Test Pack Sample
Test Pack Sample
Test Pack Sample
Project Title :
System No :
Testpack No :CIWE-JIMT-P-001
P&ID No :
Rev No :
Location :
Contractor :CIWE
Test Medium :
Type of Test Hydro Test
Test Pressure :
Tie-Ins :
Area :
Design Pressure :
Fluid :
CIWE-JIMT PROJECT
SYSTEM NO.:
TESTPACK:
CIWE-JIMT-P-001
Main P & ID :
Test Pressure :
DesignTest Pressure :
Test Medium :
Contractor : CIWE
Page 1 of 1
SYSTEM: PROJECT :
Page: 1 of 1
Test
Blind Iso Dwg. Size of Removed CIWE PMC
No. No./ Pipe line No : blind Sign Sign Remarks
PAGE 1 of 1
SYSTEM No.###
: PROJECT : ###
Cat "A" - Punch Items must be repaired/completed or corrected before (pressure) testing can take place
Cat "B" - Punch Items may be repaired, completed/corrected after (pressure) testing, but before Reinstatement Acceptance
CIWE-JIMT PROJECT
Page: 1 of 1
SYSTEM NO:
### PROJECT : ###
EFD No.:
###
1. MC ENGINEERING REVIEW
There are no outstanding Engineering issues that prevent this line from being tested.
NAME: POSITION:
DATE: SIGNATURE:
2. MC CONSTRUCTION REVIEW
All items on Pipework Pre-Test Check List have been examined and completed.
All category A Punch List items have been rectified.
The system has been set-up for testing as per requirements.
NAME: POSITION:
DATE SIGNATURE:
REMARKS
COMPLETED BY
COMPANY
SIGNATURE
NAME
DATE
CIWE-JIMT PROJECT
SYSTEM: PROJECT :
P & ID No.
ISO Drawing No. See Attached Sheets (pipe line release inspection record)
DESIGN DATA TEST DATA
Ambient Temperature Ambient Temperature
12bar 15minutes 1
8bar 2
3
0 4
t0 t1 t2 t3 t4 t5 t6 T
We confirm that the pressure test results as noted above correct and conform to the project requirements.
CIWE
PMC
SRC
CIWE-JIMT
DATE OF DRYING :
Level 0 - No drying required. This is restricted to piping that has been air tested or piping that shall
subsequently be service tested, or vents to atmosphere that shall only be subject to visual testing
Level 1 - No free (standing) water following drop flush post hydro-testing – where required this shall be
assisted by blow down with plant utility air (or suitable alternative)
Level 2 - No water following drop flush post hydro-testing – blow down with plant utility air (or suitable
alternative) to return to ambient conditions
REMARKS
COMPANY
SIGNATURE
NAME
DATE
SPT 5035 Rev 1, 02/11/09 CK ###
SINGAPORE PARALLEL TRAIN
SYSTEM:
### CONTRACT NO:
###
YES N/A NO
1. All testing has been satisfactorily completed and recorded (inc. visual checks).
2. Check flushing of lines is complete and accepted.
3. Check drying and drainage of lines is complete and accepted.
4. Check that correct bolts and gaskets are installed at all reinstated joints.
5. Check that all hydrotest vents and drains have been sealed.
6. Check that all process blinds and spades have been correctly installed
as indicated on the reinstatement P&ID.
7. Check that spectacle blinds are in the correct 'Flow' position.
8. Visually check that all pipe spools are clean and free of debris
prior to reinstatement - where possible.
9. Check that control valves have been installed in the correct 'Flow' position.
10. Check that specified block valves have locking devices correctly installed.
11. Check that all valves are functioning properly and that spindles have been
coated with 'Copa-Slip' or equal where specified.
12. Check that chain wheels for specified valves have been correctly installed.
13. Check that all extended spindles for specified valves have been installed.
14. Check that relief valves have been correctly installed.
15. Check that all thermo wells have been correctly installed.
16. Check that restriction and orifice plates have been correctly installed.
17. Check that all pump suction strainers have been correctly installed.
18. Check for correct flow through filters and strainers, traps, check valves
and globe valves.
19. Check that gags have NOT been removed from spring-loaded pipe supports
and expansion bellows.
20. Check that all pipe seals have been correctly fitted.
21. Check that all test spades have been removed and correct bolts and gaskets
installed afterwards - refer to "Test Blind List". If NO raise punch list item(s).
22. FWP Welding Supervisor to verify all hydrotest plugs have been seal welded
and PT examined.
23. FWP Welding Supervisor to verify Post Test PMI of reinstated items on alloy lines.
Remarks:
COMPANY CIWE
SIGNATURE
NAME
DATE
SPT 3422
CIWE-JIMT PROJECT
SYSTEM:
### TEST PACK NO:
LOCATION : ###
7. Line List