Merloni Elettrodomestici SpA Case Analysis Ver 1.2
Merloni Elettrodomestici SpA Case Analysis Ver 1.2
Merloni Elettrodomestici SpA Case Analysis Ver 1.2
Batch : PGCBM – 16
Besides above four plants Merloni had a centralized warehouse and seventeen warehouses across
Italy.
Here cross-docking refers to moving product from a manufacturing plant and delivering it
directly to the customer with little or no material handling in between. In the current case the
company ran a pilot project for cross docking at Milano warehouse loading area.
The following picture depicts the key logistics channel for Merloni SCM. We will discuss
4.1.1. Retailers/Customers
The customers had to be educated that if they want to receive an order delivered by
following day, they had to order before 3 PM. The company did not want to
increase the transport facility in case of high demands. Instead it would ask
customers to expect some delay in order replenishment. This will definitely create a
In the existing system over 65% of products were delivered within 24 hours,
directly from the regional warehouses. Rest 35% of products was shipped from
the central warehouse with a two to six day delivery times. Eliminating inventories
at regional warehouses would increase the delivery time for all products to two to
six days.
Further delays due to product damage could potentially double the delivery times.
The significant increase in lead time will certainly adversely affect customer-
satisfaction.
Although the two months trial that took place between the central warehouse and
Milan was successful, the distance between the two locations was relatively small
relative to the distance to the other regions.
Company decided a daily trailer-load of product from central warehouse to transit
point. Daily deliveries to some of the regions inaccessible via ground transport
were neither possible nor efficient. The company may need higher tracking facility
for other regional warehouses.
So we see that there is a trade off between responsiveness and efficiency and
company preferred efficiency.
Merloni’s objective was to remove all regional warehouses and implement cross
docking facility. By doing so, the company would save money.
The sheet at appendix gives the cost to run all seventeen warehouses.
At this channel the company was trying to work on both responsiveness and
efficiency.
Although the company had planned to replace warehouses by cross docking facility,
the cost of maintaining it could be significant. These operational cost savings would
be associated with reduction in space, utility, and labor usage.
However, Merloni would still need to maintain the facilities needed for cross-
docking as well as temporary storage of units that it was unable to delivery
immediately.
As per Mr. Bosi the total operating costs might come down to 20% if company was
able to suspend warehouse lease payments and discharge warehouse employees.
The company would better off by allowing cross docking.
At this channel the company was trying to work on both responsiveness and
efficiency.
Increased number of trailer departures from the central warehouse would also
require that extra shipping docks be installed. The cost of modifying the central
warehouse would further offset the potential cost savings realized at the regional
warehouses.
As per the case – “To further reduce inventory levels and enhance production
efficiency, Dr. Merloni wanted to streamline Merloni’s distribution system;
introduce more flexibility into the production process (by reducing set-up times to
economically attain shorter run sizes); shorten the production planning period first
to eight weeks, then to four weeks; and institute a “distribution resource planning”
program to translate product distribution forecasts into production planning needs.
The new transitpoint concept seemed to be a vital component of the vision; testing
the concept’s viability would be the first step toward the achievement of that goal.
This is what company management set out to do in January and February 1986.”
It means that the plants would be more efficient leading to cost savings.
Scraping the regional warehouses may also impact the inventory maintained at the
plant site. This could lead to some investment and maintenance at the plant site.
Some of the key logistic activities as given below would also be impacted.
Although much of the impact is already discussed in section 4.1. We will discuss
some of the activities in brief.
The Company would need advance demand forecasting and planning techniques
to avoid cost of sales and lost sales. The efficiency of the system will be
measured by tacking the problem of spur increase in demand in the month of
August. As the company is more focus on efficiency, it should make sure that the
cost of lost sales should not be very large.
Current inventory levels held at the regional offices were already 75% lesser in
comparison to historical figures. This level of inventory was established based
on customer demands and constrained by production lead-times. Although the
transit point concept would eliminate inventory stocks at the regional
warehouses, it could not reduce the overall required inventory levels. Therefore,
the current requirements of inventory would not be affected.
The Company would require advance IT systems to integrate the demand forecast
with all the logistic channels. Any instance of channels not being in sync would
cost the company heavily.
Good and reliable information flow across the entire supply chain. In the current
case it was distribution crossdocking where the crossdock itself allocates material
to its RWH.
The major operational cost for crossdock is the labor cost. Hence, the system
performance is optimized by seeking to maximize the throughput of the
crossdock operations by establishing an efficient freight flow.
As given in the case, the company had access to semi skilled labors. A transit
point system requires much more diligent planning and coordination. The
company would require skill labors which would cost it significantly. Or
providing training to existing labors would also cost it.
The administration staff might need to work longer and later hours, which could
offset some of the cost savings realized from warehouse operations. Higher
stress levels among the administration staff could also increase turnover and
associated costs.
5. Recommendation
After studying the case we can propose following few alternatives for increasing the efficiency of
its distribution network while maintaining or increasing the responsiveness of the SCM.
The conversion of the Milano warehouse into an exhibition center could lead to sales and
marketing strategic advantage. One alternative would be to continue serving the region through a
transit point. The current distribution network could then be maintained for the remaining
regions. Although this alternative would not address the primary issue (efficiency of the
distribution network as a whole), it would allow Merloni to continue operating its exhibition
center without significant risks to product delivery.
After careful analysis of the primary issue and the critical factors, the recommendation is not to
deploy the transit point concept across all the regional offices. For the reasons explained above
(please refer Analysis), doing so will increase average product delivery times and adversely affect
customer satisfaction. At the same time, the cost-savings realized from conversion of warehouses
to transit points may be offset by higher costs of transportation, costs of modifying the central
office, and cost of lost sales due to customer dissatisfaction.
The third alternative explained above, however, addresses the primary issue. It leverages the
benefits of the transit point concept as well as that of transshipment. Furthermore, it ensures that
the Milano warehouse continues to operate as an exhibition center for Merloni's clients.
In order to implement this alternative, careful analysis of transportation costs between different
regions as well as operational costs of carrying inventory in each region must be determined.
This data can then be used in combination of a linear programming solution or a DRP software
capable of determining the optimum distribution and delivery solution for maximizing efficiency
and minimizing costs and delivery times.
Appendix
http://www.slideshare.net/rivetmoscow/cross-docking-challenges-in-regional-growth-environment
http://www.echeat.com/essay.php?t=27487