SPT and CPT
SPT and CPT
SPT and CPT
_______________________________________________________________
0.0 INTRODUCTION
This is an attempt to familiarize young engineers with elements
of subsoil exploration so that they will not feel the site work
as of new kind of work or disappointed to correspond to the
contractor, client, and senior professional engineers. Each site
is different from others with topology, stratigraphy, cost, and
scope of work. So the investigation work may considerably vary
due to these factors. However, a reference is made to each topic
in the appended sheet. These references may work as guides for
fulfilment and widening of necessary skill required to work at
the site for beginners. It is believed that this small element
of presentation/“guide” when consulted with the references cited
in the front page of the text would be enough, if correctly
followed, to face challenges of detailed investigation works at
difficult site conditions with confidence.
___________________________________________________________________
Page 1 of 57
Geotechnical Investigation
_______________________________________________________________
iii) Determine the location of bedrock. The quality of bedrock
may also be determined, but this is done only when
necessary due to the excessive cost of rock, compared
with soil, drilling.
___________________________________________________________________
Page 4 of 57
Geotechnical Investigation
_______________________________________________________________
adequately designed for stability and settlement. Borings in
river channels for bridge piers should attempt to ascertain both
scour and competent soil depth.
The number of borings is highly project—and site—dependent as
well as on the professional judgement of the geotechnical
engineer. The number must be sufficient to give geotechnical
engineer reasonable confidence that the underground conditions
have been identified well enough to make recommendation at a
reasonable risk level. Since any recommendation carries some
risk, the lower the confidence level the more conservative will
be the recommendation. If these are overly conservative, the
owner client often incurs additional design costs which can
exceed the cost of making several additional borings.
The following are not very ethical practices:
i) Making large number of unnecessary borings to obtain a
good fee where the client has essentially said “do what
is necessary.” Also, making large numbers of borings to
delineate “poor” soils when the initial borings have
established that the entire site is underlain by erratic
soil deposits.
___________________________________________________________________
Page 5 of 57
Geotechnical Investigation
_______________________________________________________________
Table-1
___________________________________________________________________
Page 6 of 57
Geotechnical Investigation
_______________________________________________________________
Table-2
___________________________________________________________________
Page 7 of 57
Geotechnical Investigation
_______________________________________________________________
• The boring should penetrate a minimum of 3 m into rock when
encountered.
During the initial stage of boring practice, the termination
depth should be flexible to accommodate unanticipated ground
conditions that might be encountered.
___________________________________________________________________
Page 10 of 57
Geotechnical Investigation
_______________________________________________________________
1.7 Duties of a Supervising Engineer in the field
___________________________________________________________________
Page 11 of 57
Geotechnical Investigation
_______________________________________________________________
A schematic diagram of a wash boring set-up is shown in the
diagram below. Sump may be a portable container (not often used)
or a pit dug on site.
___________________________________________________________________
Page 12 of 57
Geotechnical Investigation
_______________________________________________________________
simultaneously with the circulation of bentonite mud and the
drilling work is in progress.
In rotary drilling, a twisting motion is applied at top of the
drill rod by the drilling machine through a rotating gear
arrangement. The twisting motion along with static vertical
pressure of the drill rods transmitted to the drill bit at the
bottom of the hole cuts the soil with a minimum disturbance
underneath as opposed to wash boring where the underneath soil
is disturbed by repeated drops of the drill rods(chopping). The
cuttings come out with the mud water at top due to circulation
of the mud. A reverse circulation of drill mud can also be
applied in which case the cuttings are flowing through the hole
of the drill rod.
___________________________________________________________________
Page 13 of 57
Geotechnical Investigation
_______________________________________________________________
d) Provision of more field tests such as vane shear,
seismicity, electrical resistivity, pressuremeter tests,
etc.
e) Ground condition (strata)
f) Field condition, accessibility etc.
___________________________________________________________________
Page 14 of 57
Geotechnical Investigation
_______________________________________________________________
___________________________________________________________________
Page 15 of 57
Geotechnical Investigation
_______________________________________________________________
___________________________________________________________________
Page 16 of 57
Geotechnical Investigation
_______________________________________________________________
Terzaghi and Peck suggested that the relative density for very
fine or silty submerged sand with a standard penetration value
N' greater than 15 would be nearly equal to that of a dry sand
with a standard penetration value, N, where:
N = 15 + 0.5(N'-15)
If this correction was not made, Terzaghi and Peck suggested
that the relative density of even moderately dense very fine or
silty submerged sand might be overestimated by the results of
standard penetration tests.
In gravel deposits, care must be taken to determine whether a
large gravel size may have influenced the results. Usually, in
the case of gravel, only the lowest values of N are taken into
account.
The standard penetration test also can be employed in stiff
clays, weak rocks and in the weathered zones of harder rocks.
The SPT N-values are corrected for:
a) Energy delivered to the drive rods
___________________________________________________________________
Page 17 of 57
Geotechnical Investigation
_______________________________________________________________
b) Energy losses due to length of rods
c) Effect of overburden pressure in sands
to obtain corrected N values. Normalised N values are used for
correlation purpose by research workers and designers.
___________________________________________________________________
Page 19 of 57
Geotechnical Investigation
_______________________________________________________________
Table-6 (13.4) (BH Diameter, Sampler, and Rod Length Correction
Factor)
___________________________________________________________________
Page 20 of 57
Geotechnical Investigation
_______________________________________________________________
___________________________________________________________________
Page 21 of 57
Geotechnical Investigation
_______________________________________________________________
___________________________________________________________________
Page 23 of 57
Geotechnical Investigation
_______________________________________________________________
___________________________________________________________________
Page 24 of 57
Geotechnical Investigation
_______________________________________________________________
___________________________________________________________________
Page 25 of 57
Geotechnical Investigation
_______________________________________________________________
___________________________________________________________________
Page 26 of 57
Geotechnical Investigation
_______________________________________________________________
B) Observe the structure of the soil; it can be mottled or
homogeneous.
___________________________________________________________________
Page 28 of 57
Geotechnical Investigation
_______________________________________________________________
___________________________________________________________________
Page 29 of 57
Geotechnical Investigation
_______________________________________________________________
___________________________________________________________________
Page 31 of 57
Geotechnical Investigation
_______________________________________________________________
___________________________________________________________________
Page 32 of 57
Geotechnical Investigation
_______________________________________________________________
1.24 Some aspects of laboratory work
A laboratory should be clean and tidy. It should contain
sufficient storage for accommodating field samples. The storage
should not be hot and maintained proper ventilation.
Sufficient facilities for testing should be available. Working
desks should be available to accommodate testing instruments.
For chemical testing, a small room with extracting fan or fume
cupboard and adequate numbers of working desks and cupboard are
required for testing. Only trained workers should be allowed to
work.
All measuring devices should regularly checked for their
reliability.
A display board showing samples and testing be maintained at
correct location and should always be updated. No sample should
lie with unaccompanied Sample Card/Sub-sample No.
___________________________________________________________________
Page 33 of 57
Geotechnical Investigation
_______________________________________________________________
With exception of organic soil and peat.
From this, the values of F200, R200, F4, and R4 are obtained as
F200: % finer than No. 200 sieve (0.075 mm) = percentage of fine
content
___________________________________________________________________
Page 35 of 57
Geotechnical Investigation
_______________________________________________________________
R200: percentage retained on No. 200 sieve (0.075 mm) = percentage
of sand and gravel content
___________________________________________________________________
Page 36 of 57
Geotechnical Investigation
_______________________________________________________________
Next, the coefficient of uniformity Cu (= D60/D10) and the
coefficient of gradation Cg (= (D30)2/(D60 × D10)) are
calculated.
FOR G OR S
1. If F200 < 50% (or R200 ≥ 50%, i.e., gravel and sand content
is more than 50%), then soil is G or S.
4. In the final step for gravel and sand, Cu and Cg values are
evaluated for modifiers W or P. For gravel, Cu ≥ 4 and 1 ≤ Cg ≤
3 are conditions for W and the other values of those are for P.
For sand, the condition for W is Cu ≥ 6 and 1 ≤ C g ≤ 3 and the
other values are for P.
___________________________________________________________________
Page 37 of 57
Geotechnical Investigation
_______________________________________________________________
5. For GW and GP soils, if percentage of sand content is at or
more than 15%, it is named as GW (or GP) with sand.
FOR C, M, O, OR PT
1. Going back to the F200 value in Figure 4.2, if F200 ≥ 50%
(i.e., fine contents are at or more than 50%), then soil is
either M or C (or possibly O or Pt).
___________________________________________________________________
Page 38 of 57
Geotechnical Investigation
_______________________________________________________________
5. Pt (peat) should be identified by its color, odour, spongy
feeling, and, frequently, by its fibrous texture by testing
engineers. O (organic soil) can be identified by observing the
change in LL values from natural soil to oven-dried (burns some
organic) soil. If LL (oven dried)/LL (natural) is <0.75, it is
classified as O. If the ratio is ≥0.75, it is non-organic.
___________________________________________________________________
Page 39 of 57
Geotechnical Investigation
_______________________________________________________________
SOLUTION
Since more than 12 percent passes the No.200 sieve, we can immediately
eliminate GW, GP, SW, and SP as possible classification for all three soils.
72 – 38 = 34 percent sand
100 – 72 = 28 percent gravel
(3) More than 12 percent passes the No. 200 sieve, and from the
Atterberg Limits, the soil plots below A line (wL = 39 and Ip =
___________________________________________________________________
Page 41 of 57
Geotechnical Investigation
_______________________________________________________________
10); thus the (-) No.40 fraction is an ML. Noting that the
percentage of sand and gravel are nearly equal, Soil B is
greyish-brown, very gravelly, silty sand with trace of organic
material, SM.
___________________________________________________________________
Page 43 of 57
Geotechnical Investigation
_______________________________________________________________
___________________________________________________________________
Page 44 of 57
Geotechnical Investigation
_______________________________________________________________
___________________________________________________________________
Page 45 of 57
Geotechnical Investigation
_______________________________________________________________
___________________________________________________________________
Page 46 of 57
Geotechnical Investigation
_______________________________________________________________
___________________________________________________________________
Page 47 of 57
Geotechnical Investigation
_______________________________________________________________
___________________________________________________________________
Page 48 of 57
Geotechnical Investigation
_______________________________________________________________
___________________________________________________________________
Page 49 of 57
Geotechnical Investigation
_______________________________________________________________
___________________________________________________________________
Page 50 of 57
Geotechnical Investigation
_______________________________________________________________
___________________________________________________________________
Page 51 of 57
Geotechnical Investigation
_______________________________________________________________
___________________________________________________________________
Page 52 of 57
Geotechnical Investigation
_______________________________________________________________
4) It allows a number of correlations between cone resistance
and the desired engineering property.
7) Engineers can gather data much faster and can take spot
decision for testing intermediate locations.
Disadvantages:
Some of the major disadvantages are that:
1) This method is applicable only in fine—grained deposits
(clay, silt, fine sands) where the material does not have
massive resistance to cone resistance. Pushing can be of
limited use in gravels and cemented soils.
___________________________________________________________________
Page 53 of 57
Geotechnical Investigation
_______________________________________________________________
7) No soil samples are taken, and
3) Atterberg Limits
It is reliable irrespective of the sample disturbance. Its
value is slightly changed when tested on an air dried
sample.
4) Unconfined Compression
It is reliable when the sample is fine and saturated
undisturbed soil. Because of its simplicity, it is
preferred by many organisations.
5) Triaxial Compression
The test is performed on undisturbed fine soils and at
different loading and drainage conditions. It is costlier
than unconfined compression test. It is a preferred test by
geotechnical engineers.
___________________________________________________________________
Page 54 of 57
Geotechnical Investigation
_______________________________________________________________
known as UU(unconsolidated undrained), CU(consolidated
undrained, and CD(consolidated drained).
7) Consolidation
The test is performed on soft fine soil to determine
consolidation parameters. It is a lengthy test to perform
but valuable parameters are obtained. The test is time
consuming.
___________________________________________________________________
Page 55 of 57
Geotechnical Investigation
_______________________________________________________________
___________________________________________________________________
Page 56 of 57
Geotechnical Investigation
_______________________________________________________________
A geotechnical engineer may find necessity of using void ratio
in compacted fill with cohesionless soil. This is because he has
to correlate these values with other geotechnical parameters
used to estimate the ground improvement to cope with potential
earthquake.
___________________________________________________________________
Page 57 of 57