Location via proxy:   [ UP ]  
[Report a bug]   [Manage cookies]                

T/L Towers

Download as pdf or txt
Download as pdf or txt
You are on page 1of 72

Classification of Towers based

on
1)No. of
Circuits
a. Single circuits towers

b. DC/SC towers

c. DC towers

d. MC towers
2)AOD
a) Suspension/Tangent towers <2 °

b) Small angle towers 2 ° -15 °

c) Medium angle towers 15 ° -30 °

d) Large Angle towers 30 ° -60 °

e) Dead end towers >60 °

f) Transposition towers(4Xarms)

g) Special towers – JC, MC, NB, NBMC

h) Pole mounted termination towers

i) Mono poles
132
KV
SC DC/SC MC NB (B/B)
(B/B) (B/B)

A P/D(4.2) K(8) 0° (1.3)

B R(7.15) L(8.7) 30° (1.31)

C&D S(7.75) M(11.5) 60°


(3.174)
Bot Xarm Bot Xarm 12.283 12.35 12.3

Ht ht

Total Total 27.381 38.46 27.1

Height height Note: All in meters


220 KV

L&T TSP M/C NB


A AV/AS X 0°
B BS Y 30°
C CS(8) Z(17) 60° (3.3)
D(11)
BotXarm Ht 16.85 19.085 17.45 11.79

Total Ht 33.5 38.035 51.4 29

Note: All in mesters


Special towers

NB MCNB(220KV) MCNB(132KV)

120m 250m 300m

60° 0, 30 & 60 Deg 0°, 30° & 60°

2.2 5.4 3.936

14 13.1 12.15
Mono pole

180m

0°, 30° & 60°

Bot Xarm Ht 15.8


JC
For river crossing suspension towers only

Height(m) Base Bot Wt.

width Xram(m) (MT)

(B/B) (m)
Full JC 88.2 12.38 69 32.5

Trunk 72.15 10.4 52.5 28.9

JC
Tower extensions:
 +3m
 +6m
 +9m
 +12m
 +18m
 +25m
 +30m
Generally extensions are added to the tower at Bottom section .
Cage Extension is added at cage for dead end towers, the extension
Will be of 3m & 5m
SPANS:
 Normal span: 320m for Panther
 350m for Zebra and L&T
towers
 380m for Moose and TSP
towers
 950m for JC
 Actual span
 Wind span
 Weight span: Left wt. span & Right wt.
span
 Equivalent span
 Negative span
Erection
a) Setting of stubs:
Template
Probe setting
B/B & diagonal at Template top
B/B & diagonal at stub top Ram bus shape
Stub cleats with B&N 2 each
Extra cleats to avoid failure of foundation
due to tower falling.
Threads to bisect
LP&AP
Template height at centre point & joining of
2 threads
b) After 14 days of curing

Built-up method:- This method consist of erection of


towers member by member. The 4 main leg members of
first section of the tower are first erected and guyed of. The
cross braces then assembled. For assembling second section
a light gin pole is placed on top of the corner legs for
raising the second section of the tower. Afterwards the gin
pole is shifted to top of second section leg to raise third
section this process is continued till complete tower is
erected.
Section method :-
Major sections of the tower are assembled on the
ground and same are erected as units.
Either mobile crane or gin pole of 10m long is
used.
Ground assembly(Proto) :-

This method consist of assembling the tower on


ground and erecting it as a complete unit. The
complete tower is assembled in line wise position
to allow Xarms to fitted. After assembly is
completed tower is picked up from ground with
the help of crane and carried to is location and
set on its foundation.
This method is not is useful when the towers are
large and heavy and the locations are difficult.
Helicopter method :-

In this method the tower is erected in section.


Bottom section is first lifted on to the stub and
then the upper section is lifted and bolted to first
section and the process is repeated till the tower
is erected. Some times complete assembled tower
is raised with the help of helicopter. This method
is adopted when approach is impossible .
MS tower parts to Galvanized tower parts
Galvanization Procedure

1 2 3 4 5 6 7 8

1. Decreasing Bath Hard HCL


2. Pickling HCL
3. Rinsing Water
4. Fluxing Ammonia and Zinc Chloride
5. Hot plate
6. Zinc batch
7. Dychromizing
8. Finishing & Filling

Galvanization :
oTower parts – 86 Microns
oBolt & Nuts - 45 Microns
Tightening of B&N
The bolts & nuts are used to join the tower parts
The bolts are of 16mm diameter and 20mm diameter
The length of bolts are various from 35mm to 80mm
multiple of 5mm
17.5mm/21.5mm dia hole is provided on tower part for
fixing bolt & nut
Spring washers - 16 x 3.5 mm- to tighten the bolt&nut
Flat washers 4, 5, 6, 8, 10,20 and 25mm to fill up gaps
between the tower parts
Check for tight of B&N using torque wrench
The threads of bolts projecting out side shall be
punched at 3 positions and do half round welding
to
ensure that nuts are not loosened in course of time

and avoid theft of angles.


Zinc epoxy painting is applied on welded portion to

avoid rusting.
Tower verticality :- 1 in 360
Slenderness Ratio = Effective length of members / Radius
of gyration

SR gives Resistance of any member to


bending
SR for leg members - 150
Tension members - 350
Grounding :-
pipe earthing –Tower foot Resistance<15
ohm
CP earthing - 15 – 30 m of 7/8 or 7/9
SWG
Explain
galvanized
practice
steelofwire
coke and salt, betonite
powder
50x6mm flat of 1.5m length is used & flat
should be buried at 0.6m below the ground

level.
 Earthing pipe is of 25mm dia, 3050 meters

length GI pipe with holes.


earthing is provided for D leg only

For Railway crossing double earthing is


to be provided.

Normally earth pipe is placed vertically


& in difficult places earth pipe placed in
slant position with prior approval.

A pit of 300mm dia and 3.2m depth is


excavated to place earth pipes.
Tower Accessories: -

Danger boards

Number plate

Phase plate

Anti Climbing Device

Step bolts 16x175 mm

Antiperch / Bird guards for suspension towers

Hanger rods
i) NO TOWER SHALL BE ERECTED ON FOUNDATION
BEFORE 10 DAYS AFTER CONCRETING.

ii) CHECK THE CORRECTNESS OF DIAGONAL AND


LEVEL OF THE STUB OF THE FOUNDATION.

iii) TOWERS ARE TO BE ERECTED AS PER ERECTION


DRAWING

iv) ASSEMBLY OF TOWER PARTS SHALL BE MADE AS


PER MARK NUMBER WISE ENGRAVED ON THE
TOWER MEMBER CORRESPONDING TO NUMBER IN
THE ERECTION DRAWING.

v) SPECIAL CARE SHALL BE TAKEN IN SELECTION OF


MARK NUMBER FOR TRANSVERSE AND
LONGITUDINAL FACE OF THE SQUARE BASE TOWER.

vi) ANY BUCKLING, DAMAGE TO STEEL MEMBER,


DAMAGE TO GALVANIZING SHALL BE AVOIDED
vii) NO MEMBER SHALL BE SUBJECTED TO UNDUE
STRESS.

viii) REASON CAN BE: (i) DEFECTIVE FABRICATION.


(ii) DEFECTIVE FOUNDATION.
(iii) DEFECTIVE ERECTION
METHOD.

viii) COLLECT MATERIAL FROM STORE TALLYING WITH


BOM.

ix) PREFERABLY TRANSPORT COMPLETE TOWER OR


COMPLETE SECTION.

x) THE TOWER MEMBER AT LOCATION SHALL BE KEPT


ON GROUND SERIALLY ACCORDING TO THE NEED
FOR FOLLOWING UP ERECTION SEQUENCE.
DERRICK TYING ROPE

DERRICK

20mm POLY
PROPYLENE
ROPE

CROW BARS

TOWER ERECTION
i) WHILE LOADING AND UNLOADING THE TOWER PARTS,
CARE SHOULD BE TAKEN FOR STACKING
SYSTEMATICALLY.

ii) HANDLE THE TOWER PARTS CAREFULLY. WHILE


HANDLING THEM WEAR SUITABLE GLOVES.

iii) ESTABLISH CLEAR SIGNAL/COMMUNICATION


BETWEEN THE PERSONS WORKING ON THE TOP AND
THE PEOPLE SUPPLYING TOWER PARTS, WATCHING
GUYS PULLING ETC SPECIAL CARE SHALL BE TAKEN
FOR R.C. TOWER.

iv) ALL LIFTING TOOLS AND TACKLES SHOULD BE LOAD


TESTED AS PER STANDARD.
vi) ENSURE THE DERRICK USED BEFORE TOWER
ERECTION HAS BEEN CHECKED FOR ADEQUATE
STRENGTH / SIZE.

vii) KEEP WATCH ON ALL GUYS USED DURING ERECTION


ANY SLIPPAGE/FAILURE IF THE GUY CAN CAUSE
ACCIDENT.

viii) POLYPROPYLENE ROPE FROM 20MM TO 25MM SIZE


SHOULD BE USED FOR GUYING & LIFTING.

ix) AFTER 5 OPERATIONS CHECK THE CONDITION OF THE


ROPE. IF WORN OUT THEN REJECT.
xi) ALL TOWER MEMBERS TO BE FITTED WITH
APPROPRIATE SIZE OF NUTS & BOLTS OF THE SECTION
ERECTED BEFORE THE ERECTION IS TAKEN UP FOR THE
NEXT SECTION.

xii) AVOID ALL TOWER ERECTION IN RAINY DAY.

xiii) HEAVILY CLOUDY DAYS AVOID ALL TYPE TOWER


ERECTION. STOP TOWER ERECTION OF R.C.TOWER.

xiv) IN CASE OF HEAVY WIND OR APPROACHING STORM


STOP ALL TOWER ERECTION. EVERY ONE SHOULD BE
AWAY FROM THE TOWER.

xv) PPE LIKE HELMET, SAFETY BELT OF PROPER QUALITY IS


USED.

xvi) FOR CLIMBING TOWER USE SAFETY BELT WHICH CAN BE


FITTED TO THE TOWER.
LINE MATERIALS

1.Conductors

Conductor Amps Kg/KM AL59 INVAR

Panther 489 974 734 Amp. Double 30+7/3.00


Panther
Zebra 737 1621 930 Amp. Double 54+7/3.18
Zebra
Moose 840 1998 54+7/3.53
AAAC- Less wt., more sag, & more current carrying capacity

ACSR- More wt., less sag, & less current carrying capacity

I. Total No. of wires = 3N(N+1)+1 ; Where N= No. of layers

Layer No. of Total


wires
Centre 1 1
1 st 6 7
2 nd 12 19
3 rd 18 37
II. Lay Ratio = Lay/OD ; Where OD = Outer diameter=(2N+1)d;
where d= Dia of single strand

18 wires 10 – 12

12 wires 12 -14

6 wires 13 -18
2.Earth wire: Shielding angle 10 – 30 °

7/3.66 → 7/3.15

Weight /KM 575 428 Kg/KM

3. Insulators: 70 KN, 120KN and 160


KN
Voltag Suspension Angle

e
132KV 9Nos 10Nos

220KV 13Nos 14Nos

400KV 23Nos 24Nos


132÷√3 = 76.2 KV ≈ 80 KV ÷ 11 = 8 Nos + 1 extra = 9 Nos

220÷√3 = 127 KV ÷ 11 = 12 Nos + 1 extra = 13 Nos

400÷√3 = 230.95 KV ÷ 11 = 21 Nos + 1 extra = 22 Nos or Say 23

a) Porcelain Insulators :- Ball and Socket


Long rod

b) SRC Insulators :- Silicon Rubber Composite

FRP rod with sheds, fiber resin plastic rod


Insulator hoisting
Suspension insulators shall be used upto deviations of 2
degrees on all tangent type towers on the line and strain
insulators on all angle type towers.

For ensuring insulation co-ordination the suspension or tension


strings on approach and terminal towers near the station ends
upto a length of 1.5 Km shall be provided with adjustable arcing
horns on tower side and fixed arcing horns on line side, keeping
the arcing gap as may be stipulated by the En gineer at site.

Insulator strings shall be assembled on the ground. These shall


be cleaned and examined before hoisting. All accessories shall
be properly fitted.

Those having glazing defects exceeding half centimeter square


shall not be used.
For suspension towers 70 KN insulators are hoisted
with Aerial rollers. The Aerial rollers are like single
sleeve pulley .Before hoisting of insulators the M pins
should be checked thoroughly for their opening so that
the insulation will not detached during stringing.
4. SSH for conductor:- PA rods 11 – 14 Nos; where PA=
Preformed Armoured Rods
5. STH for conductor 6. DSH for conductor

7. DTH for conductor 8. SSH for earth wire

9. STH for earth wire

10. 4R stock bridge vibration dampers (1.2 – 1.3m)

11. MS joint for conductor

12. MS joint for earth wire

13. Repair sleeves


WRONG METHOD CORRECT METHODS
i) SELECT CONTINUOUS STRETCH AND STARTING TYPE OF
TOWER FOR STRINGING WITH ADEQUATE CARE.
ii) PREPARE DRUM SCHEDULE FOR CONDUCTOR WITH CARE TO
REDUCE WASTAGE.
iii) SELECT PROPERLY THE PLACEMENT SCHEDULE FOR
TENSIONER AND PULLER.
iv) SELECT THE PLACE CAREFULLY FOR PLACEMENT OF
TENSIONER AND PULLER TAKING SITE CONDITION INTO
CONSIDERATION.
v) CHECK CORRECTNESS OF ERECTED TOWER AS PER
DRAWING AND SPECIFICATION FOR ALL TOWERS.
vi) CHECK COMPLETION OF EARTHING AND RECORD TOWER
FOOTING RESISTANCE OF EACH LOCATION.
vii) ALL TREES ENROUTE THE LINE SHOULD BE CLEARED AND
REMOVED FROM THE TRAVELLING PATH OF CONDUCTOR.
viii) CERTIFY AFTER VERIFICATION JOINTLY.
STRINGING

a)Paving out of conductor


b)Rough sag
c)Final tension / stringing
METHOD

 SLACK OR LAY OUT METHOD.

 PAYING BY TENSIONER PULLER.


T&P required :-
Tractor/Tensioner
Turn table (5T or 10T)
Conductor socks
Automatic come along clamp for conductor and earth wire
20mm and 25mm D shackles
Wooden packs
Ground rollers
Aerial rollers
Crowbars
Hacksaw blade
Cutting pliers
Screw driver
Spanners
1. Generally drum lengths are

Panther 2KM
Zebra 1KM
Moose 1KM
Earth wire 2KM

2. Place the conductor drum on TURN TABLE & unwind it.


3. Pull the end of conductor over ground rollers and
passing
through Aerial rollers at suspension towers reach the
4. Makenext
up the
cut end
pointoftower
conductor
using to the cut
tractor/ point tower with STH/DTH
tensioner.
5. Follow the same procedure for balance conductors
and earth wire
Rough sag
T&P required:-

Rough sag leads


Steel ropes 10mm, 12mm, 15mm and 16mm
Come along clamp (7 bolts)
Slings (20mm)
4 Sheave pulley
2 Sheave pulley
Single Sheave pulley
Manila ropes 12mm, 16mm, 18mm and 20mm
Single and double end socks
Turn buckle
D shakles 20 mm
Dead man 1to 1.2 m
6. By connecting the other end to LEPTY do the rough sag by
pulling with tractor/tensioner and see that conductors
are lifted In all spans by hand height.

LEPTY made with steel rope of 12mm of 200m and


400m lengths with four sheave pulleys on either end.

7. Common problem is BARD CAGING


Final tension /Stringing

T&P required:-

1. Leg winch
2. Sag boards
3. 100 MT joint compressor with die sets
suitable for panther, Zebra Moose and earth
wire.
4. Earth wire flat clamps
5. D shackles 16mm/25mm
6. Binoculars
7. Tractor / Tension puller
8. Travelling speed will be 5 – 8 KM per hour.

9. if speed is low causes swinging of traveler and insulator


hardware and higher speed cause damage.
10. Tension load will be around 2000 – 2500
Kgs
11. For 3 rd crossarm stringing tension will be 500
Kgs
12. For 400 KV pilot wire and tensioner is used. First pilot
wire will be passed through the entire reach with Tractor.
Conductor is winded on Tensioner. Pilot wire is knotted to
conductor. The other end of pilot wire is connected to
Puller.slowly puller load applied and tensioner is
releasing the conductor without any problem and make up
at this with STH. Once paving is completed again load
Tensioner till sag point and guyed. Then by Lepty and
Tractor make marking and cater the end.
13. Measurement of sag with equal supports use sag boards
between the two towers of sag span

14. Measurement of sag where supports are at different height


or single spans. Use Dynamo meter for tension readings

15. Sagging section length should not exceed 5KM or 15 spans

16. Physical measurement of ground clearance on roads and

important places.
DETAIL – ‘A’

A A STEEL ROPE OF 20MM DIA

BACK FILLED EARTH

1100MM
150MM
300MM
100MM

1.50M LONG ISMB 200


A
DETAIL – ‘A’

STEEL ROPE OF 20MM DIA

A A
BACK FILLED EARTH

1100MM

150MM
300MM
100MM

1.50M LONG ISMB 200

A
SUSPENSION TOWER SUSPENSION TOWER
TENSION TOWER

Excavated pit for Anchoring of Conductor


40m Approx.

STEEL ROPE OF 20MM DIA


TOOLS & PLANT REQUIRED PER CONDUCTOR
BACK FILLED EARTH
1. 20mm dia wire Rope Slings 40m length - 1 No.
1600MM 2. 20mm 'D' Shakles - 2 Nos
250MM 3. Come along Clamp (Bolted Type) - 1 No.
2.00M LONG ISMB 200 300MM 4. 20mm Sling 10m length - 1 No.
100MM 5. Deadmen wood (1000mm-1200mm long) - 1 No.
DETAIL – ‘B’
C

STEEL ROPE OF 20MM DIA

NOTE: Sling size = 20mm. Depending upon the BACK FILLED EARTH

Tension load rope size should be selected which 2100MM

is dependent on no of conductors type and the 250MM


300MM
tension applied during the sagging. 2.00M LONG ISMB 200
100MM
Arrangement should be capable of 1.5 times of
the total tension load. DETAIL – ‘C’
HOOK
HOOK HOOK

STEEL ROPE STEEL ROPE

BACK FILLED BACK FILLED


EARTH EARTH

RAIL PIECE
RAIL PIECE

IMPROPER PROPER PROPER


GUYING GUYING GUYING
ARRANGEMENT ARRANGEMENT ARRANGEMENT
After stringing ensure the following
Any departures from the correct sag in any span
does not exceed 4 percent.

The sag of any conductor does not depart by


more than 3% from the mean sag of all the
conductors in the same span subject of a
maximum of 150mm.
i) BACK TENSION OF BOTH THE TENSION TOWERS OF SAG SECTION IS MOST
IMPORTANT. PROVIDE BACK TENSION BY PAID OUT CONDUCTOR OF THE
NEXT ADJACENT SECTION OF BOTH TENSION TOWERS.

ii) BACK TENSION ON THE TOWER WITH GUY WIRE SHOULD BE AVOIDED.

iii) IF REQUIRED PREPARE A SCHEME AND GOT IT APPROVED BY THE


TECHNICAL CELL.

iv) GUY WIRE CAPACITY SHOULD BE 1½ TIMES OF MAXIMUM TENSION OF THE


CONDUCTORS.

v) INSPECT THOROUGHLY THE CONDITION OF GUY WIRES BEFORE USED.


o o
vi) GUY FIXING ANGLE SHOULD BE BETWEEN 45 TO 50 TO THE VERTICAL.

vii) GUY BLOCKING ARRANGEMENT SHOULD BE VERY CAREFULLY DONE.

viii) RESPONSIBLE PERSONS SHOULD BE DEPLOYED DURING ENTIRE SAGGING


OPERATION.

ix) MEN ON BACK STAY SHOULD BE PROVIDED WITH APPROPRIATE WHISTLE


AND COMMUNICATION.

x) MEN ON BACK STAY SHOULD BE IN CONSTANT TOUCH WITH FINAL


SAGGING PERSON.
xi) ANY WHISTLE OR COMMUNICATION FROM THE PERSON AT BACK STAY,
STRINGING SHOULD BE STOPPED.

xii) IF NECESSARY CONDUCTOR SHOULD BE RELEASED TO DE-TENSION.

xiii) FINAL SAGGING SHOULD BE DONE AS PER APPROVED SAG TENSIO N CHART.

xiv) ANY CHANGES IN THE SECTION, SPAN MADE DURING THE CONSTRUCTION
THE SAG TENSION CHART SHOULD BE GOT CORRECTED.

xv) THE PERSON IN-CHARGE OF FINAL SAGGING SHOULD HAVE COPIES OF FINAL
PROFILES, SAG TENSION CHART, FINAL TOWER SCHEDULE, SAG TEMPLATE,
PROPER RECORDING REGISTER, FORMATS, ALL DRAWINGS OF HARDWARE
AND ACCESSORIES.

xvi) TWO THERMOMETERS SHOULD BE CLAMPED ON THE TOWER IN ADVANCE ON


THE SAG SPAN.

xvii) TEMPERATURE SHOULD BE CONSTANTLY MONITORED.

xviii) NECESSARY CORRECTION OF SAG BOARD SHOULD BE DONE BEFORE FINAL


MARKING OF CONDUCTOR.

xix) ADEQUATE AND PROPER COMMUNICATION SHOULD BE AVAILABLE AT ALL


POINTS CONTROLLING SAG AND BACK TENSION POINT.
xi) ALL EQUIPMENT SHOULD BE LOAD TESTED BEFORE FINAL SAGGING
OPERATION PLANNED.

xii) USE SUITABLE DYNAMOMETERS TO CROSS CHECK SAG, SHORTER


SPAN, HILLY TERRAIN.

xiii) CHECK CONSTANTLY EVENNESS OF THE BUNDLE CONDUCTOR.

xiv) KEEP CONSTANT CHECK ON THE MOVEMENT OF AERIAL ROLLER TO


ENSURE INTERMEDIATE SPAN ALSO REACHED TO DESIRED SAG.

xv) IN CASE ANY CONDUCTOR IS PULLED ABOVE SAG IN THE SAG SPAN
THEN RELEASE BOTH THE CONDUCTORS TO BRING DOWN BELOW SAG
AND BRING EVENNESS AND THEN RE-SAGGED.

xvi) AVOID FINAL SAGGING IN WINDY DAYS, OTHER WISE ALLOWANCE IS TO


BE GIVEN FOR UPLIFT.

xvii) ALLOWANCE GIVING IS NOT DESIRABLE SINCE IT DEPENDS ON THE


WIND AND EXPERIENCE.

xviii) SPECIFIC CARE SHOULD BE TAKEN IN MEASURING FINALLY SAGGED


CONDUCTOR BEFORE CUTTING & COMPRESSING THE DEAD END
CLAMP.
i) KEEP THE CONDUCTOR FINALLY SAGGED FOR 48HRS ON
ROLLER.

ii) AGAIN CHECK THE SAG AND RE-ADJUST IT IF NECESSARY.

iii) KEEP SUSPENSION STRING ABSOLUTE VERTICAL.

iv) PLUMB MARK THE CONDUCTOR BEFORE REMOVING ROLLER BY


MEANS OF A PLUMB OR PLUMB MARKER MADE FOR SPECIFIC
PURPOSE.

v) THEN THE CONDUCTOR SHOULD BE LIFTED BY MEANS OF A


SUITABLE LIFTING DEVICE.

vi) LIFTING DEVICE MAY CONSIST OF ONE OR TWO HOOKS


DEPENDING UPON NUMBER OF CONDUCTORS.

vii) AFTER LIFTING THE CONDUCTOR FIX PREFORMED ARMOUR


RODS.

viii) TAKE 2 OR 3 RODS ON EACH SIDE OF THE CENTRE MARK SUCH


THAT THE HAND WILL NOT BE MORE THAN ONE OR TWO PITCH
LENGTHS AWAY FROM THE CENTRE MARK.
ix) THE CENTRE MARK OF THE RODS SHOULD BE LOCATED AT THE
CENTRE MARK OF THE CONDUCTOR SUPPORT.

x) APPLY THE RODS BY ROTATING ABOUT CONDUCTOR CONTINUING


FROM 1 OR 2 PITCH LENGTH OF EITHER SIDE OF THE CENTRE.

xi) FIX ARMOUR ROD APPLYING SPIRAL MOTION OF THE HANDS UNTIL
THEIR ENDS ARE SNAPPED INTO POSITION.

xii) FIX SUSPENSION STRING OVER ARMOUR ROD THEN RELEASE THE
LOAD.

xiii) CHECK THE INSULATOR ASSEMBLY IS IN PLUMB.

xiv) INSTALL VIBRATOR DAMPERS OR SPACER DAMPERS AS PER


DRAWING at 1.2 to 1.3 m

xv) IF VIBRATION DAMPERS ARE USED THEN FIX THE LINE SPACER
IMMEDIATELY THERE AFTER.
i) ALLOW THE FINALLY SAGGED CONDUCTOR FOR 48HRS TO TAKE
CARE THE CREEPAGE OR MINOR SAG ERROR DUE TO MOVEMENT OF
AERIAL ROLLER.

ii) LIFTING DEVICE SHOULD BE FIXED IN SUCH A MANNER SO THAT


LIFTING LOAD IS TRANSFERRED TO TOWER BODY.

iii) AVOID POINTED LIFTING LOAD ON THE TIP OF CROSS ARM.

iv) LIFTING HOOK SHOULD HAVE A RUBBER OR NEOPRENE LINING.

v) MATCH THE CENTRE OF THE ARMOUR ROD WITH CENTRE MARK OF


THE SUSPENSION POINT.

vi) FIX VIBRATION DAMPERS OR SPACER DAMPER IMMEDIATELY SINCE


THE CONDUCTOR AT FULL LOAD / CRITICAL TENSION.

vii) FIX LINE SPACER IMMEDIATELY FOR BUNDLE CONDUCTOR TO AVOID


CLASHING OF CONDUCTOR.
i) MEASURE THE EXACT JUMPER LENGTH REQUIRED
FOR EACH TENSION TOWER.

ii) CHECK THE JUMPER DEPTH, ANGLE AS GIVEN IN THE


ELECTRICAL CLEARANCE DIAGRAM.

iii) PRESS THE JUMPER CONE AND FIX ON THE TOWER.

iv) WHILE FIXING JUMPER THE CONDUCTOR SHOULD BE


EARTHED PREFERABLY ON BOTH THE SIDES.

v) IN CASE OF BUNDLE CONDUCTOR RIGID SPACER


SHOULD BE FIXED AS PER THE RECOMMENDATIONS
OF MANUFACTURER.
Statutory Inspection
points:
S. No.  Conductor

Location No. Earth wire

Type of tower Earth wire bonds

Chimney Number plates

Coping Danger boards

Missing bolt & Phase plates

nuts Step bolt & nuts

HR weld Protection wall

Insulators Ground

Arcing horns clearance

Jumper bolt & Tree clearance

nuts Other remarks

Jumpers
Vibration

You might also like