capable to remove undissolved as
well as dissolved water and solid containments from the hydraulic oil of the
system in a reasonable time to the desired level.
(J) Portable oil transfer unit with built in filtration facility shall be provided for
transfer ol from barrels to oil reservoir of the system.
(K) Calibration and Testing Facilities for the Hydraulic Components installed in the
hydraulic systems shall be provided as detailed below.
1. Power pack for Test Rigs of conventional control values, pumps, motors and
hydraulic cylinders.
5. Test rig and Power pack for Servo and Proportional valves (if Servo /
Proportional valves are used / installed in the hydraulic systems).
The scope of supply shall also include all components and accessories as required
to tender the system complete in all respect.
All the above equipments / components handling facility shall be provided.
Adequate facility shall also be provided for storage of components (both un -
repaired and repaired / tested components.
The Test Rigs shall have facilities for on-line acquisition of test parameters of the
components while testing and shall be transferred to the main computer for
records and references.
(L) Plate Type Heat Exchanges of adequate capacity shall be provided in the
Hydraulic Systems.
(M) The hydraulic system shall have facility for on-line Pressure measurement in P,
T, A and B lines at suitable locations of the circuit. Necessary instruments,
conditions monitoring system and facilities shall be provided by the supplier.
Hydraulic pipe work shall be assembled, pressure tested, pickled, flushed and
commissioned as per piping instructions given by the system designer /
consultant.
Provision of pipe line pickling and flushing facility shall be in the scope of work
(provision of separate tank, pumps filters elements, pickling and flushing fluids
shall be the suppliers scope).
Supply of minimum 50 nos. of spare filter elements of each type along with the
hydraulic system at the time of Erection, Testing and Commissioning shall be in
the suppliers scope of supply.
Oil cleanliness shall be checked during commissioning and facilities for checking
and monitoring oil cleanliness shall be in the bidders scope of supply.
6) Connection program after cleaning and flushing is over with built-in check for
prevention of contaminants during connections and assembling.
(P) All pipelines shall be of seamless type clamped with polypropylene heavy series
clamps. However, in the hot zone heavy series aluminum clamps shall be used.
(Q) All hydraulic pipe lines shall be painted as per the standard color mode.
2) Pumps speed shall be 1500 rpm. Electrical motor pump shall have
25% reserve power over and above required for operating the
pump at working pressure and flow.
3) The number of standby pumps shall be as follows:
ELECTRICAL
&
INSTRUMENTATION
(A) General
The Bidder shall refer to General Technical Specification (GTS) for Electrics
and Illumination for detailed specification of equipment / components. This
Technical Specification (TS), General technical Specification (GTS) including
Preferred Makes for Equipment and other attached documents considered, as
a whole shall comprise the complete Tender Specification. These are
complementary and anything laid down in one and not in other will be
deemed as binding, as though laid down in the Tender specification as a
whole. In case of conflict between the Technical specification and GTS, the
Technical specification (TS) shall prevail.
(1) Complete electrics for Wagon tippler and Side Arm charger (SAC).
(1) General
- AC drives shall have communication facility with PLCs for data transfer
and speed reference set point.
- The system shall be complete with CPU, I/O racks, memory, key board
and monitor. HMI shall depict graphics of various mechanism operations
and also provide alarm annunciation system. Spare CPU with loaded
software shall be installed in the PLC panel.
- Control desk shall have suitable nos. of status indication lamps to cover
complete dust suppression system, SAC positions & movements
including arm positions etc. and also for down stream equipment of
wagon tippler.
- A control desk shall be provided also on the side Arm Charger.
- Remaining features shall conform to General Technical Specification.
Indicating cum data logging type weighbridge for weighing both loaded
and empty wagon shall be complete with PC based operating station in
the wagon Tippler Control Room.
All drives and mechanisms shall have Auto, Remote interlocked mode
and Local mode controls. Local controls shall be provided and normally it
will be used for maintenance and testing purpose only. Only safety
interlocks shall be covered in Local control. STOP push button of Local
control shall be able to stop the drive/mechanism selected for any mode
of control.
It shall be possible to operate the side arm charger (SAC) both from
control panel located in the Operator cabin of SAC and Control desk
located in the control room. Auto operation of SAC along with wagon
tippler operation shall be done from Control desk. SAC operation from its
control box in the SAC operator cabin will be done as required after the
receipt of instructions / permissive from control desk operator.
The loaded wagon to be tippled will be decoupled manually from the rest
of the rake and the person doing the decoupling operation will press a
switch installed near-by to indicate to control room that decoupling
operation is complete. Subsequently, pulling of the wagon by SAC,
placing it on wagon tippler, return of SAC to wagon rake for start of next
cycle, tippling of wagon by wagon tippler etc. shall start automatically in
proper sequence.
The SAC will pull and place the decoupled wagon over the tippler. Once
the wagon is placed on tippler deck and SAC clears the tippler deck,
tippler will clamp the wagon, tipple it, return to its original position,
declamp the wagon and other operations as required. The wagon
vibrator will operate automatically, if selected for auto-mode when the
wagon is in inverted position. The type of wagon being unloaded,
identification of sick wagons etc. will be registered in Control desk by the
control room operator.
The water spraying for dust suppression will start automatically when
wagon is being tippled and will stop when the tippler is not operating by
establishing suitable interlocking between controls of wagon tippler and
dedusting system.
Each operational cycle will be repeated automatically till the last wagon
is tippled and removed from the tippler deck. The complete operation
will be done in automatic sequentially interlocked manner and some of
the activities will be parallel so that system can easily achieve a required
tippling rate per hour.
Positioning of Wagon Tippler and SAC will be through proximity switches
and backed-up by heavy duty rotary limit switches. All limit switches and
proximity switches must work smoothly and without adjustment and
mal-functions under severe conditions of vibrations. All rotary switch
and limit switches should be mounted and housed with suitable vibration
damping arrangement.
Bidders scope of work for all design drawings and documents shall be as
given below.
The bidder shall submit a list of all drawings and documents he proposes
to submit within 2 weeks of LOI. The list will be approved by Client /
MECON and may be modified if necessary. Each drawing/documents in
the list shall be identified with a serial number, description and
scheduled date of submission.
Bidder shall also furnish soft copies of all the drawings indicated below
and drawings of technological layout/units.
The bidder shall check all the drawings prepared by them and/or
received from their vendors/supplier/sub-supplier and satisfy
themselves about the correctness of drawings before issuing to
Purchaser/Consultant. After checking, properly stamped drawings shall
be sent to Purchaser/Consultant for approval / clearance.
1. System configuration diagram for the Automation system along with its
peripherals. Configuration should indicate nos. of Processors &
interfacing details with plant PLC.
2. Bill of quantities of all hardware & peripherals viz; CPU, I/O units,
communication & power supply modules, operator/engineering stations,
bus cables & erection accessories etc. offered for the automation system
with brief specification.
3. Detailed technical catalogues & a write-up explaining the system offered
shall also be submitted along with details of various software being
considered.
4. Total power requirement & heat load for automation system.
5. List of commissioning spares with details.
6. List of two years operation & maintenance spares with details & unit rates.
(v) Protection for Motor & IP -55 (with canopy for motor if installed
Bearing outdoor)
(vi) Shaft ends & Extension Cylindrical as per requirement Proper
drilling and tapping shall be provided for
mounting of tachos for speed feedback (if
required ) Crane motor in 225 and above
frame sizes shall have tapered shaft (1:10)
( New point)
(vii) Bearings -For motor of rating upto 5 kW, ball
bearings shall be used for both DE & NDE
end. -For ratings above 5 kW the DE end
shall be provided with roller bearing and
NDE end shall be provided with ball
bearing. -Bearings for motors shall be of C3
clearance . -Bearings shall be suitable for
running of motor in either direction.
(v) Protection for Motor & IP55 degree of protection as per IS : 4691.
Bearing
(vi) Shaft ends & Extension -Shall be of high grade steel . -Cylindrical
as per requirement -Proper drilling and
tapping shall be provided for mounting of
tachos for speed feedback (if required ) in
non drive end or shaft shall be extended
with different diameter and length .
Tapered shafts for all crane drive motors
shall be provided. Motors in 225 and above
frame size shall have tapered shaft (1:10) .
-Provision of double identical shaft
extension (cylindrical & taper) to be made
(in case of requirement for a particular
application) .
xiv) RTD & BTD ( PT100 type) All motors shall be provided with Bearing
(DE & NDE) temperature detectors and 6
nos. stator winding temperature detectors,
RTDs for monitoring alarm and trip
conditions. RTD's shall be of PT100 type
(duplex). Analog input cards shall be
provided in PLC for online monitoring of
bearing (DE & NDE) and winding
temperature of HT motors above 1000 KW .
For HT motors, temperature of each RTD
(for winding / bearing) shall be wired to
PLC system and limit value contacts for
alarm and tripping shall be generated in the
PLC along with the display of all parameters
of the motor including the winding and
bearing temperature.
xv) Vibration monitoring Vibration monitoring (online) shall be
provided at the DE end of motor bearing for
motors of ratings 1000 kW and above and
it should be connected to PLC for online
monitoring .
xvi) Paint shade Light grey , shade no. 631 as per IS 5
3.0 Terminal box
i) Protection IP -55
ii) Type Phase segregated
iii) Location As per requirement 1 no. each on opposite
sides of motor.
iv) Winding star point Winding star point shall be kept outside
in the motor for more than 200 KW HT
motor and other important HT motor . In
case no differential protection is required,
star point of the winding may be formed
inside the neutral terminal box to be
provided on one side of the motor. The
phase segregated terminal box shall be
placed on other side of the motor.
v) Suitability Termination of XLPE cables with heat
shrinkable cable end seals. Each terminal
box to have two inlets to accommodate any
parallel cables as required.
Constructional
2.0
Features
i). Frame size & rating As per IS 325
ii) Stator Frame Fabricated Steel / High grade cast Iron
Laminated sheets of high grade low loss
iii) Stator Core
silicon steel
3.0 Type of connection -Three full wave diode rectifiers supplied by phase
shifted, three phase AC to provide a fixed DC
voltage. -DC bus inductor on all ratings -DC link
capacitors -Insulated Gate Bipolar Transistor
(IGBT) power section, shall be rated for variable /
constant torque applications. The power section
shall use vector dispersal pulsewidth modulated
(PWM) IGBT gate control algorithm and soft
switching IGBTs to reduce motor terminal dv/dt
and allow longer cable length from drive to motor
without output filters. -The Main Control Board
shall be the same for all ratings to optimize spare
parts stocking and exchange -Common control
connection for all ratings.
4.0 Overload capacity -110% of the rated current for 1 minute , 30
seconds at 150% (with inverse characteristics
proportional to time) for variable torque
applications . Repetition interval shall not be less
than 9 minutes -150% of the rated current for 1
minute overload , 30 seconds at 200% (with
inverse characteristics proportional to time) and
200% of rated current for 0.5 sec. for constant
torque applications . Repetition interval shall not
be less than 60 minutes .
5.0 Efficiency More than 97% or better at full speed and full
load.
6.0 Input power supply -415 V AC +10% & -15% -3 phase . -50 Hz + / -6
% -4 wire neutral earthed system .
7.0 Voltage variation -Voltage variation of (+/-) 0.1 % with an input
variation of +10% -15%. -Steady state regulation
of (+/-) 0.25% guaranteed against 100 to 200 %
load disturbance and + 6% & -6% input supply
frequency variation. -The drive should be
designed to operate on an AC supply, which may
contain line notching, and up to 10% harmonic
distortion.
8.0 Environmental conditions
8.1 Storage ambient Upto to 70C (-40to 158F).
temperature range
8.2 Operating ambient IP42 & above : 0C to 50C (0to 122F)
temperature range
without derating.
8.3 Relative humidity Upto 100% non-condensing.
8.4 Operating elevation Up to 1000 Meters (3,300ft) without derating.
8.5 Shock 15G peak for 11ms duration
voltage
9.2 Reference signals The drive should be capable of the following
speed reference signals Digital MOP Jog HIM
(Program/Control panel) Analog Input signals
Preset Speeds Communication module
commands All reference signals may have a trim
signal applied to them for finer resolution and
accuracy. Trim source and amount should be
programmable.
9.3 Loss of reference The drive should be capable of sensing the
reference loss conditions . In the event of loss of
an analog input reference signal, the drive should
be user programmable to the following Fault the
drive Alarm and maintain last reference Alarm
and go to preset speed Alarm and go to
minimum speed Alarm and go to maximum
speed Alarm and maintain last output frequency
Signal loss detection should be available
regardless of the function of the analog input.
10.0 Output
10.1 Output voltage From 0 to rated motor voltage .
10.2 Output frequency 0.5 -400 Hz.
10.3 Output Waveform Sinusoidal
10.4 Output frequency 0.01 Hz.
resolution
11.0 Reflected wave Maximum of 3.15 times the bus voltage or 1600V,
whichever is less, up to cable lengths of 200
metres.
12.0 Starting torque 150 % / 0.3 Hz. (without PG) 150 % / 0 RPM
(with PG)
13.0 Torque accuracy + / -5 % .
14.0 Speed control + / -0.02 % . IR compensation to be provided for
accuracy drive without PG .
15.0 Ramp rate -Linear acceleration and deceleration adjustable
independently from 0 to 3600 seconds . -Provision
of remotely selectable Accel / Decel settings
should be accessible through digital inputs also.
16.0 Main power -ACB / MCCB with 50 KA rating -Matching input
components in isolation transformer / line reactor for harmonic
incoming AC side and noise suppression . For input isolation
transformer , the K factor shall be 4.0 or less. -AC
line surge suppression network . -Input contactor
.
17.0 Converter -Diode / Thyristor bridge for AC/DC. -DC link
Inverter Equipment circuit with reactor/capacitor -IGBT bridge for
Inverter for DC/AC. -Harmonic transformer . -
Main PLC to take care of interlocking and
sequencing etc. -Mimic panel (where drive is HT)
33.0 Auto / Manual -The HIM should utilize the ALT function key to
Mode transfer the drive from Automatic mode to Manual
mode and back. -When in Auto mode, the drive to
receive its frequency command from the
programmed source. -When in Manual mode,
control of the frequency command to be
transferred to the HIM speed control keys (or
potentiometer). -The user should have the choice
of preloading the HIM with the current auto
frequency reference before transferring control to
allow for smooth transitions without speed
jumps.
34.0 Communication RS485 (ModBus, ProfiBus-DP, DeviceNet) bus
Bus Internally mounted interfaces shall be provided to
connect to different buses .
35.0 Test points Two electronic test point parameters should be
available to examine data within the drive
memory that is not available through other
parameters.
36.0 Operator panel Shall be mounted on the front door of the unit . IP
66 protection class . -All adjustments to be made
with the door closed. -Status and Power LEDs
viewable through the cover -Status LEDs for
communications status, including embedded DPI
status, adapter health and communications
network status, viewable through the cover .
37.0 Membrane keypad -The keypad shall be logically designed for two
operating areas with required number of keys. -
Local operator control like -local start /stop , -jog
forward / reverse . -Programming . Facility to run
the drive without HIM shall be provided .
A. General :
1.0 Type -Metal clad . -Non drawout type.
7.0 Miscellaneous -Neosprene rubber gasket shall be provided for all the
doors , removable covers & between adjacent covers . -
Lifting hooks for the panel . -Doors shall have concealed
hinges .
8.0 Labelling Clear legible identification labels (anodized aluminium
with white letters engraved on black background ) with
letter sizes of :-25-50 mm for panel . -5 mm for
components and module name plates. -Danger board on
front and rear sides in English , Hindi and local language
9.0 Earthing -Two separate earthing terminals will be provided. -
Bolted joints with tooth spring washers for good earth
continuity.
10.0 Paint shade Shade No. 631 as per IS-5:1992 equv to RAL 7035 .
11.0 Panel space heater In each panel with thermostat , MCB .
C. Busbars
1.0 Arrangement Three phase & neutral.
2.0 Material High conductivity electrolytic aluminium alloy confirming
to grade E91E as per IS-5082 1981.
3.0 Phase Busbar -Shall be able to carry continuously the connected load
Rating (considering all derating factors) plus a 25% margin . -
Max. current density shall be -1.0 A/sq.mm for
Aluminium -1.5 A/sq.mm for Copper.
Neutral Busbar
4.0 50 % of phase busbar rating
Rating
5.0 Short circuit rating 50 KA for 1 sec.
I. Control Supply
1.0 Control 1 nos. of 415V/240V control transformer of minimum
transformer 2.5 KVA Secondary unearthed.
2.0 Input and output Input side :MCB Output side :MCB
side isolation Output side :MCB Output side :MCB
device
10.0 SPARES
(B) Consumables
The Bidder shall supply all consumables such as initial fill of lubricants,
oils, grease, chemicals, refractories, resins etc. as required to complete
the plant till commissioning and shall have a shelf life of minimum one
year. The scope of consumables shall include electrodes, shims,
packings, bolts, nuts, gaskets, rivets, washers etc. The Bidder shall
fulfill the requirement given in SBD.
(1) The Bidder shall ensure the interchangeability of the parts wherever
possible. The Bidder shall furnish an itemized list of interchangeable
spares as given in SBD.
(3) Spares list giving complete list of the replaceable parts, fully illustrated,
shall be supplied. The list shall include the following information.
Item designation
Reference drawings
Quantity installed
Quantity recommended for two years normal operation including the
insurance spares
Weight of each spare part
Supplier or sub-suppliers catalogue number
Recommended minimum stock
Expected replacement time
Installation instruction in detail shall be supplied both for original
installation and future, for replacement of major electrical
equipment, circuit wiring diagram shall be provided.
(1) The Bidder shall supply a complete and unused wet of all the special
tools and tackles including required number of tool boxes as required for
erection, maintenance, overhaul or complete replacement of the
equipment and components required for the plant. The Bidder shall
submit a list of such special erection and maintenance tools and tackles.
(2) All the tools shall be supplied in separate containers clearly marked with
the name of the equipment for which they are intended.
(4) For any fabrication / control assembly (necessary for erection) work to
be done in the plant premises the plan shall be indicated by the Bidder.
The necessary equipment such as plate bending machines, special
purpose welding machines, fixtures, tools & tackles and other equipment
required for fabrication shall be arranged by the successful Bidder.
(5) The successful Bidder shall carry out the testing of welded joints by
radiographic and ultrasonic methods. They must have only qualified /
certified welders with them for completing all the welding jobs.
(7) All tools and tackles, apparatus, special instruments required for
erection, testing, commissioning and establishment of the Performance
Guarantee Test, measurements required for establishing the pollution
control norms and such other instruments, as required, shall be
arranged by the successful Bidder. After commissioning, the successful
Bidder shall handover all the special tools & tackles to the Purchaser as
per the requirement given in SBD.
(8) The successful Bidder shall supply all required consumables, initial fill,
oil, lubricants, construction and erection materials including but not
limited to shims, packing plates, joining compounds, kerosene, solvents,
sealing compounds, tapes, connectors, brazing and soldering materials,
welding and brazing gases and rods, electrodes and wires, erection
bolts, nuts, rivets, piano wire, packing sheet and packing compounds,
temporary supports, spacer templates, jute and cotton waste cloth, sand
and emery paper etc. for the commissioning of the plant.
(9) For load testing of handling equipment, loads shall have to be arranged
by the successful Bidder. Electrical/ operation tests, as per standard
practice, shall also be arranged and completed by them.
(10) All materials, equipment, tools, tackles etc. brought at site by the
successful Bidder within the plant area shall not be removed without the
written permission of the Purchaser. Similarly, all enabling works
built/erected and/or acquired by them within the plant premises shall
not be dismantled and removed without the written permission of the
Purchaser.
(E) General tools and tackles A list of general tool and tackles to be supplied
shall be indicated as per the format given in schedule at Chapter 12.
DATA SHEETS
The Bidder shall also fill up the following questionnaire and submit with his
offer. This data shall form a part of the contract with Successful Bidder.
g) Rail gauge :
h) Load capacity :
i) No. of tipplings/hour :
k) Angle of rotation. :
r) Mode of control :
w) Track gauge :
Pump :
(a) Make :
(b) Type of pumps :
(c) Capacity, m3/h :
(d) Total head, mWC :
(e) Material of Construction
(i) Shaft :
(ii) Impeller :
(iii) Casing :
(f) NPSH required, m :
(g) Speed, rpm :
(h) Impeller dia, mm :
(i) Shaft power :
(j) Efficiency :
(k) Drive detail :
(l) Bearing type & make :
(m) Noise level at 1 m distance :
Nozzle :
(a) Make :
(b) Dia :
(c) Water spraying cap.& Pr. r equired :
(d) Material of construction :
(e) Weight :
Valve :
(a) Make & type :
(b) Material of Construction :
(c) Weight :
(d) Dia :
Pipe :
(a) Make :
(b) Material :
(c) Dia :
(d) Thickness :
(e) Weight, kg/m :
MOTOR
1 Project :
2 Make :
3 Driven Equipment :
4 Motor Tag No. :
5 Quantity :
6 Voltage With Variation :
7 No. of Phases/Connection/ : No of Terminals
8 Frequency With Variation :
9 Fault Level (Mva) & Duration :
10 Motor Type And Duty :
11. KW RATING/POLE :
At 40 Deg.C. :
At Specified Ambient Temp.:
With Derating.
BHP/BKW of Driven Eqpt. : At Rated Load
12 Frame Size/Mounting :
13 Insulation Class With Temp Rise:
14 Enclosure Type :
15 Full Load Speed :
16 Full Load Torque (FLT) :
17 Starting Torque as % of FLT :
18 Pullout Torque as % of FLT :
19 FULL LOAD CURRENT (FLC) :
20 Starting Current as % of FLC :
21. Starting Time on Rated Load At :
Rated Voltage :
85 % of Rated Voltage :
22. Locked Rotor Withstand Time
Cold :
Hot :
23 Rotation Viewed From Driving End
24 Gd Square of Motor :
25 GD Square Of Driven Equipment:
26 Weight Of Motor :
27. Power Factor at
(i) 50%Load :
(ii) 75%Load :
(iii) 100%Load :
28. Efficiency at
(iv)50%Load :
(v) 75%Load :
(iii)100%Load :
29 Space Heater Watts/Volts :
30 Terminal Box Type & :
No. of Terminals
31 No. of Starts Per Hour :
32 Noise Level at a Distance of 1m : From The Motor
33 Thermal Withstand Time :
34 Cooling :
35 Applicable Standard :
36 Location :
37 Hazardous Area Classification :
38. Bearing Details
(i) Type of DE/NDE :
(ii) Size of DE/NDE :
(iii) Make :
39 Location of Terminal Box :
Position From DE Side
40 Lubrication Type :
41 Cable Size :
42 Paint Shade :
43 G.A., Dimensions & Mounting : YES/NO
Detail Drawings Enclosed
44 Details Drawings FoR T.B. : YES/NO
45 Performance Characteristics : YES/NO
Curves Viz. Speed V/S Current & Speed V/S Torque Enclosed