PEP1 Sea Port Construction
PEP1 Sea Port Construction
PEP1 Sea Port Construction
Details of how a Sea Port is constructed, and how the progress, safety and quality will be monitored and controlled.
Also the measures to ensure that the site is environmentally friendly.
http://www.slideshare.net/DavidHMoloney/sea-port-construction-project-execution-plan
Brief Description
The purpose of this presentation is to give an understanding of the Methods, Plant David H Moloney
and Sequence to construct a Sea Port . 14th August 2016
This presentation can be used to engage Stakeholders and to get the Site Teams
commitment to the programme. Also can be used for Induction Training and as a
way to capture and share knowledge.
Project Execution Plan (PEP) details how a project will be executed, monitored and
controlled.
Video https://www.youtube.com/watch?v=6_Aco_GPO8I
Contents
ⓒ David H Moloney
Introduction
Quay Wall
Quay Wall
Quay Wall
Brief Description
Quay Wall
A screeding frame that extended from the sea bet to above water was
used to place the bedding layer to the correct level.
Up to 22 blocks were placed per day using a barge with a crane.
Part of the coping beam was cast in-sit-u in sections using concrete pumps
positioned on the reclaimed land behind the quay wall.
Sequence & Methods to Construct Quay Wall 3D Animation
Quay Wall
Quay-wall
Screed Frame for preparing Granular Foundation Placing Precast Quay Blocks
ⓒ David H Moloney
Quay Wall Beam
Screed Frame
Brief Description
Miscellaneous
Duqm, Oman
Mooring Bollards & Marine Fenders
Miscellaneous
ⓒ David H Moloney
Marine Equipment
Drawing – Quay Wall Cross Section
Breakwater & Wavewall
Breakwater & Wavewall
Breakwater & Wavewall
Breakwater & Wavewall
Brief Description
Placing Armour
Rock Sea Armour
Placing Armour
Sea Wall
Drawing – Breakwater Cross Section
Wave Wall
Precast Armour
Geotextile
Rock Armour 1 - 3 ton
Brief Description
Precast Yard & Loading Jetty
All works were inspected in accordance with the Inspection & Test
Plan on an ongoing basis, in accordance with the site Project Quality
Plan. The ITP set out in matrix form the sequence of inspection
steps, the governing document (specification, standards), the
standard to be achieved, the persons witnessing and the supporting
documents to be produced.
Precast Yard & Loading Jetty
Precast Yard & Loading Jetty
Precast Yard & Loading Jetty
Precast Yard & Loading Jetty
Precast Yard & Loading Jetty
Precast Yard & Loading Jetty
Pre-casting Quay Blocks
Precast Sea Armour
Shutters for Precast Sea Armour Shutters for Precast Sea Armour
Quarry & Aggregate Production
ⓒ David H Moloney
Quarry
Concrete Batching Plant David H Moloney
ⓒ David H Moloney
Concrete batching plant comprises - concrete mixer, control cabin, silos for cement and fly ash, aggregate bins
and conveyor belt system to feed the mixer. Also aggregate storage bays and water storage tanks.
The mixing is computer controlled and has a dynamic screen display, showing the process. Material storage
capacity to match two days concrete production
Concrete Batching Yard
Reinforcement in 12 m lengths. Delivery in 3 ton Bundles Reinforcement cut to length by Shearing Machine
Reinforcement Bent to Shape by Bending Machine Reinforcement that is cut and bent is Bundled for delivery to work site
ⓒ David H Moloney
Reinforcement Cutting & Bending
Concrete
ⓒ David H Moloney
Reinforced Wall Construction Sequence
Concrete
Brief Description
Cycle Time
Pour per Day
ⓒ David H Moloney
Reinforced Wall Construction Sequence
Concrete
ⓒ David H Moloney
General Items Concrete Mix
ⓒ David H Moloney
Dredging & Reclamation
Dredging & Reclamation
Dredging & Reclamation
Brief Description
Dredging & Reclamation
Dredgers are marine vessels used to excavate and fill under water.
Types
1. Cutter Suction Dredgers are used to dredge hard soils by cutting
and breaking up the soil using a rotating head at the end of a pipe
which is lowered onto the sea bed. The fragmented material is
sucked and pumped either into a hopper barge or through a floating
pipeline. During operation the dredger is anchored by a spud that
allows the cutting head to swing in an arc.
Boskalis Netherlands
Dredger - Cutter Suction
Dredging & Reclamation
Boskalis Netherlands
Dredging & Reclamation
Dredger - Backhoe
Rock - Excavability
The excavability of rock depends mainly on the rock strength and the layer thickness.
This diagram shows excavation methods for rock of various strengths and thicknesses,
with a free face.
ⓒ David H Moloney
Vibro Compaction - Fill behind Quay
Vibro Compaction - Fill behind Quay
Equipment.
Ope
Surveying & setting Out
Survey Tower
Setting out & Surveying
Setting out & Surveying
Port Operation
Port Operation
Port Operation
Port Operation
Port Operation
Port Operation
Port Operation
Port Operation
Site Facilities & Temporary Works
Site Facilities & temporary Works
Site Facilities & Temporary Works
Site Facilities & temporary Works
General Items Welfare Facilities
Toilets – Washing
ⓒ David H Moloney
General Items
Site Hoarding examples
ⓒ David H Moloney
Wheel Wash Drive-through
General Items
ⓒ David H Moloney
General Items
Wheel Wash Drive-through
General Items Temporary Electricity Supply & Tower Lights
Generators
General Items
Dewatering
ⓒ David H Moloney
General Items
Concrete Batching Yard 3 Nr Mixers
Health, Safety & Environmental
Health, safety & environmental
Emergency Phone Numbers & Response
Dashboard is a single page, graphical representation of
HSE Monitoring & Reporting - Dashboard current HSE Issues and historical trends
Site Safety Posters examples
Safety Precautions
Personal Protective Equipment (PPE)
Health, Safety & Environment
Personal protective
equipment (PPE) is
protective clothing,
helmets, goggles, or other
garments or equipment
designed to protect the
wearer from injury or
infection
The purpose of safety training is to provide the knowledge necessary to
Safety Training on Site perform a job safely
Miscellaneous
The purpose of safety training is to provide the knowledge necessary to
Safety Training Matrix perform a job safely
Miscellaneous
Emergency Response Drill Drills and exercises are used to rehearse anticipated emergency scenarios
HSE
Air, Noise, Water & Soil Pollution
Environmentally Friendly Site
Hazardous Substances Symbols
Health, Safety & Environment
ⓒ David H Moloney
Administration
Administration
Organogram
Brief Description
Brief Description
Brief Description
ⓒ David H Moloney
Programme & Progress Monitoring
Programme & Progress Monitoring
Progress Monitoring & Reporting - Dashboard
Dashboard is a single page, graphical representation of current progress and historical trends
ⓒ David H Moloney
Histogram Charts for Resources & Outputs
ⓒ David H Moloney
Plant & Equipment List & Worker’s Job Titles
ⓒ David H Moloney
Other Projects
Other Projects
Other Projects
Brief Description
Brief Description
Other Projects
Concrete Batching Plant on Barge. Kuwait Causeway
Other Projects
Pile Driving
Other Projects
Temporary Bridge
Other Projects
Temporary Bridge Piling
Other Projects
Other Projects
Brief Description
Marine Piles
Other Projects
Brief Description
Brief Description
Brief Description
Brief Description
Brief Description
Brief Description
Brief Description
Cofferdams examples
Other Projects Jebel Ali Dubai
Ports
Dublin Cork