SCL Protocol - 2nd Edition 2017 PDF
SCL Protocol - 2nd Edition 2017 PDF
SCL Protocol - 2nd Edition 2017 PDF
CONSTRUCTION LAW
DELAY AND DISRUPTION
PROTOCOL
2nd edition
February 2017
www.scl.org.uk
Published by the Society of Construction Law (UK),
234 Ashby Road, Hinckley, Leicestershire, LE10 1SW.
tel: 07730 474074
email: admin@scl.org.uk
www.scl.org.uk
All rights reserved. Except as expressly permitted by law, no part of this publication
may be reproduced, stored in a retrieval system or transmitted in any form or by any
means without the prior written permission of the Society of Construction Law.
Consent will usually be given for extracts to be quoted provided the Society is fully
credited. Enquiries concerning reproduction should be sent by email to:
feedback@eotprotocol.com
ISBN 978-0-9543831-2-1
CONTENTS
INTRODUCTION....................................................................................................... 1
CORE PRINCIPLES .................................................................................................. 5
1. Programme and records .................................................................................... 5
2. Purpose of EOT................................................................................................. 5
3. Contractual procedural requirements ................................................................ 5
4.
(contemporaneous analysis) .............................................................................. 5
5. Procedure for granting EOT.............................................................................. 6
6. Effect of delay ................................................................................................... 6
7. Incremental review of EOT .............................................................................. 6
10. Concurrent delay effect on entitlement to EOT ............................................. 6
11. Analysis time-distant from the delay event ...................................................... 7
12. Link between EOT and compensation .............................................................. 7
13. Early completion as it relates to compensation................................................. 7
14. Concurrent delay effect on entitlement to compensation for
prolongation ...................................................................................................... 7
15. Mitigation of delay and mitigation of loss ........................................................ 7
16. Acceleration ...................................................................................................... 7
17. Global claims .................................................................................................... 8
18. Disruption claims .............................................................................................. 8
19. Valuation of variations ...................................................................................... 8
20. Basis of calculation of compensation for prolongation .................................... 8
21. Relevance of tender allowances ........................................................................ 8
22. Period for evaluation of compensation ............................................................. 8
GUIDANCE PART A: DELAY, DISRUPTION & ACCELERATION
CONCEPTS ..................................................................................................... 9
GUIDANCE PART B: GUIDANCE ON CORE PRINCIPLES .......................... 12
1. Programme and records .................................................................................. 12
Introduction to records ............................................................ 12
Format and storage of records ................................................. 14
Categories of records .............................................................. 14
Programme .............................................................................. 18
2. Purpose of EOT............................................................................................... 22
3. Contractual procedural requirements .............................................................. 23
2. Purpose of EOT
The benefit to the Contractor of an EOT is to relieve the Contractor of liability for
damages for delay (usually liquidated damages or LDs) for any period prior to the
extended contract completion date and allows for reprogramming of the works to
completion. The benefit of an EOT for the Employer is that it establishes a new
contract completion date, prevents time for completion of the works becoming at
large and allows for coordination / planning of its own activities.
6. Effect of delay
For an EOT to be granted, it is not necessary for the Employer Risk Event already to
have begun to affect the Contractor s progress with the works, or for the effect of the
Employer Risk Event to have ended.
9. Identification of float
The identification of float is greatly assisted where there is a properly prepared and
regularly updated programme, the Accepted/Updated Programmes.
16. Acceleration
Where the contract provides for acceleration, payment for the acceleration should be
based on the terms of the contract. Where the contract does not provide for
acceleration but the Contractor and the Employer agree that accelerative measures
should be undertaken, the basis of payment should be agreed before the acceleration is
commenced. Contracting parties should seek to agree on the records to be kept when
acceleration measures are employed. Where the Contractor is considering
implementing acceleration measures to avoid the risk of liquidated damages as a
result of not receiving an EOT that it considers is due, and then pursuing a
Introduction to records
1.4 There is often a lack of good record keeping and a lack of uniformity of
approach to record keeping as relevant to management of progress of the
works and delay and disruption claims.
2. Purpose of EOT
The benefit to the Contractor of an EOT is to relieve the Contractor of liability
for damages for delay (usually LDs) for any period prior to the extended
contract completion date and allows for reprogramming of the works to
completion. The benefit of an EOT for the Employer is that it establishes a new
contract completion date, prevents time for completion of the works becoming
‘ at large’ and allows for coordination / planning of its own activities.
2.1 It is often incorrectly thought that an entitlement to an EOT automatically
carries with it an entitlement to compensation for prolongation costs during the
period of the EOT. The main effect of an EOT is that the Contractor is
relieved of its liability for liquidated damages during the period of the
extension and is able to reprogramme its works to completion. Its entitlement
6. Effect of delay
For an EOT to be granted, it is not necessary for the Employer Risk Event
already to have begun to affect the Contractor’s progress with the works, or for
the effect of the Employer Risk Event to have ended.
6.1 As explained in the guidance to Core Principle 4 in Part B, the practice of
some CAs of waiting to see what the full effect an Employer Risk Event has
on the works before dealing with the Contractor s application for EOT is
discouraged. If the Contractor is entitled to an EOT it should receive it, and
the CA should not wait to see if the Contractor actually needs the EOT, in
order not to be liable for liquidated damages.
9. Identification of float
The identification of float is greatly assisted where there is a properly prepared
and regularly updated programme, the Accepted/Updated Programmes.
9.1 Recommendations for the preparation of the Accepted/Updated Programmes
are set out as part of the guidance to Core Principle 1 in Part B.
11.6 Some of these methods require a baseline programme. If the parties have
followed the guidance to Core Principle 1 in Part B, that will be the
Accepted/Updated Programmes. If the parties have not followed the guidance
to Core Principle 1 in Part B and one of those methods is adopted in carrying
out the delay analysis, this could lead to greater scope for disagreement on the
assessment of delay.
(a) The impacted as-planned analysis method involves introducing delay
event sub-networks into a logic-linked baseline programme and its
recalculation using CPM programming software in order to determine
the prospective impact these events have on the predicted contract
completion dates shown within the baseline programme. Before
embarking upon the analysis, the analyst needs to confirm that the
sequences and durations for the works shown in the programme are
reasonable, realistic and achievable and properly logically linked
within the software, to deal with the risk that the baseline programme
contains fundamental flaws which cannot be overcome. In general, this
is thought to be the simplest and least expensive form of delay
analysis, but has material limitations, principally because it does not
consider actual progress and changes to the original planned intent.
The product of this method of analysis is a conclusion as to the likely
effect of the modelled delay events on the baseline programme. In
limited circumstances this analysis may be deemed sufficient for
assessing EOT entitlement. Such circumstances include where the
impacted as-planned method is dictated by the terms of the contract
and/or where the delay events being considered occurs right at the
outset of the works.
(b) The time impact analysis involves introducing delay event sub-
networks into a logic-linked baseline programme and recalculation of
this updated programme using CPM programming software in order to
determine the prospective impact the delay event would have on the
then predicted completion dates. The baseline programme for each
analysis can be either a contemporaneous programme or a
contemporaneously updated baseline programme (i.e. an Updated
Programme), the difference being the revised contemporaneous
programme may have logic changes / activity / resource changes from
SCL Delay and Disruption Protocol 2nd Edition: February 2017 35
the original baseline programme. In either case, the analyst needs to
verify that the baseline programme s historical components reflect the
actual progress of the works and its future sequences and durations for
the works are reasonable, realistic and achievable and properly
logically linked within the software. Mitigation and acceleration
already incorporated into the updated baseline programme need to be
considered as these can conceal or distort the projected impact of the
delay events. The number of delay events being modelled has a
significant impact on the complexity and cost of deploying this
method. The product of this method of analysis is a conclusion as to
the likely delay of the modelled delay events on the programme/critical
path that is most reflective of the contemporaneous position when the
delay events arose. This method usually does not capture the eventual
actual delay caused by the delay events as subsequent project progress
is not considered. This method is also described in the guidance to
Core Principle 4 in the context of a contemporaneous assessment of an
EOT application.
(c) The time slice analysis method is the first of two windows analysis
methods. This method requires the analyst to verify (or develop) a
reliable series of contemporaneously updated baseline programmes or
revised contemporaneous programmes reflecting an accurate status of
the works at various snapshots (being the time slices) throughout the
course of the works. Through this process, the progress of the works is
divided into time slices. The time slices are typically carried out at
monthly intervals. The series of time slice programmes reveals the
contemporaneous or actual critical path in each time slice period as the
works progressed and the critical delay status at the end of each time
slice, thus allowing the analyst to conclude the extent of actual critical
delay incurred within each window. Thereafter, the analyst investigates
the project records to determine what events might have caused the
identified critical delay in each time slice period. For each time slice
programme the analyst needs to verify that the historical components
reflect the actual progress of the works and that its future sequences
and durations for the works are reasonable, realistic and achievable and
properly logically linked within the software.
(d) The as-planned versus as-built windows analysis method is the
second of the windows analysis methods. As distinct from a time
slice analysis, it is less reliant on programming software and usually
applied when there is concern over the validity or reasonableness of the
baseline programme and/or contemporaneously updated programmes
and/or where there are too few contemporaneously updated
programmes. In this method, the duration of the works is broken down
into windows. Those windows are framed by revised contemporaneous
programmes, contemporaneously updated programmes, milestones or
significant events. The analyst determines the contemporaneous or
actual critical path in each window by a common-sense and practical
analysis of the available facts. As this task does not substantially rely
on programming software, it is important that the analyst sets out the
16. Acceleration
Where the contract provides for acceleration, payment for the acceleration
should be based on the terms of the contract. Where the contract does not
provide for acceleration but the Contractor and the Employer agree that
accelerative measures should be undertaken, the basis of payment should be
agreed before the acceleration is commenced. Contracting parties should seek to
agree on the records to be kept when acceleration measures are employed.
16.1 Some forms of contract provide for acceleration by instruction or by collateral
agreement. In other forms, acceleration may be instructed by reference to
SCL Delay and Disruption Protocol 2nd Edition: February 2017 41
hours of working and sequence. The Contractor cannot be instructed to
accelerate to reduce Employer Delay, unless the contract allows for this.
16.2 Where the contract provides for acceleration, payment for the acceleration
should be based on the terms of the contract.
16.3 Where the contract does not provide for acceleration but the Contractor and
the Employer agree that accelerative measures should be undertaken, the basis
of payment should be agreed before the acceleration is commenced.
16.4 Where acceleration is instructed and/or agreed, the Contractor is not entitled to
claim prolongation compensation for the period of Employer Delay avoided
by the acceleration measures.
Where the Contractor is considering implementing acceleration measures to
avoid the risk of liquidated damages as a result of not receiving an EOT that it
considers is due, and then pursuing a constructive acceleration claim, the
Contractor should first take steps to have the dispute or difference about
entitlement to an EOT resolved in accordance with the contract dispute
resolution provisions.
16.5 Where the Contractor is considering implementing acceleration measures to
avoid the risk of liquidated damages as a result of not receiving an EOT that it
considers is due to it, and then pursuing a constructive acceleration claim, the
Contractor should first take steps to have the dispute or difference about
entitlement to EOT resolved in accordance with the contract dispute resolution
provisions. Otherwise, there is the risk that it will not be entitled to
compensation for those acceleration measures. In any event, before pursuing
any such acceleration measures, the Contractor should provide notice with
particulars of the intended acceleration measures to the CA. The Contractor
should then include such measures in a revised programme.
16.6 Just because the Contractor implements measures to recover Employer Delay
does not necessarily mean that the full costs of those measures were caused by
the Employer Delay. For example, the addition of a second labour gang may
permit the relevant work activities to be completed in a shorter period of time
but, overall, the Contractor may have incurred the costs of the same number of
man-hours as it planned to do. Of course, the Contractor may incur higher
rates in engaging the two labour gangs later in time because of the Employer
Delay. Any such incremental costs therefore should be compared with
prolongation costs that would otherwise have arisen to identify whether those
incremental costs are reasonable. Further, any resulting crowding of labour
may lead to loss of productivity which could then form the basis of a
disruption claim.
Disruption analysis
18.6 Disruption is demonstrated by applying analytical methods and techniques to
establish the loss of productivity arising out of the disruption events and the
resulting financial loss. Disruption is not merely the difference between what
actually happened and what the Contractor planned. From the Contractor s
2. Project-comparison studies
3. Industry studies
18.14 The primary focus of a disruption analysis will be on the direct labour and
task-specific plant resources said to have been disrupted. However, there may
also be an impact on indirect resources, such as supervision staff or standing
plant (i.e. where such resources are increased rather than merely extended),
leading to additional costs. In demonstrating that the disruption events also
caused additional costs for indirect resources, the Contractor will need to
demonstrate the correlation between those costs and the loss of productivity in
the direct resources.
Productivity-based methods
18.15 There are three general categories of productivity-based methods, listed below
by order of preference because of their decreasing reliability and general
acceptance:
(a) project-specific studies;
(b) project-comparison studies; and
(c) industry studies.
Cost-based methods
18.21 Cost-based methods provide the least robust support for a disruption claim and
are often applied when lost productivity cannot be reliably calculated utilising
a productivity-based approach. These methods focus on project cost records
and seek to provide a comparison between either incurred and estimated cost,
or labour used and estimated labour, for those activities impacted by
disruption events for which the Employer is responsible.
18.22 Several formulae are available, the simplest being total labour cost expended
(by the Contractor) less total labour cost paid (by the Employer to the
Contractor), which equals total labour cost lost. However, for the reasons in
paragraph 18.6 above, this approach is unlikely to be persuasive without
further analysis. Modified formulae which exclude from the claimable costs
calculation the costs of the Contractor s tender errors and any disruption
events for which the Contractor is responsible will be more persuasive. Even if
Further guidance
18.25 Under appropriate circumstances, and in varying degrees, all of the methods
introduced above may support a disruption claim. The most reliable and
accurate are project-specific studies, particularly a properly implemented
measured mile analysis. An analysis which combines a productivity-based
method and a cost-based method may provide useful cross-checking where it
is proportionate to carry out two analyses. Whichever method is used for
identifying and establishing disruption and the resulting loss and expense, it is
necessary to isolate issues that are likely to have impacted productivity but
which are unrelated to the Employer s liability.
18.26 The Contractor should have regard to the guidance to Core Principle 1 in Part
B in relation to records in ensuring it maintains appropriate records which, if
necessary, can be relied upon to support a disruption claim.
18.27 Contractors sometimes assert claims for the cumulative impact of disruption
events on the basis of exponential lost productivity resulting from the
combination of individual disruption events over and above that apparently
accounted for by aggregating the lost productivity caused by each disruption
event. It is often the case that the greater the number of disruption events, the
harder it is to quantify losses with precision because of the record-keeping
challenges imposed through no fault of the Contractor, who would not have
expected these challenges when the contract was entered into.
18.28 This is an area where particular care has to be taken to address the risks
associated with global claims. However, if all causes of disruption can
genuinely be said to be the Employer s responsibility, and if the financial
consequences of those disruption events are impossible or impracticable to
distinguish, then such an approach may be valid and indeed persuasive. In
effect, the proposition being put is that the Contractor s analysis is not capable
of explaining the full extent of financial loss that has actually occurred by
reference to the individual disruption events, but that the loss, despite the
absence of any more proof, must be fully the responsibility of the Employer.
acceleration
The application of additional resources or alternative construction sequences or
methodologies seeking to achieve the planned scope of work in a shorter time than
planned or execution of additional scope of work within the original planned duration.
Accepted Programme
The Protocol recommends that the Contractor be required to submit a draft
programme for the whole of the works to the CA and that this draft programme be
accepted by the CA. Once accepted by the CA, it is known in the Protocol as the
Accepted Programme.
Activity
An operation or process consuming time and possibly other resources. An individual
or work team can manage an activity. It is a measurable element of the total project
programme.
activity float
The duration contingency directly related to a single activity built into the planned
duration of that activity. Activity float is established simply by dictating an activity
duration that is greater than the actual time needed to complete that activity.
activity-on-the-node network
A network in which the nodes symbolise the activities. A precedence diagram.
as-built programme
The record of the history of the construction project in the form of a programme. The
as-built programme does not necessarily have any logic links. It can be merely a bar-
chart record of the start and end dates of every activity that actually took place. As
constructed programme has the same meaning.
change/variation
Any difference between the circumstances and/or content of the contract works as
carried out, compared with the circumstances and/or content under which the works
are described in the contract documents as required to be or intended to have been
carried out. A change or variation may or may not carry with it a right to an EOT
and/or additional payment.
collapsed as-built
See paragraph 11.6(f) of Part B.
compensation
The recovery or payment of money for work done or time taken up whether by way of
valuation, loss and/or expense or damages.
completion date
See contract completion date.
concurrency
See the guidance to Core Principle 10 in Part B.
concurrent delay
See concurrency.
constructive acceleration
Acceleration following failure by the CA to recognise that the Contractor has
encountered Employer Delay for which it is entitled to an EOT and which failure
required the Contractor to accelerate its progress in order to complete the works by
the prevailing contract completion date. This situation may be brought about by the
Employer s denial of a valid request for an EOT or by the CA s late granting of an
EOT. This is rarely recognised under English law.
Contractor
The party responsible for carrying out the works is generally referred to as the
Contractor . The Protocol is applicable to sub-contracts as well as main contracts, so
when it is being applied to a sub-contract, it is the sub-contractor that is being referred
to as the Contractor in the Protocol.
critical delay
See critical path.
critical path
The longest sequence of activities through a project network from start to finish, the
sum of whose durations determines the overall project duration. There may be more
than one critical path depending on workflow logic. A delay to progress of any
activity on the critical path will, without acceleration or re-sequencing, cause the
overall project duration to be extended, and is therefore referred to as a critical
delay .
culpable delay
Expression sometimes used to describe what the Protocol calls Contractor Delay.
Delay to Completion
In common usage, this expression may mean either delay to the date when the
contractor planned to complete its works, or a delay to the contract completion date.
The Protocol uses the expressions Employer Delay to Completion and Contractor
Delay to Completion, both of which mean delay to a contract completion date - see
their definitions.
Delay to Progress
In the Protocol, this means a delay which will merely cause delay to the Contractor s
progress without causing a contract completion date not to be met. It is either an
Employer Delay to Progress or a Contractor Delay to Progress.
disruption
See paragraph 5 in Part A and the guidance to Core Principle 18 in Part B.
disruption event
An event or cause of disruption.
duration
Duration is the length of time needed to complete an activity. The time period can be
determined inductively, by determining the start and finish date of an activity or
deductively by calculation from the time necessary to expend the resources applied to
the activity.
Employer
The Employer is the party under the contract who agrees to pay for the works. In
some of the standard forms, the party who agrees to pay for the works is referred to as
the Developer, the Owner, the Client or the Authority. The Protocol is applicable to
sub-contracts as well as main contracts, so when it is being applied to a sub-contract,
it is the main contractor that is being referred to as the Employer in the Protocol.
Employer Delay
Expression commonly used to describe any delay caused by an Employer Risk Event.
The Protocol distinguishes between: Employer Delay to Progress which is a delay
which will merely cause delay to the Contractor s progress without causing a contract
completion date not to be met; and Employer Delay to Completion which is a delay
which will cause a contract completion date not to be met.
excusable delay
Expression sometimes used to describe what in the Protocol is an Employer Delay in
respect of which the Contractor is entitled to an EOT.
float
The time available for an activity in addition to its planned duration. See free float and
total float. Where the word float appears in the Protocol, it means positive not
negative float, unless expressly stated otherwise.
free float
The amount of time that an activity can be delayed beyond its early start/early finish
dates without delaying the early start or early finish of any immediately following
activity.
Gantt chart
Bar chart named after the originator, Henry Gantt.
global claim
A global claim is one in which the Contractor seeks compensation for a group of
Employer Risk Events but does not or cannot demonstrate a direct link between the
loss incurred and the individual Employer Risk Events.
hammock
An activity representing the period from the start of an activity to the completion of
another. Sometimes used as a way of summarising the duration of a number of
activities in a programme as one single duration. See also level of effort .
hanging activity
An activity not linked to any preceding or successor activities. It is the same as
dangling activity.
impact
The effect that a change has on an activity or the effect that a change to one activity
has on another activity.
key date
Expression sometimes used to describe a date by which an identifiable
accomplishment must be started or finished. Examples include power on , weather-
tight or the start or completion of phases of construction or of phases or sections of
the contract, or completion of the works.
lag
Lag in a network diagram is the minimum necessary lapse of time between the finish
of one activity and the finish of another overlapping activity. It may also be described
as the amount of time required between the start or finish of a predecessor task and
the start or finish of a successor task. (See logic links)
lead
The opposite of lag, but in practice having the same meaning. A preceding activity
may have a lag to a successor activity from the perspective of the successor activity,
that is a lead.
logic links
The common logic links are as follows:
Finish-to-start
The convention in Figure 1 shows the normal sequential relationship of one
activity following another. Activity B cannot start until activity A has finished.
-4
milestone
A key event selected for its importance in the project. Commonly used in relation to
progress, a milestone is often used to signify a key date.
mitigation
Mitigate means making less severe or less serious. In connection with Delay to
Progress or Delay to Completion, it means minimising the impact of the Risk Event.
In relation to disruption or inefficient working, it means minimising the disruption or
inefficiency. Failure to mitigate is commonly pleaded as a defence or partial defence
to a claim for delay or disruption. Acceleration is a subset of mitigation.
negative lag
See logic links above.
non-compensable event
Expression sometimes used to describe what the Protocol calls a Contractor Risk
Event.
non-excusable delay
Expression sometimes used to describe what the Protocol calls Contractor Delay.
Path
An activity or an unbroken sequence of activities in a project network.
PERT
Programme Evaluation and Review Technique: a programming technique, similar to
critical path analysis, but whereby the probability of completing by the contract
completion date is determined and monitored by way of a quantified risk assessment
based on optimistic, pessimistic and most likely activity durations.
precedence diagram
A multiple dependency, activity-on-node network in which a sequence arrow
represents one of four forms of precedence relationship, depending on the positioning
of the head and the tail of the sequence arrow. (See logic links)
programme
A tool that divides the works into a series of activities, each with a duration and logic
links to preceding and succeeding activities, forming a network of activities. The
programme may be depicted in a number of different forms, including a Gantt or bar
chart, line-of-balance diagram, pure logic diagram, time-scaled logic diagram or as a
time-chainage diagram, depending on the nature of the works. Otherwise known as
the schedule. This term should not be confused with program , being the software
used to generate the programme.
programme narrative
A written explanation of the assumptions underlying the Accepted Programme (or the
Updated Programme), its key resources, sequencing restraints, critical path, risks,
exclusions/exceptions, and execution strategy.
prolongation
The extended duration of the works during which time-related costs are incurred as a
result of a delay.
resource
Expression used to describe any variable capable of definition that is required for the
completion of an activity and may constrain the project. This may be a person, item of
equipment, service or material that is used in accomplishing a project task.
resource levelling
Expression used to describe the process of amending a schedule to reduce the
variation between maximum and minimum values of resource requirements. The
process removes peaks, troughs and conflicts in resource demands by moving
activities within their early and late dates and taking up float. Most project planning
software offers an automated resource-levelling routine that will defer the
performance of a task within the imposed logical constraints until the resources
assigned to the tasks are available.
Risk Event
See Employer Risk Event and Contractor Risk Event.
schedule
Another name for the programme.
slack
Another name for total float.
sub-network
A group of activities or durations, logically linked. In the Protocol it is to be used to
illustrate the work flowing directly from an Employer Risk Event.
Substantial Completion
See Practical Completion.
total float
The amount of time that an activity may be delayed beyond its early start/early finish
dates without delaying the contract completion date.
Updated Programme
In the Protocol the Updated Programme is the Accepted Programme updated with all
progress achieved and any revised logic or constraints. The final Updated Programme
should depict the as-built programme.
works
The scope of works to be completed by the Contractor under the contract.
1. Programme records
1.1 These records set out the Contractor s plan for carrying out the works and,
upon being updated, record the progress status of the works at the agreed
intervals and upon completion of the works. There are a number of sub-
categories of programme records as set out below.
1.2 Programmes: typically there are multiple programmes created and maintained
in relation to the works as follows:
(a) tender programmes;
(b) Contractor s proposed programmes (submitted for the purposes of
acceptance as the Accepted Programme);
(c) Accepted Programme;
(d) Updated Programmes (the last of which should be an as-built
programme);
(e) proposed revised programmes submitted by the Contractor;
(f) detailed short term look ahead programmes; and
(g) the Contractor s internal target programmes.
1.3 Also, there are supplemental detailed programmes or programming
information in a suitable format (such as CPM, line of balance or time location
analysis, tabular spreadsheet, or database) for:
(a) design;
(b) approvals (including the CA s approvals and public authority
approvals);
(c) procurement or manufacturing;
(d) delivery;
(e) installation;
(f) construction of key aspects of the works; and
(g) testing and commissioning.
2. Progress records
2.1 These records identify the progress of the works at a particular time. There are
a number of sub-categories of progress records as set out below.
2.2 Raw data records: these are records which ought to be compiled on a regular
basis, normally daily for anything other than very small projects, which record
how relevant parts of the works are being carried out. They are at the heart of
establishing progress achieved before, during, and after periods of delay or
disruption. Below are examples of these records:
(a) reports (for each major work area recording weather conditions,
manpower, deliveries of key materials, discovery of adverse site
conditions, working hours, major plant and equipment used, and work
activities underway);
(b) health, safety, environmental and/or security issues log;
(c) obstruction data (recording obstructions or impediments to planned
progress at specific work fronts, clearly identifying the obstruction
start and finish date, daily status at the work front, and the area of the
works and programme activities impacted);
(d) evidence of area handovers between contractors/others, clearly
identifying which contractor/other party is in possession of each work
area at what time;
3. Resource records
3.1 Resource records document the labour, materials and equipment utilised on the
works.
3.2 Labour and equipment allocation records set out on a daily basis in which
areas specific labour and equipment worked and should correspond to, at least
at a high level, the programme activities.
4. Costs records
4.1 Costs records demonstrate the costs incurred in carrying out the works and
assist in substantiating amounts claimed in delay and disruption claims. These
records should be kept in the normal course of business and should be project
specific.
4.2 An accounting and cost allocation system for the works should be established
from the outset to split costs into the following headings as a minimum:
(a) management;
(b) labour;
(c) plant;
(d) materials;
(e) sub-contractors; and
(f) non-staff overheads.
4.3 Costs records include:
(a) internal cost reports;
(b) cost value reconciliation reports (or similar);
(c) payroll records;
(d) time sheets;
(e) labour agreements;
(f) monthly payment applications;
(g) regarding sub-contractors:
(i) sub-contract agreements;
(ii) sub-contractor correspondence;
(iii) claims made by sub-contractors and responses;
(iv) sub-contractor applications for payment; and
(v) details of all payments made to sub-contractors.
(h) regarding suppliers:
website: www.scl.org.uk