Form Work
Form Work
Form Work
falling formwork materials. Formwork must be For example, the normal weight of liquid concrete
braced to ensure stability, especially under windy is 150 lb per cubic foot (2,403 kg per cubic metre).
conditions. Try to avoid areas where work such as So a form designed to withstand 600 lb per square
hoisting or stripping is being done overhead. feet (2929 kg per square metre) of pressure will be
Fall injuries All of the injuries above, and many able to support liquid concrete up to a height of 4
others, can result from falls. Most falls are caused feet (1.2 metres).
by missing or inadequate guardrails, failure to use
600 lb/ft2 150 lb/ft3 = 4 ft
fall-arrest equipment, failure to completely plank
scaffolds and other work platforms, and standing 2929 kg/m2 2403 kg/m3 = 1.2 m
or climbing on surfaces not meant to be used as Other factors determine how long concrete
such the tops of wall forms or 2 x 4 wales, for will remain liquid, such as temperature, slump,
example. Installing and stripping formwork often vibration, and admixtures. For example, concrete
requires the use of a fall-arrest system. will set much more quickly in hot summer weather
Falls also result from holes left unguarded or than in cold winter weather. As a result, the same
uncovered in formwork. These should be covered form filled at the same pour rate may be subjected
up or fitted with guardrails as quickly as possible. to greater pressure in winter than in summer.
Where this cannot be done, the area should
be roped off and posted with warning signs to Concrete pumping may cause additional pressure,
prevent unauthorized entry. as well as vibration, on forms and must be
considered at the design stage. The action of the
pump sends surges of pressure through the piping
Planning system which are often transmitted directly to
Planning is the first and most important step in the forms, especially for narrow walls or columns.
reducing hazards and preventing injuries. Vibration may move the forms or loosen bracing,
ties, or spreaders.
Because formwork operations must often be
carried out in congested areas where other trades Pressure acts perpendicular to formwork surfaces
are also working, planning is essential in making the (Figure 42-2). This causes an outward thrust for
most of the time and space available to improve typical wall or column forms. However, it can also
safety and efficiency. cause uplift for battered or sloping forms. These
require hold-down anchors or tie-down braces. The
Planning is a must for fall protection, work anchors will prevent the forms from lifting up or
platforms, material staging areas, housekeeping, floating on the concrete.
and material handling and movement.
Planning should take place at every level from
manager to supervisor to worker. Planning labour, Expansion Anchors Holding
materials, equipment, and work schedules to Down Battered Form
meet design requirements is the responsibility of
management and supervision. But supervisors and
workers should come together to plan the details
of their assigned tasks based on the most effective
work methods and safety measures.
Design
Safety and economy are the main factors in design. Figure 42-2: Pressure of Concrete on
Both have to be considered because adjustments in Vertical (left) and Battered Formwork
one affect the other.
For example, reducing the support structure for Consider using bracing systems and spreaders for
wall forms in expectation of reduced pouring rates wall forms. Concrete filling the bottom of the form
should not be considered if the rate of pour is not may cause forces at the top to push the two sides
going to be controlled on the job. together unless they are properly braced and/
or separated with spreaders. Formwork has to be
Fresh concrete exerts a pressure on formwork designed to resist such forces. During pouring,
similar to liquids. Concrete starts to set when ensure that spreaders are not removed until concrete
poured. So if the pour rate is slow, the maximum has reached at least two-thirds of the form height.
formwork design pressure can be reduced, since
concrete at the bottom will be set before concrete Where box forms are usedfor instance, on one-
at the top is poured. Similarly, if the forms are piece covers for open-cut tunnelsyou must use
filled to the top immediately, they must be able to bracing against the side thrusts caused by the
withstand the pressure of the full liquid head. uneven pouring rates of the walls. Resisting these
forces requires that the system be tied together
and securely braced (Figure 42-3).
Types of Formwork
Below Grade
The first concern with formwork below grade is
the stability of the excavation walls. Walls must be
either shored or sloped according to soil type as
defined by section 226 of the Construction Projects
regulation (O.Reg. 213/91). Figure 42-7 shows
typical slopes.
Fairly
Good Soil
Good Soil
Max
1.2m
(4 ft.)
Type 1 & 2 Soil
Type 3 Soil
Poor Soil
Figure 42-8: Formwork Roped-Off
from Other Operations
Type 4 Soil
Figure 42-7: Excavation Slopes for Soil Types Mud sills must be used to support any shoring or
bracing that rests on soil in the excavation (Figure
In most cases the shoring must be designed by an 42-9). The sill must bear on the soil throughout its
engineer. Engineers may also specify slopes for length. Sills should not be used to bridge holes or
excavations. In both instances the design drawings irregular surfaces. To ensure uniform bearing, soil
must be kept on the project. should be levelled before sills are set in position.
Wall Forms
Wall forms built in place are hazardous to
construct. Hazards include Figure 42-12: Temporary Bracing at
Dowels sticking up from concrete slabs or Start of Form Construction
footings
Unstable work surfaces and access created by Access to wall forms is not always given enough
poor planning thought. Forms more than 2 metres high will
Manual handling of heavy material such as require access platforms for workers involved in
plywood sheets, panels, wales, and buckets of concrete placing. The platforms can also be used
snap-ties, wedges, and plates to complete the upper portion of the formwork.
Slippery surfaces at and below grade
An alternative is a frame scaffold, which can also
Inadequate design
be used to install reinforcing steel (Figure 42-13).
Improper construction.
The best protection against dowels is a wood
cover built of lumber at least 1 1/2 inches thick and
wired in place or protective caps placed over the
exposed ends of rebar (Figure 42-11).
Flying Forms
Flying forms must always be designed by a Figure 42-24: Temporary Support of Shoring
professional engineer and constructed, hoisted, System for Flying Wall Form
moved, and set strictly according to the
instructions of the designer or manufacturer. One example is setting up trusses for a flying slab
formwork table. The trusses must be held upright
to be connected or disconnected. If not adequately
supported, they can fall over on workers.
Trusses and wall panels have also been blown over
by wind during fabrication and dismantling. Set-
up procedures should indicate the maximum wind
speed where the flying form operation can be done
safely. This wind speed should be determined by the
professional engineer who designed the system.
Work with flying forms requires adequate space
for stacking materials and components. Working in
cramped quarters is not only difficult but hazardous.
Fall Protection
A fall arrest system should be used by any worker
who is at risk of falling when:
Installing a panel
Pushing a panel out toward the slab edge
Pulling a panel in from the slab edge (Figure
42-24)
Helping other workers attach rigging hardware Figure 42-26: Rebar Anchor Cast in Concrete
such as slings
Getting on and off
Bolting and unbolting wall forms for exterior walls Safety Below Flying Forms
and elevator shafts (Figure 42-25) The previous section covered the safety of workers
Stepping onto a panel to attach slings to pick flying the forms. But precautions must also be
points taken to protect workers below the hoisting
operation and the public at large, since forms are
often swung out over sidewalks and streets. The
Construction Projects regulation (213/91, s. 103(2))
prohibits hoisting a load over the head of a person
who is not receiving the load or sinking a shaft.
The most efficient protection for workers is to
fence or rope off the area below the flying form to
prevent anyone from entering the area. Pedestrian
traffic on sidewalks, as well as vehicle traffic if
necessary, should be detoured around the area
while hoisting is under way.
Communication
Flying forms are heavy, large, and awkward to
move. Hoisting and moving them safely requires
clear reliable communication. While hand signals
are often necessary and are still used, direct
radio or cell phone communication between the
signaller and the crane operator is more accurate
and effective. Relying on hand signals alone is not
recommended.
Figure 42-24: Fall Protection Required when
Receiving a Flying Form Stripping
Formwork stripping is probably the most
hazardous operation in concrete construction.
Hazards include the following.
Falling material
Waste material and equipment underfoot
Manual handling of heavy or awkward forms,
panels, and other components
Prying forms loose from concrete presents risk of
overexertion, lost balance, and slips and falls.
Hazards can be reduced by
Planning and providing for stripping when
Figure 42-25: Attaching Chain Sling to Wall Form designing and constructing formwork
Stripping as soon as it is permitted by the
Each workers fall-arrest system must be attached engineer
to an individual anchor independent of the flying Supplying facilities and equipment for removing
form. Contractors can provide for anchorage by materials as they are stripped
casting rebar anchors in columns or other areas to Providing proper tools and adequate access for
be covered over or filled in later (Figure 42-26). the stripping crew
This type of anchorage must be approved by a Training personnel properly for this and other
professional engineer. aspects of formwork.
Concrete Placing
Forms should continue being observed during
concrete placing. Any signs of movement, crushing,
cracking, or deflection are cause for alarm. Placing
concrete should be suspended until the situation is
corrected.
Watch for the following warning signs:
Lateral displacement or movement of single-post
shoring for slab forms
Movement or deflection of lateral bracing for
single-post shores
Movement of stringers on U-heads
Crushing of wooden stringers on U-heads
(Figure 42-29)
Gaps or shoring that is not snugged up under
stringers
Deflection of stringers between supports
(Figure 42-30)
Deflection of wales or strongbacks on wall forms
Wall forms that are bulging or cracking
Crushing of wales or strongbacks at washers
for ties
Movement of wall forms
Uplifting of battered forms
Pour rates that exceed design pecifications.