INSTALLATION MANUAL
Model SJ Actuator
With
Model E391 Controller
General
The following information is intended as an aid to properly applying a Precision
Governor Electric Governor. Since these governors are used on a variety of engines in
many different applications, much of the information is somewhat general in nature. If
you need assistance concerning a specific application, please consult Precision Governors
Application Engineering at 815/229-5300.
These instructions presume no electrical test equipment other than a multimeter for
making the electrical measurements called for on the following pages. A suitable meter
may be obtained at many outlets such as Radio Shack.
Actuator installation
With the engine operable and without the electrical governor installed, run the engine and
lock the manual throttle in a position where a speed of 300-400 RPM over the maximum
desired speed is obtained. Use both adjustment screws to lock the throttle. The SJ
actuator is then mounted to the rear of the fuel injection pump in place of a shutdown
solenoid. An adapter is provided for each engine to facilitate mounting. The adapter is
mounted to the engine with a gasket and 2 M6 socket head cap screws. The actuator is
then mounted to the adapter, again, with 2 M6 socket head cap screws. (See illustrations)
Use the 2 threaded holes that make access the easiest. Be sure the o-ring is in place on
the actuator prior to installation. Slide the actuator straight into the pump to avoid
damage to the pump or actuator.
Controller installation
The controller is water and weather resistant when the cover plate is sealed with RTV by
the user. However, attention to the following points will enhance its performance and
reliability.
• The cover plate will probably need to be removed during setup in order to make
adjustments of speed setting and gain. You may wish to defer final mounting of the
controller until the adjustments are complete.
• After completing the adjustments, replace cover and seal with a fillet of RTV. Mount
so that water cannot pool on the cover. Also, mounting with this cover out of sight,
discourages tampering.
Wiring
See the wiring diagram for connection details. The following information is important
for a good installation.
• If governor power is to be switched through the ignition switch, run power to the
governor directly via a dedicated #16 wire. Check that the wiring from the battery to
the switch is at least #14.
• Go directly from the controller ground terminal by dedicated wire to the battery
minus terminal. If this cannot be done for some reason, go by dedicated wire to a
very good engine ground.
• A properly functioning engine electrical system will supply 13.5 to 14.8 VDC when
the engine is running. If wiring size is adequate, with good connections and proper
grounds, this voltage will be obtained at terminals 1 & 2 or A & B when the governor
is controlling engine speed. Be sure to verify this.
• Use a multimeter to check battery voltage at the battery. Now check battery voltage
at the machine connection points for terminals 1 & 2 or A & B. The second voltage
reading should be the same as at the battery. If not, shut down and correct wiring.
• Before proceeding, familiarize yourself with the locations of the Speed Set pot and
the Gain pot. Also, read the section on Adjustments.
• Start the engine and set the machine controls to call for the highest governed speed
required. Adjust the Speed Set pot slowly as needed to obtain the speed desired. If
engine surges, reduce the Gain slightly.
• Re-check the voltage between the connections for terminals 1 & 2 or A & B. The
reading should be between 13.5 and 14.6 VDC. If it is less, look for undersized
wiring somewhere in the system or for other components wired in parallel with the
governor.
• Carefully adjust the Gain pot. You are looking for the best compromise between
quick response and good stability. Make very small adjustments, then load and
unload the engine. Usually, a good set-up is one that makes 1 to 3 small bounces and
then settles down after a large load change. Too much Gain shows up as a rapid
(once per second) instability, most commonly at light loads. Too little Gain shows
up in large overshoots on startup or large load changes and generally sluggish
operation.
• Set machine controls to obtain low engine speed. Make any adjustments required to
the Aux speed at this time. The engine speed should now ramp between the low and
high speeds, following the action of the up/down switch on the machine. The
adjustment of the Speed Set and Aux Speed controls may need to be repeated a
couple of times as there is some interaction between the 2 adjustments.
• Re-install the cover plate. Add a fillet of RTV around the edge of the cover to seal
against dirt and moisture. Final mount the controller.
Governor adjustments
Multi-turn adjustments (Speed Set, Aux Speeds) – These adjustments are made by
turning the 1/8” brass screw clockwise (CW) to increase and counterclockwise (CCW) to
decrease the settings. The adjustment range of the pot is 25 full turns. This pot is
protected by a slip clutch at each end of the range and is not damaged by moderate over-
adjustment. However, the governor will not function while the pot is past full travel. If
you suspect you may have over-adjusted one of these pots or have lost track of where you
are, turn the pot 25 turns in one direction, then back 10-12 turns to get back into the
normal range.
Single turn adjustments (Gain, Factory Adjust) – These pots are 3/8” square and have a
!/8” plastic screw slot in the center. Be gentle! These pots turn 270 degrees and over-
turning will break the internal stops, making adjustments impossible. Turning these pots
CW increase response while turning CCW decreases response.
Troubleshooting
If the governor system fails to operate or doesn’t operate properly, check the following
and apply corrections as appropriate.
• Power and wiring – check the wiring to the diagram furnished here or with the
machine. Also, perform the voltage tests described above in the wiring section.
Wiring to the actuator should also be adequate and not be contacting the frame or
engine.
• Speed reference signal – the magnetic pick-up mounted on the engine sensing the ring
gear teeth must deliver a signal at a minimum of 5 VAC during cranking.
• Machine speed selection switches or relays – check that all machine wiring is
functioning and providing the correct signals to the control box.
If the above test do not show a fault, the unit can be operationally checked as follows:
• With the engine stopped, remove the actuator from its adapter plate. Make the
manual throttle hand operable.
• Start the engine and operate the throttle by hand running the engine above and below
the speed the governor is set for. As the engine speed goes above and below this
speed, the actuator rod should move in and out. This indicates the governor system is
working and trying to control fuel to the engine. If suitable operation is noted with
the actuator removed, check for any interference between the actuator rod and the fuel
injection unit.
• Check during cranking that the actuator rod is fully pulled in. This is a function of an
external relay furnished by the machine OEM.
Check adjustments of the controller. The controller is factory set during engine test to
perform well. If the adjustments have been changed since this test, it may be wise to
return the adjustments to a known starting point. Mid range on the speed pots is normally
satisfactory. A good starting point on the gain and factory adjust pots is full CCW, then
CW ¼ turn. The gain pot is the basic adjustment for stability or sensitivity. Make small
adjustments and then re-check performance.
Adapter Installed