TR Line Matnc TSN
TR Line Matnc TSN
TR Line Matnc TSN
and Maintenance
BY
T.Sreemannarayana Murthy
Eecutive Engineer
APSLDC
what is our generation voltage?
i) 400KV
ii) 220KV
iii)132KV
Main Discussion areas of Tr. Lines
i) Survey
ii) Construction
iii) Major faults
iv) Maintenance system
SURVEY
Survey
i) Wall over survey : The proposed line
between Substations drawn as
straight line on Topo sheet. Along this
line wall over survey is conducted.
Observations recorded as report.
ii) Now Google Maps used for the
purpose
ii)Detailed Survey
:Basedon the WOS report detailed verification of
route is carried out. The following
characteristics verified
Theodolite
Total station
After completion of survey, levels of
terrain and chainage, report
prepared for tower spotting
Survey team in the field
Check survey
132kv 23mts
220kv 33mts
400Kv 45mts
Tower extensions
Available in following
+3m
+6m
+9M
+12m
+18m
+25m
+30M
Generally the extensions added at the bottom
of the tower
Insulators
Suspension Tension
132KV 9 10
220KV 13 14
400Kv 23 24
iv)Fixing hardware
Vibration dampers
suspension hardware
Tension hardware
Line spacers
MSCJ ( Midspan compressor joint)
Earthwire suspension and tension
hardware and copper jumper
Deadend cone with jumper clamp
Hardware of Transmission lines
Vibration Damper
400KV suspension hardware
(twin Moose)
Spacer between two moose
conductors
Spacer between two moose
conductors
MSCJ: Midspan compressor
joint
MSCJ after jointing
Earthwire suspension and
tension hardware
Tension dead end cone with
jumper clamp
Previous one after erection
Tension hardware
Tension hardware
Tension hardware on a charged
line
400Kv DC line
tower
315MVA PTR at 400KV SS
Mahaboob Nagar
Tower Earthing
Every tower earthed at D Leg
Two earths provided for Railway
crossing towers
Pipe earthing and counter poise
earthing methods followed
generally depending upon the
tower foot resistance.
<15 Ohm Pipe earthing
15 -30 Ohm counter poise earthing
stringing
Maintenance of records
Residual life assessment(RLA)
Log books Remedial measures
Contingency Maintenance
ERS : Emergency restoration system
Minimum three(3) ERS towers of different voltages
should keep as contingency to minimise the outage
time of supply .
In Every Tr line work
TR utility keeps 5 no suspension and
1no each angle towers as spare
5 to 10 % of line accessories as spare
For 400Kv system the spares available in SS itself
For 220kv and 132kv system the spares available in
stores
Any Questions
Thank You
Thank You