Main Report
Main Report
INTRODUCTION
Location:
Development Region Western Development Region
Zone Gandaki Zone
District Tanahun District
Village/town Sepa Bagaicha
Right of Bank Barbhanjyang V.D.C (ward no-5), Tanahun
Left of Bank Bhanu V.D.C (ward no-3), Tanahun
Name of the Road: Bhansar-Chandrawati Road
Easting : 539070.4296 (Longitude- 84 23 42.9)
Northing : 3099945.3095 (Latitude- 28 01 06)
Elevation: 450.73m
Type of Bridge: RCC T-Beam (Beam Slab type)
Total Span: 50m (double span 25m each)
No. of main girders 2
No. of Cross Girders 12
Wearing Coat Asphalt Concrete
Bearing Elastomeric bearing
Type of Abutment Reinforced Concrete Abutment
This project lies in Sepa Bagaicha in between of the ward no 5 of Barbhanjyang VDC
and ward no 3 of Bhanu VDC in Tanahun District. The elevation of site is about
450.75 m from sea level and lies at Easting 539070.4296, Northing 3099945.3095
while considering the origin of coordinate 500000 at intersection of 84 center
meridian and equator. This project site is connected by Bhansar-Chandrawati Road
which starting point is Sepa Bagaicha, point of Dumre-Besisahar-Chame (F036) feeder
road. The access road has categorized as "Class-C" road in DTMP report of Tanahun
district.
1
1.1 CHALLENGES AND DRAWBACKS
Although the complete design of bridge is done, the project is still cannot be
adapted for real purpose due to lack of few other important aspects of design and
analysis such as:
The client requires short span economic bridge connecting two VDC's to a main
road, where the temporary connectivity has been assisted by a 16.33 m RC-
slab bridge. The bridge is to be of single lane, no provision of footpath but railings
are needed. Topographical, Hydrological and geo-technical data are provided by
LRBSU. Some of the main features and characteristics of the data provided have
been attached to the report.
2
2. METHODOLOGY
Besides all the assignments the works such as calculation of discharge and SPT
value for the bearing capacity of the soil was also done. Hydrological data were
supplied and suitable stations were used to find out the rainfall data.
3
2.3 STRUCTURAL PLANNING AND PRELIMINARY DESIGN
The design procedure of a bridge is a completely based on the provisions
specified in different codes and guidelines. The major decisions that have to be
made in the process of the design of bridges are the selection of the type of
structure, selection of materials to be used, selection of the type of the
protection works and the road approaches to the bridge. The determining
parameters for the design are hydrology of the catchments area, the hydraulics
of the river, the soil and foundation type and available materials and technology
for the construction.
Prior to commencing on the detailed design of the bridge it is imperative that
standard criteria be followed and certain major decision should be made in
the area of the materials used, technology used and the quality to be
maintained in the construction. These aspects have been considered in the
detailed design of this bridge design.
1. Technical Factors
Technical factors are related to the technical requirements regarding the:
Span coverage of bridge superstructure
Horizontal and vertical clearance of bridge
Sub-soil condition of bridge site
Durability of bridge structure
Time of construction of bridge
Method of construction
2. Economic factors
Cost of labour
Cost of material
Construction detail
Transportation and election cost
Span length and pier height
No. of span
4
Structural system and its cross-section
Time available for construction
Design load
Maintenance cost
3. Environmental factors
They are related to the impact of the structure on the environment during and
after construction. The effects of construction on the marine line, surrounding
human life and plant life are the major concern of environmental considerations
4. Aesthetic Factor
It is related to the quality of beauty and the functionality of bridge structure.
The important aesthetic characteristics and the consideration are:
Appearance
Color
Proportion
Contrast
Scale
Order
Environmental
Functionality
Different types of bridge according to the superstructure and their optimal span
length are as follows:
Type of bridge Span (m)
RC Slab 6-10
RC T-Girder 10-30
Composite 25-40
RC box 30-50
Prestressed Concrete Box 40-80
Arch
- Masonry 15-30
- Concrete 40-70
- Steel 50-100
Cable Stayed 100-200
Suspension 300-2000
Truss 25-300
The choice of an appropriate type of bridge is an important and responsible
step which needs to be considered by the designer. The possible types of bridges
to be adopted for the proposed sites may be as follows:
a. Pre-stressed concrete bridges
b. Reinforced concrete bridge
c. Truss bridge
d. Plate girder bridge
Selection of suitable type of bridge is very difficult subject. It depends upon the
specific site conditions in our case proposed site have following characteristics:
a. Perennial flow of water.
b. Span requirement more than 25 m.
5
c. Probability of coming large sediments during flood is low.
d. Traffic volume is low.
e. Flatter river slope and low depth of water due to flat terrain
As per this bridge site location the RC-T Girder with double span was the most
suitable because of span being greater than 25 m which could be
constructed economically.
RC-T Girder is one of the most reliable, durable and widely used construction
materials in bridge projects around the world.
RC- T Girder bridge is mostly used because of the many advantages such as:
Lower construction cost
Smaller section of the different structural member.
Longer span lengths reduce the cost of the sub structure.
Superstructure:
Carriage way = 4.25 m for single lane
7 m or 7.5m for double lane
Height of railing (h) 1.1m
Width of kerb (b) 0.3m
Width of footpath (b) 0.6m
Df min= 200mm (150mm at tip)
D= 10 to 15 for simple span
= 25 to 20 for continuous span
bw 250mm
6
110 (150mm 300mm)
Spacing of main beam= 2 to 3m
Spacing of cross beam = 3 to 5m
No of cross beam 5
Bearing:
The preliminary planning of bearing is done based on the load from
superstructure. Based on this load the plan dimension and design data are taken
from Annex 1 of IRC 83 1987: Standard specification and code of practice for
road bridges, Section IX, Bearings, Part II: Elastomeric Bearings, 1987
Sub structure:
Abutment:
Height (H) of abutment was taken
dependent upon scour depth and cross
section.
Width of abutment cap: 300mm to 450 mm
Projection of cap: 75 to 200 mm
Width of abutment: H/12 to H/10
Height of footing: H/12 to H/10
Width of dirt wall: stem width (150mm 2
+ bearing width)
Pier:
Height (H) of abutment was taken dependent upon scour depth and cross section.
Width of pier cap: (2bearing width + expansion joint + 215mm)
Projection of cap: 50 to 200mm
Side slope: 1/50 to 1/12
Thickness of cap: 300mm to 450mm
7
2.4 IDEALIZATION OF BRIDGE COMPONENTS
2.4.1 Loads
There are many forces acting on the bridge. Some of them are:
1. Dead load
The dead load carried by the girder or the member consists of portion of
the weight of the superstructure which is supported wholly or in part by the
girder or the member including its own weight. Dead load for bridge is taken
as per the Cl.203 of IRC 6- 2010.
2. Live load
Bridge design standards specify the design loads, which are meant to reflect
the worst loading that can be caused on the bridge by traffic, permitted and
expected to pass over it. For the analysis of this bridge class A load is taken.
3. Impact load
In the members of any bridge either for class A or class B loading, the impact
percentage shall be determined from the curves. The impact fraction shall
be determined from the following equations which are applicable for spans
between 3m and 45m.
Impact factor for RCC bridge = 4.5/6+L
4. Braking load
Load due to braking effort of Class A load is given as 20% of live
load on the superstructure.
Braking loads acts at 1.2m above wearing coat. Point of application of
braking load is calculated from 1.2 meters high from wearing coat to the
depth of main bearing.
5. Wind load
Wind load in is calculated as per Cl. 209 of IRC 6. Wind load in transverse
direction of bridge is given as
(FWT) = PZ A G CD
8
Taken height of the bridge was taken as 10 m, Basic wind speed as 47 m/s
and Terrain with obstruction
Where,
P = Hourly mean wind pressure in N/m2 at top height of building which is
Z
given as
It states for deck supported by two or more beams or box girder Cd shall be
taken as 1.5 times Cd for single box or beam, however the value shall
not be less than1.3 where Cd foe single beam is taken as 1.5 for b/d ratio
of 2 and as 1.3 if
b/d 6.
6. Seismic load
Seismic load is calculated as per clause 219 of IRC 6 2010
Seismic load (FS h) = Z/2*I/R*Sa/g
Where
Z is the zone factor which is given as per clause 219.2 of IRC 6 2010.
I is the importance factor which is given by clause 219.5.1.1 of IRC 6.
Its value is found from table 7 of IRC 6 2010
R is the response reduction factor given as table 8 of IRC 6 2010.
Vertical reaction due to seismic load on support ofS bridge (Fv) is also
taken. Seismic loads acts on c. g. of seismic weight. It creates additional
vertical load on support. We considered C. G. of seismic weight is 0.9 m from
bearing. From this reaction, vertical reaction on abutment per unit length
when seismic load is acting in transverse direction and vertical reaction on
abutment per unit length when seismic load acts in longitudinal direction is
calculated.
9
Where,
Fcst is Strain due to temp., creep and shrinkage
is Horizontal deformation of bearing
G is Shear modulus of elastomeric
h0 is Preliminary height of bearing (h0)
A is Preliminary effective sectional area of bearing
9. Load due to active earth pressure: According to Coulomb's Theory which is given
as:
Load due to active earth pressure has been found by Coulombs Theory.
Static Earth Pressure
Pa= 0.5 soil H2 KA
Where
cos2 ( )
sin( ) sin( i ) 1 / 2 2
cos2 cos( ) 1
cos( i ) cos( ) Ka= 0.244
11. Load due to dynamic earth pressure:
Load due to active earth pressure has been found by Mononobe Okabe
Theory.
PA= 0.5 soil H2 KAdyn
Where,
KAdyn=(1+ v)*
cos2 ( )
sin( ) sin( i )
cos cos2 cos( ) 1
cos( i) cos( )
1 / 2
2
10
h is the height of earth fill
W is the weight of surcharge
2.4.2 Super structure
The superstructure of the bridge consists of RCC slab with railing details.
This system covers RCC tee beams with RCC slab and railing details.
a. Deck Slab
Cantilever slab
The outer face of the main beam is taken as the support of the cantilever
slab. Live load considered is 114 kN axle load of Class A load conforming to
IRC 6-2000 maintaining 150 mm clear distance from the edge of the kerb and
dead load comprises of the self-weight of the cantilever slab itself, kerb and
railings whose maximum response is calculated using effective width method
at the junctions of the main beam. The slab is analyzed and designed for 1 m
strip. In addition, distribution reinforcement has been provided assuming
the summation of 0.3 times the maximum live load bending moment
and 0.2 times the dead load bending moment in accordance with IRC 21:
1987 Clause 305.18.1. The temperature and shrinkage reinforcements are
provided at the top of the deck slab as per codal provision.
Restrained slab
The interior panel of the deck slab has been designed as a two way slab. The
maximum bending moment at the critical section is determined by deploying
Pigeauds method, considering IRC Class A loading, confirming to IRC 6
2000 as a live load and the self-weight of the slab and wearing course as dead
load. The moment due to the load has been computed using Pigeauds curves.
Since the curves are intended for slab simply supported on all four sides, the
values of maximum bending moment have been multiplied by a
continuity factor of 0.8.
The RC slab is designed as rectangular SR-URS by the principle of Limit State
of Design Method of slab. The temperature and shrinkage reinforcements are
provided at the top of the deck slab as per codal provision.
Pigeaud's Method:
In this method, the long span and short span bending moment coefficient are
read from the curves developed by M.Pigeaud. These curves are used for
slabs supported along four edges with restrained corners and
subjected to symmetrically placed load distributed over some well
defined area. Poisson's ratio of 0.15 is considered. A wheel load being
centrally placed on a panel of dimension B(short span) x L(long span). If b
and l are wheel contract dimensions imprinted on the slab, and if t is the
thickness of a wearing coat and as the load disperses through the wearing
coat media at an angle 45 0, the dispersed dimensions of the wheel on slab
becomes
11
V = l + 2t (along long span) U = b + 2t (along short span)
The values of moment coefficient m1 (for short span) and m2 (for long span)
for the slab are given by Pigeauds curves for various values of the aspect
ratios (K=B/L) and ratios U/B and V/L. The BM in the slabs can then be
calculated using the following equations.
Two Girder systems have been adopted for main girder. Live load on the girder
has been determined by Courbon's method assuming the supports of the deck
slab as unyielding. The center to center spacing of the main girder has been
fixed as 3m.
Maximum bending moment and shear force for RCC beams due to dead and live
loads have been determined at various sections of the RCC beams with the help
of influence lines. The detailed calculations are presented in the design
calculation.
'
Courbon's Method
Courbon, a French Engineer, assumed the cross girders to be infinitely rigid and
worked out the proportions of live loads on these girder based on that
consideration. According to his theory, no flexure of transverse deck is possible
because of the presence of infinitely rigid diaphragms and a concentric load,
instead of one pushing down only nearby girders, causes equal deflection of all the
girders.
Courbon's theory is applicable when the following conditions are satisfied.
1. The span width ratio is greater than 2 and less than 4.
2. At least five symmetrical cross girders connecting the longitudinal girders
are present.
3. The depth of cross girder is at least ( )th of the depth of longitudinal girders.
For bridge decks in which the girder have different moment inertia the
distribution coefficient are given by
K= / + [ 1 1/ 2]
Where W= the eccentric concentrated load
n= number of longitudinal girders
e= eccentricity of the wheel load from the centre line of the deck
X1= the distance of the girder under the consideration from central axis of
deck
2 =the sum of distance of the longitudinal girders from the centre line of
deck
1= the moment of inertia of the girder under consideration
= the moment of inertia of n girder
13
Influence Line Diagram
An influence line graphs the variation of a function (such as the shear felt in a
structure member) at a specific point on a beam or truss caused by a unit load
placed at any point along the structure. Some of the common functions studied
with influence lines include reactions (the forces that the structures supports must
apply in order for the structure to remain static),shear, moment and deflection.
Influence lines are important in designingbeams and trusses used in bridges,
crane rails, conveyor belts, floor girders, and other structures where loads will
move along their span. The influence lines show where a load will create the
maximum effect for any of the functions studied.
c. Cross Girders
Dead load bending moment in the cross girder has been calculated considering
trapezoidal distribution of weights of slab and the wearing coat. Cross girder has
been considered as partially fixed beams over two supports.
Live load bending moment in the cross girder has been computed considering
different disposition of standard loadings over the cross beam. Similar
computation procedure has been determined the shear forces.
14
Different disposition of Standard loading over interior cross beam
114 kN axle wheels of IRC class A loading are so placed such that they impose
maximum B.M and S.F in the load contributory area of the cross beams. The live load
conditions remain the same for all depths of the cross beams considered. So only a
case calculation is done here which will be used for all depths. Details are specified in
the figure below.
15
Different disposition of Standard loading over interior cross beam
114 kN axle wheels of IRC Class A loading are positioned as shown in the figure for
maximum B.M. and S.F. case acquisition. The live load loading condition remains the
same for all cases. Loads positioned under the contributory area are only considered for
responses in the end cross girders.
16
2.4.3 Bearing
Working stress method is used for the analysis of bearing. Various loads are
calculated for the analysis of bearing. They are dead load of superstructure,
live load acting on superstructure, braking load, seismic load, load due to
temperature variation, shrinkage and creep and wind load.
Bearing is worked out referring to IR 83 part II: Elastomeric bearing.
2. Horizontal loads
Force due to Braking Effort
Force due to Frictional Resistance of Bearing
Wind Load
Force due to Earthquake
Force due to Earth Pressure
Force induced by creep, shrinkage and temperature variation
Force due to surcharge
17
Stability Check:
1. Overturning and restoring moment about toe of abutment for different
load combination was found.
Backfill + DL+ LL+ temperature load/braking load
Backfill + DL+ Surcharge due to compacting equipment/LL
Backfill + DL+ par. LL + seismic load
2. Overturning effect:
M restoring /M overturning 2 for basic combination
1.5 for seismic combination
3. Shear and resisting shear at the base of footing
Shear = sum of horizontal forces at base
Resisting shear = sum of vertical load at base tan
4. Sliding effect
V resisting/ V sliding 1.5 for basic combination
1.25 for seismic combination
5. Bearing pressure at base of footing
Pressure = P/A Pe/Z bearing capacity of soil &
Upward pressure of soil should be positive.
Design of Abutment Cap, Main Stem, Back Wall and Slab Base
18
area of bar in one face 0.0012
Spacing of vertical bars 200 mm
Horizontal Reinforcement
Area of horizontal reinforcement 2.5% of total area of vertical bars
0.001 of concrete area
Spacing of horizontal bars 300 mm
Diameter of bar 8mm or one fourth of vertical bars
Transverse Reinforcement
If the area of load carrying vertical bar in two faces > 0.02 area of
concrete theses bars should be enclosed by stirrups
b. Pier:
List of forces acting on Pier
1. Vertical loads
Self wt. of Pier
Dead & Superimposed Dead Load from Superstructure
Live Load
Earthquake load (vertical component)
Wind load (vertical component)
Uplift by braking effort
Buoyancy
2. Horizontal loads
Force due to Braking Effort
Force due to Frictional Resistance of Bearing
Wind Load
Force due to Earthquake
Force due to Hydrodynamic Pressure
Force induced by creep, shrinkage and temperature variation
Force due to Water Current
When bearing stress in cap does not exceed the permissible value of bearing
stress in concrete, provide reinforcement according to IRC78 & check the
thickness of cap for punching shear.[Refer abutment design]
19
Detailing of reinforcement [Refer Cl. 16.3, IRC 112]
Vertical Reinforcement
Dia. of bar 12mm, 40 mm
Total area steel of vertical bar 0.0024 to 0.04 of area of concrete
area of bar in one face 0.0012
Spacing of vertical bars 200 mm
Horizontal Reinforcement
Area of horizontal reinforcement 2.5% of total area of vertical bars
0.001 of concrete area
Spacing of horizontal bars 300 mm
Diameter of bar 8mm or one fourth of vertical bars
Transverse Reinforcement
If the area of load carrying vertical bar in two faces > 0.02 area of
concrete these bars should be enclosed by stirrups
20
3. ACQUISITION OF DATA
3.1 FINDINGS
The topographical and geotechnical studies were made prior to the visit of the
site. The topography of the site was pre determined by the LBRP and the proper
study was made to understand the existing conditions. Reconnaissance was
carried out to verify topographical map of the bridge site area visual by
inspection. The area covered by the survey was 500m upstream and 200m
downstream from the proposed bridge axis. Both benchmarks were fixed on
permanent embedded stone blocks. The RCC peg at station A and B is fixed along
bridge axis at left and right bank to make permanent reference point. The three
reference points for each station A and B were also fixed. The detailed survey of
approach road at right and left bank is connecting the existing road.
1. Existing configuration of the river and approach roads.
2. Bench marks.
3. Bridge axis
4. Contour
The longitudinal axis of proposed bridge site was found and measured. The
length was measure using tape and a handheld GPS unit and the length was
found to be nearly 106m in each case. The longitudinal axis of bridge was
measured from point A to point B as set by the surveying group. The axis was
found to be much longer than the proposed length of the bridge which is 50m.
From the enquiry with locals it was found that in the maximum discharge season
i.e. in the monsoon period 9 years before, the river reached to a distance of
about 83m at the left side of the river. On the basis of which we estimated that
the length of bridge axis of 50m was suitable depending upon the maximum
flood discharge of return period of about 9-10 yrs.
River cross section was also determined by the survey group but our job was to
verify the data. The cross section of river was taken at various points in the river
bed at the longitudinal axis of bridge. The details are listen below:
21
RL of deepest bed level : 442m
RL of HFL (left side) : 446.5m
RL of HFL (right side): 446.5m
The RL of other points in the waterway was also taken but the accuracy of which
might not be true due to inappropriate methods using stick.
The approximate velocity of water was found out using the paper boat. The paper
boat was made to float through a certain distance under some time. The velocity of
river was found to be 0.35m/s. This value is also verified the use of Manning's
formula.
V= R2/3 S1/2
Where,
n= Manning's coefficient
R= Hydraulic Radius
S= Slope of stream
The upstream and downstream distances of 500m and 250m respectively were
walked through. The upstream of river has a meandering near to the proposed bridge
site. The main highlight of the upstream river side was only the meandering and
other features were not much noticeable in comparison to the meandering. The river
upstream was somewhat straight and at the reach of nearly 350m the river turned a
bit to left from. The downstream side of the river was a straight reach to some 100m
and after slight turn was observed towards right hand side and then if follows sharp
turn to right side and follows straight. The overall topography of the upstream and
downstream was found to be flat area like in Terai. There wasnt any steep paths
22
near the river banks. The right side of the river had few settlement areas whereas the
left side of the river had no settlements and mostly was covered by the cultivated
lands.
From the existing condition at the site, we found out that the approach to bridge is
rather downgrade. The road connecting the bridge from the Bhanu V.D.C (ward no-
3), Tanahun to the other bank at Barbhanjyang V.D.C (ward no-5), Tanahun is
blacktopped single lane road. The approach at the bridge is of small width at existing
pedestrian bridge. The total width available at the bridge approach connecting the
main Bhansar-Chandrawati Road is about 15m.
12 34.12 0.35
10 29.41 0.34
23
Return Period
c) Fullers Method
Qmax = Qt (1+2(A/2.59)^-0.3)
Qmax is maximum instantaneous flood discharge.
Qt = Qav(1+0.8logT)
Qt = maximum 24 hour flood with frequency T years
Qav=Cf A^0.8
Cf =1.03 for Nepal.
A=Catchment area=59.3sq.km
Qav=27 m3/sec
Q50=63.70 m3/sec
Q100=70.2 m3/sec
Qmax for 50 year return period=113.50 m3/sec
Qmax for 100 year return period=125.08 m3/sec
d) Rational Method
The flood discharge Q=CIA
Where,
Q = Peak discharge m3/sec
C= A function depending on the characteristics of the catchment in producing
the peak run-off
= =0.1011
I = Peak intensity of rainfall in mm/hr =8.46 for 50 year and 9.39 for 100 year
return period
A= Catchment area in sq. Km =59.3km2
tc= time of concentration in hours
==(0.87*L3/H)0.385 =1.215 hr
Where,
24
L= length of the stream in km =12.5 km
H= fall between the two end levels of L in meter =1024m
Q50=50.71 m3/sec
Q100=56.29 m3/sec
1995 85 131.2 6 4
25
2010 135.2 79.0 21 1.14
26
Scour depth:
dsm=1.34( )0.33
Where,
Db =discharge in m3/s per m width= = 3.41
Ksf =0.85 (assumed)
So.
dsm= 3.17m from HFL
27
3.3 Geotechnical Computations:
3.3.1Borehole data:
28
Location: Left bank
29
Location: Middle of river section
30
Correction of CPT Values
Bore hole No. 1 (Right bank)
effective Correct
Corrected
overburd ed SPT
Dept CP Equivalent SPT for
en for
h T SPT overburd
pressure dilatenc
en
KN/m2 y
16.666666
1.5 25 67 20.70 25.5 20.2
36.666666
3.0 55 67 41.40 47.5 31.3
>8
4.5 0 50 62.10 58.1 36.5
>8
6.0 0 50 82.80 53.2 34.1
44.666666
7.5 67 67 103.50 44.2 29.6
>8
10.0 0 50 138.00 44.7 29.9
>8
11.5 0 50 158.70 42.4 28.7
43.333333
13.0 65 33 179.40 34.9 25.0
43.333333
14.5 65 33 200.10 33.4 24.2
16.0 75 50 220.80 36.8 25.9
Average N Value = 27.20
effective Correct
Correcte
overbur ed SPT
Dep Equivalen d SPT for
CPT den for
th t SPT overbur
pressure dilaten
den
KN/m2 cy
1.5 23 15.33 20.70 23.4 19.2
36.66666
3.0 55 667 41.40 47.5 31.3
4.5 >80 50 62.10 58.1 36.5
6.0 >80 50 82.80 53.2 34.1
39.33333
7.5 59 333 103.50 39.0 27.0
9.0 >80 50 124.20 46.5 30.7
10.5 >80 50 144.90 43.9 29.4
12.0 70 46.66666 165.60 38.9 26.9
31
667
13.5 >80 50 186.30 39.7 27.3
15.0 >80 50 207.00 37.9 26.5
Averag
e N-
Value = 27.98
All DCPT values are corrected for N-values, dilatancy and effective overburden
pressure
effective Correct
Correcte
overbur ed SPT
Dep Equivalen d SPT for
CPT den for
th t SPT overbur
pressure dilaten
den
KN/m2 cy
1.5 34 22.67 20.70 34.6 24.8
3.0 45 30 41.40 38.9 27.0
4.5 56 37.33 62.10 43.3 29.2
41.33333
6.0 62 333 82.80 44.0 29.5
7.5 80 50 103.50 49.5 32.3
Averag
e N-
Value = 30.90
All DCPT values are corrected for N-values, dilatancy and effective overburden
pressure
The surface as well as surface geological features existing at the bridge site is
shown in the borehole logs. At the bridge site the top soil of silty clay in nature to
a depth of about 0.5m sandy gravel upto 3m. Beyond these depths there are
sandy gravel and big boulders of gneiss, quartzite and conglomerate.
32
3.3.3 Foundation analysis:
The analyzed foundation was spread footing with its depth of 4.6 m from
ground position.
33
TP-10 539002.684 3099935.435 449.766
34
4. STRUCTURAL PLANNING AND DESIGN
2) Substructure
a) Abutment
i) Abutment Cap M25
ii) Abutment Stem M20
iii) Footing M20
b) Pier
i) Pier Cap M20
ii) Pier Stem M20
iii) Footing M20
4.2.1 Superstructure
35
ii) Width and Height of Safety Kerb:
Width of Kerb = Offset + Width of railing post + min. clearance from
post
= 50 + 225 + 325 =600mm
Height of Kerb > minimum height from road surface = 300mm
Height of wearing course = 50mm
Minimum height of kerb from wearing course = 225mm
iii) Type of wearing coat
Asphalt concrete for wearing coat of bridge. Thickness of wearing
course is taken 50mm at edge and 95 at crown of carriage way to
give about 2% camber.
iv) Type of Railing
Heavy Steel Pipe with RC post as railing.
RC post of 225mm 225mm 1100mm
Number of post = 26 at 2m spacing on each side.
Railing should have minimum height of 1.1m above roadway.
Clear distance between lower rail and top of kerb shall not exceed
150mm.
0.2m
0.4m
1.1m
48.3 mm dia. heavy
steel pipe,
0.4m
0.1m
0.225m
v) Size of RC slab:
250mm thickness of slab at middle part.
150 300 mm fillet at the ends.
36
4.2.2 Analysis and Design of Cantilever Slab:
0. 1 5 m
0. 40 m Wheel of 114 KN
m axle of C lass A load
axle
0. 3 m
0. 17 m
0. 4 0 m
0
0.6 m 0. 55 m
37
=0.3*53.576+0.2*10.98
=18.26
Design of slab dprovided =450 -25- 10/2 =370mm
dbal = 136.18mm
Q=0.36*fck*0.48*(1-0.416*0.48) =3.45
Hence, dprovided>dbal
Reinforcement calculation
Primary reinforcement
Mu=
Ast=494.15 mm2
Pt= (494.15*100)/ (370*1000) =0.133%
Adopt 10mm bars @150mm
Transverse Reinforcement
Adopt 10 mm bars @ 150 mm
Temperature reinforcement
Ast min=444 mm2
adopt 10mm bar 2160mm c/c
Checking of slab for shear
Not necessary as it is designed by effective width method.
38
4.2.3 Analysis and Design of restrained slab
Analysis of slab:
500mm
m
I 250mm 4.75m
1.2m
II
2.7m
Position of class A load for maximum BM
K= = , = 1.76
39
BM due to wheel II
Patch I Patch II
4.75m
= _
II
2.7m
Patch I along shorter span: Wheel of 114 KN
Axle of Class A
K= 0.56, = = 0.24
= = 0.588
Shorter span:
BM due to patch I = (0.14 + 0.15 0.045) 1140.132 =133.85 KNm
BM due to patch II =
40
For longer span:
BM= Patch I - Patch II
Patch I = (0.045 + 0.15 0.14) 1140.132 0.8= 60.19 KNm
Patch II = (0.05 + 0.15 0.15) 857.9 0.8 = 49.75 KNm
Design moment due to DL and LL in shorter span= 17.14 + 7.06 = 24.2 KNm
Design moment due to DL and LL in longer span= 20.45 + 2.95 = 23.4 KNm
= + =
1.8m
4.75m
I
1.2m
2.7m
41
For wheel II
= 1.776 0.3275 (1- = 0.906m
a= 2.7 - 1.8 - 0.5725 =0.3275m
mod = 0.3 + + 1.2 + = 2.078m [Width of cross beam is taken for effective
width]
Load due to wheel I (F1) = = = 95.67 KN/m
95.67 KN 116.02 KN
0.572m 1.8m 0.3275m
A B
A
2.7m
Reaction at A and B:
RA 2.7 = 95.67 (2.7 - 0.572) + 116.02 0.3275
RA = 89.47 KN
RB = 122.22 KN
Design SF due to DL and LL in shorter span:
= 122.22 + 10.77 = 133 KN
Design:
Checking Depth of Slab
Effective depth of main reinforcement (d1) = 250 25 10/2 = 220 mm
Effective depth of secondary reinforcement (d2) = 250 25 10 10/2 = 210 mm
Here,
Reinforcing bars
42
=312.01 mm2
= > = 0.12 %
Spacing = = =251.77
Along longer span
=327.66 mm2
= > = 0.12 %
Spacing = = =239.7
b. Temperature Reinforcement
= 252 mm2
Spacing = = = 311.67
43
4.2.4 Analysis and Design of main girder:
Effective span= 25m
slab thickness = 250mm
Width of rib= 400 mm (min. 250 mm)
Spacing of main beam= 3m
Overall depth of beam= 2.10m
5m
25 m
RA = 825.43 KN Loads on Main Girder RB = 825.43 KN
Calculation of Maximum BM and SF at critical sections due to DL
Mu = RA 12.5 5.46 12.5 18.11 7.5 18.11 2.5 -62.7 x 12.5 x = 5170.08 KN-m
44
Mu at A = 825.43 x 8.5 5.46 x 8.5 18.11 x 3.5 62.7 x 8.52/2 = 4640.32 KN-m
Mu at B = 825.43 x 4.5 5.46 x 4.5 62.7 x 4.52/2 =3055.027 KN-m
S.F. at A = 825.43 -5.46-18.11-62.7 x 8.5= 268.91 KN
S.F. at B = 825.43-5.46-62.7 x 4.5=537.82 KN
2
W W 5 KN/m
0.5 m 1.8 m
0.6 m
2.3 m 2.2 m
1 2
1.35 m 3 m
Fig: Transverse positioning of Class A and uniformly distributed load in bridge deck
In single lane bridge, Class A occupies 2.3 m strip of carriage way. Remaining strip
[4.50 - 2.3 = 2.2 m] should be loaded with UDL of 5 KN/m2 [Refer Table 2, IRC 6]. Reaction
from UDL of girder 1 is found by Courbons Method.
45
Calculation of maximum BM at mid span due to live load:
Case 1 14.57 KN/m
78.2 KN
131.01 KN
31.05 KN
BM=31.05(0.30+0.51)+131.10(2.5+3.05)+78.20(5.2+5.8+4.3+2.80)+70.69x14.57
=3198.12 KN
Case 2
14.57 KN/m
131.10 KN 78.2 KN
31.05 KN
46
BM at Quarter span:
14.57 KN/m
131.10 KN 78.2 KN
31.05 KN
131.10 KN 78.2 KN
31.05 KN
47
BM at section B (4.5m from support):
14.57 KN/m
1.2 4.3 3 3 3
25m
Vu=131.10(1+0.952)+78.20(.78+0.66+0.54+0.42)+0.5x1x25x14.57
=625.71 KN
48
2. At quarter span
14.57 KN/m
0.75
6.25 18.75
Vu=131.10 x (0.75+0.702) +78.20 x (0.53+0.41+0.29+0.17) + 0.5x0.75x18.75x14.57
=402.28 KN
0.66
6.25 18.75
Vu=131.10x(0.66+0.6120 + 78.20x(0.44+0.32+0.32+0.08)
=325.72 KN
49
4. At section B (4.5m from support):
14.57 KN/m
0.82
Vu=131.10x(0.82+0.77)+78.20x(0.60+0.48+0.36+0.24)
=470.95 KN
bact = 2.85 m
0.17 m
0.40 m 0.25 m
x 0.6 m x
0.3 m
2.10 m
1.15 m 1.30 m
0.3
Df = = 0.2475 m=.250m
Where
Av. thickness of left part of slab = = 0.225 m
50
Av. thickness of right part of slab = = 0.27m
bef = 2. 70 m
0.25 m
2.10 m
= 1425
.
0.4 m
1.35 m
Design Section
C.G. of section
Y= = 1.425m
= 0.053555 m4
Find area of steel for SRURS flanged section when N.A. lies in flange
Astreq = = =12831.24 mm^2
Where, Astmin = 0.2% of bd = 0.002 400 1948 = 1558.40 mm2 [Refer
Cl.305.1, IRC21]
No. of bar= =15.95
Find area of steel for SRURS flanged section when N.A. lies in flange
Astreq = = =9468.30 mm^2
Where, Astmin = 0.2% of bd = 0.002 400 1948 = 1558.40 mm2 [Refer Cl.305.1,
IRC21]
No. of bar= =11.67
52
Adopt no. of bar =16
Provide 16-32 mm dia. bar
Ast. Provided =12867.97 mm2
Pt=1.60%<2.5% Hence design is ok.
Find area of steel for SRUR flanged section when N.A. lies in flange
Astreq = = =7536.54 mm^2
Where, Astmin = 0.2% of bd = 0.002 400 1948 = 1558.40 mm2 [Refer
Cl.305.1, IRC21]
No. of bar= =9.29
Quarter Section
(V)= 908.75 KN
=
= 1.147 N/mm2
53
From IRC 456-2000
for M25 & Pt=1.60%
2
c =0.75 N/mm
2
c max=3.1 N/mm
2
c max=3.1 N/mm
Here,
> c, design shear reinforcement.
Take 10 mm - 2 legged vertical stirrups for shear reinforcement.
Sv = =
= 357.138mm < 0.75 d > 300 mm
Adopt Sv=300 mm
Provide 10 mm 2-legged vertical stirrups 300 mm c/c from quarter span to quarter
span of other side.
Adopt Sv=300 mm
Provide 10 mm 2-legged vertical stirrups 300 mm c/c from quarter span to quarter
span of other side.
54
Sv = =
= 223.987mm < 0.75 d > 300 mm
Adopt Sv=220 mm
Provide 10 mm 2-legged vertical stirrups 220 mm c/c from section B(4.5m from
support) to quarter span.
Detailing of Reinforcement
the length of extension of bar beyond the theoretical cutoff point (ld).
ld =
for straight end
= 0.994
ld = 1 x 0.994 x 46 x 40
= 1464mm
2/3ld = 831.19 mm
55
4.2.5 Analysis and Design of Intermediate Cross Girder
Analysis:
Load due to self wt. of slab &WC:
Here the load due to self-weight of slab and wearing coat acts on contributory area of
triangular shape.
1. DL from slab =
=12.65 KN/m
2. DL from WC =
=4.158 KN/m
Total= 16.808 KN/m
DL due to self wt. of cross beam and fillet acts as UDL:
Load due to self-weight of cross beam and fillet acts as a uniformly distributed load.
14.93 KN/m
114 KN axle of
class A
Calculation of Live Load on Cross Girder:
1.8m
1.2m
120.55 KN 120.55 KN
1.5m
5m
1.8m
3m
3m
1.8m 1.2m
3m
Longitudinal position of class A load for maximum SF 1.5m
5m
3m 56
Calculation of BM (max) at mid-span due to DL & LL
Mu =
= 101.726 KNm
Calculation of SF(max) @ support due to DL & LL
Vu =
= 251.99 KN 252 KN
End Cross Girder
Calculation of dead load on End Cross Girder
Load due to Self wt. of slab & wearing coat acts on contributory area of triangular
shape
1. self wt. of W.C.= = 2.079 KN/m
2. self wt. of Slab = 0.25*1.5*25*1.35* = 6.32 KN/m
Total= 8.399 KN/m
Load due to self wt. of cross beam & fillet acts as a UDL
1. Fillet = = 0.76 KN/m
2. Self wt. of cross beam=0.3*1.325*25*1.35
=13.41 KN/m
Total = 14.7 KN/m
8.407 KN/m
14.17 KN/m
= 94.576 KN-m
Calculation of max. SF at support due to DL & LL
Vu =
=244.55 KN
57
Design of Cross Girder
Design section:
d =1575 40 =1521mm
Ast=
= 1521300
=912.6mm2
Provide 2-28mm bars
Ast provided=1231.5mm2
Pt=0.269%
Design section of shear:
uv = = = 0.55N/mm2
58
uc,max= 3.1N/mm2 for M25
Sv =
=1112.03 mm
Provide 10mm 2 legged vertical stirrups @ 300 mm C/C
d=900 - 40 - =846mm
=745.07 KNm
Here, Mu < Mul,, So, Its SRURS
Mu=0.36 fck beff Xu (d - 0.416Xu)
Or, 94.576106 = 0.36 25 600 Xu (846-0.416Xu)
X4=20.91mm<Df
Area of steel:
Ast=
59
=312.84mm2 < Ast=0.2% of bd
= 846300
=507.6mm2
Provide 3-16mm bars
Pt=0.23%
Design section for shear:
uv = = = 0.96N/mm2
Sv =
= = 309.91mm
60
Moment calculation for service load= Mdead+Mlive
=5170.8/1.35+3542.75/1.14
=6937.89 KN-m
The neutral axis depth kd is obtained by considering moments of the cracked transformed
section about the NA.
b*(kd)2/2=mAst(d-kd)
2700*k2*19482/2=2*105/25000*12867.96*(1948-k*1948)
k=0.1792
Kd=349.16 mm
So Icr=b(kd)3/3+m Ast (d-kd)2
=2700*(k *1948)3/3+2*105/(25000)*12867.96(1948-k*1948)2
=3.01*1011 mm4
=(1-0.1792/3)(1-0.1792)*(400/2700)=0.1143
Mcr= fcr*Igr/yt
=0.7 25 *5.94*1011/(1425)=1.458*109 mm4
Ieff=Icr/(1.2-(Mcr/M)
=3.01*1011/(1.2-(1.458*109/6937.89*106)*0.114)=2.572*1011mm2
Icr> Ieff< Igr
So, Ieff=2.57*1011mm2
5m
25 m
RA = 825.43 KN RB = 825.43 KN
61
Moment due to UDL,M1D=62.70*252/8=4898.437 KN-m
For concentrated load
Reaction force =41.68 KN
Moment due to UDL M2D= -5.46*12.5-18.11*7.5-18.11*2.5+41.68*12.5=271.65 KN-m
Taking moment of area of cracked transformed section .
400*(kd)2/2+(20.8-1) *(400*1948*0.55/100)*(kd-56)=(20.8*400*1948*1.93/100)*(1948-
kd)
kd=1020.49
Icr=b(kd)3/3+mAst(d-kd)2*(m-1)Asc(kd-d)2
=3.86*1011mm4
Icr< Igr
Ieff=3.76*1011mm4
i,cc(perm)= 5/48*l2*( M1D+ M2D)/(Ece*Ieff)
=5/48*250002*(4998.43+0.8*271.65)*106/(11903*3.76*1011)=75.87mm
Mcr= fcr*Igr/yt=0.7 25 *5.94*1011/(1425)=1.458*109
Ieff= Icr/(1.2-(Mcr/M) =3.10*1011/(1.2-(1.458*109/6937.89*106)*0.114)=2.57*1011mm4
Ieff< Igr
So Ieff=2.57*1011mm4
i(perm)= 5/48*l2*( M1D+ M2D)/(Ec* Ieff)
=5/48*250002*(4998.43+0.8*271.65)/(25000*2.57*1011)=52.85mm
Hence, cc(perm)=i,cc(perm)-i(perm)= 75.87-52.85=23 mm
DEFLECTION DUE TO SHRINKAGE:(refer IS 456:2000 Annex C)
cs=k3*cs*l2
where,
k3=constant depending upon the support condition
0.5 for cantilevers
0.125 for simply supported member
0.086 for members continuous at one end
and
0.063 for fully continuous members
cs = shrinkage curvature = k4 * cs/D,
where cs=ultimate shrinkage strain of concrete (IS 456:2000 cl 6.2.4.1)
=0.0003
K4=0.72*(pt- pc)/ pt 1.0 for 0.25 pt-pc < 1.0
= 0.65*(pt-pc)/ pt 1.0 for pt-pc 1.0
In our case; pt=1.60%, pt=0.55%
So, pt- pc=1.05
K4= 0.65*(pt-pc)/ pt =0.54
cs = k4 * cs/D=0.54*0.0003/2100=7.71*10-8
cs=k3*cs*l2=0.125*7.71*10-8*250002=6.02 mm
Hence, final deflection due to all loads including the effects of creep, temperature
and shrinkage is
=(70.30mm+23mm+6.02mm)=99 mm, which should not normally exceed
(span/250=100mm) hence, main girder is safe on deflection.
62
4.2.6 Analysis and Design of Bearing
1. DL from Superstructure
2. LL from Superstructure
4. Wind load
63
Wind load in transverse direction of bridge (FwT) = PZ A G CD = 117.58 KN
64
Seismic Load (Longitudinal) = *WL
= 0.25*2452.8
= 551.88 KN
Seismic Load (Transverse) = 571.32 KN
V. reaction on a bearing when s. load acts in tr. dir. (FSVT) = 85.698 KN
Vertical react. on a bearing when seis. load acts in long. dir. (FSVL) = 9.93 KN
65
Calculation of Loads on Bearing According to Combination of Loads
Vertical and horizontal loads subjected to bearing in the direction of traffic are only
taken for design.
Combination I [N]
Total Vertical load = DLSup + LL + FbrV = 613.2+1024.92+5.845= 1643.965 KN
Total Horizontal load = FbrH = 21.6 KN
Combination VI [N+T+S]
Total Horizontal load = 0.5 FbrH + Fcst + FshL = 0.5 21.6 + 3.7 + 137.97 = 152.47 KN
1. Geometrical design
In geometrical design, approximate length, breadth and thicKNess of elastomeric
pad and number, thicKNess and cover of steel laminates are found. Geometrical
design is carried out using the guidelines of IRC.
[Refer standard plan dimensions of IRC 83, Part II, Cl. 916.2, Appendix I]
66
Nmin = DL = 613.2 KN; Nmax = Tot. Vertical load on bearing = 1643.965KN; H = 21.6
KN
Take,
b0 = 400 mm, b = 388 mm
l0 = 630 mm, l = 618 mm
hi = 12 mm
he = hi/2 = 6 mm
hs = 4 mm
n=4
c = 6 mm
h0 = (n +1)hs+nhi + 2he = 80 mm < 84 mm OK
h= nhi + 2he= 60 mm
2. Structural design
Bearing is further checked for translation, rotation, friction and shear
a) Check for translation
Design strain in bearing (d) < 0.7
< 0.7
Where,
= 0.09 ; G=shear mod of Elasticity=1 N/mm2
67
b) Check for rotation
Design rotation in bearing (d) nbimax
= 0.00684< nbimax
nbimax = 0.0088
Where,
MDL = 5170.08 KN-m
MLL = 4023.65 KN-m
= 25000 N/mm2
=
0.05911154 m4
= 0.1m= 0.1 6.85=
0.685
n=3
bimax =
=
Where,
Shear stress due to axial compression ( c)=1.5*
= 1.0347 N/mm2
68
Shear stress due to horizontal deformation ( r) = d = 0.377 N/mm2
Shear st. due to rotation ( )=0.25*( )2 *bimax
2
=0.5* *0.00156
=0.815 KN/mm2
Check of Elastomeric Pad Bearing for Combination VI [N+T+S]
Loads are not varied significantly in first three combinations of loads. But in seismic
combination i.e. in N + T + S case, horizontal load is about two times greater than
other combinations. So designed bearing has been checked for seismic combination
(along the traffic) of loads only.
Nmin = 613.2 KN
Nmax = 831.056 KN
H = 152.47 KN
*25 =0.104
=
d = 0.104+0.635 = 0.739 > 0.7
Size of bearing provided for loads of combination I (N) is not sufficient for loads of
combination VI (N+T+S). Check for translation shows that provided size of bearing could
not accommodate the horizontal force of combination VI. In the situation it is required
to provide elastomeric pad bearing with pin on one side of support to resist horizontal
load
69
Diameter of Pin
Shear stress in pin due to horizontal loads Allowable shear stress in pin ( )
Take pin of Fe250 grade
;
= 22.03
Provide 28 mm dia. stainless steel pin. Pin should be extended up to the depth of cap
of support.
400mm
0
388 mm
Steel laminates 6 mm
of 4 mm 8
6 mm
80 mm
12 mm 618 mm 630 mm
28 mm
Provide 800*400 mm bearing which will satisfy the Transitional failure at one side and
630*400 mm with pin at the other side.
70
4.2.6 Analysis and Design of RC Abutment
Minimum seating width = 305 + 2.5 span + 10 Ht. of abutment [Ref. Cl. 219.9, IRC 6]
= 305 + 2.5 x 25+10 x 9
= 457.5 mm
Seating width Bearing width + 150 mm + Projection of cap + Width of Expansion Joint
= 0.4+ 0.15 + 0.1 + 0.04 = 0.69 m
Width of Expansion joint 25 103 0.000011/ 0C 500 = 6.875 mm
5 10-4 25 103 = 6.25 mm and 20 mm
Adopt 40 mm
Height of dirt wall = Depth of girder + height of bearing thickness of approach slab
= 2.1 + 0.08 0.3 m = 1.88 m
Thickness of footing
Thickness of footing = = = 1.125 m
71
Analysis and Design of Abutment Cap
Check thickness of abutment cap for punching shear
uv ks c
Where, uv =
= 2.871 N/mm2
2
ks c = 1.25 N/mm
Take area of steel AS = 1 % of area of cap and distribute these bars equally at top
and bottom of cap. [IRC 78 CL. 716.2]
As in longitudinal direction of abutment
= 1% of 550 875 = 4812.5 mm2, As on one side = 4812.5/2 =2406.25 mm2
Take 12 mm bar, n = 22
As in transverse direction of abutment
= 1% of 550 4600 = 25300 mm2 As on one side = 12650 mm2
Take 12 mm bar Adopt n = 112 bars
In transverse direction bars are provided in the forms of stirrups.
1. DL from superstructure
= Wt. of railing + Wt. of Kerb + Wt. of slab + Wt. of main beam + Wt. of cross beam
= 39.6+229.5+911.875+948.6+140.205 = 2269.775 KN
72
Load on an abutment per unit length (DL Ap.S) = = 13.26 KN/m
4. LL from superstructure
LL = 702.09 KN
6. Wind load
Transverse Wind load per unit length FwT = KN/m
Z = 0.36, I = 1, R = 3,
W = 2452.8 KN in longitudinal direction
W = 2534.2 KN in transverse direction
Vertical reaction on abutment per unit length when seismic load acts in trans. dir.
FSvT = KN/m
Vertical reaction on abutment per unit length when seismic load acts in long. dir.
73
FSvL = KN/m
9. Self-weight of Abutment
Self-weight = (1.88 0.35 + 0.55 1.1 + 5.645 1) 4.6 25 = 794.42 KN
Load per unit length DLAb = = 172.7 KN/m
FS AbthT= FS AbthL = w KN
=
= 119.163 KN
Load per unit length FS AbthT = = 25.9 KN/m
= 0.5
= 198.184 KN/m
where, KA
Horizontal component of load per unit length PEPH(s) = PA cos (24) = 181.054
KN/m
Vertical component of load per unit length PEPV(s) = PA sin (24) = 80.61
KN/m
12. Load due to dynamic earth pressure
Load due to active earth pressure has been found by Mononobe
Okabe Theory.
PA= 0.5 soil H 2 KAdyn = 0.5 KN/m
Where,
KAdyn = 0.4
74
Horizontal component of load per unit length PEPH(d) = PA cos (24) = 296.81 KN/m
Vertical component of load per unit length PEPV(d) = PA sin (24) = 132.148 KN/m
13. Surcharge load
1.2 m earth fill from road surface is taken as surcharge load.
Psur = KA s h W = 0.244 18 1.2 9.5= 50.06 KN/m
Horizontal component of load per unit length PsurH = Psur cos (24) = 45.7 KN/m
Vertical component of load per unit length PsurV = Psur sin (24) = 20.36 KN/m
75
Analysis of Abutment Stem
76
Responses of abutment at its bottom in seismic combination of loads
Distance
from eccentricity
Load (KN/m) bottom x (m) y (m) Pu(KN) Mux(KNm) Muy(KNm) Hx(KN) Hy(KN)
DLss 246.71 1 -0.04 246.71 -9.8684 0
DLwc 19.89 1 -0.04 19.89 -0.7956 0
DLap.s 13.26 1 0.375 13.26 4.9725 0
LL 152.62 0.2 -0.04 30.524 -1.22096 0
Fbrh 1.138 0.2 6.275 0 0 1.42819 0.2276
Fbrv 2.5 0.2 -0.04 0.5 -0.02 0
Fs hl 4.845 1 6.275 0 0 30.402375 4.845
Fs vl 2.87 1 -0.04 2.87 -0.1148 0
Fcst 6.79 1 6.275 0 0 42.60725 6.79
DLab 172.7 1 0 172.7 0 0
Fs abt
hl 25.9 1 3.625 0 0 93.8875 25.9
Pep
v(D) 132.148 1 0.55 132.148 72.6814 0
Pep
h(D) 296.81 1 4.575 0 0 1357.90575 296.81
PsurV 20.36 0.2 0.55 4.072 2.2396 0
PsurH 45.74 0.2 3.625 0 0 33.1615 9.148
Total 622.674 1627.266305 343.7206
77
Responses of abutment at 2m from its bottom in basic combination of loads
78
Responses of abutment at 2m from its bottom in seismic combination of
loads
Distance from
eccentricity
x
Load (KN/m) bottom (m) y (m) Pu(KN) Mux(KNm) Muy(KNm) Hx(KN) Hy(KN)
DLss 246.71 1 -0.04 246.71 -9.8684 0
DLwc 19.89 1 -0.04 19.89 -0.7956 0
DLap.s 13.26 1 0.375 13.26 4.9725 0
LL 152.62 0.2 -0.04 30.524 -1.22096 0
Fbrh 1.138 0.2 4.275 0 0 0.97299 0.2276
Fbrv 2.5 0.2 -0.04 0.5 -0.02 0
Fs hl 4.845 1 4.275 0 0 20.712375 4.845
Fs vl 2.87 1 -0.04 2.87 -0.1148 0
Fcst 6.79 1 4.275 0 0 29.02725 6.79
DLab 122.7 1 0 172.7 0 0
Fs abt
hl 18.405 1 3.1875 0 0 58.6659375 18.405
Pep
v(D) 59.5 1 0.55 59.5 32.725 0
Pep
h(D) 133.65 1 3.825 0 0 511.21125 133.65
PsurV 8.57 0.2 0.55 1.714 0.9427 0
PsurH 19.25 0.2 3.1875 0 0 12.271875 3.85
Total 547.668 683.207 167.7676
79
Design of Abutment Stem
Results of analysis shows that maximum design axial load (Pu = 1146.73 KN) is less than
0.1 fck Ac i.e.(0.1 20 1000 4.6 x 1) = 9200 KN. For the case, where P u 0.1 fck Ac,
compression member is treated as a flexure member. So abutment stem has been designed
as a cantilever slab. Since design bending moment is higher in seismic combination of
loads, design of abutment stem has been carried out for seismic combination of loads only.
dbal =
Q =0.36 x fck x 0.48(1-0.416 X 0.48) = 2.76
Hence, dprov dbal
For reinforcing bars
Since dprov dbal , section is designed as Singly Reinforced Under-Reinforced Section (SRURS).
=0.87fyAstd(1- )
1627.26 x 106 = 0.87 x 415 x Ast x 937.5 x (1- )
Ast = 5469.67 mm2
Spacing =
=
= 89.74 mm
Provide 25 mm bar @ 75 mm c/c
Astprov =
= 6544.98 mm2
pt = =
= 0.69 %
As = mm2
80
Provide 16 mm bar @ 150 mm c/c,[vertical bars spacing 200 mm]
Astprov =1340.412 mm2, ptprov= 0.13 %
c. Horizontal Reinforcement
Take, As = 0.1% of stem area of abutment or 25% of main vertical bars
= 0.001 1000 1000
= 5645 mm2
Provide 30 - 16 mm bar on each face of abutment
dbal =
Where, Q = 0.36 fck 0.48 (1 0.416 0.48) = 2.76
Since dprov> dbal, section is designed as Singly Reinforced Under-Reinforced Section (SRURS).
pt = 0.35 %
Curtail half of main vertical bars (bars designed for bottom section of abutment) at
2.94m (2 m + d) from the bottom of abutment.
b. Horizontal Reinforcement
Take, As = 0.1% of stem area of abutment or 25% of main vertical bars
= 0.001 5645 1000 = 5645 mm2
81
Provide 30 - 16 mm on each face of abutment.
82
Stability Check
Stability of abutment is checked for overturning and sliding. In the following table
overturning moment and restoring moment about the toe of footing of abutment and shear
at the base of footing have been calculated.
Check:
a. 5.034752 (safe)
b. = 4.206784 (safe)
83
Stability Check for seismic combination of loads
Lever
Overturning Restoring
Load (KN/m) overturning Restoring arm moment moment Shear force Vertical load
DLss 246.71 1 2.41 0 594.5711 0 246.71
DLwc 19.89 1 2.41 0 47.9349 0 19.89
DLap.s 13.26 1 2.825 0 37.4595 0 13.26
LL 152.62 0 2.41 0 0 0 0
Fbrh 1.138 0.2 7.4 1.68424 0 0.2276 0
Fbrv 2.5 0 2.41 0 0 0 0
Fs hL 4.845 1 0 0 4.845 0
Fs vL 2.87 0 0 0 0
Fcst 6.79 0.5 7.4 25.123 0 3.395 0
DLab 172.7 1 2.5 0 431.75 0 172.7
Fs Abt hL 25.9 1 0 0 25.9 0
Pep v(D) 132.148 0 3 0 0 0 0
Pep H(D) 296.81 1 3.99 1184.2719 0 296.81 0
Psur V 20.36 0 3 0 0 0 0
Psur H 45.74 4.75 0 0 0 0
WBF 545.0625 1 4.875 0 2657.179688 0 545.0625
W footing 189.84 1 3.375 0 640.71 0 189.84
Total 1211.07914 4409.605188 331.1776 1187.4625
Check:
a. = 3.641055 (safe)
b. =2.509903 (safe)
84
Analysis and Design of spread footing:
Analysis of spread footing:
85
Responses of footing at its base in seismic combination of loads
Dist
from eccentricity Muy
Load (KN/m) bottom x (m) y (m) Pu(KN) Mux(KNm) (KNm) Hx(KN) Hy(KN)
DLss 246.71 1 0.965 -0.04 246.71 238.07515 0
DLwc 19.89 1 0.965 -0.04 19.89 19.19385 0
DLap.s 13.26 1 0.55 0.375 13.26 7.293 0
LL 152.62 0.2 0.965 -0.04 30.524 29.45566 0
Fbrh 1.138 0.2 7.4 0 0 0 1.68424 0.2276
Fbrv 2.5 0.2 0.965 -0.04 0.5 0.4825 0
Fs hl 4.845 1 7.4 0 0 0 35.853 4.845
Fs vl 2.87 1 0.965 -0.04 2.87 2.76955 0
Fcst 6.79 1 7.4 0 0 0 50.246 6.79
DLab 172.7 1 0.875 0 172.7 151.1125 0
Fs abt hl 25.9 1 3.9475 0 0 0 102.24025 25.9
Pep v(D) 132.148 1 0.375 0.55 132.148 49.5555 0
Pep h(D) 296.81 1 5.7 0 0 0 1691.817 296.81
PsurV 20.36 0.2 0.375 0.55 4.072 1.527 0
PsurH 45.74 0.2 4.75 0 0 0 43.453 9.148
W BF 545.0625 1 -1.6875 545.063 -919.793 0
W footing 189.84 1 0 189.84 0 0
Total 1357.58 1504.9652 343.72
Seismic Combination
86
d d = 1125 - 75 - 20/2 =1040mm
1.125m
IIv IIM IM Iv
2 2
333.76 KN/m 378.37 KN/m
2
399.37 KN/m
2
251.746 KN/m
2 2
311.011 KN/m 355.63 KN/m
Analysis of footing
Find Maximum BM at face of abutment and one-way shear at the section lying at d distance
from the face of abutment.
Maximum BM at IM = = 755 KN-m
Maximum BM at IIM = = 2058.42 KN-m
Maximum SF at IV = = 373.31 KN
Design of footing
Check depth of footing
dbal =
87
Astprov = 4021.23 mm2, ptprov= 0.38%
Provide 32 mm bar @ 200 mm c/c
Since, provided length > , additional anchorage for bars are not required
88
Analysis and Design of RC Pier:
Geometry of Pier
L = C/c distance of main girder + 2 12 bearing width + 2 0.5 = 3 + 2 0.4/2 + 2 0.55 = 4.5 m
Where, = / 0 = 1643.96 1.5 1000/2 (630 + 400+502 + 502) 502 = 1.20 N/mm2
=1 h f h h .
89
Load Calculation
Dead Load on a pier from both span (DLss) = (3213.65/) 2 =3213.6 5KN =714.14 KN/m
0.952
0.78
0.66 0.54 0.42
LL1=114*1.25(1+0.952)+68*1.25(.78+.66+.54+.42)
6
=482.16KN
LL2=27*1.25(.78+.824)+114*1.25(.952+1)+68*1.25(.824+.71+.59+.468)
= 552.96 KN
90
Case: 5 KN/m2 Load
Where,
Z = 0.36, I = 1, R = 4, / = 2.5
91
8. Seismic load (Sub Structure)
Seismic loads due to self weight of pier in longitudinal and transverse direction of bridge are equal
FST(Sub) = FSL(Sub) = ( / )( / )( / ) Wpier
Where,
Z = 0.36, I = 1, R = 4, = 2.5
Wpier = ((1.91+2.85)/2)x4.50x9x25+4.50x2.11x.55x25
=2537.31KN
The load due to temperature variation, creep and shrinkage effect from two spans acts in
opposite direction. So it is not considered in design.
Wpier = ((1.91+2.85)/2)x4.50x9x25+4.50x2.11x.55x25
=2537.31KN
= 52 K (V cos200)2 A
= 52 0.66 (6.24 cos200)2 2.455x7.5 10-2
= 217.27KN
= 52 K (V sin200)2 A
= 52 0.66 (6.24 sin200)2 4.5 7.5 10-2
= 52.75 KN
92
Design of Pier Cap
Take area of steel AS = 1 % of area of cap and distribute these bars equally at top and bottom of
cap. [Refer IRC 78 CL. 716.2]
Ast in longitudinal direction of abutment
93
Analysis and Design of Pier Stem:
Case I
Basic combination of loads
Distance
Load(KN/m) f from Eccentricity Pu Mux Muy Hx Hy
(KN.m/m) (KN.m/m) (KN/m) (KN/m)
94
Case I
Seismic combination of loads
Distance
Load(KN/m) f from Eccentricity Pu Mux May Hx Hy
bottom(m) X Y (KN/m) (KN.m/m) (KN.m/m) (KN/m) (KN/m)
95
Case II
Basic combination of loads
Distance
Load(KN/m) f from Eccentricity Pu Mux May Hx Hy
bottom(m) X y (KN/m) (KN.m/m) (KN.m/m) (KN/m) (KN/m)
96
Case II
Seismic combination of loads
Distance
Load(KN/m) f from Eccentricity Pu Mux May Hx Hy
bottom(m) X y (KN/m) (KN.m/m) (KN.m/m) (KN/m) (KN/m)
97
Design and Detailing of Pier Stem at bottom
Check slenderness ratio of column [Refer Cl. 306, IRC 21]
Case 2 (i)
2
/( ) = 665.8 106/(201000x1910^2) = 0.01
/ )=1954.48 1000/(201000x1910) =0.051
= 0.018 [From chart , SP 16]
p=200.018= 0.36 % < pmin
Provide pmin = 0.8 %
Case 2 (ii)
2
/( ) = 0.016
/ ) =0.035
= 0.02 [From chart , SP 16]
p=200.018= 0.4 % < pmin
Provide pmin = 0.8 %
Hence, = 0.80/100(1910x1000)= 15280
Total area =15280x4.5=68760
Using 28 mm bar,
No of bar = =111.66, Adopt n=116, Bar on each side =58
Spacing < b=1910 mm, 16x28=448mm,300mm
Provide 116-28 mm bar @75 mm c/c.
98
Ast min= x4448810 = 35590.40
Using 28 mm bar
b. Transverse Reinforcement
Size of footing:
Adopt B= 7.70 m
99
D=2000-50-10 =1940 mm
Mu=0.87fyAstd(1- )
Ast=2704.69
Using 25 mm diameter bar as longitudinal bar.
Pt = 100 =0.16%
v= = 0.192 N/
Ld= = =1176 mm
100
5. QUANTITY ESTIMATE
Quantity estimates are performed for all super-structural elements which include railing post,
kerb, cantilever and restrained slab and girders. The sub-structural components are
composed of two mains, abutments and a RC solid wall type pier. Only the quantity estimates
are taken. However, to determine the actual cost of the material of construction, detailed
rate analysis pertaining to current rate of items as specified by concern district authority has
to be performed.
Length Breadth Height Quantity Unit
S.N. Description of item No.
(m) (m) (m)
Superstructure
1 Railing 58 0.225 0.225 1.1 3.22988 cu.m
Total 3.22988 cu.m
Railing bar mm dia @ 4.37
12 25 1311 Kg
Kg/m
5 Main Beam
Web 2 50 0.4 1.85 74 cu.m
6 Cross Beam
End cross beam 4 3.6 0.195 sq.m 2.808 cu.m
Intermediate cross beam 8 3.6 0.3975 sq.m 11.448 cu.m
Total 194.176 cu.m
Substructure
7 Abutments
Dirt wall M20 2 4.6 0.35 1.88 6.0536 cu.m
Abutment capM25 2 4.6 1.1 0.55 5.566 cu.m
Abutment stem M20 2 4.6 1 5.65 51.98 cu.m
Abutment Foundation M20 2 4.6 6.75 1.125 69.8625 cu.m
Total 133.4621 cu.m
8 Pier
Pier cap M25 1 4.5 2.11 0.55 5.22225 cu.m
Stem (M20)
Semicircular part 2 2.224 sq.m. 9 20.016 cu.m
Rectangular part 1 4.5 1.91 9 77.355 cu.m
Footing M20 1 7.7 7.35 2 113.19 cu.m
101
Total 215.78325 cu.m
9 Approach slab(M25)
ss slab 2 3.5 4.65 0.3 9.765 cu.m
kerb 2 3.5 0.5 0.3 1.05 cu.m
Railing post 6 0.225 0.225 1.1 0.334125 cu.m
Rail Bars
Railing bar 48.3 mm dia @
4.37 Kg/m 6 3 78.66 Kg
102
References
[1] T.T. Jagadesh & M.A. Jayaram Design of Bridge Structure PHI Learning Pvt.
Ltd,
New Delhi, 2010
[2] Johnson, Victor. D, Essentials of Bridge Engineering, Oxford & IBH Publications,
New Delhi, 1980
[3] Pillai and Menon, Reinforced Concrete Design
[4] Swami Saran, Design of Substructures
[5] IRC 5 -2000: Standard specification and code of practice for road bridges,
Section I,
General features of Design, 20000
[6] IRC 6 2000: Standard specification and code of practice for road bridges,
Section II,
Loads and Stresses, 2000
[7] IRC 21 2000: Standard specification and code of practice for road bridges,
Section III,
Cement Concrete (Plain and Reinforced), 2000
[8] IRC 112 2011: Code of practice for concrete road bridges
[9] IS 456 2000: Indian standard Plain and Reinforced concrete Code of Practice
[10] SP 16 - 1980: Design aids for Reinforced Concrete to IS: 45 1978
[11] SP 34 - 1987: Hand book on concrete reinforcement and detailing
[12] IRC 83 1987: Standard specification and code of practice for road bridges,
Section IX,
Bearings, Part II: Elastomeric Bearings, 1987
[13] IRC 78 1983: Standard specification and code of practice for road bridges,
Section VII,
Foundations and Substructures, 1988
[14] Design examples and training materials for bridge components, N.C Sharma
103