Construction Claims: Presented By: Janice Kong & Felix LAU
Construction Claims: Presented By: Janice Kong & Felix LAU
Construction Claims: Presented By: Janice Kong & Felix LAU
CLAIMS
PRESENTED BY : JANICE KONG & FELIX
LAU
WHAT IS CONSTRUCTION
CLAIM?
A claim is a demand for damages rightfully or allegedly due to the
aggrieved party
If there is any breach of contract by one party that causes actual
damages, a claim for damages can be made under common law or
under clause 74 of Contract Act.
However,
There is a limit for the right to claim for specific matter ONLY
Contractor must also follow the conditions & procedure laid in the
contract
TYPES OF CLAIMS
1. Contractual claims (PAM 2006)
This type of claim arises from the contract itself.
Ex:
. Clause 11.6 & 11.7 (variation works)
. Clause 23.1 extension of time.
. Clause 24.1 enables the contractor to pursue his entitlement to
loss and expense caused by matters affecting the regular
progress of the works.
. Clause 24.1(a) also preserves the right of contractor to seek his
entitlement under common law.
ii)
ii)
CLAIM PROCEDURE
Step 1
1. Written notice of intention to claim for loss and/or expense
2. Initial estimate of his claim, duly supported by all necessary calculations shall be stated
3. Such notice must be given within 28 Days from the date of AI (or the start of the
occurrence of relevant event, whichever, is earlier).
4. The written notice shall be a condition precedent to any entitlement to loss and/or
expense.
Step 2
i)
ii)
Formal application shall include complete particulars of his claim for loss and/or
expense, together with all necessary evidence and calculation to substantiate his
claims.
iii) This formal application shall be submitted after the 28 Days of completion of the
relevant matters.
iv) Failure to submit within 28 days or any extended date agreed; it is deemed the
contractor has waived his right to claim.
ii)
2. Extra-contractual Claim
(common law claim)
This include :
1. claims for breach of contract claims arising outside the
expressed term of contract.
2. claims for implied contract claim for work done based on a
Letter of Intent.
3. claim under tort claim for negligence, e.g. Architect refusing to
issue Interim Certificate with valid reasons.
4. claim under quantum merit claim for a reasonable sum for work
done where there is no contract or where the contract is silence
on how the work is to be paid.
RESTRICTIONS TO CLAIM
1) VERY tedious! Contractors needs to prove damages
with sufficient evidence and some damages are difficult to
quantify.
2) Claims cannot be made immediately upon occurrence.
Claim must go through arbitration or litigation only after
practical completion or after determination of contractors
employment.
3. EX-GRATIA CLAIMS
1) A LAST RESORT!
2) NO legal basis. NOT legally binding but for which some moral
obligation is felt.
3) It is premised on grounds of undue hardship.
4) Payment is discretionary. Usually made on goodwill basis or
on moral grounds or generosity.
5) Such ex-gratia payment is usually made to settle a claim on a
compromise basis and without prejudice (admitting) to liability,
thus avoiding lengthy and costing litigation process.
PAYMENT OF LOSS
AND/OR EXPENSE
Any lost and/or expense ascertained and
approved shall include in payment
certificates and Contract Sum adjusted
accordingly.
Lost and/or expense payment shall not be
subject to retention.
QS should find out the actual lost and not
estimate.
EXPLANATORY NOTES
ON TERMS
Materially Affected refers to works or
progress affected in a substantial extent.
Disruption Of Works refers to the low
productivity due to the disturbance or
interruptions.
Regular Progress refers to the speed of
progress which are directly related to the
completion date.
PROBLEMS WITH
CONTRACTUAL CLAIMS
Standardizing meaning in the construction industry.
Problem with proving loss.
Problem with Quantifying effects of cause into monetary
terms.
QUESTIONS!
1. Which of the following claim is harder to pursue? WHY?