Turn Key PDF
Turn Key PDF
Turn Key PDF
Turn-key Contracts
for the
Realisation of Capital Works Projects
Principally for Public Sector Healthcare Facilities
prepared by
Tony Gibbs
under contract to
The Pan American Health Organisation
with funding from
The United States Agency for International Development
November 2008
An Assessment of Turn-key Contracts
for the Realisation of Capital Works Projects
Principally for Public Sector Healthcare Facilities
by Tony Gibbs BSc DCT(Leeds) FICE FIStructE FASCE FConsE FRSA FRICS
November 2008
1 Preambles
The traditional approach to capital works building projects in Anglo-Saxon countries, including
the Commonwealth Caribbean, is for the owner to have separate contracts for architects,
structural & civil engineering consultants, electrical & mechanical engineering consultants,
quantity surveyors (except in North America) and construction contractors. Occasionally the
design team (architects, structural & civil engineering consultants, electrical & mechanical
engineering consultants, quantity surveyors) are consolidated into one contract. Occasionally
there is added to the team a project manager, although this coordinating role is traditionally
allocated to the architect in buildings for human occupancy. The main construction contractor
would usually have several sub-contractors although these sub-contractor services are sometimes
contracted separately and directly by the owner.
In recent decades there has been a gradual increase in the use of various forms of package
contracts. These various forms will be described in outline in the section which follows.
Because of the increasing use and contemplation of use of package contracts for healthcare
facilities in the Caribbean, the Pan American Health Organisation an assessment of such
arrangements. In particular, this document will outline some of the reasons why package
contracts are used and examine the advantages and disadvantages of such contracts. To the
extent that there are disadvantages, proposals for their mitigation are presented herein.
2 Definitions
The various, more common forms of package contracts are outlined in order of greater inclusion
of services.
3
commencement of the contract.
Turn-key Contract The term turn-key contract encompasses all of the above
variations, and several more Build-Operate-Transfer (BOT);
Build-Operate-Own-Transfer (BOOT);
Rehabilitate-Operate-Transfer (ROT)
1
International Federation of Consulting Engineers (the acronym stands for the French version of the name)
represents globally the consulting engineering industry. As such, the Federation promotes the business interest of
firms supplying technology-based intellectual services for the built and natural environment.
4
states: turnkey contract [bus.] A design and build contract in
which a single contractor is responsible for providing all services,
including finance.
There are a number of reasons why an owner would select a Turn-key Contract for a particular
project. Many of these reasons are well-founded. Some of the reasons may be due to
misconceptions.
Faster Overall Schedule There are at least two scenarios where this is important. If the
project will generate income for the owner, the earlier it could be
put into use, the more favourable the situation. It is easier to fast
track a Turn-key Contract. Construction work could commence
at an earlier stage in the design process.
5
exchange for losing some control over the design.
Single Responsibility Turn-key contracts take many forms. There are differences in
financing structures, procurement procedures, completeness of
design at the time of contract start, internal arrangements between
designers and builders, responsibilities for operating the facility
and long-term maintenance of the facility are some of the issues.
However, there is one essential characteristic of Turn-key
contracts a single point of responsibility for design and
construction.
Innovation New and unique design and construction processes can more easily
be incorporated in projects where the designer and builder are
contractually joined together. Introducing construction contractor
knowledge and experience early into the design fosters creativity
6
and innovation.
Owners Capability When the project is outside of the owners previous experience and
when the owners in-house technical resources are unable to
monitor the work of designers and constructors, a Turn-key
Contract may provide a degree of comfort.
If the owner is considering utilising a Turn-key Contract for a particular project, it is highly
desirable (some may say essential) that the following questions be tabled, discussed and
answered before making a final decision. The questions should be answered pragmatically,
objectively, avoiding over-optimism and political pressures.
Project Timing The questions which follow deal with the projects time horizon:
! Can there be significant time savings by carrying out
design and construction concurrently?
! Will constraints from the owners human resources affect
the project schedule?
! Are there deadlines for the start and end of the project?
! Can potential time savings actually be realised?
Complexity The owner should review the technical complexity of the project.
Here are some questions to be answered:
! Does the project include several distinct and different
features eg buildings, treatment plants, access roads?
! Are the different features closely related?
! Will construction scheduling be a major issue?
! Does the site have unusual conditions?
! Are specialist skills required for design and construction?
! Are specialists available in the locality of the project?
7
use of accelerated construction schedules?
Scope At the end of the deliberations over the previous questions, should
the decision be taken to proceed with a Turn-key Contract, the
owners team should conclude this exercise by preparing a formal
project scope. The steps to be taken and documented could be
those listed below:
! Agree on the single most important for the project cost,
schedule or quality.
! List the reasons for deciding on a Turn-key approach.
! List the potential benefits of using the Turn-key approach
as well as the owners actions required to realise those
benefits.
! List the major components of the project.
! List the essential functions associated with each
component.
! List the design constraints associated with each component.
! For each essential function list the performance
requirements that define that function.
! For each performance requirement, list the performance
criteria necessary to satisfy the requirement.
PFI The PFI model for public projects is only likely to be applicable
where:
! The private sector has the expertise to deliver and there is
good reason to think it will offer value for money;
! The structure of the project is appropriate, allowing the
public sector to define its needs as service outputs that can
be adequately contracted for in a way that ensures
effective, equitable and accountable delivery of public
services in the long term;
! It can be demonstrated that PFI offers greater value for
money for the public sector compared with other forms of
procurement;
! The nature of the assets and services which form part of the
PFI scheme are capable of being costed on a whole-of-life,
long-term basis.
8
made it too difficult to establish long-term requirements.
5 Potential Advantages
It must be recognised that the advantages to be gained (potentially) from utilising various forms
of Turn-key contracts usually require complementary actions on the part of the owner.
Some of the advantages of Turn-key contracts are already described in Section 3 Reasons for
Using Turn-key Contracts. They include Faster Overall Schedule, Single point of
Responsibility, constructability and innovation.
Cost Considerations The project cost could be fixed before detailed design is well
advanced. By giving one entity total control over scope, design
and budget reduces the likelihood of scope-related price changes.
Disputes The owner should be relatively sheltered from liability arising rom
design errors or omissions. No longer is the designer an agent of
the owner. Turn-key contract reduce the possibility of adversarial
relationships between the designer and builder.
Size and Complexity Many owners do not have the in-house knowledge and experience
to manage large or complex projects involving separate contracts
for several design entities and construction contractors. Dealing
with one entity would reduce the administrative burden.
Sharing Risk Where the sharing of risk is done appropriately and effectively, it
is the key to ensuring that the value-for-money benefits in PFI
projects are realised. There are certain risks that are best managed
9
by government in a public sector project. To seek to transfer these
risks would be counterproductive in terms of costs.
The key risks that the public sector should not seek to transfer are
usually:
! the need for the facility on the date given and the adequacy
of its overall size to meet the public service needs
! the possibility of a change in public sector requirements in
the future
! whether the standards of delivery set by the public sector
sufficiently meet public needs
! in most cases the extent to which the facility is used or not
over the contracts life
! general inflation risk
The key risks that the public sector usually seeks to transfer by
contract to the private sector over the term of the contract should
be specifically identified and limited. This could be the following:
! meeting required standards of delivery
! cost overrun risk during construction
! timely completion of the facility
! underlying cost to the operator of the service delivery, and
the future costs associated with the asset
! risk of industrial action or physical damage
! in limited cases, certain market risks
Private-sector Skills With Private Finance Initiative the public sector can harness the
private sector to deliver investment in better quality public services
while maintaining frontline services in the public sector. The
10
public sector defines what is required to meet public needs and
remains the client throughout the life of the contract.
Long-term Maintenance PFI ensures that contractors are bound into long-term maintenance
contracts and shoulder the responsibility for the quality of the work
they do.
Under-investment PFI provides government with a vehicle for reversing the legacy of
under-investment in public-service infrastructure. This legacy has
resulted in falling standards in hospitals, schools and other public-
service assets.
PFI Potential In the right circumstances, and where effectively used, PFI can
help ensure:
! new services are more likely to start on time, since the
private-sector contractor does not get paid until it delivers;
! more efficient use of public money. Under PFI the public
sector only pays for the service for which it has contracted,
at the stipulated price, and only when the service is
available;
! contractors have the incentive to deliver the required
service over a long-term life of the asset. The private
sector contractor only gets paid if it maintains standards
throughout the length of the contract (eg 25 years in the
case of a new PFI hospital). This means that in designing,
building and maintaining aq PFI hospital the private sector
has a strong incentive to high standards are built in and
maintained across the buildings long life. (If an operating
theatre in a PFI hospital is unavailable, a deduction would
be made from the unitary charge paid to the contractor until
the theatre is again in full working order.)
6 Disadvantages
11
is right, and users tend to accept it because they are led to
believe in the expertise of the providers. Users who
discover problems when using facilities tend to suffer in
silence rather than blame openly the providers. Providers
tend to blame owners for not correctly using and
maintaining the facilities. Providers often win the silent
battle between themselves and the owners. In Appendix I
is reproduced a table prepared by architects Kernohan,
Gray, Daish and Joiner illustrating cultural differences
between owners (users) and Turn-key contractors
(Providers). These can pose problems, especially when the
control over design is handed to another party, as in the
case of Turn-key contracts.
Restricted Pool of Bidders Turn-key contracts can require the provision of many items and
services, including the provision of land, obtaining planning
permissions, designs, long-term finance, construction, equipment,
commissioning services, long-term maintenance, and long-term
management of the facility for up to (say) 25 years. At a
minimum, the Turn-key contractor must supply design and
construction services. The availability of suitable and willing
contractors to bid on a project is inversely proportional to the
number of distinct services they are required to provide.
Therefore, one of the important disadvantages of Turn-key
contracts is the narrowing of the field on candidates. There are
cases where this narrowing actually causes the project to be
cancelled in its Turn-key form.
Bid Costs and Times High bid costs and long procurement times represent concerns for
both the public and private sectors. These costs are eventually
passed on to clients. Thus they impair value for money for the
public sector and limit contractors capacity to bid for projects.
Bid costs are higher and procurement time scales are longer than
for conventional procurement.
Complete Design There are projects where there the final design must be completed
before an accurate estimate of cost can sensibly be made. If the
bidders are encouraged to submit tenders which allow for a high
degree on uncertainty, the owner would end up probably paying
too much for the facility. This is so because the design-builder
would have to include a large contingency sum to cover those
uncertainties. The other, equally unsatisfactory, scenario is that
one of the competing bidders underbids the project. In both cases
the owner would be faced with difficult decisions.
12
Owner Input The owner may want significant input in the design. Successful
Turn-key projects necessitates the design-builder to own the
details of design. There is an assumption of trust between the
owner and the contractor. If the owner attempts (or needs) to
influence the details of design after the award of the contract, there
could be negative cost implications and a breakdown in
relationships.
Small Projects Projects that are too small to attract competent Turn-key
contractors should utilise the tradition procurement processes. The
design-builder is taking on more risk than usual. The project must
be large enough to a commensurate reward.
13
! the duration and phasing of investment, where high
technology projects have a short life, and include
significant asset refresh, makes defining and enforcing
long-term service needs problematic.
Procurement Periods Long lead times for procurement can be associated with PFI
contracts. Extended procurement periods can be the result of:
! the increased complexity of procuring a PFI project,
including securing the necessary technical, legal and
financial advice and conducting contract negotiations;
! the need for the public sector to specify carefully its actual
service requirements, rather than provide a prescriptive
design specification.
With the gradually increasing use of Turn-key contracts for hospitals and other large capital
projects in the Caribbean and elsewhere, it is appropriate to provide some guidance towards
improving the success of such projects.
Procurement Skills Strong procurement skills are required from owners for
delivering quality investment on time and in a way that
secures value for money for the public sector. It is
important that the owner has the capacity and the support
needed for effective PFI procurement. PFI requires
relevant expertise long-term options appraisal, significant
use of specialist advisers and probably complex contract
negotiations reflecting the owners approach to risk
sharing.
14
the contract from its start. All essential matters should be
settled at this time.
Objectives The owner has four main objectives when establishing the
performance scope of work in a Turn-key contract:
! Develop a clear project description in functional
terms.
! Define operational and quality requirements in
performance terms.
! Define all the projects requirements without
relying on the post-award process.
! Outline the performance/acceptance tests required
that will demonstrate the requisite level of quality
for each item of work.
Performance Categories There are essentially four types of performance criteria that
15
must be developed for every Turn-key project:
! Management
! Schedule
! Technical
! Cost
Management Criteria This category can be broken down into six major areas:
! Applicable technical design experience
! Applicable technical construction experience
! Turn-key experience
! Experience working with current Turn-key partners
as a team
! Experience working for the owner
! Experience in the projects geographic location
16
persons preparing the technical criteria for the bid
documents should answer the following questions:
! Which requirements are minimum or threshold
requirements?
! What is each threshold?
! Are there maximum requirements?
! What design constraints will apply?
Value for Money The public sector should aim at achieving the optimum
combination of whole-life cost and quality (fitness for
purpose) to meet the user requirements. It should seek to
ensure that:
! the evaluation of which procurement option to
17
adopt is undertaken with no inherent preference for
one over another;
! value is not taken to be the least cost;
! a full evaluation of costs and benefits on a whole-
life basis is undertaken, including an assessment of
risk.
Employee Protection PFI projects sometimes have the potential of affecting the
terms and conditions of current employees in the system.
The following guidelines are provided to address this
potential problem:
! Be open with staff by providing greater
transparency about workers rights.
! Protect the terms and conditions for both transferees
and new joiners to PFI workforces.
! Protect staff pensions.
! Retain flexibility in public service delivery,
including through PFI, to ensure efficient workforce
management and encourage innovation in service
delivery.
18
Oversight/Checking Consultant The role of the oversight/checking consultant is essential in
Turn-key contracts. This is to be emphasised in geographic
locations (such as the Caribbean) where there are multiple
hazards to be accommodated, with the corresponding need
for significant care and attention to detail in all aspects of
design, construction and maintenance of the built
environment.
19
Appendix I
Cultural Differences:
Comparison of Providers and Users Attitudes and Beliefs
with respect to Facilities
Appendix II
Detailed Engineering:
Check List for Designing to Counteract Natural Hazards
(Earthquakes, Hurricanes and Torrential Rains)
APPENDIX II
DETAILED ENGINEERING
1.1 History
1.1.1 Earthquake
1.1.2 Hurricane
1.1.3 Torrential rain
1.2 Geology
1.3 Tectonics
2 Site Conditions
2.1 Soils
2.1.1 Liquefaction
2.1.2 Seismic characteristics
2.2 Topography
2.2.1 Landslide
2.2.2 Building on slopes
2.2.3 Topographic effect on wind speeds
2.2.3.1 Ridges
2.2.3.2 Valleys
2.2.4 Flood prone areas
23
2.2.4.1 Torrential rains
2.2.4.2 Storm surge
2.2.4.3 Tsunami
3.1 Function
3.2 Cost
3.3 Reliability
3.3.1 Serviceability for different components of the facility
3.3.2 Safety for different components of the facility
4 Design Philosophy
24
5 Choice of Form or Configuration
Poor design concepts can be made safe but are unlikely to perform really well in strong
earthquakes
25
5.2.7.4.2 Deep re-entrant angles
5.2.7.4.3 Establish structural breaks (create rectangular plan forms -
see 5.2.2)
5.2.7.5 H and Y shaped buildings
5.2.7.5.1 Aspect ratios
5.2.7.5.2 Deep re-entrant angles
5.2.7.5.3 Establish structural breaks (create rectangular plan forms -
see 5.2.2)
5.2.7.6 External access stairs
5.2.7.7 False symmetry - regular perimeter masking irregular positioning
of internal elements
5.2.8 Soft storey
5.2.9 Cantilevers to be designed conservatively
5.2.10 Desirable roof shapes for hurricane resistance
5.2.10.1 Steep pitched roofs (20 - 40 degrees)
5.2.10.2 Hipped roofs are preferable
5.2.10.3 Gable roofs are an acceptable compromise
5.2.10.4 Mono-pitched roofs are undesirable
5.2.10.5 Boxed eaves recommended for overhangs exceeding 450mm
5.2.10.6 Parapets reduce wind uplift
5.2.10.7 Ridge ventilators reduce internal pressures
6 Choice of Materials
6.3 Costs
6.4 Politics
26
6.5.2 High strength-to-weight ratio
6.5.3 Homogeneous
6.5.4 Ease of making connections
6.5.5 Durable
7 Construction Considerations
7.1 Supervision
7.2 Workmanship
8 Components
8.2 Foundations
8.2.1 Continuous
8.2.2 Isolated (to be avoided)
8.2.3 Piled
8.4 Diaphragms
8.6 Welded beam-column joints for moment-resisting steel frames (to be avoided)
27
8.7 Shear walls and cross bracing
9 Elements
9.1 Structure
9.2 Architecture
9.3 Equipment
9.3.1 Electrical feed to be kept clear of roof structure
9.3.2 Electrical feed to be routed underground within the property
9.4 Contents
10 Cost Considerations
11 Analysis
28
11.6 Stress concentrations
12 Detailing
12.5 Shelving
13 Construction Quality
14 Maintenance
29
Appendix III
Earthquakes:
Check List for Non-structural Components for Earthquakes
APPENDIX III
EARTHQUAKES
This Appendix constitutes a list of items and issues to be considered in designing the
non-structural components of healthcare facilities to counteract the effects of
earthquakes. Check lists are valuable as aides-mmoire for the exercise. For any
particular project all of the items may not be relevant, but excluding items from a
comprehensive list is always easier than adding relevant items to a short list.
1 Electricity
1.1 Generator
1.1.1 Anchorage of the emergency generator
1.2 Batteries
1.2.1 Attachment of the batteries to the battery rack
1.2.2 Cross-bracing the rack in both directions
1.2.3 Battery rack bolted securely to a concrete pad
2 Fire Fighting
31
2.1.1 Properly mounted
2.1.2 Control system and fire doors securely anchored
3 Propane Tanks
4 Plumbing
4.2 Pumps
4.2.1 Anchored or mounted on vibration isolation springs with seismic lateral restraints
32
4.3.5 Free of asbestos insulation (which can be broken in an earthquake)
5 Elevators
5.1 Cab
5.1.1 Properly attached to the guide rails
5.1.2 Alarm system for emergencies
6 Air Conditioning
6.3 Ducts
6.3.1 Laterally braced
6.3.2 Able to accommodate movement at locations where they cross separation joints
6.4 Diffusers
6.4.1 Grills anchored to the ducts or to the ceiling grid or to the wall
6.4.2 Hanging diffusers adequately supported
33
7.2 Stud-wall and other Lightweight Walls
7.2.1 Partial-height partitions braced at their top edges
7.2.2 If they support shelving or cabinets, securely attached to the structure of the
building
8.1 Ceilings
8.1.1 Suspended ceilings with diagonal bracing wires
8.1.2 Plaster ceilings with the wire mesh or wood lath securely attached to the structure
above
8.2 Lighting
8.2.1 Light fixtures (eg lay-in fluorescent fixtures) with supports independent of the
ceiling grid
8.2.2 Pendant fixtures with safety restraints (eg cables) to limit sway
8.2.3 Emergency lights mounted to prevent them falling off shelf supports
9.1 Doors
9.1.1 If exit doors are heavy metal fire doors that might jam in an earthquake, provision
of a crowbar or sledge hammer readily available to facilitate emergency opening
9.1.2 Automatic doors with manual overrides
9.1.3 Directions in which the doors swing
9.2 Windows
9.2.1 Glazing designed to accommodate lateral movement
9.2.2 Large windows, door transoms and skylights with safety glass
34
10.3.1 Signs adequately anchored
10.3.2 Heavy and/or tall sculptures anchored to prevent overturning
11 Movable Equipment
11.1 Communications
11.1.1 Radio equipment restrained from sliding off shelves
11.1.2 Telephones placed away from edges of desks and counters
11.1.3 Elevated loud speakers and CCTV anchored to the structure
11.2 Computers
11.2.1 Vital computer information backed up regularly and stored off site
11.2.2 Heavy computer equipment of significant height relative to width anchored or
braced
11.2.3 Desktop items prevented from sliding off tables
11.2.4 Access floors braced diagonally or with seismically-certified pedestals
11.5 Furniture
11.5.1 Heavy potted plants restrained from falling or located away from beds
11.5.2 Beds and tables and equipment with wheels provided with locks or other
restraints to prevent them rolling unintentionally
35
Appendix IV
Hurricanes:
Check List for Non-structural Components for Hurricanes
APPENDIX IV
HURRICANES
This Appendix constitutes a list of items and issues to be considered in designing the
non-structural components of healthcare facilities to counteract the effects of hurricanes.
Check lists are valuable as aides-mmoire for the exercise. For any particular project all
of the items may not be relevant, but excluding items from a comprehensive list is always
easier than adding relevant items to a short list.
1 Roofs
NB i In all cases the methods of fixing must, at least, comply with the
manufacturers' recommendations for specified hurricane locations
ii If battens are used, the fastening of the battens to the close
boarding must be at least as strong as the fastening of the covering
to the battens
NB i In all cases the methods of fixing must, at least, comply with the
manufacturers' recommendations for specified hurricane locations
ii If battens are used, the fastening of the battens to the close
boarding must be at least as strong as the fastening of the covering
to the battens
37
2 Windows
2.1 Made of laminated glass fixed to frames with structural silicon and able to resist, without
breaching, the impact of flying objects such as an 8-foot long 2-inch by 4-inch piece of
timber moving at 35 miles per hour (similar to the requirements of Dade, Broward and
Palm Beach Counties of Florida)
or
2.2 Protected by pre-installed or pre-fabricated shutters which are able to resist without
breaching the impact of flying objects such as an 8-foot long 2-inch by 4-inch piece of
timber moving at 35 miles per hour
or
2.3 Made of timber or aluminium louvres with provisions for excluding the rain during storm
conditions and which are able to resist without breaching the impact of flying objects
such as an 8-foot long 2-inch by 4-inch piece of timber moving at 35 miles per hour
3 External Doors
or
38
3.1.5 Tracks of the top and bottom rails deep enough to prevent the moving doors from
being dislodged in specified hurricanes
4 Other Apertures
4.1 Protection from wind and rain provided by pre-installed or pre-fabricated shutters which
are able to resist without breaching the impact of flying objects such as an 8-foot long 2-
inch by 4-inch piece of timber moving at 35 miles per hour
4.2 Shutters secured to the walls, slabs, beams or columns near all corners of each panel or in
accordance with the manufacturers' recommendations for specified hurricane locations
5.1 Certificates from the suppliers indicating compliance with the requirements for the
appropriate intensity of hurricanes for both manufacture and installation
39
Appendix V
1 General
The physical condition of many Caribbean hospitals is poor. Most components show
lack of maintenance and repair. It is considered that a major effort should be taken to
bring the condition of the buildings to the standard where a normal maintenance crew can
be expected to deal with the routine maintenance requirements of the facility. It is
considered, also, that the existing staff and maintenance budget is generally insufficient
to provide for proper maintenance.
It is normal that for public buildings with the heavy usage of a hospital, the annual
maintenance budget should amount to about 4% of the contemporary capital cost of the
building and equipment, assuming that the facilities are in good condition to start with.
For hospitals, it is estimated that the replacement cost is about US$130,000 per bed.
(This figure includes for common and administrative areas as well as infrastructure.) The
maintenance allocation should therefore be no less than US$5,000 per bed per year.
The maintenance of a hospital, rather than being a one-off activity as is the construction
of the hospital, is a continuous daily operation of the institution and is an important
ingredient in the delivery of healthcare.
A good maintenance system is also a good disaster mitigation system, as the review of
damage caused by recent hurricanes and floods has shown. To some extent the damage
to buildings was due to lack of sustained maintenance of critical items. Also, a well-
operated system of maintenance for buildings and equipment has the effect of being a
very effective disaster mitigation measure in terms of cost and facility usage. It ensures
the most economic way to keep the building and equipment in the best of form for normal
use, given the original design and materials. It is essential that a maintenance plan be
included in disaster mitigation plans.
This Manual therefore stresses the need for continuous attention to all parts of the
building and equipment from sweeping of the floors to care of the grounds.
This Manual does not deal with the maintenance needs of off-site electricity, telephone
communications and off-site water supply as maintenance of these lifelines are carried
out by the relevant utility organisations. On the other hand, standby electricity plant and
water systems (storage tanks and pumps) must be maintained by the hospital-
maintenance organisation.
41
2 Proposed Maintenance System
The purposes for maintaining a building and its associated plant are to ensure that the
facility can:
" function at its designed level at all times;
" function for the normal life spans of the building and of the plant;
" resist the effects of extreme natural events such as hurricanes, floods, and
earthquakes without damage to its occupants and with minimal repair or
rehabilitation necessary after the passing of the event (provided that the original
design and construction were satisfactory for this purpose).
All maintenance activities should be systematised and pro-active and not merely reactive.
It is important to recognise that maintenance is not necessarily repair. Too often repair is
considered to be the main purpose of the maintenance system rather than the prevention
of the need for repair. The scheduled oiling of door hinges and window operators or the
painting of exterior wooden members is necessary to prevent failure of the equipment or
rotting of the wooden members.
The planning of the maintenance activities will normally be carried out by the hospital
superintendent but this planning, which should include the development of a detailed
annual maintenance budget, can only be effective if there is a detailed list of areas,
spaces, materials and equipment to be maintained and a list of defects to be corrected.
The maintenance staff must therefore be trained to examine all parts of the buildings and
plant in their care and to record deficiencies. Such lists must be prepared on an annual
basis, but this does not preclude the immediate attention to problems which are endemic
in many hospitals.
It must be emphasised that a careful record of all maintenance activities is essential, and
every effort must be taken to avoid returning to the situation where ad hoc repair is the
norm. The check list given in this Manual is a guide for the detailed examination of all
parts of the facility and should be reviewed by the hospital superintendent and hospital
42
administrator to ensure that maintenance is indeed being carried out efficiently.
Reporting of work done is also an essential part of the maintenance system. A simple
reporting form is included in this Manual but the hospital superintendent may wish to
devise his own form which may be more responsive to the problems in the particular
hospital. It is considered, however, that the simpler the form the better will be the
chances of having the form properly filled out and submitted monthly.
If a good system for maintenance is not properly organised, funded, staffed and carried
out, then all other disaster mitigation methods could prove insufficient. Experience
indicates that roofs, walls, and equipment in general are more vulnerable to failure if
normally operated at near breakdown or at any level of technical deficiency.
While a properly designed and maintained building would be resistant to natural hazards
yet experience shows that some additional precautions may have to be taken to secure the
hospital and allow it to function during and immediately after such events. The principal
areas to be examined for maintaining hurricane resistance (in particular) of the hospital
and the corrective measures to be taken are:
4.1 Roofs
" Examine the doors and windows. They must close tightly.
" Ensure that the operators on louvred windows are all working.
" Replace all broken glass in windows.
Flooding often follows a hurricane. Check to see how high the water reached in previous
heavy rain storms and ensure that drains are cleared to carry the rain water away from the
building and that no storm water can get into the building.
43
Basic assumptions:
" The hospital administrator is responsible to the ministry for the efficient operation
of the hospital (including the general staff matters, buildings, equipment and
grounds) and for the expenditures authorized in the annual estimates.
" The hospital superintendent is responsible for the maintenance of all buildings
and plant and for providing advice to the hospital administrator on capital
requirements and on the condition of the buildings and plant.
" Technical staff (as required) report to the hospital superintendent including:
carpenters
plumbers
electricians
painters
" The gardeners and cleaning staff report to the hospital administrator.
" Major repair or renovation projects must be specifically authorized by the hospital
superintendent and the hospital administrator depending on the budget
requirements, but normal maintenance and minor repair can be carried out by in-
house staff without specific authorization.
It is expected that major renovation work which may be necessary will be contracted out
and not carried out by the regular maintenance staff.
44
The following abbreviations are used in the tables:
Frequency Operator
45
6.1 Building Interior
46
Furniture
47
6.2 Building Exterior
48
Metal Panels
Inspect A MS
Wash and remove graffiti A MS
49
6.3 Compound
Sweep D C
Clear litter and rubbish D C
Drainage Ditches
Clean routinely W C
Clear blockages caused by excessive rain I MS
Repair damaged drains A (in August) MS
Water Mains
50
Erosion near Structures
51
7 Proposed Monthly Report Form
Date: _________________________
Doors
Windo
ws
Roof
Floors
Masonr
y
Electric
ity
Plumbi
ng
52
Paintin
g
Other
trades
53
8 Guidelines for Maintenance Checklists
" Where the walls are made of rubble stone see if the
mortar is in good condition ------- -------
" Check to see if the walls are damaged and need ------- -------
repairing
(c) Ceilings, Interior Roofs, and Canopies
" See if the ceilings and the undersides of the roofs and
canopies have any watermarks which indicate leaks in -------- -------
the roof
-------- -------
" See if any timber supports are rotten
" Where the roof supports are of steel, check to see if -------- -------
there is any rust
-------- -------
" See if any ceiling tiles need replacing
54
Spaces/Materials Good Bad
(d) Plumbing
" Check to see if there is any water on the floor -------- --------
" If there is, examine the wash basin to see if it is -------- --------
plugged
-------- --------
" Examine the WC to see if the bowl is cracked
-------- --------
" See if the flush tank is cracked
-------- --------
" Check to see if the toilet seat cover is broken
-------- --------
" See if the flush handle or pull chain is broken
" See if the toilet bowl is fixed properly to the floor so -------- --------
that it does not rock when being used
" See if the sewer pipe is properly fixed to the toilet and -------- --------
that there is no leaking at the joint
(e) Electricity
" See if all light bulbs are working and that all are in -------- --------
place
-------- --------
" See if the wall plates are in good condition
-------- --------
" See if the wall switches or pull switches are working
-------- --------
" See if wall outlets are working
55
Spaces/Materials Good Bad
(f) Windows
" See if the bolts and locks are in working condition -------- --------
" See if the windows leak even when closed -------- --------
" See if the bolts and locks are in place and are working -------- --------
" See if the door frame is in good condition and that the
timber is not rotten -------- --------
" Where the door is a wood door (brace and batten) see
that the door has not warped -------- --------
" Check the partitions to see if the walls are in good -------- --------
condition
-------- --------
" Report any loose mortar in a rubble wall
-------- --------
" Report any cracked wall
56
Spaces/Materials Good Bad
" Check gutter brackets to see if they are broken or rusted -------- --------
(i) Fence
" With a chain link fence, check to see if the fence is -------- --------
broken
-------- --------
" See if the fence posts are firmly in the ground
-------- --------
" With a timber fence, check for rotten timber
" Check ground to see if there are any wet spots which
would indicate a leaking water main -------- --------
57
Spaces/Materials Good Bad
" Check to see if the tank has been cleaned in the last -------- --------
three years
" See if the access covers fit properly, are in good -------- --------
condition and can be removed for cleaning
" If the access covers can be opened too easily, members -------- --------
of the public may remove the covers wilfully
" See if the holders for the covers will cause people to
trip. The holder should be recessed with just enough -------- --------
room for a pickaxe blade to get under the holder.
" See if the inlet pipe is firmly fixed to the tank and that -------- --------
there is no leak
" Where there is a soak-away check to see if the pipe to -------- --------
the soak-away is firmly bedded
" See if there is any odour around the tank. If there is, the -------- --------
tank needs cleaning or another soak-away should be
dug
-------- --------
" Where there are tile fields, check to see if the pipes
(tiles) are exposed. They should be well below ground
level -------- -------
" See if the tiles are working and that there is no water on
the ground around the pipes
58
Spaces/Materials Good Bad
" Check around the pipes to see if the pipes that were
buried are still properly buried -------- --------
59