Piping Estimating
Piping Estimating
Piping Estimating
MAN-HOUR MANUAL
ZAGREB, 2003.
(Completed edition)
You can buy the electronic version of the Manual containing all the figurest and other related data at the
following prices:
Individuals Legal entity
2. EACH CHAPTER
NOTE: +20* = THE FIRST 13 PAGES OF THE MANUAL AND 7 PAGES OF THE APPENDIX
4. Please, email us your full address and indicate the purchase option you have decided for.
We shall send you the electronic manual immediately.
As soon as your payment is received we shall send you the password that will enable you to
open and use the e-manual.
We congratulate you on your choice and thank you for buying our electronic Manual.
1
PREFACE
All 40 years of my working life, I spent on erection of different process plants most of which were oil industry projects
in the country and abroad, in Europe and North Africa. Since 1978 with occasional interruptions because of
simultaneous involvement in several different projects, I worked mostly on technical calculations. I have made
hundreds and hundreds calculations based on all kinds of tenders and erection of mech anical equipment. The
tenders were written in various foreign languages and alphabet, even in Cyrillic. I am fully aware of the problems an
estimator encounters when working on technical calculations for specific technologies. Very often tenders were not
complete and not detailed enough, and the time required for a good technical calculation is getting every day
shorter. It is not easy to present exact technical figures and quantities for the equipment or operations not fully
defined, hard to comprehend, or even unknown to the estimator. Technical terms and expressions written in
different languages and dialects are often incorrect and specific for individual branches. Enormous experience is
needed, an ability to assess and estimate, and even the courage to write down the technical quantities and figures.
That was the reason for collecting various technical bibliography, standards, catalogues, man hours and rates from
the European and USA countries. I have made the analyses, comparisons, simulations, new measures, and manhour
tables. A great deal of that was verified in practice during the plant erection. I surveyed the results and analyses of
as-built designs. On many occasions, I sought a compromise between different opinions and standpoints. Too many
things collected on too many places. Finally, I decided to write this manual for discriminative estimators. It is
important to understand that there are no identical projects or jobs in this business, that each project is specific and
that no automatism or copying is possible. Approach to any job should be serious and professional and a technical
calculation should be made with the assistance of this Manual. Many people try to include the man hours from the
tables into the computer systems, which I oppose. Those are the people, which instead of using a computer, a
computer uses them. An estimator himself must choose the values and define the man hours taking into account all
the elements that might have any influence on them. Only when the relevant man hours are estimated and selected,
a computer can be used. A saying Switch on your brain before switching on the computer should be followed.
The most complex work in developing these man hours was the work on the man hours for piping above ground. A
basis I used was a system for estimating the value of erection works of a German Company LINDE, which I
completed and modified. Generally, for elaboration of the man hours for erection/installation of process equipment,
I used the English man hours of the Oil and Chemical Plant Constructors Association, but I used other sources as
well.
The source or the author was noted for other tables and if I modified them, I provided the modification basis. Where
there are no such notes, I am the only author.
A complete edition of this manual in the Croatian language and its sections were published in 1997 and
2000. This is why I have not given a unified percentage of the production efficiency but each chapter has its own.
Marko Buli
2
CONTENTS
page
PREFACE...........................................................................................................................2
INTRODUCTION..............................................................................................................11
ABBREVIATIONS & UNITS.................................................................................................13
CHAPTER I. PIPING ABOVE GROUND................................................................................14
DERIVED OPERATING TIME STANDARD FOR
TABLES FACTOR OF BASIC ASSEMBLY
1. PIPES (ANSI B. 36.10)...................................................................................14
1.1 PIPE - INSTALLATION ON PROCESS PLANT...............................................................14
1.2 PIPE - INSTALLATION ON PIPE RACK OR SLEEPER WAY............................................15
2. FITTINGS (ANSI B. 16.9).......................................................................................16
2.1 ELBOWS...............................................................................................................16
2.2 CAPS....................................................................................................................16
2.3 TEES....................................................................................................................17
2.3.1 STRAIGHT TEE.....................................................................................................17
2.3.2 REDUCED TEE......................................................................................................17
2.4 REDUCERS - CONCENTRIC AND ECCENTRIC..........................................................18
1. PIPES (DIN 2448/2458)..............................................................................19
1.1 PIPE - INSTALLATION IN PROCESS PLANT..............................................................19
1.2 PIPE - INSTALLATION ON PIPE RACK OR SLEEPER WAY............................................21
1.3 STEAM TRACING (ANSI & DIN)..............................................................................23
1.4 INSTRUMENT AND CONTROL PIPING.....................................................................23
1.5 STEAM DISTRIBUTORS AND CONDENSATE COLLECTORS
FABRICATED FROM PIPES AND FITTINGS...............................................................23
1.6 STEAM DISTRIBUTORS AND CONDENSATE COLLECTORS FABRICATED
FROM READY MADE DISTRIBUTORS FOR 4 CONNECTIONS.....................................23
2. FITTINGS (DIN)............................................................................................24
2.1 ELBOWS..............................................................................................................24
2.2 CAPS...................................................................................................................24
2.3 TEES...................................................................................................................26
2.4 REDUCERS - CONCENTRIC AND ECCENTRIC..........................................................28
3. FLANGES.......................................................................................................30
3.1 WELDING NECKS..................................................................................................30
3.2 SLIP - ON.............................................................................................................31
3.3 SOCKET WELDING................................................................................................31
3.4 LAP JOINT + STUB END........................................................................................31
3.5 BLIND..................................................................................................................31
3.6 ORIFICE COMPLETE..............................................................................................31
4. SMALL FITTINGS...........................................................................................32
4.1 WELDOLETS, SOCKOLETS, NIPOLETS, etc..............................................................32
4.2 HALF COUPLINGS FOR WELDINGS.........................................................................32
4.3 FITTINGS WITH SOCKET ENDS..............................................................................32
4.4 THREADED FITTINGS............................................................................................32
3
5. VALVES................................... ........ ..........................................................33
5.1 VALVES WITH FLANGED ENDS...............................................................................33
5.2 VALVES WITH WELDING ENDS..............................................................................34
5.3 VALVES FOR THREADED ENDS..............................................................................34
5.4 PRESSURE GAUGES..............................................................................................34
5.5 THERMOMETERS..................................................................................................34
RATES FOR TENDER CALCULATIONS...............................................................35
1. MANHOUR ESTIMATE FOR INSTALLATION OF PIPING.............................................35
2. EFFECT ASSESSMENT FOR QUICK CALCULATION...................................................36
2.1 PIPING IN PROCESS PLANT...................................................................................36
2.2 PIPES (CARBON STEEL - NOT INSULATED) - MEAN VALUE......................................37
2.3 FITTINGS (CARBON STEEL) - MEAN VALUE.............................................................38
2.4 VALVES - MEAN VALUE..........................................................................................39
2.5 PIPE SUPPORTS....................................................................................................39
2.6 AVERAGE DIAMETER - Manner of Calculation..........................................................39
3. RATES FOR INSTALLATION OF POLYETHYLENE PIPING...........................................40
4. RATES FOR ERECTION OF PVC & FRP PIPING........................................................41
5. CARBON STEEL PIPING CEMENT LINED INSIDE......................................................41
6. PIPING MADE OF STEEL AND GREY CAST-IRON......................................................42
7. RATES FOR PIPING BASED ON INCH-DIAMETER (ID)...............................................43
8. RATES FOR UNITS OF OPERATION - BASED ON INCH-DIAMETER (ID).......................44
9. RATES FOR PIPING WELDING...............................................................................46
10. MAN HOURS FOR WELDING OF PIPING................................................................47
11. WORK CALCULATION - MAN HOURS FOR PIPING MODIFICATION AT SITE...............48
12. INSTALLATION OF PIPING ABOVE - GROUND
Prefabrication and installation breakdown..............................................................49
4
CHAPTER . ... ...................57
III. STEEL STRUCTURE ERECTION.......................................
1. BASIC MAN HOURS - UNIT.....................................................................57
1.1 SORTING THE STRUCTURE....................................................................................57
1.2 PRE-ERECTION OF STRUCTURE.............................................................................57
1.3 TRANSPORT OF STRUCTURE TO ERECTION PLACE.................................................57
1.4 INSTALLATION OF ANCHOR BOLTS........................................................................57
1.5 STRUCTURE ERECTION.........................................................................................57
1.6 INSTALLATION OF LOST FORMWORK.....................................................................58
1.7 INSTALLATION OF WIRE ROPE CLAMPS..................................................................58
1.8 REAMING OF HOLES.............................................................................................58
1.9 BOLTING FROM SCAFFOLDING...............................................................................58
2. ERECTION OF MISCELLANEOUS STEEL STRUCTURES.................................59
2.1 BASIC MANHOUR RATES.......................................................................................59
3. CORRECTION FACTORS................................................................................59
4. STEEL STRUCTURES IN OIL REFINERIES AND PETROCHEMICAL PLANTS...61
4.1 LIGHT STRUCTURE (to 30 kg/m)...........................................................................61
4.2 MEDIUM-WEIGHT STRUCTURE (31 60 kg/m)......................................................61
4.3 HEAVY STRUCTURE (above 60 kg/m).......................................................................61
4.4 MISCELLANEOUS STRUCTURES..............................................................................61
4.5 PIPE HANGERS AND SUPPORTS.............................................................................61
5. ERECTION AND DISMANTLING OF
MISCELLANEOUS STEEL STRUCTURES.............................................................62
5.1 ERECTION OF STEEL STRUCTURES - ACC. TO THE WEIGHT....................................62
5.2 MISCELLANEOUS STRUCTURES.............................................................................62
5.3 REMOVAL OF STEEL STRUCTURE AND MISCELLANEOUS ITEMS...............................66
5
3. TOWERS & VESSELS - INSTALLATION OF INTERIOR
COMPONENTS & EQUIPMENT.....................................................................71
3.1 INSTALLATION OF TRAYS AND DEMISTERING PADS...............................................71
3.2 VESSELS & TOWER PACKINGS...............................................................................71
3.3 OPENING AND CLOSING OF MANHOLES.................................................................71
3.4 ERECTION OF PLATFORMS, LADDERS AND FLOOR GRIDS.......................................72
4. EQUIPMENT SCAFFOLDING.........................................................................72
4.1 TUBULAR SCAFFOLD.............................................................................................72
4.2 PATENT SCAFFOLDING.........................................................................................73
6
CHAPTER IX. ESTIMATES...........................................................................................109
1. ESTIMATE OF SCAFFOLDS........................................ . .............................109
1. ESTIMATES OF SCAFFOLDING WHEN CONTRACTED TO A SPECIALIST FIRM..........109
2. ESTIMATE OF SCAFFOLDING WHEN DONE BY AN ERECTION COMPANY.................110
2. ESTIMATE OF WELDING ROD CONSUMPTION
AND ADDITIONAL WELDING MATERIAL........................................................112
1. PIPING...............................................................................................................112
2. STEEL STRUCTURES............................................................................................113
3. CYLINDRICAL STORAGE TANKS............................................................................113
4. EQUIPMENT IN PETROCHEMICAL INDUSTRY.........................................................113
3. ESTIMATE OF CONSUMPTION OF TECHNICAL
GAS AND GRINDING PLATES..........................................................................114
4. ESTIMATE OF ELECTRICITY CONSUMPTION.............................................115
5. ESTIMATE OF CONSUMPTION OF FUEL AND LUBRICANT.........................116
1. FUEL CONSUMPTION...........................................................................................116
2. LUBRICANT CONSUMPTION.................................................................................116
6. TOOL COST ESTIMATE AT THE JOB SITE...................................................117
7. ESTIMATE OF SAFETY AT WORK MEANS...................................................117
8. ESTIMATE OF ERECTION TIME...................................................................117
9. SELECTION OF HOISTING MACHINERY.....................................................118
9.1 SELECTION OF THE LARGEST CRANE...................................................................119
9.2 PIPING IN PLANTS..............................................................................................119
9.3 PIPING BETWEEN PLANTS...................................................................................120
9.4 PIPELINES.........................................................................................................120
9.5 ERECTION OF STEEL STRUCTURE.......................................................................120
9.6 INSTALLATION OF PROCESS EQUIPMENT.............................................................120
9.7 ERECTION OF CYLINDRICAL STORAGE TANKS......................................................120
10. UNLOADING, HANDLING AND SORTING OF THE MATERIAL.....................121
10.1 MATERIAL FOR PIPING.......................................................................................121
10.2 STEEL STRUCTURE.............................................................................................121
10.3 PROCESS EQUIPMENT.........................................................................................121
10.4 CYLINDRICAL STORAGE TANKS...........................................................................121
11. TEMPORARY WORKS, SPACE REQUIRED
AND CONNECTIONS AT THE SITE...................................................................122
1. TEMPORARY WORKS...........................................................................................122
2. AREA NEEDED....................................................................................................123
3. CONNECTIONS NEEDED......................................................................................123
12. ESTIMATE OF THE NUMBER OF WELDS
AND RADIOGRAMS FOR PIPING....................................................................124
1. ESTIMATE OF BUTTWELDS BASED ON A LIST OF MATERIAL
- PIPES, FITTINGS AND FLANGES.........................................................................124
2. ESTIMATE OF BUTTWELDS BASED ON A LIST OF MATERIAL
- FITTINGS AND FLANGES ONLY...........................................................................124
3. ESTIMATE OF BUTTWELDS BASED ON THE PIPING LENGTHS................................125
4. ESTIMATE OF TOTAL WELDS (ALL TYPES)............................................................125
5. ESTIMATE OF RADIOGRAMS ON THE PIPING........................................................125
7
CHAPTER X. PIPING ABOVE GROUND
EXPLANATION TO THE ERECTION ITEMS............................................................127
1.0 PIPING......................................................................................................127
1.1 PIPE INSTALLATION IN PLANTS..........................................................................127
1.2 PIPE INSTALLATION ON PIPERACKS.....................................................................127
1.3 PIPE DISMANTLING............................................................................................127
2.0 FITTING.....................................................................................................127
2.1 ADJUSTMENT OF FITTINGS WITH ONE CONNECTION END....................................128
2.2 ADJUSTMENT OF FITTINGS WITH TWO CONNECTION ENDS................................128
2.3 ADJUSTMENT OF FITTINGS WITH THREE CONNECTION ENDS..............................128
3.0 PIPEWELD MAKE-ON AND WELDING.......................................................128
3.1 BUTT WELD MAKE-ON AND WELDING..................................................................128
3.2 FILLET (SOCKET) WELD - PERFORMANCE AND WELDING......................................128
3.3 MITRE WELD MAKE-ON AND WELD......................................................................129
3.4 NOZZLE WELD MAKE-ON AND WELDING..............................................................129
3.5 WELDOLET, NIPOLET - INSTALLATION AND WELDING..........................................129
3.6 REINFORCEMENT PAD MAKE-ON AND WELDING...................................................129
3.7 SEAL RING MAKE-ON AND WELDING (ACC. TO DIN 2695).....................................129
3.8 INSERT RING (FOR AL ONLY)..............................................................................130
3.9 WELD CUTTING FOR MODIFICATIONS.................................................................130
3.10 MATERIAL MULTIPLIER FACTORS (f)....................................................................130
4.0 FLANGED AND THREADED JOINTS, BENDING OF PIPES..........................130
4.1 4.3 FLANGED JOINT...................................... .................................................130
4.4 INSTALLATION OF MEASURING ORIFICES, BLANKING PLATES, etc.........................130
4.5 PIPE BENDING....................................................................................................130
4.6 PREPARATION OF THREADED ENDS....................................................................131
4.7 THREADED CONNECTION MAKE-ON....................................................................131
4.8 DISASSEMBLING Item 4.1 4.4 and 4.7.................................................................131
5.0 VALVES......................................................................................................131
5.1 VALVE INSTALLATION (WITH AND WITHOUT HAND DRIVE)..................................131
5.2 VALVE INSTALLATION WITH ACTUATORS (SOLENOID, AIR)...................................131
5.3 BUTTERFLY VALVE INSTALLATION WITH ACTUATOR.............................................131
5.4 BUTTERFLY VALVE INSTALLATION........................................................................131
5.5 CONTROL VALVE INSTALLATION..........................................................................131
5.6 SAFETY VALVE INSTALLATION.............................................................................132
5.7 HYDRANT INSTALLATION....................................................................................132
5.8 SPINDLE EXTENSIONS.........................................................................................132
5.9 DISMANTLING OF VALVES...................................................................................132
6.0 PRESSURE TESTING..................................................................................132
6.1 PRESSURE TEST..................................................................................................132
6.2 SERVICE TEST.....................................................................................................132
8
.
7.0 MISCELLANEOUS.......................................... ......................................132
7.1 SUPPORTS - FABRICATION AND WELDING...........................................................132
7.2 SUPPORT INSTALLATION (WITHOUT FABRICATION).............................................132
7.3 INSTALLATION OF SPRING HANGERS AND SUSPENSIONS.....................................133
7.4 GRINDING OF EXCESS MATERIAL ON WELDING ROOTS........................................133
7.5 INSTRUMENT CONNECTION - DRILLING..............................................................133
8.0 ACTIVITIES DERIVED FROM BASIC ITEMS.............................................133
8.1 PIPES...............................................................................................................133
8.1.1 PIPE HANDLLING AND CUTTING IN PREFABRICATION...........................................133
8.1.2 INSTALLATION OF PREFABRICATED SPOOLS.........................................................133
8.1.3 SPATIAL SHIFTING OF PIPES...............................................................................133
8.1.4 MAKE-ON OF OUTSIDE PIPE FOR A DOUBLE-WALL
PIPING (JACKETED PIPING)................................................................................134
8.1.5 MAKE-ON AND INSTALLATION OF LINE PIPING
DN 20/25 ON JACKETED PIPING..........................................................................134
8.2 MISCELLANEOUS FITTINGS............................................................................134
8.2.1 HALF COUPLINGS................................................................................................134
8.2.2 WELD COMPENSATOR.........................................................................................134
8.2.3 WELD METER RUNS............................................................................................134
8.2.4 PREFABRICATED OF SPOOLS FOR WELDING.........................................................134
8.2.5 MEASURING ORIFICES - MEASURING FLANGES....................................................135
8.3 WELDING........................................................................................................135
8.3.1 TACK WELDING ON VALVE SIMULATORS..............................................................135
8.3.2 LONGITUDINAL WELDS ON PIPE HALF SHELLS....................................................135
8.3.3 THERMOMETER BRANCH (TI).............................................................................135
8.3.4 PREFABRICATED WELDS AT INSTALLATION OF
PREFABRICATED SECTIONS (SPOOLS).................................................................135
8.4 FLANGED JOINTS............................................................................................135
8.4.1 REPLACEMENT OF BOLTS....................................................................................135
8.5 VALVES.............................................................................................................136
8.5.1 ROTATING THE VALVE INSTALLATED....................................................................136
8.5.2 EXPANSION JOINTS WITH FLANGED ENDS...........................................................136
8.6 WALL PASS FOR PIPES...................................................................................136
8.7 MISCELLANEOUS.............................................................................................136
8.7.1. FABRICATION AND INSTALLATION OF PIPE HOLDERS,
HANGERS, AND SUPPORTS (to 100 kg per item)...................................................136
8.7.2 DISMANTLING OF PIPE HOLDERS, HANGERS, AND SUPPORTS...............................136
8.7.3 HOLE DRILLING IN CONCRETE............................................................................136
8.8 EXTRAS............................................................................................................136
8.8.1 CHANGE IN BILL OF QUANTITIES BEFORE THE
CLIENT'S APPROVAL FOR FABRICATION..............................................................136
8.8.2 CHANGE IN ISOMETRY PRIOR TO THE
CLIENT'S APPROVAL FOR FABRICATION...............................................................136
9
8.8.3 HAND DRAFTING OF ISOMETRY ACCORDING
TO THE CLIENT'S INSTRUCTION..........................................................................137
8.8.4 INSTALLATION OF MISSING MATERIAL.................................................................137
8.8.5 PIPING MODIFICATION.......................................................................................137
8.8.6 SAND BLASTING HANDLING, PRIMER COAT ON PIPING, AND PIPE SUPPORTS...........137
8.8.7 UNDERGROUND PIPING......................................................................................137
8.8.8 FACTORS FOR CALCULATION OF MAN HOURS FOR
PREFABRICATION AND INSTALLATION OF PIPING................................................138
TABLE Item. 3.10 MULTIPL. FACTORS FOR DIFF. KIND OF MATERIALS.................139
FORMS FOR CALCULATION OF MAN HOUR RATES...................................................142
1.0 PIPES......................................................................................................142
2.0 FITTINGS................................................................................................142
3.0 FLANGES.................................................................................................143
4.0 SMALL FITTINGS......................................................................................143
5.0 VALVES....................................................................................................144
6.0 PIPE EXPANSION JOINTS AND FLOWRATE METERS....................................145
7.0 OTHER INSTALLATION WORKS.................................................................145
8.0 ESTIMATE POINTS FOR BUILD-IN ITEMS OF A. G. PIPING.........................147
CHAPTER XIV. FACTORS AND MAN HOURS FOR PIPING AND STEEL
STRUCTURE WORKS IN CALL FOR TENDERS OF "TECHNIP" COMPANY......230
A. PIPING BETWEEN PLANTS AND IN PLANTS...........................................................230
B. STEEL STRUCTURE ERECTION.............................................................................232
10
INTRODUCTION
With proper and conscientious application of these data for making estimates, the estimator will calculate
hourly time requirements i.e. the man hours required for the erection.
The man hours (Mhr) do not refer to any condition or PRODUCTIVITY EFFICIENCY PERCENTAGES (PEP,
Leistungsfhigkeit - Prozentsatz), but to precisely determined below stated PEPs.
Man hours in this Manual refer to the following Productivity Efficiency Percentages:
1.1Calculation based on the estimate points of basic erection items and man hours and ef fects
derived thereby
1.2Calculation based on man hours and ef fects for quick calculation and special man hours
1.3Calculation based on man hou rs for piping per inch - diameter (ID)
2.PIPELINES
3.STEEL STRUCTURES
PEP = average 70 %
7. CORROSION PROTECTION
8. THERMAL INSULATION
11
For each project, before the labour value is calculated, the Productivity Efficiency Percentage should
be determined. This is done by the project manager with the assistance of his collaborators.
John S. Page (USA) stated six production elements that have an impact on PEP determination.
They are:
1. Project Management and Supervision
2. Labour Conditions
3. Job Conditions
4. Machinery and Equipment
5. Weather Conditions
6. General Economy (for J. S. P. this is a leading element, which I shall not consider)
2. Labour Conditions
Does the company have a good labour relations man? Has the company sufficient number of skilled
and trained labour? What are the foremen like? Will they be satisfied with their salaries? Will they be
satisfied with accommodation, food, transport? How often will they be able to visit their families?
Estimate the percentage according to the PEP table.
3. Job Conditions
What is the scope of the work and just what is involved in the job? What is the schedule? Is it tight, or
do you have ample time to complete the work? What is the condition of the site? Is it low and muddy,
and hard to drain, or is it high and dry? Does it involve a plant already in operation? Will there be tie-ins
to the existing systems? What will the relationship be between the pr oduction personnel and office
personnel? Will most of the operations be manual or mechanized? What kind of material procurement
will you have?
Estimate the percentage according to the PEP table.
5. Weather Conditions
What were past weather conditions for the area? If necessary, can they be
checked? What future weather forecasts? Will there be much rain or snow? What
differences are expected in the weather with regard to Central Europe - Zagreb?
Estimate the percentage according to PEP table. When we have considered and analysed all the
percentages, we have to divide the total sum by five to arrive at an average percentage of productivity
that is the Productivity Efficiency Percentage (PEP).
Dividing the PEP declared by the average PEP we obtain a factor. This factor is
multiplied by the calculated man hours (MHr) and will give actually needed man
hours (MHr). The number of hours can be either increased or decreased.
12
ABBREVIATIONS & UNITS
Notice:
Decimal numbers are listed with a comma (European way).
13
I. PIPING ABOVE GROUND
DERIVED OPERATING TIME STANDARD FOR TABLES FACTOR OF BASIC ASSEMBLY
POSITION CHAPTER X, ACCORDING TO FORMS ON PAGE 142 146
Productivity efficiency percentage (PEP) = 80% FOR PREFABRICATION : 8%
1. PIPES (ANSI B 36.10) FOR INSTALLATION : 92%
1.1 PIPE INSTALLATION ON PROCESS PLANT [Mhr/m]
14
250 10 273 10
300 12 323,9 12
350 14 355,6 14
400 16 406,4 16
450 18 457 18
500 20 508 20
550 22 559 22
600 24 610 24
650 26 660 26
700 28 711 28
750 30 762 30
800 32 813 32
850 34 864 34
900 36 914 36
15
300 12 323,9 12
350 14 355,6 14
400 16 406,4 16
450 18 457 18
500 20 508 20
550 22 559 22
600 24 610 24
650 26 660 26
700 28 711 28
750 30 762 30
800 32 813 32
850 34 864 34
900 36 914 36
16
350 14 355,6 14
400 16 406,4 16
450 18 457 18
500 20 508 20
550 22 559 22
600 24 610 24
650 26 660 26
700 28 711 28
750 30 762 30
800 32 813 32
850 34 864 34
900 36 914 36
17
250 10 273 10
300 12 323,9 12
350 14 355,6 14
400 16 406,4 16
450 18 457 18
500 20 508 20
550 22 559 22
600 24 610 24
650 26 660 26
700 28 711 28
750 30 762 30
800 32 813 32
850 34 864 34
900 36 914 36
18
350 14 355,6 14
400 16 406,4 16
450 18 457 18
500 20 508 20
550 22 559 22
600 24 610 24
650 26 660 26
700 28 711 28
750 30 762 30
800 32 813 32
850 34 864 34
900 36 914 36
19
300 323,9 5,6\7,1 323,9
350 355,6 5,6\8 355,6
400 406,4 6,3\8,8 406,4
450 457 6,3\10 457
500 508 6,3\11 508
550 559 6,3\12,5 559
600 610 6,3\12,5 610
650 660 7,1\14,2 660
700 711 7,1 711
750 762 8 762
800 813 8 813
850 864 8,8 864
900 914 10 914
Materials: k
Man hour include next activities: - Stainless steel [Mhr/m] x 1,10
- handling - erection - High temp. alloy steel [Mhr/m] x 1,10
Mhr/m x 0,3048 = Mhr/ft
- on-site transport - welding - Prewrapped [Mhr/m] x 1,15 (underground install.)
- prefabrication - pressure testing - Galvanized [Mhr/m] x 0,70
- Aluminium alloy [Mhr/m] x 0,85
1. PIPES (DIN 2448/2458) FOR PREFABRICATION : 8%
1.1 INSTALLATION IN PROCESS PLANT [Mhr/m] FOR INSTALLATION : 92%
20
350 355,6 5,6\8 355,6
400 406,4 6,3\8,8 406,4
450 457 6,3\10 457
500 508 6,3\11 508
550 559 6,3\12,5 559
600 610 6,3\12,5 610
650 660 7,1\14,2 660
700 711 7,1 711
750 762 8 762
800 813 8 813
850 864 8,8 864
900 914 10 914
Materials: k
Man hour include next activities: - Stainless steel [Mhr/m] x 1,10
- handling - erection - High temp. alloy steel [Mhr/m] x 1,10
Mhr/m x 0,3048 = Mhr/ft
- on-site transport - welding - Prewrapped [Mhr/m] x 1,15
- prefabrication - pressure testing - Galvanized [Mhr/m] x 0,70
- Aluminium alloy [Mhr/m] x 0,85
1. PIPES (DIN 2448/2458) FOR PREFABRICATION : 8%
1.2 INSTALLATION ON PIPE RACK OR SLEEPER WAY [Mhr/m] FOR INSTALLATION : 92%
21
350 355,6 5,6\8 355,6
400 406 6,3\8,8 406,4
450 457 6,3\10 457
500 508 6,3\11 508
550 559 6,3\12,5 559
600 610 6,3\12,5 610
650 660 7,1\14,2 660
700 711 7,1 711
750 762 8 762
800 813 8 813
850 864 8,8 864
900 914 10 914
22
350 355,6 5,6\8 355,6
400 406,4 6,3\8,8 406,4
450 457 6,3\10 457
500 508 6,3\11 508
550 559 6,3\12,5 559
600 610 6,3\12,5 610
650 660 7,1\14,2 660
700 711 7,1 711
750 762 8 762
800 813 8 813
850 864 8,8 864
900 914 10 914