SCHEDULE-A
(See Clause 2.1 & 8.1)
1 THE SITE
1.1 Site of the Two-Lane Project Highway shall include the land, buildings, structures
and road works as described in Annex-I of this Schedule-A.
1.2 The dates of handing over the Right of Way to the Contractor are specified in
Annex-II of this Schedule-A.
1.3 An inventory of the Site including the land, buildings, structures, road works, trees
and any other immovable property on or attached to the Site shall be prepared jointly
by the Authority Representative and the Contractor and such inventory shall form part
of the memorandum referred to in Clause 8.2.1 of this Agreement.
1.4 The alignment plans of the Project Highway are specified in Annex-III. In the case of
sections where no modification in the existing alignment of the Project Highway is
contemplated, the alignment plan has not been provided. Alignment plans have only
been given for sections where the existing alignment is proposed to be modified.
1.5 The status of the environment clearances obtained or awaited is given in Annex IV.
Development of Bhopal Berasia Sironj Road of SH -23 from km. 4/100 to km. 110/42 (Design Length 106.320 km) to two lane with paved
shoulder road in the state of M.P. on EPC mode.
Page | A-1
MPRDC Schedules to Concession Agreement
Annex - I
(Schedule-A)
Site for Two-Lanning
1. The Site
1.1 The Site comprises of the section of proposed Bhopal Berasia Sironj road is a segment
of SH-23 having total length of 106.900km. The Project Road for widening and up
gradation of existing road starts from Bhopal (km.4/100) at Karond Junction and
terminates near Sironj (km. 00/000). Under the proposal, existing chainage starts from
Bhopal (km.4/100) to Berasia (km. 40/800) is proposed to be widened to two-lane
carriageway with 1.5m wide Paved Shoulder. For Existing Chainage from Berasia (km
67/000) to Sironj (Km 0/000)is proposed for reconstruction to two-lane carriageway
width with 2.5m wide hard shoulder in rural area on either side of the project road.
1.2 Referencing System
Kilometer stones are existing in entire length of the project highway. It is called the
Existing Chainage. During topography survey with Total Station, observations made
are referred to Design Chainage. The relationship between the Existing Chainage
and the Design Chainage as per field surveys of the location of existing km stones
using the Total Station for the Project Highway is given at Appendix A-I. Total
design length is 106.320km.
2. Land
The Site of the Project Highway comprises the land described below:
Development of Bhopal Berasia Sironj Road of SH -23 from km. 4/100 to km. 110/42 (Design Length 106.320 km) to two lane with paved
shoulder road in the state of M.P. on EPC mode.
Page | A-2
MPRDC Schedules to Concession Agreement
Development of Bhopal Berasia Sironj Road of SH -23 from km. 4/100 to km. 110/42 (Design Length 106.320 km) to two lane with paved
shoulder road in the state of M.P. on EPC mode.
Page | A-3
MPRDC Schedules to Concession Agreement
Development of Bhopal Berasia Sironj Road of SH -23 from km. 4/100 to km. 110/42 (Design Length 106.320 km) to two lane with paved
shoulder road in the state of M.P. on EPC mode.
Page | A-4
MPRDC Schedules to Concession Agreement
3. Carriageway
Chainage Side
S.No.
From To LHS RHS
1 14+400 15+885 1485 1485
2 15+890 17+360 1470 1470
3 17+390 18+380 990 990
4 18+520 19+180 660 660
5 19+400 20+752 1352 1352
6 20+764 23+070 2306 2306
7 23+080 23+740 660 660
8 23+770 25+000 1230 1230
9 25+080 25+680 600 600
10 26+520 26+990 470 470
11 28+060 29+120 0 1060
12 28+385 29+130 745 0
13 29+200 29+720 520 520
14 29+940 30+620 680 680
15 30+780 31+720 940 940
Development of Bhopal Berasia Sironj Road of SH -23 from km. 4/100 to km. 110/42 (Design Length 106.320 km) to two lane with paved
shoulder road in the state of M.P. on EPC mode.
Page | A-5
MPRDC Schedules to Concession Agreement
Chainage Side
S.No.
From To LHS RHS
16 31+760 32+200 440 440
17 32+300 32+825 525 525
18 32+880 34+020 1140 1140
Total Length in Mt. 16213 16528
3.2.2 Reconstruction of existing road has been completed upto WMM level in following
stretches.
Chainage Side
S.No.
From To LHS RHS
1 14+400 14+600 0 200
2 14+600 15+220 620 620
3 15+220 15+885 665 665
4 15+890 17+360 1470 1470
5 17+390 18+380 990 990
6 18+520 19+180 660 660
7 19+400 20+752 1352 1352
8 20+764 23+070 2306 2306
9 23+080 23+740 660 660
10 23+770 25+000 1230 1230
11 25+080 25+680 600 600
12 26+520 26+990 470 470
13 28+080 29+120 0 1040
14 28+385 29+130 745 0
15 29+200 29+720 520 520
16 29+940 30+600 660 660
17 30+780 31+720 940 940
18 31+760 32+200 440 440
Development of Bhopal Berasia Sironj Road of SH -23 from km. 4/100 to km. 110/42 (Design Length 106.320 km) to two lane with paved
shoulder road in the state of M.P. on EPC mode.
Page | A-6
MPRDC Schedules to Concession Agreement
Chainage Side
S.No.
From To LHS RHS
19 32+300 32+825 525 525
20 32+880 33+100 220 220
21 33+100 34+020 920 920
Total Length in Mt. 15993 16488
3.2.3 Reconstruction of existing road has been completed up to DBM level in following
stretches.
Chainage Side
S.No.
From To LHS RHS
1 14+400 14+800 0 400
2 14+800 15+885 1085 1085
3 15+890 17+360 1470 1470
4 17+390 18+380 990 990
5 18+520 19+180 660 660
6 19+400 20+752 1352 1352
7 20+764 23+070 2306 2306
8 23+080 23+740 660 660
9 23+770 25+000 1230 1230
10 25+080 25+680 600 600
11 26+520 26+990 470 470
12 28+080 28+385 0 305
13 28+385 29+120 735 735
14 29+120 29+130 10 0
15 29+200 29+720 520 520
16 29+940 30+600 660 660
17 30+810 31+690 880 880
18 31+775 31+780 0 5
19 31+780 32+200 420 420
Development of Bhopal Berasia Sironj Road of SH -23 from km. 4/100 to km. 110/42 (Design Length 106.320 km) to two lane with paved
shoulder road in the state of M.P. on EPC mode.
Page | A-7
MPRDC Schedules to Concession Agreement
Chainage Side
S.No.
From To LHS RHS
20 32+340 32+820 480 480
21 32+880 34+020 1140 1140
Total Length in Mt. 15668 16368
4. Structures
There are 02 major bridges, 25minor bridges and 124 culverts on the
existing alignment of the project road. The details of existing major &
minor bridges, slab & pipe culverts are shown in Table A-1.
Table A 1
Existing
124 25 02 Nil
Structure
Existing Condition
SI. Type of Structure No. x Spans of Bridge
Existing Overall
No with Span
Chainage (km) width
. Superstructure length (m)
(m)
Good
1 11/8 Solid 6x12.0 8.40
25/4 Good
3 x 10.00 +
2 (B/w Berasia Solid & T Beam 8.40
2 x 24.70
Sironj)
NIL
Development of Bhopal Berasia Sironj Road of SH -23 from km. 4/100 to km. 110/42 (Design Length 106.320 km) to two lane with paved
shoulder road in the state of M.P. on EPC mode.
Page | A-8
MPRDC Schedules to Concession Agreement
NIL
Development of Bhopal Berasia Sironj Road of SH -23 from km. 4/100 to km. 110/42 (Design Length 106.320 km) to two lane with paved
shoulder road in the state of M.P. on EPC mode.
Page | A-9
MPRDC Schedules to Concession Agreement
NIL
Span
Chainage
arrangement
Sr. as per Type of
PWD or Dia. of Pipe Carriageway Width of
Survey Structures
Culvert (m) Width (CW) Culvert
(Pipe/Slab/
No. (m.) (m.)
No. km. Box/Arch)
Vent/
No.
Width
Development of Bhopal Berasia Sironj Road of SH -23 from km. 4/100 to km. 110/42 (Design Length 106.320 km) to two lane with paved
shoulder road in the state of M.P. on EPC mode.
Page | A-10
MPRDC Schedules to Concession Agreement
Type of Span
PWD Chainage Carriageway Width of
Structures arrangement
Sr. Culvert as per Width (CW) Culvert
(Pipe/Slab/ or Dia. of Pipe
No. Survey (m.) (m.)
Box/Arch) (m)
Development of Bhopal Berasia Sironj Road of SH -23 from km. 4/100 to km. 110/42 (Design Length 106.320 km) to two lane with paved
shoulder road in the state of M.P. on EPC mode.
Page | A-11
MPRDC Schedules to Concession Agreement
Type of Span
PWD Chainage Carriageway Width of
Structures arrangement
Sr. Culvert as per Width (CW) Culvert
(Pipe/Slab/ or Dia. of Pipe
No. Survey (m.) (m.)
Box/Arch) (m)
Development of Bhopal Berasia Sironj Road of SH -23 from km. 4/100 to km. 110/42 (Design Length 106.320 km) to two lane with paved
shoulder road in the state of M.P. on EPC mode.
Page | A-12
MPRDC Schedules to Concession Agreement
Type of Span
PWD Chainage Carriageway Width of
Structures arrangement
Sr. Culvert as per Width (CW) Culvert
(Pipe/Slab/ or Dia. of Pipe
No. Survey (m.) (m.)
Box/Arch) (m)
Development of Bhopal Berasia Sironj Road of SH -23 from km. 4/100 to km. 110/42 (Design Length 106.320 km) to two lane with paved
shoulder road in the state of M.P. on EPC mode.
Page | A-13
MPRDC Schedules to Concession Agreement
Type of Span
PWD Chainage Carriageway Width of
Structures arrangement
Sr. Culvert as per Width (CW) Culvert
(Pipe/Slab/ or Dia. of Pipe
No. Survey (m.) (m.)
Box/Arch) (m)
Length
SI. No. Chainage (km) Left Hand Side Right Hand Side
(m)
NIL
12 Truck Lay byes: - NIL
The details of Truck lay byes on the Site are as follows:
Development of Bhopal Berasia Sironj Road of SH -23 from km. 4/100 to km. 110/42 (Design Length 106.320 km) to two lane with paved
shoulder road in the state of M.P. on EPC mode.
Page | A-14
MPRDC Schedules to Concession Agreement
Location Type
SI. No Masonry/CC Earthern
From Km to Km
(Pucca) (Kutcha)
NIL
14 Major junctions: - 05 Nos.
The details of major junctions are as follows:
Development of Bhopal Berasia Sironj Road of SH -23 from km. 4/100 to km. 110/42 (Design Length 106.320 km) to two lane with paved
shoulder road in the state of M.P. on EPC mode.
Page | A-15
MPRDC Schedules to Concession Agreement
Existing
Sr. No. Chainage At Grade Separated Remarks
(Km\m)
11 17 .52 T-Junction V.Road
12 18 .05 T-Junction V.Road
13 19 .41 T-Junction V.Road
14 20.06 T-Junction V.Road
15 20.22 T-Junction V.Road
16 25 .20 T-Junction V.Road
17 27 .75 T-Junction V.Road
18 29 .29 T-Junction V.Road
19 32 .72 T-Junction V.Road
20 33 .65 T-Junction V.Road
21 36 .50 T-Junction V.Road
22 38 .94 T-Junction V.Road
23 63.7 T-Junction V.Road
24 53.9 T-Junction V.Road
25 45.15 T-Junction V.Road
26 42.62 T-Junction V.Road
27 37.82 T-Junction V.Road
28 33.9 T-Junction V.Road
29 28.02 T-Junction V.Road
30 24.9 T-Junction V.Road
31 24.3 T-Junction V.Road
32 22 T-Junction V.Road
33 19.9 T-Junction V.Road
34 16.6 T-Junction V.Road
35 8.8 T-Junction V.Road
36 7.65 T-Junction V.Road
37 2.50 T-Junction V.Road
16 Other Junctions: NIL
The details of otherjunctions are as follows:
NIL
17 Bypasses: - NIL
The details of the bypasses are as follows:
Name of bypass
S. No.
(town) Chainage Length Carriageway
Development of Bhopal Berasia Sironj Road of SH -23 from km. 4/100 to km. 110/42 (Design Length 106.320 km) to two lane with paved
shoulder road in the state of M.P. on EPC mode.
Page | A-16
MPRDC Schedules to Concession Agreement
NIL
Development of Bhopal Berasia Sironj Road of SH -23 from km. 4/100 to km. 110/42 (Design Length 106.320 km) to two lane with paved
shoulder road in the state of M.P. on EPC mode.
Page | A-17
MPRDC Schedules to Concession Agreement
Annex - II
(Schedule-A)
Dates for providing Right of Way
The dates on which the Authority shall provide Right of Way to the Contractor on
different stretches of the Site are stated below:
Development of Bhopal Berasia Sironj Road of SH -23 from km. 4/100 to km. 110/42 (Design Length 106.320 km) to two lane with paved
shoulder road in the state of M.P. on EPC mode.
Page | A-18
MPRDC Schedules to Concession Agreement
Annex III
(Schedule-A)
Alignment Plans
The existing alignment of the Project Highway shall be modified as per the enclosed
alignment plan. Finished road level indicated in the alignment plan are indicative and
the finished road level of the project highway in any case, shall not be less than those
indicated in the alignment plan.
Development of Bhopal Berasia Sironj Road of SH -23 from km. 4/100 to km. 110/42 (Design Length 106.320 km) to two lane with paved
shoulder road in the state of M.P. on EPC mode.
Page | A-19
MPRDC Schedules to Concession Agreement
Annex - IV
(Schedule-A)
Environment Clearances
Development of Bhopal Berasia Sironj Road of SH -23 from km. 4/100 to km. 110/42 (Design Length 106.320 km) to two lane with paved
shoulder road in the state of M.P. on EPC mode.
Page | A-20
MPRDC Schedules to Concession Agreement
Appendix A-I
Development of Bhopal Berasia Sironj Road of SH -23 from km. 4/100 to km. 110/42 (Design Length 106.320 km) to two lane with paved
shoulder road in the state of M.P. on EPC mode.
Page | A-21
MPRDC Schedules to Concession Agreement
Development of Bhopal Berasia Sironj Road of SH -23 from km. 4/100 to km. 110/42 (Design Length 106.320 km) to two lane with paved
shoulder road in the state of M.P. on EPC mode.
Page | A-22
MPRDC Schedules to Concession Agreement
Development of Bhopal Berasia Sironj Road of SH -23 from km. 4/100 to km. 110/42 (Design Length 106.320 km) to two lane with paved
shoulder road in the state of M.P. on EPC mode.
Page | A-23