A Guide to Construction Contracts
Contents
04 Introduction
05 What is a contract?
05 Construction contracts
22 Key concepts
26 Applicable legislation
27 Useful links
3
BOWMANS
Introduction
429 000
individuals
The industry continues to grow.
This handbook provides some basic
knowledge and understanding regarding
contracting in this industry.
4
A Guide to Construction Contracts
What is a Construction
contract? contracts
5
BOWMANS
Contractor Commissioned to
construct the works
6
A Guide to Construction Contracts
Employers usually elect to work through Handover in good time all notices,
a representative who may be an architect, advices, time delay claims, bad weather
an engineer, a project manager, a quantity reports, certificates for payment,
surveyor or any other qualified third party. invoices, lists of workers, plant
The employer gives his or her representative on-site, etc.
the authority to act on his or her behalf
in the execution of certain provisions of Make sure claims are submitted in
the contract. strict compliance with the applicable
contractual provisions, in writing within
The representatives role is to oversee and the period stated in the contract. If a
administer the contract and the project itself. claim cannot be prepared within the
It is important to develop a good working required period, extensions should
relationship with the employer and/ or his or be sought prior to the expiry of the
her representative, as the contractor always period. If no extension is granted or
benefits from trust and co-operation arising communicated prior to the expiry of
from this relationship. the time periods, the claim (even if
not fully complete) and all documents
Importantly, the employers representative available at that time should be
is usually the person to whom all notices, submitted (explaining if possible why
invoices and claims must be submitted and is the claim cannot be completed and
the person who determines the amounts due submitted on time), with any further
to the contractor. documents and information required
to be provided thereafter.
There are some important steps a contractor
can take to develop this relationship such as: Only make reasonable claims for
additional payment. Inflated or
Report all problems to the employer, frivolous claims will be rejected.
through the appointed representative,
as quickly as possible. This is very Carry out all written instructions. If the
important if the problems could cause instructions are difficult or impossible
cost increases or delay completion.
7
BOWMANS
Different forms
of contracts
to execute, talk to the representative The type of contract form to be used will
who issued the instructions as soon as depend on the employers preference as
possible to see if it can be done in a well as the works to be executed. Two
different way do not delay. common ways in which parties can contract
are either through a bespoke contract or
a standard form contract.
8
A Guide to Construction Contracts
9
BOWMANS
10
A Guide to Construction Contracts
Different ways
of contracting
There are different ways in which a the main contractor, these rights and
prospective contractor can participate in a responsibilities will be exercised by
construction contract. Some examples are and between the subcontractor and
listed below: the main contractor.
Main contractor The contractor himself The subcontractor does not have a
or herself concludes a contract with an contract with the employer, and in most
employer to build/ construct something. instances does not have a relationship
(eg building a school). with them. In some instances, however, the
employer can take up this responsibility.
Joint venture partner The contractor
forms an agreement with one or more When an employer wants to use a
other contractors on an equal footing. subcontractor of their choice, the
They then jointly sign a contract to subcontractor is referred to as a
build/ construct all or a part of the nominated subcontractor and in
project. It is important to note that in certain instances, the employer will
this case, each contractor in the joint take up risk due to its nomination.
venture is responsible to the employer
for all obligations under the contract.
In other words, as between the employer
and the members of the joint venture,
each member of the joint venture is
responsible for the actions or breach
of any other member.
11
BOWMANS
Construction contract
arrangements
12
A Guide to Construction Contracts
Construction Industry
Development Board
13
BOWMANS
Deciding on which
contract to use
The idea of standard form contracts is to Main contractor and subcontractor (rights,
include provisions that are beneficial to both responsibilities and risks)
parties to the contract in accordance with
good practice. Some contracts are, however, Usually in construction contracts the main
not based on the approach of good practice. contractor will be responsible for the entire
project. He or she will take responsibility
It is therefore important to be familiar for the safety of his or her employees and,
with the three Rs when deciding which most of the time, the subcontractors.
contract to use: A summary of the more common rights,
responsibilities and risks follows:
ights these are entitlements that one
1. R
party has against another, entitling the 1. RIGHTS
party who has the right to compel the
other party to do or not to do something. Timeous payments the main
contractor is entitled to be paid within
2. Responsibilities these are obligations the time stated in the contract, failing
to do, or not to do something, for the which he or she should usually be able
party who has the right. to claim interest on late payment.
14
A Guide to Construction Contracts
15
BOWMANS
unless otherwise stated in the contract Delays the main contractor should
agreement, the contractor must also ensure that materials are delivered
substantiate such a claim in order on time, licences obtained and that
to ensure swift settlement of such his or her employees perform the
a payment. works timeously. Failure to do so will
lead to a situation where delays occur
Subcontracts main contractors should and depending on the wording of the
ensure that written agreements are contract the main contractor might be
entered into between themselves and subject to delay damages.
the subcontractors. This is to ensure
that they are able to properly hold Penalties the main contractor should
such subcontractors liable should be aware of the fact that depending
any issue arise. on the wording of the contract, he or
she might be liable for penalties should
3. RISKS he or she fail to meet certain set dates
or fail to meet certain performance
Financial loss: guarantees. It is important to note
though, that if a penalty applies, the
Errors in calculations the main employer does not have to prove that
contractor should ensure that his or her loss stemming from the
measurements regarding the works price breach is equal to the penalty, but may
are done completely and accurately. not claim further amounts from the
The contractor must also include a contractor in respect of the breach
contingency amount within the price to which the penalty applies. In other
for loss that could be suffered for risks words the contractors liability to pay
for which no additional compensation is damages for the breach is limited to the
allowed under the contract. amount of the penalty.
16
A Guide to Construction Contracts
17
BOWMANS
Common construction
contract terms/
procedures
Main contractors must ensure that Not all contracts will follow the terms/
communication with subcontractors procedures listed below this is intended
remains at an optimum level, and to provide an overview of possible and
if there are various subcontractors, common contract terms/ procedures.
ensure that they have access to
the site at the time which they CONTRACT PROCEDURES
are promised access.
The contractor must check if Tendering and contract award
standard form contract conditions
have been changed by the employer The tender is advertised by the
and how this will affect him or her. employer or his or her representative;
Always stick to the timelines Contractors submit their tenders by
allowed within the contract. the required date;
The tenders are evaluated, and a
Ensure there is a contract in place tender evaluation report is produced
between the subcontractor and the recommending the preferred
main contractor. As a subcontractor tender bid;
one should look out for the following The employer reviews the tender
conditions, which should be avoided evaluation report and awards
or negotiated against: the contract;
The contract is negotiated and
Reduction of and/ or set-off from eventually signed by both the
amounts certified for payment contractor and the employer;
to the subcontractor to cover The contractor is responsible for the
amounts allegedly owed to the provision of insurance and the surety/
main contractor; guarantee as stipulated in the contract;
Settling disputes only through The site is officially handed over to
the courts with no provision for the contractor;
adjudication or mediation; The contractor establishes his or her
The subcontractor only gets camp and site office and orders the
paid once the main contractor has materials required to start construction;
been paid by the employer; and The contractor sets out the work and
Unreasonable retention percentages starts construction.
and periods.nancial Loss:
18
A Guide to Construction Contracts
Monthly activities during the contract The employer (or his or her agent)
carries out a final inspection. If he or
Daily, weekly or monthly site meetings she (or his or her agent) is satisfied that
between the employer and the the works/ project is now substantially
contractor and inspection of the work complete, he or she or his or her agent
by the employers representative to will certify/ confirm that the works/
ensure quality; project is ready to be handed over;
Preparation of monthly payment The contractor hands the works/
certificates by the contractor; project over to the employer (that is,
Review and certification of the payment the employer takes possession of the
certificate. Queries are referred to works/ project).
the contractor;
The certified payment certificate is Final account
submitted for payment by the employer;
Payment is made to the contractor The contractor or the employer
within the period specified in (as required in terms of the contract)
the contract. prepares the final account during the
handover period and submits it to
Handover procedure the employer;
The final account is certified and issued
The contractor requests the employer to the employer once the employer
to inspect the completed project prior has issued a (practical/ taking-over)
to handover; completion certificate;
The employer inspects the project, The employer pays the final account less
identifies outstanding items to be the retention money;
completed by the contractor prior to This retention money is released to the
the handover of the project and issues contractor at the end of the defects
a snag list to the contractor listing liability period.
the outstanding items;
The contractor completes the Defects liability period and final completion
outstanding items and notifies the
employer that the project is complete The contractor is responsible for making
and ready for a final inspection; good items which show defects during
the defects liability period;
19
BOWMANS
Near the end of the defects liability on which he or she became or ought to
period, the contractor requests the have become aware of the latent defect.
employer to inspect the project and
identify any defective items which the Disputes and how to resolve them
contractor is responsible for making
good in terms of the contract; Most standard form contracts will cater
The money held in retention by the for a dispute resolution mechanism
employer will only be paid when the which will state the procedure to be
contractor has properly completed followed when a dispute arises. If a
the list of defects; bespoke contract is used, it is best
Once the employer has issued a copy to have a clause that prescribes a
of the final completion certificate, he dispute resolution mechanism as such
or she is required to pay the retention mechanisms can lead to disputes being
money due to the contractor. settled timeously and amicably.
20
A Guide to Construction Contracts
Dispute Court
If either party is not satisfied with the If no provision is made for arbitration
determination made, they can declare in the contract, and the parties
a dispute or notify their dissatisfaction do not agree to this or any other
and, depending on the provisions of mechanism to resolve the dispute,
the contract, either: try to mediate the the normal South African court
dispute; approach a DAB/ arbitration; system may be followed to settle
approach the court or follow any other the dispute.
mechanism set out by the contract.
Contractors should ensure that after the
DAB/ Arbitration award of a tender the agreement tendered
In employing this mechanism parties for is the agreement that they sign.
will usually negotiate and conclude an
arbitration/ adjudication agreement Contractors should note that they may
which will state the exact procedure to ask for the relaxation of certain strict or
be followed in arbitrating/ adjudicating unfair terms of the contract, but they must
the dispute. An arbitrator(s)/ ensure that this does not render them
adjudicator(s) will be agreed upon, and disqualified, and they must voice this
dates for submissions and argument, concern in the prescribed format
issues relating to costs, and all other (usually tender specific).
logistical issues will be agreed in
a meeting with the arbitrator(s)/ Although arbitration offers a quicker,
adjudicator(s). This agreement will then controlled and much more discreet
be followed until a decision is made by solution to disputes, it is not always
the arbitrator(s)/ adjudicator(s). It is the cheapest solution.
important to note that the ruling of an
arbitrator/ adjudicator is binding on the
parties and can be made an order of
the court. If it is agreed that the award
by an arbitrator or adjudicator is final
and binding, a court will, save in the
most exceptional cases, not overturn
the award.
21
BOWMANS
Key concepts
22
A Guide to Construction Contracts
The defect liability period starts when Escalation clauses: Caters for the rise
the employer is satisfied that the and fall of economic factors, where a
works are complete and takes delivery. project/ contract exceeds a duration of
The defects liability period varies, one year, eg labour rates, commodity
depending on the nature of the prices, etc.
work, and can range from three
to 12 months. Extension of time (EOT): An
extended time for completion of the
Deviation: When a plan, design works, relieving the contractor from
or specifications agreed by the having to pay penalties for
parties is not followed during the delay.
the construction process.
Force majeure: An exceptional event
Disputes: In general, a dispute is or circumstance beyond a partys
defined as an unresolved matter of control that renders performance of
dissatisfaction or difference. the works impossible for a period of
time or forever (eg war, terrorism, etc).
Employer: Also known as the client,
the employer may be a person or a Performance guarantee: A guarantee
government agency or a corporation, procured by the contractor from a
and is the party who wants the project financial institution in favour of the
constructed and who will pay for the employer as security for the due
work. The employer also signs performance of the contractors
the contract. obligations under the contract. The
employer can claim against this
Employers representative: security should the contractor fail to
A representative of the employer, perform the obligations for which the
usually a professional architect, security has been given. The security
engineer, project manager or quantity is returned when the contract is
surveyor. This is the person with whom satisfactorily completed. The terms
the contractor will have the greatest of the guarantee will determine the
contact during the contract. nature thereof, and the instances in
which it can be called, and must for
that reason be read very carefully.
23
BOWMANS
24
A Guide to Construction Contracts
25
BOWMANS
Applicable legislation
26
A Guide to Construction Contracts
Useful links
International Chamber of
Commerce (ICC)
www.iccwbo.org
27
Antananarivo
T: +261 20 224 3247
E: info-mg@bowmanslaw.com
Cape Town
T: +27 21 480 7800
E: info-cpt@bowmanslaw.com
Dar es Salaam
T: +255 22 219 8000
E: info-tz@bowmanslaw.com
Durban
T: +27 31 265 0651
E: info-dbn@bowmanslaw.com
Johannesburg
T: +27 11 669 9000
E: info-jhb@bowmanslaw.com
Kampala
T: +256 41 425 4540
E: info-ug@bowmanslaw.com
Nairobi
T: +254 20 289 9000
E: info-ke@bowmanslaw.com
Follow us on Twitter:
@Bowmans_Law
www.bowmanslaw.com