Final Rules - Annex A of Res20
Final Rules - Annex A of Res20
Final Rules - Annex A of Res20
Final Rules
05 December 2017
llPage
Table of Contents
l
5
I. General pro~sions
1.1 Background 5
::::::l:::::::::::::::::::::::::::::::::::::
!
::::::::::::::::::::
1.4 Construction of the Rules
:::::
::::
::::
::::
:::::: 6
21page
ANNEX A:.Methodology for Segregating DSL 21
i
A.1 Introduction 21
A.2 Comppnents of Distribution System Loss 21
I
A.3 Calculation of Distribution System Loss 22
I .
A.4 Distribution Network Models ~..26
A.S Distribution Load Models 30
A.6 Data Requirements : 32
31Page
List of Tables
List ofFi~res
I
Figure 1. Rew~rd Structure ofllie PIS for Electric Cooperatives 14
Figure 2. Reward Structure of the PIS for Private Distribution Utilities 15
Figure 3. Conductor Arrangement 42
Figure 4. Bundling of Conductors 44
Figure 5. Conductor Spacing 45
Figure 6. Spacing of Phase Conductors and Ground Wire ..45
Figure 7. Distkce between Ground Wires .45
Figure 8. Dist~nce between Circuit 1 and Circuit 2 46
Figure 9. Height of Phase Conductors and Ground Wires 46
Figure 10. Constructional Data of Underground Cable .48
Figure 11. Conductor Arrangement 58
4lPage
I. Gene,al Provisions
1.1 Background
sebon 38 of Republic Act No. 9136, otherwise known as the Electric Power
Industry Reform Act of 2001 or EPIRA, created the Energy Regulatory
Cohtmission (ERC) as an independent quasi-judicial regulatory body.
SIPage
1.2 Purpose
This Rules for Setting the Distribution System Loss Cap and Establishing
Performance Incentive Scheme for Distribution Efficiency embodies the
new regulatory framework for all Distribution Utilities (DUs) that is
designed to achieve the following:
a. Determine reasonable DSL Caps for all DUs based on technical criteria
i and objectives given in the EPIRA;
b. Align the new DSL Caps with the existing Performance Incentive
I Schemes (PIS) that promote efficient operation and service of the DUs;
and
c. Promote submission from the DUs of comprehensive information
relevant to DSL.
Scope
I
This Rules shall apply to all DUs, whether Electric Cooperative (EC) or
Private Distribution Utility.
61Page
This is the sum of Feeder Technical Loss and Non-
Distribution
Feeder Loss Technical Loss.
The system of wires and associated facilities that
Distribution
belong to a franchised Distribution Utility,
SYstem extending between the delivery points on the
Transmission or Sub-Transmission System or
generator connection and the point of connection
to the remises of the End-User.
The electric Energy Input minus the electric
Distribution Energy Output for a specified billing period or set
System Loss
DSL of billin eriods.
Any Electric Cooperative, private corporation,
Distribution
government-owned utility, or existing local
Utility (DU)
government unit, which has an exclusive franchise
to operate a Distribution System in accordance
with its franchise and EPIRA.
The aggregate of energy used for the proper
Oistribution
Utili Use o eration of the distribution tern.
The level of Distribution System Loss recoverable
DSLCap
from Customers.
I The Distribution System data containing
OSLData
information that can be used to simulate the
Technical Loss, and is described under Annex A of
this Rules.
A Distribution Utility organized pursuant to
Electric Presidential Decree No. 269, as amended, or
Cooperative
, (00)
I
otherwise rovided in EPIRA.
Generating Units that is indirectly connected to
Embedded the Grid through the Distribution Utilities' lines or
Generators
industrial generation facilities that are
synchronized with the Grid. For the purpose of
this Rules, this term shall include a Generating
Plant that is connected to an Isolated Distribution
Stem.
The integral of electrical power with respect to
';Energy time and is measured in kilowatt-hours Wh.
I Energy delivered to the Distribution System by the
iEnergy Input Transmission System, Embedded Generators,
other Distribution Systems, and User Systems
with eneratin facilities.
Energy delivered to the Users ofthe Distribution
i Energy Output System, including the Energy for Distribution
! Utili Use.
The independent quasi-judicial regulatory body
Energy Regulatory
Commission created under EPIRA.
RC A group of Distribution Utilities entering a
Entrant Group regulatory program at the same time, as defined in
ERC Resolution No. 10, Series of 2010 for Private
DUs or in ERC Resolution No.8, Series of 2011 for
Electric Coo eratives.
Republic Act No. 9136, otherwise known as the
EPlRA Electric Power Indus Reform Act of 2001. .
All apparatus, machines, and conductors, among
Equipment others, that are used as a part of or in connection
with an electrical installation.
7\Page
Feeder Technical The sum of the Technical Losses associated with
Loss the Primary Distribution System and the
Seconda Distribution S em.
Generating Plant A facility consisting of one or more Generating
Units.
Generating Units A conversion apparatus, including auxiliaries and
associated Equipment, that function as a single
unit and is used to produce electric Energy from
some other form of Ener .
Grid The high voltage backbone System of
interconnected transmission lines, substations,
and related facilities, located in each of Luzon,
Visayas, and Mindanao, or as may be determined
by the ERC in accordance with Section 45 of the
EPIRA.
Higher Voltage A Customer that is connected to and served
Customer (HV or through the Sub-Transmission System or the
MVCustomer Prim Distribution Stem.
Isolated The backbone system of wires and associated
Distribution facilities that are not directly connected to anyone
System of the national Transmission Systems of Luzon,
, Visa s or Mindanao.
Low Voltage A Customer that is not a Residential Customer and
:Customer (LV is connected to and served through the Secondary
Customer Distribution S em.
.Non-Technical The aggregate of Energy lost due to pilferage,
Loss(NTL) meter reading errors, meter tampering, and any
Energy loss that is not related to the physical
characteristics and functions of the electric
tern.
An Electric Cooperative that operates an Isolated
I Off-Grid EC
I Distribution tern.
I
An Electric Cooperative that operates a
IOn-GridEC Distribution System that is connected to anyone
of the national Transmission Systems in Luzon,
Visa s or Mindanao.
The maximum value of power, measured in MW,
Peak Power
required by the Distribution Utility for a specific
Demand
billin eriod or set of billin eriods.
Performance Mechanism designed to incentivize the
Distribution Utility to improve its performance.
i Incentive
For the purpose of this Rules, performance shall
I Schemes (PIS) be in terms of distribution efficiency measured
throu h Distribution em Loss.
A compilation of rules and regulations that govern
philippine
Distribution Code the Distribution Utilities in the operation and
maintenance of their Distribution Systems, which
(PDC) includes, among others, standards for service and
performance, and defines and establishes the
relationship of the Distribution Systems with the
facilities or installations ofthe parties connected
thereto.
A portion of the Distribution System delineated by
Primary the secondary side of the Substation transformer
Distribution and the primary side of aU Distribution
System.
transformers.
8lPage
Private A Distribution Utility that is operated by a private
Distribution corporation.
Utili PD
Reference An idealized version ofthe Distribution System,
Distribution formulated as prescribed in Section 4 of this
Network Rules.
Regulatory Period A period of time over which the rates of the
Distribution Utility is defined under a set of rules
issued b the ERe.
Republic Act No. The law otherwise known as the Anti-electricity
and Electric Transmission Lines/Materials
7832
Pilfer e Act of 1
Residential A Customer that is residential in nature and
Customer connected to and served through the Secondary
I Distribution S stem.
Secondary A portion of the Distribution System that is at the
Distribution secondary side of a Distribution transformer.
S stem
Secondary Line A Distribution line connected at the Secondary
Distribution System.
Sub-Transmission This is the sum of Sub-Transmission System and
and Substation Substation Technical Losses and Non-Technical
Loss Loss.
Sub-Transmission The sum of the Technical Losses associated with
and Substation the Sub-Transmission System and Distribution
Technical Loss substations.
Sub-Transmission The portion of the Distribution System that is
System delineated by the connection point to the
Transmission System and the primary side of all
Substation transformers.
System A group of components connected or associated in
a fixed configuration to perform a specific
I function.
System Loss The charge representing recovery of the cost of
Chare ower due to Distribution Stem Loss.
System Loss Rate The rate determined in accordance with ERe
Resolution No. 16, Series of 2009 and any
I amendments thereto.
The component of Distribution System Loss that is
Technical Loss
(TL) inherent in the physical delivery of electric
Energy. It includes conductor loss, transformer
I, core loss and technical error in meters.
Three-Phase An analytical tool that simulates the power flows
Power Flow in an unbalanced three-phase Distribution
Stem.
Transmission Has the same definition as "Grid".
Stem
User A person or entity that uses the Distribution
System and related distribution facilities.
User System A System owned or operated by a User of the
Distribution System.
91Page
1.6 Provision of Information
i
1.7.4 For the purpose oftbis Rules, no distinction shall be made between a
Captive Customer and a Contestable Customer. They shall be
considered Customers insofar as they are served through the
Distribution System of the DU.
10lPage
II. Distribution System Loss Caps
2.1 Electric Cooperatives Clusters
2.1.1
I For the DSL Caps, the following clusters of Electric Cooperatives are
set as shown in Table 1to Table 3. '
BANELCO MASELCO
BASELCO MOPRECO
BATANELCO OMECO
BISELCO ORMECO
CASELCO PALBCO
CELCO PROSIELCO
DlELCO ROMELCO
FICELCO SIARELCO
IFELCO SIASELCO
KAELCO SULECO
LUBELCO TAWELCO
MARELCO TlELCO
MARIPIPI TlSELCO
111 P age
Table 3. Electric Cooperatives Cluster 3
BATELECII
MORESCO I
PENELCO
SOCOTECOI
CENECO
LEYECOII
SOCOTECOII
ZAMCELCO
2018 6.50%
2019 6.25%
2020 6.00%
2021 5.50%
121Page
I
I
Where,
SLsysLossCharge = Total Distribution System Loss that can be
recovered through the System Loss Charge, in
percent;
DSLsT+ss = Sub-Transmission and Substation Loss, in percent;
TLfdr = Feeder Technical Loss, in percent;
NTL = Non-Technical Loss, in percent; and
DSLfdr,cap = Distribution Feeder Loss cap, in percent.
2-4-4 In the absence of Metered DSLsT+SS data submitted by the DU, the
I Distribution Feeder Loss (DSLjar) shall be set to 0.00.
3.1.2 The PIS shall involve a price-linked reward for DUs. The reward shall ~
1
I be a percentage of the Distribution Charge. ~,.
i
3.~.3 The Distribution Feeder Loss to be used for the PIS shall be
computed based on the actual Distribution Feeder Loss for the most
recent 12-month period.
131Page
3.i.4 The reward under the PIS for distribution efficiency is separate from
and does not affect the System Loss Rate that the Distribution Utility
can pass on to its Customers through the System Loss Charge.
3.2J2 The PIS reward structure for ECs shall be as shown in Figure 1, with
three regions, in order of improving distribution efficiency: (1) no
reward, (2) increasing reward, and (3) maximum reward.
a
•...................•.............................
Distribution Feeder Loss (%)
3.2.3
, The distribution feeder loss component ofthe performance incentive
I factor (8) shall be computed in the following manner:
3.2.4 Based on the value of the actual total DSUdrand its relationship with
the various thresholds in the PIS reward structure for ECs, the value of
the Performance Assessment Factor (PerfDSLfdr.t-1) shall be
determined in the manner shown in Table 6.
3.2.5 The values of the thresholds (a and b) in the PIS structure for each
cluster of electric cooperatives are shown in Table 7.
141Page
Maximum reward a ~ DSLfdr PerfDSL{dr.t-l = +1.0
Proportional b - DSLfdr)
b ~ DSLfdr>a . Per fDSL{dr,t-l = ( b_ a
reward
I
3.2.6 The thresholds of the PIS structure shall be used by the Commission in
its setting of the maximum price-linked incentive for ECs.
3.3.1 The PIS reward structure for Private DUs shall be as shown in
Figure 2, with three regions, in order of improving distribution
efficiency: (1) no reward, (2) increasing reward, and (3) maximum
reward.
a
•...................•........................•....
Distribution Feeder Loss (%)
Where,
SDSL{dr.t = Performance incentive for Distribution Feeder
Loss for year t;
!
= Weight assigned to Distribution Feeder Loss
performance; and
Per fDSL{dr.t-1 =
Performance Assessment Factor for Distribution
Feeder Loss in the previous year.
151Page
3.34 Based on the value of the actual total DSLfdrand its relationship with
the various thresholds in the PIS structure for Private DUs, the value
of the Performance Assessment Factor (PerfDSLfdT,t-l) shall be
determined in the manner shown in Table 8.
I
3.3.5• The values of the thresholds (a and b) in the PIS reward structure for
Private DUs are shown in Table 9.
.. '.,
"
;
The thresholds of the PIS structure shall be used by the Commission in
the next setting of the maximum price-linked incentive for Private
DUs.
. :
161Page
IV. Application for Individualized DSLCaps
4.1 Geheral
, Provisions for the Individualized DSL Cap
4.1i.1 A Distribution Utility may elect to use an alternative method for
determining an individualized DSL Cap that shall be applied to it.
This section of the Rules is intended to provide the framework for
such a method.
4.1.2 The individualized DSL Cap shall have two components: one for
Technical Loss and another for Non-Technical Loss in accordance
with the prescribed methodologies in this Rules.
4.1.3 If a Distribution Utility has elected for an individualized DSL cap (or
a component thereof), it may continue to use the existing cap subject
to prior approval ofthe Commission.
4:2.2 For each segment of the Reference Distribution Network, the total
cost shall include capital expenditures, operating and maintenance
expenditures, the cost of Technical Loss, and all other associated
costs. In deciding the appropriate size for each segment, the DU may
consider load forecasts and associated costs up to the expected
economic life of the segment (for example, 30 years for distribution
lines). For segments where special considerations must be made (for
example, in segments where one type of conductor is favored due to
environmental considerations), the DU must be able to justify these.
4.2.3 To the extent possible, the characteristics of the load of the Reference
Distribution Network shall have the same characteristics (in terms of
location and load behavior) as the Customers of the Distribution
Utility. c:/
In determining the Technical Loss component of the individualized
DSL Cap, the DU may use load forecasts up to the end of the next
Regulatory Period.
17 I P age ,
4.2.5 For each year; from the test year to the end of the next Regulatory
Period, the Technical Loss of the Reference Distribution Network
shall be determined based on load flow simulations. If the load flow
simulations show that there are voltage violations in the distribution
network, the DU must first correct these in the model through
selection of appropriate sizes of distribution lines and distribution
transformers, application of corrective equipment such as automatic
voltage regulators and capacitors, or change in nominal system
voltages, among others.
4.2.6 The Technical Loss component of the individualized DSL Cap shall be
based on the maximum value of the Technical Loss obtained over all
relevant periods for the Reference Distribution Network.
4.3.2 The NTL Cost Curve represents the cost of Non-Technical Loss to
Customers, assuming these costs are pass-through.
4.3.3 The NTL Reduction Cost Curve represents the cost that the DU
expects to incur to achieve a certain level of Non-Technical Loss.
4.3.4 The NTL Total Cost Curve shall be calculated as the sum of the NTL
Cost Curves and the NTL Reduction Cost Curve, also expressed as a
function of the Non-Technical Loss. The level of Non-Technical Loss
at which the NTL Total Cost Curve is the minimum shall serve as the
basis for the Non-Technical Loss component of the individualized
DSLCap.
181page
5. Monthly submission of power supply bill/s and supporting documents"
This data in PDF format shall be submitted on or before the 30th day of
the following month.
The Distribution Utility shall be issued fines and penalties for incomplete
submission or non-submission of the documents and data described in
Section 5.1 of this Rules. The ERG Resolution No. 03, Series of 2009 (A
Resolution Amending the Guidelines to Govern the Imposition of
Administrative Sanctions in the Form of Fines and Penalties Pursuant to
Se'ction 46 of Republic Act No. 9136), and any amendments thereto shall
apply.
I
VI. Final Provisions
6.1 Exception from the Provisions of this Rules
,
Where good cause appears, the Commission may allow an exception from
a~y provision of this Rules, if such exception is found to be in public interest
arid is not contrary to the law, rules and regulations.
I
6.2 Regulatory Costs
I Distribution Utilities shall bear the regulatory implementation costs or
All
costs associated with the implementation of this Rules, including but not
limited to, costs attendant to the public hearings in the DU's localities.
6.3 Effect of the New System Loss Cap under this Rules on DU's
Existing Cap
The DSL Caps determined under this Rules shall supersede the existing
approved cap of the DUs and mandatory bind them to adopt this new loss
cap, except as otherwise provided herein.
I
6.4 Repealing/Separability Clause
6'.4.1 All existing Rules or any part thereof which are inconsistent with this
I Rules are hereby repealed, amended or modified accordingly.
6-4.2 If any provision or part of a provision of this Rules is declared invalid
I or unconstitutional by a court of competent jurisdiction, those
provisions which are not affected thereby shall continue to be in full
force and effect.
6.5 Effectivity
I
I
This Rules shall take effect on the billing month of 2018.
20lPage,
v. Reportorial Requirements
5.1 Relwar Review by the Energy Regulatory Commission
Thl Distribution Utility shall submit the following documents and data for
the1reviewand verification of the ERC:
1. Monthly DSL data for the Sub-Transmission network (including
Connection Assets), the Customers connected to the Sub-Transmission
network, and the distribution substations encoded according to the ERC-
prescribed template. Refer to Annex B Section B.1 of this Rules for the
data description. This DSL sub-transmission data in MS Excel format
shall be submitted on or before the 30th day of the following month.
2. Monthly DSL data per feeder for the whole coverage area encoded
according to the ERC-prescribed template. Refer to Annex B Section B.2
of this Rules for the data description. This DSL feeder data in MS Excel
format shall be submitted on or before the 30th day of the following
month.
3. Annual summary of Energy quantities and relevant network parameters
such as the following:
This annual data (in MS Excel format) from the previous year shall be
submitted by the end of May of the current year.
4. Monthly submission of actual Sub-Transmission Line and Substation
. single line diagram with the location of billing meter/s, including feeder
metering, and any changes therein. In the alternative, a DU may submit
a sworn statement that no changes/modifications were made. This data
in PDF format shall be submitted on or before the 30th day of the
following month.
191Page
ANNEX A: Methodology for Segregating DSL
A.l Introduction
This dJcument describes the methodology for segregating Distribution System
Loss acCordingto its various components and various occurrences throughout the
distribution network. The methodology presented is consistent with the
,
methodology which is part of the Guidelinesfor the Application and Approval of
Caps on the Recoverable Rate of Distribution System Losses (ERC 2004). In
additioh, this document enhances the previous document as follows: (a)
recognizing Distribution Utility Use as the aggregate energy used for the proper
I
operati\:mof the distribution system which is consistent with ERC Resolution No.
17 Series of 2008, thus replacing the term Administrative Loss; (b) providing
t
in the1following:
21\ P age
I
I
A.3
I
Calculation of Distribution System Loss
ERe:
...
, ,""" .
22IPage
a. Distribution Substations;
'b. Offices of the Distribution Utility;
c. Warehouses and Workshops ofthe Distribution Utility; and
d. Other essential electrical loads ofthe Distribution Utility.
distribution Utility Use shall be the sum of actual electric energy
consumption of the essential loads used by the facilities of the Distribution
U;tilityduring the BillingPeriod.
Ih equation form, the Distribution Utility Use shall be calculated as
follows:
Equation A.2. Distribution Utility Use
I
A.3.4 Sub-Transmission and Substation Technical Loss
I
1'he Sub-Transmission and Substation Technical Loss for the Billing
~eriod shall be the sum of the hourly Load Losses and No-Load Losses
incurred by the sub-transmission network and the distribution
~ubstations. It shall be calculated based on Load Flow simulations of the
sub-transmission network and distribution substations using the
appropriate network models and load models. The Load Flow simulations
must capture the Technical Loss from the metering point associated with
the root branch of the sub-transmission network to the root branch of the
medium-voltage distribution feeders (typically at the secondary of the
Distribution Substation transformer).
I
In equation form, the Sub-Transmission and Substation Technical Loss
khall be computed as follows:
Equation A.3 Sub-Transmission and Substation Technical Loss
Subtransmission and Substation Technical Loss
=L Hourly Load Losses in Subtranmission Lines
+L Hourly Load Losses in Substation Transformers
+L Hourly No - Load Losses in Substation Transformers
+L Hourly Load Losses in Subtransmission Service Drops
+L Hourly Load Losses in Subtransmission Voltage Regulators
231Page
A.3.5 FJeder Technical Loss
nJe Feeder Technical Loss for the Billing Period shall be the sum of the
hdurly Load Losses and No-Load Losses in all medium-voltage
dibbution equipment, devices and conductors, excluding the hourly Load
Ldsses and No-Load Losses in the Sub-Transmission System and
I
Distribution Substations (which are already accounted for under Section
2.4).
,
It shall be calculated based on Three-Phase Load Flow simulations of
the Distribution System using the appropriate distribution network models
a~d distribution load models. The Load Flow simulations must capture the
T~chnical Loss from the metering point associated with the root branch of
th'e medium-voltage distribution feeders to the connection points of the
U~ers and loads covered under Distribution Utility Use.
241Page
I Equations A.5. MeteringEquipmentLoss
I
Potential Transformer Loss
I = Lt ower Loss in PTI x Number of PT,
x Number of Operating Hours
251Page
In equation form, the Non-Technical Loss shall be computed as follows:
I,
A
A
~ «- a
I. I.
Impedance
B
~
(or Admittance)
«- I, b
f Ie parameters of
c
~
Distribution System «- c
element
VA v. vel v.l V. V,
,
A.4.1ILine Models
Overhead sub-transmission lines and overhead primary distribution lines
shall be represented by a three-phase pi (11) equivalent network with the
corresponding self- and mutual impedances of the phase and ground
conductors, as shown in Figure A-2.
Z61Page
a
A z•• Z•• Z"
B Z•• Z•• z., b
..••
!;r ...•!F
Figure A-2. Equivalent 7t-Network of Distribution Lines
The series self- and mutual impedances of the conductors are given by the
Carson
, equations:
I
The shunt parameters consist of self- and mutual capacitive reactance due
tp the voltages (potentials) across and electrical charges of the conductors
and their mirror images below the ground, as illustrated in Figure A-g.
g
rese parameters[::]n be[::ain;a: us~~ th;a:]l1[o:]n equations:
Where,
I
i 1 Hxx
P. =-!n- Eq.Bb
"" 21rE T,
"
1 H"y
PXy = -2 !n- Eq.Bc
1rE D
""
Z71Page
= Distance of conductor x to its image;
H"" Distance of conductor x to the image of conductor Yj
H"y,
=
r,,: = Radius of conductor Xi
Distance between conductors x and y (xy can be ab, bc, or cal;
D,,~ = and
£1 = Permittivity of the region surrounding the conductors.
i
I ' X =-=--
c
1
wC
1
21rfC
Eq.9
Where,
6> = angular frequency in radians per second; and
f = frequency in cyclesper second.
llnderground and submarine cables shall be modeled using the self- and
mutual impedance and admittances, taking into account the characteristics
9f the phase and neutrals conductor, the geometry and spacing of the
Conductors inside the cable, the type of cable (for example, if the cable is of
concentric neutral or tape-shielded type), and the parameters of the
material used inside the cables.
281Page
Secondary Distribution Lines and Service Drops may be modeled similarly,
but i the shunt capacitances and mutual reactances for these may be
neglected.
,
I
A.4.2 Trll-nsformer Models
I
Bus
RandX
or
I Ploss, Qvar
I
j Figure A-4. Shunt Capacitor Model
I
I
Shunt inductors shall be modeled as impedance (a resistance and a
r~actance in series) that is connected to a bus, as illustrated in Figure A-5.
1'he inherent resistance of the shunt inductor shall account for the losses
ih the shunt inductor. .
Bus
Z91Page
Series inductors shall be modeled as series impedance that is connected
across two buses, similar to distribution lines, neglecting the shunt
admittances and mutual reactances, as illustrated in Figure A-6. The
inherent resistance of the series inductor shall account for the losses in the
series inductor.
Busi Busj
R X
I "N~.r-
ttl. I
I 'M-l_tn.
u
I
I 'M-l---
ffil I
Reference Ground
1
350
300-
c
\1!liP
••
qOO
150
100
o Period 50
i LoadCurva 0-
Period
1_
'l
t Customer Energy Bill
!~ Converted to Hourly power
~
Demand
30lPage
l
Figure A-~I shows the step-by-step procedure for converting energy consumption
(expressed in kWh for one billing period) to 24 hourly kW demands. The real
power d~mand Pt for time t is obtained from the per unit (p.u.) demand pt
divided by the total area under the normalized load curve.
Hourly Demand
Figure A-S. Converting Monthly Customer Energy Billto Hourly power Demand
The poler factor (Pit) is used to compute for the hourly reactive power demand
(Qt) ba~ed on the real power demand of the corresponding hour.
The re~l power and reactive power may be divided into three components to
represerit constant power, constant current, and constant impedance load models
if theit coefficients are known. For the purpose of segregating Distribution
systeml Loss, constant power load models (that is, constant P and Q) shall be
I
.acceptable.
Figure IA-9 shows
I
the shows an example of the hourly real and reactive power
demanas for a customer.
Real and Reactive Power (Residential)
350
_ 300
~ 250
•••Iii 200
~ 150.
1
E 100.
2l 50
o 1 2 3 4 5 6 7 8 9 1011 121314151617 18 192021 222324
31\ P age
The Distrfbution Utility may develop more accurate load models by preparing as
many loaa curves as possible through a load survey for each type of customer,
and even ~or each sub-type of customer. Different load curves may also consider
seasonal :variations (for example: dry and wet season) and variations based on
,
types ofthe day (for example: weekday, weekend, and/or holidays).
321Page
Table 2. Customer Data
CustomerID
Customer Name
CiIstomer Tvne
Service Voltal!e
No.ofPhasclS)
I
Table
Billin Period Code
Period Covered of the Billin
Number of Da for the Billi Period
Number of Hours for the Billin Period
I
Table . Customer Ener
CustomerID
Billin Period Code
Ener Consumed Wh b the Customer for the Billin Period
Measured or Estimated Power Factor
,
I
Table . Load Curve Data
Customer e
Descri tion of the Customer e
p'er Unit Load of each Customer Type for Hour 1 to Hour 24
a) Bus Data;
b) Sub-Transmission Line Data;
c) Substation Power Transformer Data;
d) Primary Distribution Line Data;
e) Distribution Transformer Data;
o Secondary Distribution Line Data;
g) Primary and Secondary Customer Service Drop Data;
h) Voltage Regulator Data;
i) Shunt Capacitor Data;
j) Shunt Inductor Data; and
k) Series Inductor Data.
The details of these Distribution System data are specified in Table 6 to
T~ble 21 and shall be submitted to the ERe using Templates found in
Mtnex C of this Rules.
I
Table 6. Bus Data
[Identification of Connection Points (Bus ID)
IBusDescrintion (e.ll:. Location of the Connection Point)
INominal Voltlll!eof the Connection Point
Note:Connectionpoint refersto a deliverypoint or a point connectingtwo
o'rmorediBtributionByBtem element
331Page
Ta b.Ie". Su b-TransmIsSIon Lme Data - Over hea d
Subtransmission Line Sev:ment ID
Connection Points Identification (From Bus ID and To Bus ID)
Phasinv:
Confil!:Uration
No. of Ground Wires
Lenv:th of Subtransmission Line Seltment
Phase Conductor 1'vne
Size of Phase Conductors
No. of Strands of Phase Conductors
No. of Bundled Conductors
Bundled Conductors SnaciIIV:
Conductor TvDe of Ground Wire
Size of Ground Wire
lITo.of Strands of Ground Wire
Snacinv: between nhase conductors
Snacinv: between nhase conductors and e;round wire
Snacinv: between v:round wires (meters)
Spacing between circuits for parallel/double circuits
Heiv:ht of Phase Conductors
HeilZht of Ground Wire
Earth Resistivitv
341Page
Ta bi e 12. PnmarvDIStribution
. Lme Data - Un d ergroun
Primarv Distribution line Se"ment ID
Connection Points Identification (From Bus ID and To Bus II))
. Phasine:
, Lenlrth of PrimarY Distribution Line Se"ment
I Conductor TYPe
, Conductor Size
No. of Cores
Diameter under Armor
Armor Wire Diameter
Overall Diameter
AC Resistance
Inductive Reactance
Canacitance
I Earth Resistivitv
3SlPage
Size of Phase Conductors
No. of Strands of Phase Conductors
ConductorTvne of Neutral Wire
Size of Neutral Wire
No. of Strands of Neutral Wire
Snacinl!:betweenohase conductors
~acingbetw~nohaseconooctms~dNootralW~
Spacing between Circuits for Parallel/Double Circuits
Heililit of Phase Conductors
Heil!:ht of Neutral Wire
-garth ResistiVitY
Table PrimarY Customer Service Dron Data - Underl!:round
:lA
Primarv Customer Service Dron ID
Connection Points Identification (From Bus ID and To Bus II»)
Phasinl!:
Lenl!:th of Service Dron
ConductoiTVDe
'Conductor Size
:No.ofCores
•Diameter under Armor
!Armor Wire Diameter
IOverall Diameter
I AC Resistance
I Inductive Reactance
I Caoaci~ce
I Earth Resistivitv
361page
, Shunt Inductor ID
, Connection Point Identification (Bus ID)
, PhaseTvne
Phasine:
Voltae:e Ratine:
Resistance
Reactance
371Page