Location via proxy:   [ UP ]  
[Report a bug]   [Manage cookies]                

Analisa Harga Satuan

Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 138

ANALISA HARGA SATUAN PEKERJAAN

(Permen PUPR No. 28/PRT/M/2016)

PEKERJAAN :
LOKASI :

1 Jenis Pekerjaan : Mobilisasi dan Demobilisasi


Satuan Pembayaran : ls
Standar : -

Harga Total Harga


No. Uraian Koefisien Satuan Jumlah
(Rp) (Rp)

A TENAGA

SUB JUMLAH A -

B BAHAN

SUB JUMLAH B -

C PERALATAN
Hydrolik Jacking Pile 1.0000 unit 26,500,000.00 26,500,000.00
Bulldozer 1.0000 unit 2,500,000.00 2,500,000.00
Water tank truck 1.0000 unit 750,000.00 750,000.00
Mesin Beton Molen / Concrete Mixer 3.0000 unit 500,000.00 1,500,000.00
Pompa Air 1.0000 unit 150,000.00 150,000.00
Generator set 1.0000 unit 150,000.00 150,000.00
Compressor 1.0000 unit 150,000.00 150,000.00
Theodolite 1.0000 unit 75,000.00 75,000.00
Mesin Las Listrik 1.0000 unit 250,000.00 250,000.00
Concrete Vibrator 1.0000 unit 75,000.00 75,000.00
Hand Stamper 1.0000 unit 150,000.00 150,000.00
Scafolding 300.0000 unit 2,500.00 750,000.00

SUB JUMLAH C 33,000,000.00

D JUMLAH (A+B) 33,000,000.00


E HARGA SATUAN PEKERJAAN (D) 33,000,000.00

2 Jenis Pekerjaan : Pengukuran dan pemasangan 1 m' Bouwplank


Satuan Pembayaran : m1
Standar : A.2.2.1.4

Harga Total Harga


No. Uraian Koefisien Satuan Jumlah
(Rp) (Rp)

A TENAGA
Pekerja 0.1000 Org/ Hr 75,000.00 7,500.00
Tukang 0.1000 Org/ Hr 80,000.00 8,000.00
Kepala Tukang 0.0100 Org/ Hr 90,000.00 900.00
Mandor 0.0050 Org/ Hr 100,000.00 500.00

SUB JUMLAH A 16,900.00

B BAHAN
Kayu 5/7 0.0120 m³ 3,300,000.00 39,600.00
Paku Biasa 2" - 3" 0.0200 kg 15,000.00 300.00
Kayu Papan 3/20 0.0070 m³ 3,500,000.00 24,500.00

SUB JUMLAH B 64,400.00

C PERALATAN

SUB JUMLAH C -

D JUMLAH (A+B+C) 81,300.00


E Overhead & Profit 10% x D 8,130.00
F HARGA SATUAN PEKERJAAN (D+E) 89,430.00

3 Jenis Pekerjaan : Membersihkan Lapangan dan Peralatan


Halaman 1
ANALISA HARGA SATUAN PEKERJAAN
(Permen PUPR No. 28/PRT/M/2016)

PEKERJAAN :
LOKASI :

Satuan Pembayaran : m2
Standar : A.2.2.1.9

Harga Total Harga


No. Uraian Kuantitas Satuan Jumlah
(Rp) (Rp)

A TENAGA
Pekerja 0.1000 Or/hr 75,000.00 7,500.00
Mandor 0.0500 Or/hr 100,000.00 5,000.00

SUB JUMLAH A 12,500.00

B BAHAN

SUB JUMLAH B -

C PERALATAN

SUB JUMLAH C -

D JUMLAH (A+B+C) 12,500.00


E Overhead & Profit 10% x D 1,250.00
F HARGA SATUAN PEKERJAAN 13,750.00

4 Jenis Pekerjaan : Pembongkaran 1 m3 dinding tembok bata


Satuan Pembayaran : m3
Standar : A.2.2.1.14

Harga Total Harga


No. Uraian Kuantitas Satuan Jumlah
(Rp) (Rp)

A TENAGA
Pekerja 6.6670 Org/ Hr 75,000.00 500,025.00
Mandor 0.3330 Org/ Hr 100,000.00 33,300.00

SUB JUMLAH A 533,325.00

B BAHAN

SUB JUMLAH B -

C PERALATAN

SUB JUMLAH C -

D JUMLAH (A+B+C) 533,325.00


E Overhead & Profit 10% x D 53,332.50
F HARGA SATUAN PEKERJAAN 586,657.50

Halaman 2
ANALISA HARGA SATUAN PEKERJAAN
(Permen PUPR No. 28/PRT/M/2016)

PEKERJAAN :
LOKASI :

5 Jenis Pekerjaan : Penggalian 1 m3 tanah biasa sedalam 1 m


Satuan Pembayaran : m3
Standar : A.2.3.1.1

Harga Total Harga


No. Uraian Kuantitas Satuan Jumlah
(Rp) (Rp)

A TENAGA
Pekerja 0.750 Org/ Hr 75,000.00 56,250.00
Mandor 0.025 Org/ Hr 100,000.00 2,500.00

SUB JUMLAH A 58,750.00

B BAHAN

SUB JUMLAH B -

C PERALATAN

SUB JUMLAH C -

D JUMLAH (A+B+C) 58,750.00


E Overhead & Profit 10% x D 5,875.00
F HARGA SATUAN PEKERJAAN (D+E) 64,625.00

6 Jenis Pekerjaan : Penggalian 1 m3 tanah biasa sedalam 2 m


Satuan Pembayaran : m3
Standar : A.2.3.1.2

Harga Total Harga


No. Uraian Kuantitas Satuan Jumlah
(Rp) (Rp)

A TENAGA
Pekerja 0.900 Org/ Hr 75,000.00 67,500.00
Mandor 0.045 Org/ Hr 100,000.00 4,500.00

SUB JUMLAH A 72,000.00

B BAHAN

SUB JUMLAH B -

C PERALATAN

SUB JUMLAH C -

D JUMLAH (A+B+C) 72,000.00


E Overhead & Profit 10% x D 7,200.00
F HARGA SATUAN PEKERJAAN (D+E) 79,200.00

Halaman 3
ANALISA HARGA SATUAN PEKERJAAN
(Permen PUPR No. 28/PRT/M/2016)

PEKERJAAN :
LOKASI :

7 Jenis Pekerjaan : Penggalian 1 m3 tanah biasa sedalam 3 m


Satuan Pembayaran : m3
Standar : A.2.3.1.3

Harga Total Harga


No. Uraian Kuantitas Satuan Jumlah
(Rp) (Rp)

A TENAGA
Pekerja 1.050 Org/ Hr 75,000.00 78,750.00
Mandor 0.067 Org/ Hr 100,000.00 6,700.00

SUB JUMLAH A 85,450.00

B BAHAN

SUB JUMLAH B -

C PERALATAN

SUB JUMLAH C -

D JUMLAH (A+B+C) 85,450.00


E Overhead & Profit 10% x D 8,545.00
F HARGA SATUAN PEKERJAAN (D+E) 93,995.00

8 Jenis Pekerjaan : Pengurugan kembali 1 m3 galian tanah


Satuan Pembayaran : m3
Standar : A.2.3.1.9

Pengurugan kembali 1 m3 galian di hitung dari 1/3 kali dari koefisien pekerjaan galian

Harga Total Harga


No. Uraian Kuantitas Satuan Jumlah
(Rp) (Rp)

A TENAGA
Pekerja 0.250 Org/ Hr 75,000.00 18,750.00
Mandor 0.008 Org/ Hr 100,000.00 833.33

SUB JUMLAH A 19,583.33

B BAHAN

SUB JUMLAH B -

C PERALATAN

SUB JUMLAH C -

D JUMLAH (A+B+C) 19,583.33


E Overhead & Profit 10% x D 1,958.33
F HARGA SATUAN PEKERJAAN (D+E) 21,541.67

Halaman 4
ANALISA HARGA SATUAN PEKERJAAN
(Permen PUPR No. 28/PRT/M/2016)

PEKERJAAN :
LOKASI :

9 Jenis Pekerjaan : Pemadatan tanah 1 m3 tanah (per 20 cm)


Satuan Pembayaran : m3
Standar : A.2.3.1.10

Harga Total Harga


No. Uraian Kuantitas Satuan Jumlah
(Rp) (Rp)

A TENAGA
Pekerja 0.500 Org/ Hr 75,000.00 37,500.00
Mandor 0.050 Org/ Hr 100,000.00 5,000.00

SUB JUMLAH A 42,500.00

B BAHAN
Pekerja 0.750 Or/hr 75,000.00 56,250.00
Mandor 0.025 Or/hr 100,000.00 2,500.00

SUB JUMLAH B 58,750.00

C PERALATAN

SUB JUMLAH C -

D JUMLAH (A+B+C) 101,250.00


E Overhead & Profit 10% x D 10,125.00
F HARGA SATUAN PEKERJAAN (D+E) 111,375.00

10 Jenis Pekerjaan : Pengurugan dengan pasir urug


Satuan Pembayaran : m3
Standar : A.2.3.1.11

Harga Total Harga


No. Uraian Kuantitas Satuan Jumlah
(Rp) (Rp)

A UPAH
Pekerja 0.3000 Org/ Hr 75,000.00 22,500.00
Mandor 0.0100 Org/ Hr 100,000.00 1,000.00

SUB JUMLAH A 23,500.00

B BAHAN
Pasir Urug 1.200 m³ 120,000.00 144,000.00

SUB JUMLAH B 144,000.00

C UPAH
-

SUB JUMLAH C -

D JUMLAH (A+B+C) 167,500.00


E Overhead & Profit 10% x D 16,750.00
F HARGA SATUAN PEKERJAAN (D+E) 184,250.00

Halaman 5
ANALISA HARGA SATUAN PEKERJAAN
(Permen PUPR No. 28/PRT/M/2016)

PEKERJAAN :
LOKASI :

11 Jenis Pekerjaan : Pengurugan dengan Tanah Urug


Satuan Pembayaran : m3
Standar : -

Harga Total Harga


No. Uraian Kuantitas Satuan Jumlah
(Rp) (Rp)

A TENAGA
Pekerja 0.3000 Org/ Hr 75,000.00 22,500.00
Mandor 0.0100 Org/ Hr 100,000.00 1,000.00

SUB JUMLAH A 23,500.00

B BAHAN
Tanah Urug 1.200 m³ 80,500.00 96,600.00

SUB JUMLAH B 96,600.00

C PERALATAN
-

SUB JUMLAH C -

D JUMLAH (A+B+C) 120,100.00


E Overhead & Profit 10% x D 12,010.00
F HARGA SATUAN PEKERJAAN 132,110.00

12 Jenis Pekerjaan : Pengadaan Mini Pile 25 x 25 L 6 m


Satuan Pembayaran : m
Standar : -

Harga Total Harga


No. Uraian Kuantitas Satuan Jumlah
(Rp) (Rp)

A TENAGA
-

SUB JUMLAH A -

B BAHAN
Tiang Pancang Minipile Beton 25x25 1.000 m 205,000.00 205,000.00

SUB JUMLAH B 205,000.00

C PERALATAN
-

SUB JUMLAH C -

D JUMLAH (A+B+C) 205,000.00


E Overhead & Profit 10% x D 20,500.00
F HARGA SATUAN PEKERJAAN (D+E) 225,500.00

Halaman 6
ANALISA HARGA SATUAN PEKERJAAN
(Permen PUPR No. 28/PRT/M/2016)

PEKERJAAN :
LOKASI :

13 Jenis Pekerjaan : Pemancangan Mini Pile 25 x 25


Satuan Pembayaran : m
Standar : -

Harga Total Harga


No. Uraian Kuantitas Satuan Jumlah
(Rp) (Rp)

A TENAGA
Pekerja 0.1875 Org/ Hr 75,000.00 14,062.50
Tukang 0.0388 Org/ Hr 80,000.00 3,104.00
Kepala Tukang 0.0039 Org/ Hr 90,000.00 349.20
Mandor 0.0172 Org/ Hr 100,000.00 1,720.00

SUB JUMLAH A 19,235.70

B BAHAN
-

SUB JUMLAH B -

C PERALATAN
Hydraulic Jacking 0.090 jam 400,000.00 36,000.00
Alat Bantu 1.000 ls 15,000.00 15,000.00

SUB JUMLAH C 51,000.00

D JUMLAH (A+B+C) 70,235.70


E Overhead & Profit 10% x D 7,023.57
F HARGA SATUAN PEKERJAAN (D+E) 77,259.27

14 Jenis Pekerjaan : Sambungan Tiang Pancang


Satuan Pembayaran : joint
Standar : -

Harga Total Harga


No. Uraian Kuantitas Satuan Jumlah
(Rp) (Rp)

A TENAGA
Pekerja 0.1875 Org/ Hr 75,000.00 14,062.50
Mandor 0.0172 Org/ Hr 100,000.00 1,720.00

SUB JUMLAH A 15,782.50

B BAHAN
-

SUB JUMLAH B -

C PERALATAN
Mesin Las Listrik 0.1875 jam 150,000.00 28,125.00
Kawat Las 0.2490 kg 28,000.00 6,972.00

SUB JUMLAH C 35,097.00

D JUMLAH (A+B+C) 50,879.50


E Overhead & Profit 10% x D 5,087.95
F HARGA SATUAN PEKERJAAN (D+E) 55,967.45

Halaman 7
ANALISA HARGA SATUAN PEKERJAAN
(Permen PUPR No. 28/PRT/M/2016)

PEKERJAAN :
LOKASI :

15 Jenis Pekerjaan : Pemotongan Kepala Tiang Pancang


Satuan Pembayaran : ttk
Standar : -

Harga Total Harga


No. Uraian Kuantitas Satuan Jumlah
(Rp) (Rp)

A TENAGA
Pekerja 0.1875 Org/ Hr 75,000.00 14,062.50
Mandor 0.0172 Org/ Hr 100,000.00 1,720.00

SUB JUMLAH A 15,782.50

B BAHAN
-

SUB JUMLAH B -

C PERALATAN
Mesin Las Listrik 0.1875 jam 150,000.00 28,125.00
Alat Bantu 1.000 ls 15,000.00 15,000.00

SUB JUMLAH C 43,125.00

D JUMLAH (A+B+C) 58,907.50


E Overhead & Profit 10% x D 5,890.75
F HARGA SATUAN PEKERJAAN (D+E) 64,798.25

16 Jenis Pekerjaan : Membuat 1 m3 Lantai Kerja Beton Mutu f'c = 7.4 Mpa (K100), Slump (3-6) cm, w/c=0.87
Satuan Pembayaran : m3
Standar : A.4.1.1.4

Harga Total Harga


No. Uraian Kuantitas Satuan Jumlah
(Rp) (Rp)

A TENAGA
Pekerja 1.2000 Org/ Hr 75,000.00 90,000.00
Tukang 0.2000 Org/ Hr 80,000.00 16,000.00
Kepala Tukang 0.0200 Org/ Hr 90,000.00 1,800.00
Mandor 0.0600 Org/ Hr 100,000.00 6,000.00

SUB JUMLAH A 113,800.00

B BAHAN
Semen Portland / kg 230.000 kg 1,400.00 322,000.00
Pasir Beton / kg 893.000 kg 117.86 105,246.43
Kerikil (Maks 30 mm) / kg 1,027.000 Kg 191.11 196,271.11
Air 200.000 liter 200.00 40,000.00

SUB JUMLAH B 663,517.54

C PERALATAN

SUB JUMLAH C

C JUMLAH (A+B+C) 777,317.54


D Overhead & Profit 10% x C 77,731.75
E HARGA SATUAN PEKERJAAN 855,049.29

Halaman 8
ANALISA HARGA SATUAN PEKERJAAN
(Permen PUPR No. 28/PRT/M/2016)

PEKERJAAN :
LOKASI :

17 Jenis Pekerjaan : Membuat 1 m3 beton mutu f'c = 14.5 Mpa (K175), Slump (12 ±2) cm, w/c=0.66
Satuan Pembayaran : m3
Standar : A.4.1.1.5

Harga Total Harga


No. Uraian Kuantitas Satuan Jumlah
(Rp) (Rp)

A TENAGA
Pekerja 1.6500 Org/ Hr 75,000.00 123,750.00
Tukang 0.2750 Org/ Hr 80,000.00 22,000.00
Kepala Tukang 0.0280 Org/ Hr 90,000.00 2,520.00
Mandor 0.0830 Org/ Hr 100,000.00 8,300.00

SUB JUMLAH A 156,570.00

B BAHAN
Semen Portland / kg 326.000 kg 1,400.00 456,400.00
Pasir Beton / kg 760.000 kg 117.86 89,571.43
Kerikil (Maks 30 mm) / kg 1,029.000 Kg 191.11 196,653.33
Air 215.000 liter 200.00 43,000.00

SUB JUMLAH B 785,624.76

C PERALATAN

SUB JUMLAH C

D JUMLAH (A+B+C) 942,194.76


E Overhead & Profit 10% x D 94,219.48
F HARGA SATUAN PEKERJAAN (D+E) 1,036,414.24

18 Jenis Pekerjaan : Membuat 1 m3 beton mutu f'c = 16.9 Mpa (K200), Slump (12 ±2) cm, w/c=0.61
Satuan Pembayaran : m3
Standar : A.4.1.1.6

Harga Total Harga


No. Uraian Kuantitas Satuan Jumlah
(Rp) (Rp)

A TENAGA
Pekerja 1.6500 Org/ Hr 75,000.00 123,750.00
Tukang 0.2750 Org/ Hr 80,000.00 22,000.00
Kepala Tukang 0.0280 Org/ Hr 90,000.00 2,520.00
Mandor 0.0830 Org/ Hr 100,000.00 8,300.00

SUB JUMLAH A 156,570.00

B BAHAN
Semen Portland / kg 352.000 kg 1,400.00 492,800.00
Pasir Beton / kg 731.000 kg 117.86 86,153.57
Kerikil (Maks 30 mm) / kg 1,031.000 Kg 191.11 197,035.56
Air 215.000 liter 200.00 43,000.00

SUB JUMLAH B 818,989.13

C PERALATAN

SUB JUMLAH C

D JUMLAH (A+B+C) 975,559.13


E Overhead & Profit 10% x D 97,555.91
F HARGA SATUAN PEKERJAAN (D+E) 1,073,115.04

Halaman 9
ANALISA HARGA SATUAN PEKERJAAN
(Permen PUPR No. 28/PRT/M/2016)

PEKERJAAN :
LOKASI :

19 Jenis Pekerjaan : Membuat 1 m3 beton mutu f’c = 19,3 MPa (K 225), slump (12 ± 2) cm, w/c = 0,58
Satuan Pembayaran : m3
Standar : A.4.1.1.7

Harga Total Harga


No. Uraian Kuantitas Satuan Jumlah
(Rp) (Rp)

A TENAGA
Pekerja 1.6500 Org/ Hr 75,000.00 123,750.00
Tukang 0.2750 Org/ Hr 80,000.00 22,000.00
Kepala Tukang 0.0280 Org/ Hr 90,000.00 2,520.00
Mandor 0.0830 Org/ Hr 100,000.00 8,300.00

SUB JUMLAH A 156,570.00

B BAHAN
Semen Portland / kg 371.000 kg 1,400.00 519,400.00
Pasir Beton / kg 698.000 kg 117.86 82,264.29
Kerikil (Maks 30 mm) / kg 1,047.000 Kg 191.11 200,093.33
Air 215.000 liter 200.00 43,000.00

SUB JUMLAH B 844,757.62

C PERALATAN

SUB JUMLAH C

D JUMLAH (A+B+C) 1,001,327.62


E Overhead & Profit 10% x D 100,132.76
F HARGA SATUAN PEKERJAAN 1,101,460.38

20 Jenis Pekerjaan : Membuat 1 m3 beton mutu f’c = 21.7 MPa (K 250), slump (12 ± 2) cm, w/c = 0,56
Satuan Pembayaran : m3
Standar : A.4.1.1.8

Harga Total Harga


No. Uraian Kuantitas Satuan Jumlah
(Rp) (Rp)

A TENAGA
Pekerja 1.6500 Org/ Hr 75,000.00 123,750.00
Tukang 0.2750 Org/ Hr 80,000.00 22,000.00
Kepala Tukang 0.0280 Org/ Hr 90,000.00 2,520.00
Mandor 0.0830 Org/ Hr 100,000.00 8,300.00

SUB JUMLAH A 156,570.00

B BAHAN
Semen Portland / kg 384.000 kg 1,400.00 537,600.00
Pasir Beton / kg 692.000 kg 117.86 81,557.14
Kerikil (Maks 30 mm) / kg 1,039.000 Kg 191.11 198,564.44
Air 215.000 liter 200.00 43,000.00

SUB JUMLAH B 860,721.59

C PERALATAN

SUB JUMLAH C

D JUMLAH (A+B+C) 1,017,291.59


E Overhead & Profit 10% x D 101,729.16
F HARGA SATUAN PEKERJAAN 1,119,020.75

Halaman 10
ANALISA HARGA SATUAN PEKERJAAN
(Permen PUPR No. 28/PRT/M/2016)

PEKERJAAN :
LOKASI :

21 Jenis Pekerjaan : Membuat 1 m3 beton mutu f’c = 24 MPa (K 275), slump (12 ± 2) cm, w/c = 0,53
Satuan Pembayaran : m3
Standar : A.4.1.1.9

Harga Total Harga


No. Uraian Kuantitas Satuan Jumlah
(Rp) (Rp)

A TENAGA
Pekerja 1.6500 Org/ Hr 75,000.00 123,750.00
Tukang 0.2750 Org/ Hr 80,000.00 22,000.00
Kepala Tukang 0.0280 Org/ Hr 90,000.00 2,520.00
Mandor 0.0830 Org/ Hr 100,000.00 8,300.00

SUB JUMLAH A 156,570.00

B BAHAN
Semen Portland / kg 406.000 kg 1,400.00 568,400.00
Pasir Beton / kg 684.000 kg 117.86 80,614.29
Kerikil (Maks 30 mm) / kg 1,026.000 Kg 191.11 196,080.00
Air 215.000 liter 200.00 43,000.00

SUB JUMLAH B 888,094.29

C PERALATAN

SUB JUMLAH C

D JUMLAH (A+B+C) 1,044,664.29


E Overhead & Profit 10% x D 104,466.43
F HARGA SATUAN PEKERJAAN 1,149,130.71

22 Jenis Pekerjaan : Membuat 1 m3 beton mutu f’c = 26.4 MPa (K 300), slump (12 ± 2) cm, w/c = 0,52
Satuan Pembayaran : m3
Standar : A.4.1.1.10

Harga Total Harga


No. Uraian Kuantitas Satuan Jumlah
(Rp) (Rp)

A TENAGA
Pekerja 1.6500 Org/ Hr 75,000.00 123,750.00
Tukang 0.2750 Org/ Hr 80,000.00 22,000.00
Kepala Tukang 0.0280 Org/ Hr 90,000.00 2,520.00
Mandor 0.0830 Org/ Hr 100,000.00 8,300.00

SUB JUMLAH A 156,570.00

B BAHAN
Semen Portland / kg 413.000 kg 1,400.00 578,200.00
Pasir Beton / kg 681.000 kg 117.86 80,260.71
Kerikil (Maks 30 mm) / kg 1,021.000 Kg 191.11 195,124.44
Air 215.000 liter 200.00 43,000.00

SUB JUMLAH B 896,585.16

C PERALATAN

SUB JUMLAH C

D JUMLAH (A+B+C) 1,053,155.16


E Overhead & Profit 10% x D 105,315.52
F HARGA SATUAN PEKERJAAN 1,158,470.67

Halaman 11
ANALISA HARGA SATUAN PEKERJAAN
(Permen PUPR No. 28/PRT/M/2016)

PEKERJAAN :
LOKASI :

23 Jenis Pekerjaan : Membuat 1 m3 beton mutu f’c = 28.8 MPa (K 325), slump (12 ± 2) cm, w/c = 0,49
Satuan Pembayaran : m3
Standar : A.4.1.1.11

Harga Total Harga


No. Uraian Kuantitas Satuan Jumlah
(Rp) (Rp)

A TENAGA
Pekerja 2.1000 Org/ Hr 75,000.00 157,500.00
Tukang 0.3500 Org/ Hr 80,000.00 28,000.00
Kepala Tukang 0.0350 Org/ Hr 90,000.00 3,150.00
Mandor 0.1050 Org/ Hr 100,000.00 10,500.00

SUB JUMLAH A 199,150.00

B BAHAN
Semen Portland / kg 439.000 kg 1,400.00 614,600.00
Pasir Beton / kg 670.000 kg 117.86 78,964.29
Kerikil (Maks 30 mm) / kg 1,006.000 Kg 191.11 192,257.78
Air 215.000 liter 200.00 43,000.00

SUB JUMLAH B 928,822.06

C PERALATAN

SUB JUMLAH C

D JUMLAH (A+B+C) 1,127,972.06


E Overhead & Profit 10% x D 112,797.21
F HARGA SATUAN PEKERJAAN 1,240,769.27

24 Jenis Pekerjaan : Membuat 1 m3 beton mutu f’c = 31.2 MPa (K 350), slump (12 ± 2) cm, w/c = 0,48
Satuan Pembayaran : m3
Standar : A.4.1.1.12

Harga Total Harga


No. Uraian Kuantitas Satuan Jumlah
(Rp) (Rp)

A TENAGA
Pekerja 2.1000 Org/ Hr 75,000.00 157,500.00
Tukang 0.3500 Org/ Hr 80,000.00 28,000.00
Kepala Tukang 0.0350 Org/ Hr 90,000.00 3,150.00
Mandor 0.1050 Org/ Hr 100,000.00 10,500.00

SUB JUMLAH A 199,150.00

B BAHAN
Semen Portland / kg 448.000 kg 1,400.00 627,200.00
Pasir Beton / kg 667.000 kg 117.86 78,610.71
Kerikil (Maks 30 mm) / kg 1,000.000 Kg 191.11 191,111.11
Air 215.000 liter 200.00 43,000.00

SUB JUMLAH B 939,921.83

C PERALATAN

SUB JUMLAH C

C JUMLAH (A+B+C) 1,139,071.83


D Overhead & Profit 10% x C 113,907.18
E HARGA SATUAN PEKERJAAN 1,252,979.01

Halaman 12
ANALISA HARGA SATUAN PEKERJAAN
(Permen PUPR No. 28/PRT/M/2016)

PEKERJAAN :
LOKASI :

25 Jenis Pekerjaan : Pembesian 10 kg dengan Besi Polos atau Besi Ulir


Satuan Pembayaran : kg
Standar : A.4.1.1.17

Harga Total Harga


No. Uraian Kuantitas Satuan Jumlah
(Rp) (Rp)

A TENAGA
Pekerja 0.0700 Org/ Hr 75,000.00 5,250.00
Tukang 0.0700 Org/ Hr 80,000.00 5,600.00
Kepala Tukang 0.0070 Org/ Hr 90,000.00 630.00
Mandor 0.0040 Org/ Hr 100,000.00 400.00

SUB JUMLAH B 11,880.00

B BAHAN
Besi Beton Ulir 10.500 kg 13,000.00 136,500.00
Kawat Beton 0.150 kg 20,000.00 3,000.00

SUB JUMLAH A 139,500.00

C PERALATAN
-

SUB JUMLAH A -

D HARGA SATUAN PEKERJAAN UNTUK 10 KG BESI (A+B+C) 151,380.00


E Overhead & Profit 10% x D 15,138.00
F HARGA SATUAN PEKERJAAN 166,518.00
G HARGA SATUAN PEKERJAAN UNTUK 1 KG BESI 16,651.80

26 Jenis Pekerjaan : Pembesian 10 kg Jaring Kawat Baja (Wiremesh)


Satuan Pembayaran : kg
Standar : A.4.1.1.19

Harga Total Harga


No. Uraian Kuantitas Satuan Jumlah
(Rp) (Rp)

A TENAGA
Pekerja 0.025 Org/ Hr 75,000.00 1,875.00
Tukang 0.025 Org/ Hr 80,000.00 2,000.00
Kepala Tukang 0.025 Org/ Hr 90,000.00 2,250.00
Mandor 0.001 Org/ Hr 100,000.00 100.00

SUB JUMLAH A 6,225.00

B BAHAN
Besi Beton Polos 10.200 kg 12,200.00 124,440.00
Kawat Beton 0.050 kg 20,000.00 1,000.00

SUB JUMLAH B 125,440.00

C PERALATAN
-

SUB JUMLAH C -

D HARGA SATUAN PEKERJAAN UNTUK 10 KG BESI (A+B+C) 131,665.00


E Overhead & Profit 10% x D 13,166.50
F HARGA SATUAN PEKERJAAN 144,831.50
G HARGA SATUAN PEKERJAAN UNTUK 1 KG WIREMESH 14,483.15

Halaman 13
ANALISA HARGA SATUAN PEKERJAAN
(Permen PUPR No. 28/PRT/M/2016)

PEKERJAAN :
LOKASI :

27 Jenis Pekerjaan : Pemasangan 1 m2 Bekisting untuk Pondasi


Satuan Pembayaran : m2
Standar : A.4.1.1.20

Harga Total Harga


No. Uraian Kuantitas Satuan Jumlah
(Rp) (Rp)

A TENAGA
Pekerja 0.520 Org/ Hr 75,000.00 39,000.00
Tukang 0.260 Org/ Hr 80,000.00 20,800.00
Kepala Tukang 0.026 Org/ Hr 90,000.00 2,340.00
Mandor 0.026 Org/ Hr 100,000.00 2,600.00

SUB JUMLAH A 64,740.00

B BAHAN
Kayu/ Papan Bekisting 0.040 m³ 2,200,000.00 88,000.00
Paku Biasa 2" - 5" 0.300 kg 15,000.00 4,500.00
Minyak Bekisting/ Teak Oil 0.100 liter 9,500.00 950.00

SUB JUMLAH B 93,450.00

C PERALATAN
-

SUB JUMLAH C -

D JUMLAH (A+B+C) 158,190.00


E Overhead & Profit 10% x D 15,819.00
F HARGA SATUAN PEKERJAAN 174,009.00

28 Jenis Pekerjaan : Pemasangan 1 m2 Bekisting untuk Sloof


Satuan Pembayaran : m2
Standar : A.4.1.1.21

Harga Total Harga


No. Uraian Kuantitas Satuan Jumlah
(Rp) (Rp)

A TENAGA
Pekerja 0.520 Or/hr 75,000.00 39,000.00
Tukang 0.260 Or/hr 80,000.00 20,800.00
Kepala Tukang 0.026 Or/hr 90,000.00 2,340.00
Mandor 0.026 Or/hr 100,000.00 2,600.00

SUB JUMLAH A 64,740.00


B BAHAN
Kayu/ Papan Bekisting 0.045 m³ 2,200,000.00 99,000.00
Paku Biasa 2" - 5" 0.300 kg 15,000.00 4,500.00
Minyak Bekisting/ Teak Oil 0.100 liter 9,500.00 950.00

SUB JUMLAH B 104,450.00

C PERALATAN
-

SUB JUMLAH C -

D JUMLAH (A+B+C) 169,190.00


E Overhead & Profit 10% x D 16,919.00
F HARGA SATUAN PEKERJAAN 186,109.00

Halaman 14
ANALISA HARGA SATUAN PEKERJAAN
(Permen PUPR No. 28/PRT/M/2016)

PEKERJAAN :
LOKASI :

29 Jenis Pekerjaan : Pemasangan 1 m2 Bekisting untuk Kolom


Satuan Pembayaran : m2
Standar : A.4.1.1.22

Harga Total Harga


No. Uraian Kuantitas Satuan Jumlah
(Rp) (Rp)

A TENAGA
Pekerja 0.660 Or/hr 75,000.00 49,500.00
Tukang 0.330 Or/hr 80,000.00 26,400.00
Kepala Tukang 0.033 Or/hr 90,000.00 2,970.00
Mandor 0.033 Or/hr 100,000.00 3,300.00

SUB JUMLAH A 82,170.00

B BAHAN
Kayu/ Papan Bekisting 0.040 m³ 2,200,000.00 88,000.00
Paku Biasa 2" - 5" 0.400 kg 15,000.00 6,000.00
Minyak Bekisting/ Teak Oil 0.200 liter 9,500.00 1,900.00
Kayu/ Papan Klas II 0.015 m³ 3,300,000.00 49,500.00
Plywood 9 mm 0.350 lbr 133,000.00 46,550.00
Dolken Kayu Ø (8-10)cm, panjang 4 m 2.000 btg 15,000.00 30,000.00

SUB JUMLAH B 221,950.00

C PERALATAN
-

SUB JUMLAH C -

D JUMLAH (A+B+C) 304,120.00


E Overhead & Profit 10% x D 30,412.00
F HARGA SATUAN PEKERJAAN 334,532.00

30 Jenis Pekerjaan : Pemasangan 1 m2 Bekisting untuk Balok


Satuan Pembayaran : m2
Standar : A.4.1.1.23

Harga Total Harga


No. Uraian Kuantitas Satuan Jumlah
(Rp) (Rp)

A TENAGA
Pekerja 0.660 Or/hr 75,000.00 49,500.00
Tukang 0.330 Or/hr 80,000.00 26,400.00
Kepala Tukang 0.033 Or/hr 90,000.00 2,970.00
Mandor 0.033 Or/hr 100,000.00 3,300.00

SUB JUMLAH A 82,170.00

B BAHAN
Kayu/ Papan Bekisting 0.040 m³ 2,200,000.00 88,000.00
Paku Biasa 2" - 5" 0.400 kg 15,000.00 6,000.00
Minyak Bekisting/ Teak Oil 0.200 liter 9,500.00 1,900.00
Kayu/ Papan Klas II 0.018 m³ 3,300,000.00 59,400.00
Plywood 9 mm 0.350 lbr 133,000.00 46,550.00
Dolken Kayu Ø (8-10)cm, panjang 4 m 2.000 btg 15,000.00 30,000.00

SUB JUMLAH B 231,850.00

C PERALATAN
-

SUB JUMLAH C -

D JUMLAH (A+B+C) 314,020.00


E Overhead & Profit 10% x D 31,402.00
F HARGA SATUAN PEKERJAAN 345,422.00

Halaman 15
ANALISA HARGA SATUAN PEKERJAAN
(Permen PUPR No. 28/PRT/M/2016)

PEKERJAAN :
LOKASI :

31 Jenis Pekerjaan : Pemasangan 1 m2 Bekisting untuk Lantai


Satuan Pembayaran : m2
Standar : A.4.1.1.24

Harga Total Harga


No. Uraian Kuantitas Satuan Jumlah
(Rp) (Rp)

A UPAH
Pekerja 0.660 Or/hr 75,000.00 49,500.00
Tukang 0.330 Or/hr 80,000.00 26,400.00
Kepala Tukang 0.033 Or/hr 90,000.00 2,970.00
Mandor 0.033 Or/hr 100,000.00 3,300.00

SUB JUMLAH A 82,170.00

B BAHAN
Kayu/ Papan Bekisting 0.040 m³ 2,200,000.00 88,000.00
Paku Biasa 2" - 5" 0.400 kg 15,000.00 6,000.00
Minyak Bekisting/ Teak Oil 0.200 liter 9,500.00 1,900.00
Kayu/ Papan Klas II 0.015 m³ 3,300,000.00 49,500.00
Plywood 9 mm 0.350 lbr 133,000.00 46,550.00
Dolken Kayu Ø (8-10)cm, panjang 4 m 6.000 btg 15,000.00 90,000.00

SUB JUMLAH B 281,950.00

C PERALATAN
-

SUB JUMLAH C -

D JUMLAH (A+B+C) 364,120.00


E Overhead & Profit 10% x D 36,412.00
F HARGA SATUAN PEKERJAAN 400,532.00

32 Jenis Pekerjaan : Pemasangan 1 m2 Bekisting untuk Dinding


Satuan Pembayaran : m2
Standar : A.4.1.1.25

Harga Total Harga


No. Uraian Kuantitas Satuan Jumlah
(Rp) (Rp)

A TENAGA
Pekerja 0.660 Or/hr 75,000.00 49,500.00
Tukang Kayu 0.330 Or/hr 80,000.00 26,400.00
Kepala Tukang 0.033 Or/hr 90,000.00 2,970.00
Mandor 0.033 Or/hr 100,000.00 3,300.00

SUB JUMLAH A 82,170.00

A BAHAN
Kayu bekisting Kelas III 0.030 m3 2,200,000.00 66,000.00
Paku 5 cm - 10 cm 0.400 kg 15,000.00 6,000.00
Minyak Bekisting 0.200 ltr 9,500.00 1,900.00
Balok Kayu Kelas II 0.020 m3 3,300,000.00 66,000.00
Plywood Tebal 9 mm 0.350 lbr 133,000.00 46,550.00
Dolken Kayu Galam, ø (8-10)cm, 4 m 3.000 btg 15,000.00 45,000.00
Penjaga Jarak Bekisting/ Spacer 4.000 bh -

SUB JUMLAH B 231,450.00

C PERALATAN
-

SUB JUMLAH C -

D JUMLAH (A+B+C) 313,620.00


E Overhead & Profit 10% x D 31,362.00
F HARGA SATUAN PEKERJAAN 344,982.00

33 Jenis Pekerjaan : Pemasangan 1 m2 Bekisting untuk Tangga


Halaman 16
ANALISA HARGA SATUAN PEKERJAAN
(Permen PUPR No. 28/PRT/M/2016)

PEKERJAAN :
LOKASI :

Satuan Pembayaran : m2
Standar : A.4.1.1.26

Harga Total Harga


No. Uraian Kuantitas Satuan Jumlah
(Rp) (Rp)

B TENAGA
Pekerja 0.660 Or/hr 75,000.00 49,500.00
Tukang 0.330 Or/hr 80,000.00 26,400.00
Kepala Tukang 0.033 Or/hr 90,000.00 2,970.00
Mandor 0.033 Or/hr 100,000.00 3,300.00

SUB JUMLAH A 82,170.00

B BAHAN
Kayu/ Papan Bekisting 0.030 m³ 2,200,000.00 66,000.00
Paku Biasa 2" - 5" 0.400 kg 15,000.00 6,000.00
Minyak Bekisting/ Teak Oil 0.150 liter 9,500.00 1,425.00
Kayu/ Papan Klas II 0.015 m³ 3,300,000.00 49,500.00
Plywood 9 mm 0.350 lbr 133,000.00 46,550.00
Dolken Kayu Ø (8-10)cm, panjang 4 m 2.000 btg 15,000.00 30,000.00

SUB JUMLAH B 199,475.00

C PERALATAN
-

SUB JUMLAH C -

D JUMLAH (A+B+C) 281,645.00


E Overhead & Profit 10% x D 28,164.50
F HARGA SATUAN PEKERJAAN 309,809.50

Halaman 17
ANALISA HARGA SATUAN PEKERJAAN
(Permen PUPR No. 28/PRT/M/2016)

PEKERJAAN :
LOKASI :

34 Jenis Pekerjaan : Membuat 1 m3 Balok Beton Bertulang (200 kg Besi + Bekisting)


Satuan Pembayaran : m3
Standar : A.4.1.1.31

Harga Total Harga


No. Uraian Kuantitas Satuan Jumlah
(Rp) (Rp)

A TENAGA
Pekerja 6.350 Or/hr 75,000.00 476,250.00
Tukang Batu 0.275 Or/hr 80,000.00 22,000.00
Tukang Kayu 1.650 Or/hr 80,000.00 132,000.00
Tukang Besi 1.400 Or/hr 80,000.00 112,000.00
Kepala Tukang 0.333 Or/hr 90,000.00 29,970.00
Mandor 0.318 Or/hr 100,000.00 31,800.00

SUB JUMLAH A 804,020.00

B BAHAN
Kayu bekisting Kelas III 0.320 m3 2,200,000.00 704,000.00
Paku 5 cm - 10 cm 3.200 kg 15,000.00 48,000.00
Minyak Bekisting 1.600 ltr 9,500.00 15,200.00
Besi Beton Polos 210.000 kg 12,200.00 2,562,000.00
Kawat Beton 3.000 kg 20,000.00 60,000.00
Semen Portland 336.000 kg 1,400.00 470,400.00
Pasir Beton 0.540 m3 165,000.00 89,100.00
Kerikil 0.810 m3 258,000.00 208,980.00
Balok Kayu Kelas II 0.140 m3 3,300,000.00 462,000.00
Plywood Tebal 9 mm 2.800 lbr 133,000.00 372,400.00
Dolken Kayu Galam, ø (8-10)cm, Panjang 16.000 btg 15,000.00 240,000.00

SUB JUMLAH B 5,232,080.00

C PERALATAN
-

SUB JUMLAH C -

D JUMLAH (A+B+C) 6,036,100.00


E Overhead & Profit 10% x D 603,610.00
F HARGA SATUAN PEKERJAAN 6,639,710.00

Halaman 18
ANALISA HARGA SATUAN PEKERJAAN
(Permen PUPR No. 28/PRT/M/2016)

PEKERJAAN :
LOKASI :

35 Jenis Pekerjaan : Membuat 1 m3 Kolom Beton Bertulang (150 kg Besi + Bekisting)


Satuan Pembayaran : m3
Standar : A.4.1.1.32

Harga Total Harga


No. Uraian Kuantitas Satuan Jumlah
(Rp) (Rp)

A UPAH
Pekerja 5.300 Or/hr 75,000.00 397,500.00
Tukang Batu 0.275 Or/hr 80,000.00 22,000.00
Tukang Kayu 1.300 Or/hr 80,000.00 104,000.00
Tukang Besi 1.050 Or/hr 80,000.00 84,000.00
Kepala Tukang 0.265 Or/hr 90,000.00 23,850.00
Mandor 0.265 Or/hr 100,000.00 26,500.00

SUB JUMLAH A 657,850.00

B BAHAN
Kayu bekisting Kelas III 0.320 m3 2,200,000.00 704,000.00
Paku 5 cm - 10 cm 3.200 kg 15,000.00 48,000.00
Minyak Bekisting 1.600 ltr 9,500.00 15,200.00
Besi Beton Polos 157.500 kg 12,200.00 1,921,500.00
Kawat Beton 2.250 kg 20,000.00 45,000.00
Semen Portland 336.000 kg 1,400.00 470,400.00
Pasir Beton 0.540 m3 165,000.00 89,100.00
Kerikil 0.810 m3 258,000.00 208,980.00
Balok Kayu Kelas II 0.120 m3 3,300,000.00 396,000.00
Plywood Tebal 9 mm 2.800 lbr 133,000.00 372,400.00
Dolken Kayu Galam, ø (8-10)cm, Panjang 32.000 btg 15,000.00 480,000.00

SUB JUMLAH B 4,750,580.00

C PERALATAN
Pekerja -

SUB JUMLAH B -

D JUMLAH (A+B+C) 5,408,430.00


E Overhead & Profit 10% x D 540,843.00
F HARGA SATUAN PEKERJAAN 5,949,273.00

Halaman 19
ANALISA HARGA SATUAN PEKERJAAN
(Permen PUPR No. 28/PRT/M/2016)

PEKERJAAN :
LOKASI :

36 Jenis Pekerjaan : Membuat 1 m' Kolom Praktis Beton Bertulang (11 x 11) cm
Satuan Pembayaran : m1
Standar : A.4.1.1.35

Harga Total Harga


No. Uraian Kuantitas Satuan Jumlah
(Rp) (Rp)

A TENAGA
Pekerja 0.180 Or/hr 75,000.00 13,500.00
Tukang Batu 0.020 Or/hr 80,000.00 1,600.00
Tukang Kayu 0.020 Or/hr 80,000.00 1,600.00
Tukang Besi 0.020 Or/hr 80,000.00 1,600.00
Kepala Tukang 0.006 Or/hr 90,000.00 540.00
Mandor 0.009 Or/hr 100,000.00 900.00

SUB JUMLAH A 19,740.00

B BAHAN
Kayu bekisting Kelas III 0.002 m3 2,200,000.00 4,400.00
Paku 5 cm - 10 cm 0.010 kg 15,000.00 150.00
Minyak Bekisting ltr 9,500.00 -
Besi Beton Polos 3.000 kg 12,200.00 36,600.00
Kawat Beton 0.450 kg 20,000.00 9,000.00
Semen Portland 4.000 kg 1,400.00 5,600.00
Pasir Beton 0.006 m3 165,000.00 990.00
Kerikil 0.009 m3 258,000.00 2,322.00

SUB JUMLAH B 59,062.00

C UPAH
-

SUB JUMLAH C -

D JUMLAH (A+B+C) 78,802.00


E Overhead & Profit 10% x D 7,880.20
F HARGA SATUAN PEKERJAAN 86,682.20

Halaman 20
ANALISA HARGA SATUAN PEKERJAAN
(Permen PUPR No. 28/PRT/M/2016)

PEKERJAAN :
LOKASI :

37 Jenis Pekerjaan : Membuat 1 m' Ring Balok Beton Bertulang (10 x 15) cm
Satuan Pembayaran : m3
Standar : A.4.1.1.36

Harga Total Harga


No. Uraian Kuantitas Satuan Jumlah
(Rp) (Rp)

A TENAGA
Pekerja 0.297 Or/hr 75,000.00 22,275.00
Tukang Batu 0.033 Or/hr 80,000.00 2,640.00
Tukang Kayu 0.033 Or/hr 80,000.00 2,640.00
Tukang Besi 0.033 Or/hr 80,000.00 2,640.00
Kepala Tukang 0.100 Or/hr 90,000.00 9,000.00
Mandor 0.015 Or/hr 100,000.00 1,500.00

SUB JUMLAH A 40,695.00

B BAHAN
Kayu bekisting Kelas III 0.030 m3 2,200,000.00 66,000.00
Paku 5 cm - 10 cm 0.020 kg 15,000.00 300.00
Minyak Bekisting - ltr 9,500.00 -
Besi Beton Polos 3.600 kg 12,200.00 43,920.00
Kawat Beton 0.050 kg 20,000.00 1,000.00
Semen Portland 5.500 kg 1,400.00 7,700.00
Pasir Beton 0.009 m3 165,000.00 1,485.00
Kerikil 0.015 m3 258,000.00 3,870.00

SUB JUMLAH B 124,275.00

C UPAH
-

SUB JUMLAH C -

D JUMLAH (A+B+C) 164,970.00


E Overhead & Profit 10% x D 16,497.00
F HARGA SATUAN PEKERJAAN 181,467.00

38 Jenis Pekerjaan : Pemasangan 1 m1 Railing Tangga


Satuan Pembayaran : m2
Standar : -

Harga Total Harga


No. Uraian Kuantitas Satuan Jumlah
(Rp) (Rp)

A TENAGA
Biaya Pemasangan 1.000 m¹ 230,000.00 230,000.00

SUB JUMLAH A 230,000.00

B BAHAN
Railing Tangga Bahan Stainlessteel 1.0000 m¹ 1,150,000.00 1,150,000.00
termasuk aksesoris

SUB JUMLAH B 1,150,000.00

C PERALATAN
Peralatan (10% x Harga) 1.000 ls 115,000.00 115,000.00

SUB JUMLAH C 115,000.00

D JUMLAH (A+B+C) 1,495,000.00


E Overhead & Profit 10% x D 149,500.00
F HARGA SATUAN PEKERJAAN 1,644,500.00

Halaman 21
ANALISA HARGA SATUAN PEKERJAAN
(Permen PUPR No. 28/PRT/M/2016)

PEKERJAAN :
LOKASI :

39 Jenis Pekerjaan : Pemasangan 1 kg Rangka Kuda-Kuda Baja IWF


Satuan Pembayaran : kg
Standar : A.4.1.1.2

Harga Total Harga


No. Uraian Kuantitas Satuan Jumlah
(Rp) (Rp)

A TENAGA
Pekerja 0.060 Or/hr 75,000.00 4,500.00
Tukang Batu 0.060 Or/hr 80,000.00 4,800.00
Kepala Tukang 0.006 Or/hr 90,000.00 540.00
Mandor 0.003 Or/hr 100,000.00 300.00

SUB JUMLAH A 10,140.00

B BAHAN
Baja Struktural / Profil 1.150 kg 20,800.00 23,920.00

SUB JUMLAH B 23,920.00

C UPAH
-

SUB JUMLAH C -

D JUMLAH (A+B+C) 34,060.00


E Overhead & Profit 10% x D 3,406.00
F HARGA SATUAN PEKERJAAN 37,466.00

40 Jenis Pekerjaan : Pasangan Dinding 1 Bata Campuran 1 : 2


Satuan Pembayaran : m2
Standar : A.4.4.1.1

Harga Total Harga


No. Uraian Kuantitas Satuan Jumlah
(Rp) (Rp)

A TENAGA
Pekerja 0.6000 Org/ Hr 75,000.00 45,000.00
Tukang 0.2000 Org/ Hr 80,000.00 16,000.00
Kepala Tukang 0.0200 Org/ Hr 90,000.00 1,800.00
Mandor 0.0300 Org/ Hr 100,000.00 3,000.00

SUB JUMLAH A 65,800.00

B BAHAN
Batu Bata Biasa (5 x 11 x 22) 140.0000 bh 500.00 70,000.00
Semen Portland / kg 43.5000 kg 1,400.00 60,900.00
Pasir Pasang 0.0800 m³ 140,000.00 11,200.00

SUB JUMLAH B 142,100.00

C PERALATAN
-

SUB JUMLAH C -

D JUMLAH (A+B+C) 207,900.00


E Overhead & Profit 10% x D 20,790.00
F HARGA SATUAN PEKERJAAN 228,690.00

Halaman 22
ANALISA HARGA SATUAN PEKERJAAN
(Permen PUPR No. 28/PRT/M/2016)

PEKERJAAN :
LOKASI :

41 Jenis Pekerjaan : Pasangan Dinding 1/2 Bata Campuran 1 : 2


Satuan Pembayaran : m2
Standar : A.4.4.1.7

Harga Total Harga


No. Uraian Kuantitas Satuan Jumlah
(Rp) (Rp)

A TENAGA
Pekerja 0.3000 Org/ Hr 75,000.00 22,500.00
Tukang 0.1000 Org/ Hr 80,000.00 8,000.00
Kepala Tukang 0.0100 Org/ Hr 90,000.00 900.00
Mandor 0.0150 Org/ Hr 100,000.00 1,500.00

SUB JUMLAH A 32,900.00

B BAHAN
Batu Bata Biasa (5 x 11 x 22) 70.0000 bh 500.00 35,000.00
Semen Portland / kg 18.9500 kg 1,400.00 26,530.00
Pasir Pasang 0.0380 m³ 140,000.00 5,320.00

SUB JUMLAH B 66,850.00

C PERALATAN
-

SUB JUMLAH C -

D JUMLAH (A+B+C) 99,750.00


E Overhead & Profit 10% x D 9,975.00
F HARGA SATUAN PEKERJAAN 109,725.00

42 Jenis Pekerjaan : Pasangan Dinding 1/2 Bata Campuran 1 : 4


Satuan Pembayaran : m2
Standar : A.4.4.1.9

Harga Total Harga


No. Uraian Kuantitas Satuan Jumlah
(Rp) (Rp)

A TENAGA
Pekerja 0.3000 Org/ Hr 75,000.00 22,500.00
Tukang 0.1000 Org/ Hr 80,000.00 8,000.00
Kepala Tukang 0.0100 Org/ Hr 90,000.00 900.00
Mandor 0.0150 Org/ Hr 100,000.00 1,500.00

SUB JUMLAH A 32,900.00

A BAHAN
Batu Bata Biasa (5 x 11 x 22) 70.0000 bh 500.00 35,000.00
Semen Portland / kg 11.5000 kg 1,400.00 16,100.00
Pasir Pasang 0.0430 m³ 140,000.00 6,020.00

SUB JUMLAH B 57,120.00

C PERALATAN
-

SUB JUMLAH C -

D JUMLAH (A+B+C) 90,020.00


E Overhead & Profit 10% x D 9,002.00
F HARGA SATUAN PEKERJAAN 99,022.00

Halaman 23
ANALISA HARGA SATUAN PEKERJAAN
(Permen PUPR No. 28/PRT/M/2016)

PEKERJAAN :
LOKASI :

43 Jenis Pekerjaan : Plesteran Dinding Campuran 1 : 2 Tebal 15 mm


Satuan Pembayaran : m2
Standar : A.4.4.2.2

Harga Total Harga


No. Uraian Kuantitas Satuan Jumlah
(Rp) (Rp)

B TENAGA
Pekerja 0.3000 Org/ Hr 75,000.00 22,500.00
Tukang 0.1500 Org/ Hr 80,000.00 12,000.00
Kepala Tukang 0.0150 Org/ Hr 90,000.00 1,350.00
Mandor 0.0150 Org/ Hr 100,000.00 1,500.00

SUB JUMLAH A 37,350.00

B BAHAN
Semen Portland / kg 10.2240 kg 1,400.00 14,313.60
Pasir Pasang 0.0200 m³ 140,000.00 2,800.00

SUB JUMLAH B 17,113.60

C PERALATAN
-

SUB JUMLAH C -

D JUMLAH (A+B+C) 54,463.60


E Overhead & Profit 10% x D 5,446.36
F HARGA SATUAN PEKERJAAN 59,909.96

44 Jenis Pekerjaan : Plesteran Dinding Campuran 1 : 4 Tebal 15 mm


Satuan Pembayaran : m2
Standar : A.4.4.2.2

Harga Total Harga


No. Uraian Kuantitas Satuan Jumlah
(Rp) (Rp)

A TENAGA
Pekerja 0.0300 Org/ Hr 75,000.00 2,250.00
Tukang 0.1500 Org/ Hr 80,000.00 12,000.00
Kepala Tukang 0.0150 Org/ Hr 90,000.00 1,350.00
Mandor 0.0150 Org/ Hr 100,000.00 1,500.00

SUB JUMLAH A 17,100.00

B BAHAN
Semen Portland / kg 6.2400 kg 1,400.00 8,736.00
Pasir Pasang 0.0240 m³ 140,000.00 3,360.00

SUB JUMLAH B 12,096.00

C PERALATAN
-

SUB JUMLAH C -

D JUMLAH (A+B+C) 29,196.00


E Overhead & Profit 10% x D 2,919.60
F HARGA SATUAN PEKERJAAN 32,115.60

Halaman 24
ANALISA HARGA SATUAN PEKERJAAN
(Permen PUPR No. 28/PRT/M/2016)

PEKERJAAN :
LOKASI :

45 Jenis Pekerjaan : Acian


Satuan Pembayaran : m2
Standar : A.4.4.2.2

Harga Total Harga


No. Uraian Kuantitas Satuan Jumlah
(Rp) (Rp)

A TENAGA
Pekerja 0.2000 Org/ Hr 75,000.00 15,000.00
Tukang 0.1000 Org/ Hr 80,000.00 8,000.00
Kepala Tukang 0.0100 Org/ Hr 90,000.00 900.00
Mandor 0.0100 Org/ Hr 100,000.00 1,000.00

SUB JUMLAH A 24,900.00

B BAHAN
Semen Portland / kg 3.2500 kg 1,400.00 4,550.00

SUB JUMLAH B 4,550.00

C PERALATAN
-

SUB JUMLAH C -

C JUMLAH (A+B+C) 29,450.00


D Overhead & Profit 10% x C 2,945.00
E HARGA SATUAN PEKERJAAN 32,395.00

46 Jenis Pekerjaan : Aluminium Composit Panel


Satuan Pembayaran : m2
Standar : -

Harga Total Harga


No. Uraian Kuantitas Satuan Jumlah
(Rp) (Rp)

A TENAGA
Biaya 1.0000 m2 55,000.00 55,000.00

SUB JUMLAH A 55,000.00

B BAHAN
Aluminium Composit Panel 1.0500 m2 550,000.00 577,500.00

SUB JUMLAH B 577,500.00

C PERALATAN
Peralatan 1.0000 ls 55,000.00 55,000.00

SUB JUMLAH C 55,000.00

D JUMLAH (A+B+C) 632,500.00


E Overhead & Profit 10% x D 63,250.00
F HARGA SATUAN PEKERJAAN 695,750.00

Halaman 25
ANALISA HARGA SATUAN PEKERJAAN
(Permen PUPR No. 28/PRT/M/2016)

PEKERJAAN :
LOKASI :

47 Jenis Pekerjaan : Pemasangan 1 m2 Lantai Granit Ukuran 60 x 60


Satuan Pembayaran : m2
Standar : -

Harga Total Harga


No. Uraian Kuantitas Satuan Jumlah
(Rp) (Rp)

A TENAGA
Pekerja 0.2500 Org/ Hr 75,000.00 18,750.00
Tukang 0.1250 Org/ Hr 80,000.00 10,000.00
Kepala Tukang 0.0130 Org/ Hr 90,000.00 1,170.00
Mandor 0.0130 Org/ Hr 100,000.00 1,300.00

SUB JUMLAH A 31,220.00

B BAHAN
Granit 60 x 60 2.778 bh 80,000.00 222,222.22
Semen Portland / kg 9.800 kg 1,400.00 13,720.00
Semen Warna 1.300 Kg 2,600.00 3,380.00
Pasir Pasang 0.045 m³ 140,000.00 6,300.00

SUB JUMLAH B 245,622.22

C PERALATAN
-

SUB JUMLAH C -

D JUMLAH (A+B+C) 276,842.22


E Overhead & Profit 10% x D 27,684.22
F HARGA SATUAN PEKERJAAN 304,526.44

48 Jenis Pekerjaan : Pemasangan 1 m2 Lantai Granit Ukuran 30 x 30


Satuan Pembayaran : m2
Standar : A.4.4.3.10

Harga Total Harga


No. Uraian Kuantitas Satuan Jumlah
(Rp) (Rp)

A TENAGA
Pekerja 0.2600 Org/ Hr 75,000.00 19,500.00
Tukang 0.1300 Org/ Hr 80,000.00 10,400.00
Kepala Tukang 0.0130 Org/ Hr 90,000.00 1,170.00
Mandor 0.0130 Org/ Hr 100,000.00 1,300.00

SUB JUMLAH A 32,370.00

B BAHAN
Granit 30 x 30 11.870 bh 25,000.00 296,750.00
Semen Portland / kg 10.000 kg 1,400.00 14,000.00
Semen Warna 1.500 Kg 2,600.00 3,900.00
Pasir Pasang 0.045 m³ 140,000.00 6,300.00

SUB JUMLAH B 320,950.00

C PERALATAN
-

SUB JUMLAH C -

D JUMLAH (A+B+C) 353,320.00


E Overhead & Profit 10% x D 35,332.00
F HARGA SATUAN PEKERJAAN 388,652.00

Halaman 26
ANALISA HARGA SATUAN PEKERJAAN
(Permen PUPR No. 28/PRT/M/2016)

PEKERJAAN :
LOKASI :

49 Jenis Pekerjaan : Pemasangan 1 m2 Dinding Granit 30 x 60


Satuan Pembayaran : m2
Standar : -

Harga Total Harga


No. Uraian Kuantitas Satuan Jumlah
(Rp) (Rp)

A TENAGA
Pekerja 0.2600 Org/ Hr 75,000.00 19,500.00
Tukang 0.1300 Org/ Hr 80,000.00 10,400.00
Kepala Tukang 0.0130 Org/ Hr 90,000.00 1,170.00
Mandor 0.0130 Org/ Hr 100,000.00 1,300.00

SUB JUMLAH A 32,370.00

B BAHAN
Granit 30 x 60 5.556 bh 31,000.00 172,222.22
Semen Portland / kg 10.000 kg 1,400.00 14,000.00
Pasir Pasang 0.045 m³ 140,000.00 6,300.00
Semen Warna 1.500 Kg 2,600.00 3,900.00

SUB JUMLAH B 196,422.22

C PERALATAN
-

SUB JUMLAH C -

D JUMLAH (A+B+C) 228,792.22


E Overhead & Profit 10% x D 22,879.22
F HARGA SATUAN PEKERJAAN 251,671.44

50 Jenis Pekerjaan : Pemasangan 1 m2 Lantai Keramik 40 x 40


Satuan Pembayaran : m2
Standar : -

Harga Total Harga


No. Uraian Kuantitas Satuan Jumlah
(Rp) (Rp)

A TENAGA
Pekerja 0.7000 Org/ Hr 75,000.00 52,500.00
Tukang 0.3500 Org/ Hr 80,000.00 28,000.00
Kepala Tukang 0.0350 Org/ Hr 90,000.00 3,150.00
Mandor 0.0350 Org/ Hr 100,000.00 3,500.00

SUB JUMLAH A 87,150.00

B BAHAN
Keramik 40 X 40 1.050 doos 75,000.00 78,750.00
Semen Portland / kg 9.800 kg 1,400.00 13,720.00
Pasir Pasang 0.045 m³ 140,000.00 6,300.00
Semen Warna 0.500 Kg 2,600.00 1,300.00

SUB JUMLAH B 100,070.00

C PERALATAN
-

SUB JUMLAH C -

D JUMLAH (A+B+C) 187,220.00


E Overhead & Profit 10% x D 18,722.00
F HARGA SATUAN PEKERJAAN 205,942.00

Halaman 27
ANALISA HARGA SATUAN PEKERJAAN
(Permen PUPR No. 28/PRT/M/2016)

PEKERJAAN :
LOKASI :

51 Jenis Pekerjaan : Pemasangan 1 m2 Lantai Keramik 30 x 30


Satuan Pembayaran : m2
Standar : A.4.4.3.35

Harga Total Harga


No. Uraian Kuantitas Satuan Jumlah
(Rp) (Rp)

A TENAGA
Pekerja 0.7000 Org/ Hr 75,000.00 52,500.00
Tukang 0.3500 Org/ Hr 80,000.00 28,000.00
Kepala Tukang 0.0350 Org/ Hr 90,000.00 3,150.00
Mandor 0.0350 Org/ Hr 100,000.00 3,500.00

SUB JUMLAH A 87,150.00

B BAHAN
Keramik 30 x 30 1.050 doos 75,000.00 78,750.00
Semen Portland / kg 10.000 kg 1,400.00 14,000.00
Pasir Pasang 0.045 m³ 140,000.00 6,300.00
Semen Warna 0.500 Kg 2,600.00 1,300.00

SUB JUMLAH B 100,350.00

C PERALATAN
-

SUB JUMLAH C -

D JUMLAH (A+B+C) 187,500.00


E Overhead & Profit 10% x D 18,750.00
F HARGA SATUAN PEKERJAAN 206,250.00

52 Jenis Pekerjaan : Keramik 1 m2 Lantai Keramik 20 x 20


Satuan Pembayaran : m2
Standar : A.4.4.3.36

Harga Total Harga


No. Uraian Kuantitas Satuan Jumlah
(Rp) (Rp)

A TENAGA
Pekerja 0.7000 Org/ Hr 75,000.00 52,500.00
Tukang 0.3500 Org/ Hr 80,000.00 28,000.00
Kepala Tukang 0.0350 Org/ Hr 90,000.00 3,150.00
Mandor 0.0350 Org/ Hr 100,000.00 3,500.00

SUB JUMLAH A 87,150.00

B BAHAN
Keramik 20 x 20 1.050 doos 71,000.00 74,550.00
Semen Portland / kg 10.400 kg 1,400.00 14,560.00
Pasir Pasang 0.045 m³ 140,000.00 6,300.00
Semen Warna 0.500 Kg 2,600.00 1,300.00

SUB JUMLAH B 96,710.00

C PERALATAN
-

SUB JUMLAH C -

D JUMLAH (A+B+C) 183,860.00


E Overhead & Profit 10% x D 18,386.00
F HARGA SATUAN PEKERJAAN 202,246.00

Halaman 28
ANALISA HARGA SATUAN PEKERJAAN
(Permen PUPR No. 28/PRT/M/2016)

PEKERJAAN :
LOKASI :

53 Jenis Pekerjaan : Pemasangan 1 m2 Dinding Keramik 30 x 60


Satuan Pembayaran : m2
Standar : -

Harga Total Harga


No. Uraian Kuantitas Satuan Jumlah
(Rp) (Rp)

A TENAGA
Pekerja 0.9000 Org/ Hr 75,000.00 67,500.00
Tukang 0.4500 Org/ Hr 80,000.00 36,000.00
Kepala Tukang 0.0450 Org/ Hr 90,000.00 4,050.00
Mandor 0.0450 Org/ Hr 100,000.00 4,500.00

SUB JUMLAH A 112,050.00

B BAHAN
Keramik 30 x 60 1.050 doos 76,000.00 79,800.00
Semen Portland / kg 9.300 kg 1,400.00 13,020.00
Pasir Pasang 0.018 m³ 140,000.00 2,520.00
Semen Warna 1.940 Kg 2,600.00 5,044.00

SUB JUMLAH B 100,384.00

C UPAH
-

SUB JUMLAH C -

D JUMLAH (A+B+C) 212,434.00


E Overhead & Profit 10% x D 21,243.40
F HARGA SATUAN PEKERJAAN 233,677.40

54 Jenis Pekerjaan : Pemasangan 1 m2 Dinding Keramik 20 x 25


Satuan Pembayaran : m2
Standar : -

Harga Total Harga


No. Uraian Kuantitas Satuan Jumlah
(Rp) (Rp)

A TENAGA
Pekerja 0.9000 Org/ Hr 75,000.00 67,500.00
Tukang 0.4500 Org/ Hr 80,000.00 36,000.00
Kepala Tukang 0.0450 Org/ Hr 90,000.00 4,050.00
Mandor 0.0450 Org/ Hr 100,000.00 4,500.00

SUB JUMLAH A 112,050.00

B BAHAN
Keramik 20 x 25 1.050 doos 74,800.00 78,540.00
Semen Portland / kg 9.300 kg 1,400.00 13,020.00
Pasir Pasang 0.018 m³ 140,000.00 2,520.00
Semen Warna 1.940 Kg 2,600.00 5,044.00

SUB JUMLAH B 99,124.00

C UPAH
-

SUB JUMLAH C -

D JUMLAH (A+B+C) 211,174.00


E Overhead & Profit 10% x D 21,117.40
F HARGA SATUAN PEKERJAAN 232,291.40

Halaman 29
ANALISA HARGA SATUAN PEKERJAAN
(Permen PUPR No. 28/PRT/M/2016)

PEKERJAAN :
LOKASI :

55 Jenis Pekerjaan : Pemasangan 1 m2 Langit - Langit Gypsum Board Ukuran (120 x 240 x 9) mm, tebal 9 mm
Satuan Pembayaran : m2
Standar : -

Harga Total Harga


No. Uraian Kuantitas Satuan Jumlah
(Rp) (Rp)

A TEBAGA
Pekerja 0.1500 Org/ Hr 75,000.00 11,250.00
Tukang 0.4500 Org/ Hr 80,000.00 36,000.00
Kepala Tukang 0.0450 Org/ Hr 90,000.00 4,050.00
Mandor 0.0080 Org/ Hr 100,000.00 800.00

SUB JUMLAH A 52,100.00


B UPAH
Gypsum Board 6 mm 0.8600 lbr 76,375.00 65,682.50
Paku Sekrup 0.1500 kg 28,000.00 4,200.00
Alat Bantu 1.0000 ls 6,568.25 6,568.25

SUB JUMLAH B 76,450.75

C PERALATAN
-

SUB JUMLAH C -

D JUMLAH (A+B+C) 128,550.75


E Overhead & Profit 10% x D 12,855.08
F HARGA SATUAN PEKERJAAN 141,405.83

56 Jenis Pekerjaan : Pemasangan 1 m2 Langit - Langit PVC


Satuan Pembayaran : m2
Standar : -

Harga Total Harga


No. Uraian Kuantitas Satuan Jumlah
(Rp) (Rp)

A TEBAGA
Pekerja 0.1500 Org/ Hr 75,000.00 11,250.00
Tukang 0.4500 Org/ Hr 80,000.00 36,000.00
Kepala Tukang 0.0450 Org/ Hr 90,000.00 4,050.00
Mandor 0.0080 Org/ Hr 100,000.00 800.00

SUB JUMLAH A 52,100.00


B UPAH
Gypsum PVC 1.0000 m² 85,000.00 85,000.00
Alat Bantu 1.0000 ls 8,500.00 8,500.00

SUB JUMLAH B 93,500.00

C PERALATAN
-

SUB JUMLAH C -

D JUMLAH (A+B+C) 145,600.00


E Overhead & Profit 10% x D 14,560.00
F HARGA SATUAN PEKERJAAN 160,160.00

Halaman 30
ANALISA HARGA SATUAN PEKERJAAN
(Permen PUPR No. 28/PRT/M/2016)

PEKERJAAN :
LOKASI :

57 Jenis Pekerjaan : Pemasangan 1 m1 List Plafond Gypsum


Satuan Pembayaran : m1
Standar : -

Harga Total Harga


No. Uraian Kuantitas Satuan Jumlah
(Rp) (Rp)

A TENAGA
Pekerja 0.0500 Org/ Hr 75,000.00 3,750.00
Tukang 0.0500 Org/ Hr 80,000.00 4,000.00
Kepala Tukang 0.0030 Org/ Hr 90,000.00 270.00
Mandor 0.0030 Org/ Hr 100,000.00 300.00

SUB JUMLAH A 8,320.00

B BAHAN
List Plafond Gypsum 1.0500 m¹ 28,750.00 30,187.50

SUB JUMLAH B 30,187.50

C PERALATAN
-

SUB JUMLAH C -

D JUMLAH (A+B+C) 38,507.50


E Overhead & Profit 10% x D 3,850.75
F HARGA SATUAN PEKERJAAN 42,358.25

58 Jenis Pekerjaan : Pemasangan 1 m1 List Langit - Langit PVC


Satuan Pembayaran : m1
Standar : -

Harga Total Harga


No. Uraian Kuantitas Satuan Jumlah
(Rp) (Rp)

A TENAGA
Pekerja 0.0500 Org/ Hr 75,000.00 3,750.00
Tukang 0.0500 Org/ Hr 80,000.00 4,000.00
Kepala Tukang 0.0030 Org/ Hr 90,000.00 270.00
Mandor 0.0030 Org/ Hr 100,000.00 300.00

SUB JUMLAH A 8,320.00

B BAHAN
List Plafond PVC 1.0500 m¹ 25,000.00 26,250.00

SUB JUMLAH B 26,250.00

C PERALATAN
-

SUB JUMLAH C -

D JUMLAH (A+B+C) 34,570.00


E Overhead & Profit 10% x D 3,457.00
F HARGA SATUAN PEKERJAAN 38,027.00

Halaman 31
ANALISA HARGA SATUAN PEKERJAAN
(Permen PUPR No. 28/PRT/M/2016)

PEKERJAAN :
LOKASI :

59 Jenis Pekerjaan : Pemasangan 1 m1 List Langit - Langit Kayu Profil


Satuan Pembayaran : m1
Standar : A.4.5.1.9

Harga Total Harga


No. Uraian Kuantitas Satuan Jumlah
(Rp) (Rp)

A TENAGA
Pekerja 0.0500 Org/ Hr 75,000.00 3,750.00
Tukang 0.0500 Org/ Hr 80,000.00 4,000.00
Kepala Tukang 0.0030 Org/ Hr 90,000.00 270.00
Mandor 0.0030 Org/ Hr 100,000.00 300.00

SUB JUMLAH A 8,320.00

B BAHAN
List Profil 1.0500 m¹ 15,000.00 15,750.00

SUB JUMLAH B 15,750.00

C PERALATAN
-

SUB JUMLAH C -

D JUMLAH (A+B+C) 24,070.00


E Overhead & Profit 10% x D 2,407.00
F HARGA SATUAN PEKERJAAN 26,477.00

60 Jenis Pekerjaan : Pengecatan 1 m2 Tembok Baru (1 Lapis Plamuur, 1 Lapis Cat Dasar, 2 Lapis Cat Penutup)
Satuan Pembayaran : m2
Standar : A.4.7.1.10

Harga Total Harga


No. Uraian Kuantitas Satuan Jumlah
(Rp) (Rp)

A TENAGA
Pekerja 0.0200 Org/ Hr 75,000.00 1,500.00
Tukang 0.0630 Org/ Hr 80,000.00 5,040.00
Kepala Tukang 0.0063 Org/ Hr 90,000.00 567.00
Mandor 0.0030 Org/ Hr 100,000.00 300.00

SUB JUMLAH A 7,407.00

B BAHAN
Plamir 0.1000 kg 40,000.00 4,000.00
Cat Dasar Tembok 0.1000 kg 15,000.00 1,500.00
Cat Air 0.2600 kg 65,000.00 16,900.00

SUB JUMLAH B 22,400.00

C PERALATAN
-

SUB JUMLAH C -

D JUMLAH (A+B+C) 29,807.00


E Overhead & Profit 10% x D 2,980.70
F HARGA SATUAN PEKERJAAN 32,787.70

Halaman 32
ANALISA HARGA SATUAN PEKERJAAN
(Permen PUPR No. 28/PRT/M/2016)

PEKERJAAN :
LOKASI :

61 Jenis Pekerjaan : 1 m2 Pengecatan Bidang Kayu Baru (1 Lapis Plamuur, 1 Lapis Cat Dasar, 2 Lapis Cat Penutup)
Satuan Pembayaran : m2
Standar : A.4.7.1.4

Harga Total Harga


No. Uraian Kuantitas Satuan Jumlah
(Rp) (Rp)

A TENAGA
Pekerja 0.0700 Org/ Hr 75,000.00 5,250.00
Tukang 0.0090 Org/ Hr 80,000.00 720.00
Kepala Tukang 0.0060 Org/ Hr 90,000.00 540.00
Mandor 0.0030 Org/ Hr 100,000.00 300.00

SUB JUMLAH A 6,810.00

B BAHAN
Cat Menie 0.2000 kg 74,000.00 14,800.00
Plamir 0.1500 kg 40,000.00 6,000.00
Cat Dasar Kayu 0.1700 kg 36,225.00 6,158.25
Cat Minyak 0.2600 kg 85,000.00 22,100.00
Kuas 0.0100 bh 11,500.00 115.00
Pengencer 0.0300 kg 28,000.00 840.00
Amplas 0.2000 lbr 5,000.00 1,000.00

SUB JUMLAH B 51,013.25

C PERALATAN
-

SUB JUMLAH C -

D JUMLAH (A+B+C) 57,823.25


E Overhead & Profit 10% x D 5,782.33
F HARGA SATUAN PEKERJAAN 63,605.58

62 Jenis Pekerjaan : Pemasangan 1 buah Closet Jongkok


Satuan Pembayaran : Bh
Standar : A.5.1.1.2

Harga Total Harga


No. Uraian Kuantitas Satuan Jumlah
(Rp) (Rp)

A TENAGA
Pekerja 1.000 Org/ Hr 75,000.00 75,000.00
Tukang 1.500 Org/ Hr 80,000.00 120,000.00
Kepala Tukang 0.150 Org/ Hr 90,000.00 13,500.00
Mandor 0.160 Org/ Hr 100,000.00 16,000.00

SUB JUMLAH A 224,500.00


B BAHAN
Kloset Jongkok 1.000 bh 415,000.00 415,000.00
Semen Portland / kg 6.000 kg 1,400.00 8,400.00
Pasir Pasang 0.010 m³ 140,000.00 1,400.00

SUB JUMLAH B 424,800.00

C PERALATAN
-

SUB JUMLAH C -

D JUMLAH (A+B+C) 649,300.00


E Overhead & Profit 10% x D 64,930.00
F HARGA SATUAN PEKERJAAN 714,230.00

Halaman 33
ANALISA HARGA SATUAN PEKERJAAN
(Permen PUPR No. 28/PRT/M/2016)

PEKERJAAN :
LOKASI :

63 Jenis Pekerjaan : Pemasangan 1 buah Closet Duduk


Satuan Pembayaran : Bh
Standar : A.5.1.1.1

Harga Total Harga


No. Uraian Kuantitas Satuan Jumlah
(Rp) (Rp)

A TENAGA
Pekerja 3.300 Org/ Hr 75,000.00 247,500.00
Tukang 1.100 Org/ Hr 80,000.00 88,000.00
Kepala Tukang 0.010 Org/ Hr 90,000.00 900.00
Mandor 0.160 Org/ Hr 100,000.00 16,000.00

SUB JUMLAH A -
B BAHAN
Kloset Duduk 1.000 bh 1,735,000.00 1,735,000.00
Perlengkapan 6% x Kloset Duduk 1.000 ls 104,100.00 104,100.00

SUB JUMLAH B 1,839,100.00

C PERALATAN
-

SUB JUMLAH C -

D JUMLAH (A+B+C) 1,839,100.00


E Overhead & Profit 10% x D 183,910.00
F HARGA SATUAN PEKERJAAN 2,023,010.00

64 Jenis Pekerjaan : Pemasangan 1 buah Urinoir


Satuan Pembayaran : Bh
Standar : A.5.1.1.4

Harga Total Harga


No. Uraian Kuantitas Satuan Jumlah
(Rp) (Rp)

A TENAGA
Pekerja 1.000 Org/ Hr 75,000.00 75,000.00
Tukang 1.000 Org/ Hr 80,000.00 80,000.00
Kepala Tukang 0.100 Org/ Hr 90,000.00 9,000.00
Mandor 0.050 Org/ Hr 100,000.00 5,000.00

SUB JUMLAH A 169,000.00


B BAHAN
Urinoir 1.000 bh 1,587,000.00 1,587,000.00
Semen Portland / kg 6.000 kg 1,400.00 8,400.00
Pasir Pasang 0.010 m³ 140,000.00 1,400.00
Perlengkapan 30% x Urinoir 1.000 Ls 476,100.00 476,100.00

SUB JUMLAH B 2,072,900.00

C PERALATAN
-

SUB JUMLAH C -

D JUMLAH (A+B+C) 2,241,900.00


E Overhead & Profit 10% x D 224,190.00
F HARGA SATUAN PEKERJAAN 2,466,090.00

Halaman 34
ANALISA HARGA SATUAN PEKERJAAN
(Permen PUPR No. 28/PRT/M/2016)

PEKERJAAN :
LOKASI :

65 Jenis Pekerjaan : Pemasangan 1 buah Washtafel


Satuan Pembayaran : Bh
Standar : A.5.1.1.5

Harga Total Harga


No. Uraian Kuantitas Satuan Jumlah
(Rp) (Rp)

A TENAGA
Pekerja 1.200 Org/ Hr 75,000.00 90,000.00
Tukang 1.450 Org/ Hr 80,000.00 116,000.00
Kepala Tukang 0.150 Org/ Hr 90,000.00 13,500.00
Mandor 0.060 Org/ Hr 100,000.00 6,000.00

SUB JUMLAH A 225,500.00


B BAHAN
Washtafel 1.200 bh 1,425,000.00 1,710,000.00
Semen Portland / kg 6.000 kg 1,400.00 8,400.00
Pasir Pasang 0.010 m³ 140,000.00 1,400.00
Perlengkapan 12% x Washtafel 1.000 Ls 171,000.00 171,000.00

SUB JUMLAH B 1,890,800.00

C PERALATAN
-

SUB JUMLAH C -

D JUMLAH (A+B+C) 2,116,300.00


E Overhead & Profit 10% x D 211,630.00
F HARGA SATUAN PEKERJAAN 2,327,930.00

66 Jenis Pekerjaan : Meja Washtafel


Satuan Pembayaran : Bh
Standar : -

Harga Total Harga


No. Uraian Kuantitas Satuan Jumlah
(Rp) (Rp)

A TENAGA
Biaya Pemasangan 1.0000 bh 150,000.00 150,000.00

SUB JUMLAH A 150,000.00


B BAHAN
Meja Washtafel 1.0000 bh 750,000.00 750,000.00

SUB JUMLAH B 750,000.00

C PERALATAN
-

SUB JUMLAH C -

D JUMLAH (A+B+C) 900,000.00


E Overhead & Profit 10% x D 90,000.00
F HARGA SATUAN PEKERJAAN 990,000.00

Halaman 35
ANALISA HARGA SATUAN PEKERJAAN
(Permen PUPR No. 28/PRT/M/2016)

PEKERJAAN :
LOKASI :

67 Jenis Pekerjaan : Pemasangan 1 buah Kran air dia. 1/2"atau 3/4"


Satuan Pembayaran : Bh
Standar : A.5.1.1.19

Harga Total Harga


No. Uraian Kuantitas Satuan Jumlah
(Rp) (Rp)

A TENAGA
Pekerja 0.010 Org/ Hr 75,000.00 750.00
Tukang 0.400 Org/ Hr 80,000.00 32,000.00
Kepala Tukang 0.040 Org/ Hr 90,000.00 3,600.00
Mandor 0.005 Org/ Hr 100,000.00 500.00

SUB JUMLAH A 36,850.00


B BAHAN
Kran Air 1.000 bh 94,100.00 94,100.00
Sealtape 0.025 bh 7,500.00 187.50

SUB JUMLAH B 94,287.50

C UPAH
-

SUB JUMLAH C -

D JUMLAH (A+B+C) 131,137.50


E Overhead & Profit 10% x D 13,113.75
F HARGA SATUAN PEKERJAAN 144,251.25

68 Jenis Pekerjaan : Pemasangan 1 buah Kran air Washtafel


Satuan Pembayaran : Bh
Standar : -

Harga Total Harga


No. Uraian Kuantitas Satuan Jumlah
(Rp) (Rp)

A TENAGA
Pekerja 0.010 Org/ Hr 75,000.00 750.00
Tukang 0.400 Org/ Hr 80,000.00 32,000.00
Kepala Tukang 0.040 Org/ Hr 90,000.00 3,600.00
Mandor 0.005 Org/ Hr 100,000.00 500.00

SUB JUMLAH A 36,850.00


B BAHAN
Kran Air Washtafel 1.000 bh 185,000.00 185,000.00
Sealtape 0.025 bh 7,500.00 187.50

SUB JUMLAH B 185,187.50

C UPAH
-

SUB JUMLAH C -

D JUMLAH (A+B+C) 222,037.50


E Overhead & Profit 10% x D 22,203.75
F HARGA SATUAN PEKERJAAN 244,241.25

Halaman 36
ANALISA HARGA SATUAN PEKERJAAN
(Permen PUPR No. 28/PRT/M/2016)

PEKERJAAN :
LOKASI :

69 Jenis Pekerjaan : Pemasangan 1 buah Jet Shower


Satuan Pembayaran : Bh
Standar : -

Harga Total Harga


No. Uraian Kuantitas Satuan Jumlah
(Rp) (Rp)

A TENAGA
Pekerja 0.010 Org/ Hr 75,000.00 750.00
Tukang 0.400 Org/ Hr 80,000.00 32,000.00
Kepala Tukang 0.040 Org/ Hr 90,000.00 3,600.00
Mandor 0.005 Org/ Hr 100,000.00 500.00

SUB JUMLAH A 36,850.00


B BAHAN
Jet Shower 1.000 bh 165,000.00 165,000.00
Sealtape 0.025 bh 7,500.00 187.50

SUB JUMLAH B 165,187.50

C UPAH
-

SUB JUMLAH C -

D JUMLAH (A+B+C) 202,037.50


E Overhead & Profit 10% x D 20,203.75
F HARGA SATUAN PEKERJAAN 222,241.25

70 Jenis Pekerjaan : Pemasangan 1 buah Shower


Satuan Pembayaran : Bh
Standar : -

Harga Total Harga


No. Uraian Kuantitas Satuan Jumlah
(Rp) (Rp)

A TENAGA
Pekerja 0.010 Org/ Hr 75,000.00 750.00
Tukang 0.400 Org/ Hr 80,000.00 32,000.00
Kepala Tukang 0.040 Org/ Hr 90,000.00 3,600.00
Mandor 0.005 Org/ Hr 100,000.00 500.00

SUB JUMLAH A 36,850.00


B BAHAN
Shower 1.000 bh 250,000.00 250,000.00
Sealtape 0.025 bh 7,500.00 187.50

SUB JUMLAH B 250,187.50

C UPAH
-

SUB JUMLAH C -

D JUMLAH (A+B+C) 287,037.50


E Overhead & Profit 10% x D 28,703.75
F HARGA SATUAN PEKERJAAN 315,741.25

Halaman 37
ANALISA HARGA SATUAN PEKERJAAN
(Permen PUPR No. 28/PRT/M/2016)

PEKERJAAN :
LOKASI :

68 Jenis Pekerjaan : Pemasangan 1 buah Floor Drain


Satuan Pembayaran : Bh
Standar : A.5.1.1.14

Harga Total Harga


No. Uraian Kuantitas Satuan Jumlah
(Rp) (Rp)

A UPAH
Pekerja 0.010 Org/ Hr 75,000.00 750.00
Tukang 0.100 Org/ Hr 80,000.00 8,000.00
Kepala Tukang 0.010 Org/ Hr 90,000.00 900.00
Mandor 0.005 Org/ Hr 100,000.00 500.00

SUB JUMLAH A 10,150.00


B BAHAN
Floor Drain 1.000 bh 115,000.00 115,000.00

SUB JUMLAH B 115,000.00

C UPAH
-

SUB JUMLAH C -

D JUMLAH (A+B+C) 125,150.00


E Overhead & Profit 10% x D 12,515.00
F HARGA SATUAN PEKERJAAN 137,665.00

69 Jenis Pekerjaan : Pembatas Urinoir


Satuan Pembayaran : Bh
Standar : -

Harga Total Harga


No. Uraian Kuantitas Satuan Jumlah
(Rp) (Rp)

A TENAGA
Biaya Pemasangan 1.000 bh 65,000.00 65,000.00

SUB JUMLAH A 65,000.00

B BAHAN
Pembatas Urinoir dan Aksesoris 1.000 bh 325,000.00 325,000.00

SUB JUMLAH B 325,000.00

C UPAH
-

SUB JUMLAH C -

D JUMLAH (A+B+C) 390,000.00


E Overhead & Profit 10% x D 39,000.00
F HARGA SATUAN PEKERJAAN 429,000.00

Halaman 38
ANALISA HARGA SATUAN PEKERJAAN
(Permen PUPR No. 28/PRT/M/2016)

PEKERJAAN :
LOKASI :

70 Jenis Pekerjaan : Pemasangan 1 buah Bak Fiber


Satuan Pembayaran : Bh
Standar : A.5.1.1.10

Harga Total Harga


No. Uraian Kuantitas Satuan Jumlah
(Rp) (Rp)

A TENAGA
Pekerja 0.300 Org/ Hr 75,000.00 22,500.00
Tukang 0.450 Org/ Hr 80,000.00 36,000.00
Kepala Tukang 0.045 Org/ Hr 90,000.00 4,050.00
Mandor 0.015 Org/ Hr 100,000.00 1,500.00

SUB JUMLAH A 64,050.00

B BAHAN
Bak Air Fiber 1.000 bh 489,800.00 489,800.00
Perlengkapan 12% x Bak Fiber 1.000 Ls 58,776.00 58,776.00

SUB JUMLAH B 548,576.00

C PERALATAN
-

SUB JUMLAH C -

D JUMLAH (A+B+C) 612,626.00


E Overhead & Profit 10% x D 61,262.60
F HARGA SATUAN PEKERJAAN 673,888.60

71 Jenis Pekerjaan : Pemasangan 1 buah Cermin


Satuan Pembayaran : Bh
Standar : -

Harga Total Harga


No. Uraian Kuantitas Satuan Jumlah
(Rp) (Rp)

A TENAGA
Biaya Pemasangan 1.000 bh 45,000.00 45,000.00

SUB JUMLAH A 45,000.00

B BAHAN
Cermin 1.000 bh 225,000.00 225,000.00
termasuk aksesoris

SUB JUMLAH B 225,000.00

C UPAH
-

SUB JUMLAH C -

D JUMLAH (A+B+C) 270,000.00


E Overhead & Profit 10% x D 27,000.00
F HARGA SATUAN PEKERJAAN 297,000.00

Halaman 39
ANALISA HARGA SATUAN PEKERJAAN
(Permen PUPR No. 28/PRT/M/2016)

PEKERJAAN :
LOKASI :

72 Jenis Pekerjaan : Pemasangan 1 buah Bak Cuci Piring Stainlessteel


Satuan Pembayaran : Bh
Standar : A.5.1.1.12

Harga Total Harga


No. Uraian Kuantitas Satuan Jumlah
(Rp) (Rp)

A TENAGA
Pekerja 0.030 Org/ Hr 75,000.00 2,250.00
Tukang 0.300 Org/ Hr 80,000.00 24,000.00
Kepala Tukang 0.030 Org/ Hr 90,000.00 2,700.00
Mandor 0.015 Org/ Hr 100,000.00 1,500.00

SUB JUMLAH A 30,450.00

B BAHAN
Kitchen Zink 1.000 bh 425,000.00 425,000.00

SUB JUMLAH B 425,000.00

C UPAH
-

SUB JUMLAH C -

D JUMLAH (A+B+C) 455,450.00


E Overhead & Profit 10% x D 45,545.00
F HARGA SATUAN PEKERJAAN 500,995.00

73 Jenis Pekerjaan : Meja Pantry


Satuan Pembayaran : Bh
Standar : -

Harga Total Harga


No. Uraian Kuantitas Satuan Jumlah
(Rp) (Rp)

A TENAGA
Biaya Pemasangan 1.0000 Bh 170,000.00 170,000.00

SUB JUMLAH A 170,000.00


B BAHAN
Meja Pantry 1.000 bh 850,000.00 850,000.00

SUB JUMLAH B 850,000.00

C UPAH
-

SUB JUMLAH C -

D JUMLAH (A+B+C) 1,020,000.00


E Overhead & Profit 10% x D 102,000.00
F HARGA SATUAN PEKERJAAN 1,122,000.00

Halaman 40
ANALISA HARGA SATUAN PEKERJAAN
(Permen PUPR No. 28/PRT/M/2016)

PEKERJAAN :
LOKASI :

74 Jenis Pekerjaan : Pembuatan dan Pemasangan 1 m3 Kusen Pintu dan Jendela, Kayu Kelas I
Satuan Pembayaran : m3
Standar : A.4.6.1.1

Harga Total Harga


No. Uraian Kuantitas Satuan Jumlah
(Rp) (Rp)

A TENAGA
Pekerja 7.0000 Org/ Hr 75,000.00 525,000.00
Tukang 21.0000 Org/ Hr 80,000.00 1,680,000.00
Kepala Tukang 2.1000 Org/ Hr 90,000.00 189,000.00
Mandor 0.3500 Org/ Hr 100,000.00 35,000.00

SUB JUMLAH A 2,429,000.00

B BAHAN
Kayu/ Papan Klas I 1.1000 m³ 5,000,000.00 5,500,000.00
Paku Biasa 2" - 5" 1.2500 kg 15,000.00 18,750.00
Lem Kayu 1.0000 liter 30,000.00 30,000.00

SUB JUMLAH B 5,548,750.00

C UPAH
-

SUB JUMLAH C -

D JUMLAH (A+B+C) 7,977,750.00


E Overhead & Profit 10% x D 797,775.00
F HARGA SATUAN PEKERJAAN 8,775,525.00

75 Jenis Pekerjaan : Pembuatan dan Pemasangan 1 m2 Pintu Panel, Kayu Kelas I atau Kelas II
Satuan Pembayaran : m2
Standar : A.4.6.1.5

Harga Total Harga


No. Uraian Kuantitas Satuan Jumlah
(Rp) (Rp)

A TENAGA
Pekerja 1.0000 Org/ Hr 75,000.00 75,000.00
Tukang 3.0000 Org/ Hr 80,000.00 240,000.00
Kepala Tukang 0.3000 Org/ Hr 90,000.00 27,000.00
Mandor 0.0500 Org/ Hr 100,000.00 5,000.00

SUB JUMLAH A 347,000.00


B BAHAN
Kayu/ Papan Klas I 0.0400 m³ 5,000,000.00 200,000.00
Lem Kayu 0.5000 liter 30,000.00 15,000.00

SUB JUMLAH B 215,000.00

C PERALATAN
-

SUB JUMLAH C -

D JUMLAH (A+B+C) 562,000.00


E Overhead & Profit 10% x D 56,200.00
F HARGA SATUAN PEKERJAAN 618,200.00

Halaman 41
ANALISA HARGA SATUAN PEKERJAAN
(Permen PUPR No. 28/PRT/M/2016)

PEKERJAAN :
LOKASI :

76 Jenis Pekerjaan : Partisi Double Multiplek 6 mm Rangka Multiplek 18 mm Fin. HPL


Satuan Pembayaran : m2
Standar : -

Harga Total Harga


No. Uraian Kuantitas Satuan Jumlah
(Rp) (Rp)

A TENAGA
Pekerja 0.2000 Org/ Hr 75,000.00 15,000.00
Tukang 0.6000 Org/ Hr 80,000.00 48,000.00
Kepala Tukang 0.0600 Org/ Hr 90,000.00 5,400.00
Mandor 0.0100 Org/ Hr 100,000.00 1,000.00

SUB JUMLAH A 69,400.00


B BAHAN
Plywood 18 mm 1.0000 lbr 172,000.00 172,000.00
Plywood 9 mm 0.8600 lbr 133,000.00 114,380.00
Paku Biasa 2" - 3" 0.0300 kg 15,000.00 450.00
Lem Kayu 0.5000 liter 30,000.00 15,000.00
Pelapis Kayu Bahan HPL 2.0000 m² 43,000.00 86,000.00

SUB JUMLAH B 387,830.00

C PERALATAN
-

SUB JUMLAH C -

D JUMLAH (A+B+C) 457,230.00


E Overhead & Profit 10% x D 45,723.00
F HARGA SATUAN PEKERJAAN 502,953.00

77 Jenis Pekerjaan : Pemasangan 1 m1 Kusen Aluminium


Satuan Pembayaran : m1
Standar : A.4.2.1.11

Harga Total Harga


No. Uraian Kuantitas Satuan Jumlah
(Rp) (Rp)

A TENAGA
Pekerja 0.0430 Org/ Hr 75,000.00 3,225.00
Tukang 0.0430 Org/ Hr 80,000.00 3,440.00
Kepala Tukang 0.0043 Org/ Hr 90,000.00 387.00
Mandor 0.0021 Org/ Hr 100,000.00 210.00

SUB JUMLAH A 7,262.00

B BAHAN
Kusen Aluminium 1.1000 m¹ 125,000.00 137,500.00
Sekrup Fixer 2.0000 bh 500.00 1,000.00
Sealant 0.0600 tube 22,000.00 1,320.00

SUB JUMLAH B 139,820.00

C PERALATAN
-

SUB JUMLAH C -

D JUMLAH (A+B+C) 147,082.00


E Overhead & Profit 10% x D 14,708.20
F HARGA SATUAN PEKERJAAN 161,790.20

Halaman 42
ANALISA HARGA SATUAN PEKERJAAN
(Permen PUPR No. 28/PRT/M/2016)

PEKERJAAN :
LOKASI :

78 Jenis Pekerjaan : Pemasangan 1 m2 Pintu/ Jendela Rangka Aluminium


Satuan Pembayaran : m1
Standar : -

Harga Total Harga


No. Uraian Kuantitas Satuan Jumlah
(Rp) (Rp)

A TENAGA
Pekerja 0.0850 Or/hr 75,000.00 6,375.00
Tukang 0.0850 Or/hr 80,000.00 6,800.00
Kepala Tukang 0.0090 Or/hr 90,000.00 810.00
Mandor 0.0050 Or/hr 100,000.00 500.00

SUB JUMLAH A 14,485.00

B BAHAN
Rangka Aluminiumm 4.4000 m1 125,000.00 550,000.00
Profil Kaca 1.0000 m2 111,625.00 111,625.00
Sealant 0.2700 tube 22,000.00 5,940.00

SUB JUMLAH B 667,565.00

C PERALATAN
-

SUB JUMLAH C -

D JUMLAH (A+B+C) 682,050.00


E Overhead & Profit 10% x D 68,205.00
F HARGA SATUAN PEKERJAAN 750,255.00

79 Jenis Pekerjaan : Pemasangan 1 m2 Pintu/ Jendela Rangka Aluminium


Satuan Pembayaran : unit
Standar : -

Harga Total Harga


No. Uraian Kuantitas Satuan Jumlah
(Rp) (Rp)

Jendela Kaca Uk. 0.5 x 0.7 0.3500 m2/unit 750,255.00 262,589.25


Jendela Kaca Uk. 1.0 x 0.7 0.7000 m2/unit 750,255.00 525,178.50
Jendela Kaca Uk. 0.96 x 0.7 0.6720 m2/unit 750,255.00 504,171.36
Jendela Kaca Uk. 0.86 x 0.7 0.6020 m2/unit 750,255.00 451,653.51
Jendela Kaca Uk. 0.91 x 0.7 0.6370 m2/unit 750,255.00 477,912.44
Jendela Kaca Uk. 0.96 x 0.7 0.6720 m2/unit 750,255.00 504,171.36
Jendela Kaca Uk. 0.78 x 0.7 0.5460 m2/unit 750,255.00 409,639.23
Jendela Kaca Uk. 0.5 x 0.145 0.7250 m2/unit 750,255.00 543,934.88
Jendela Kaca Uk. 0.46 x 0.7 0.3220 m2/unit 750,255.00 241,582.11
Jendela Kaca Uk. 0.8 x 0.65 0.5600 m2/unit 750,255.00 420,142.80

Halaman 43
ANALISA HARGA SATUAN PEKERJAAN
(Permen PUPR No. 28/PRT/M/2016)

PEKERJAAN :
LOKASI :

80 Jenis Pekerjaan : Pemasangan 1 m2 Kaca tebal 5 mm


Satuan Pembayaran : m2
Standar : A.4.2.1.17

Harga Total Harga


No. Uraian Kuantitas Satuan Jumlah
(Rp) (Rp)

A TENAGA
Pekerja 0.0150 Or/hr 75,000.00 1,125.00
Tukang 0.1500 Or/hr 80,000.00 12,000.00
Kepala Tukang 0.0150 Or/hr 90,000.00 1,350.00
Mandor 0.0008 Or/hr 100,000.00 80.00

SUB JUMLAH A 14,555.00

B BAHAN
Kaca tebal 5 mm 1.1000 m1 111,625.00 122,787.50
Sealant 0.0500 tube 22,000.00 1,100.00

SUB JUMLAH B 123,887.50

C PERALATAN
-

SUB JUMLAH C -

D JUMLAH (A+B+C) 138,442.50


E Overhead & Profit 10% x D 13,844.25
F HARGA SATUAN PEKERJAAN 152,286.75

81 Jenis Pekerjaan : Pemasangan 1 m2 Kaca tebal 12 mm


Satuan Pembayaran : m2
Standar : A.4.6.1.19

Harga Total Harga


No. Uraian Kuantitas Satuan Jumlah
(Rp) (Rp)

A TENAGA
Pekerja 0.0250 Or/hr 75,000.00 1,875.00
Tukang 0.2500 Or/hr 80,000.00 20,000.00
Kepala Tukang 0.0250 Or/hr 90,000.00 2,250.00
Mandor 0.0013 Or/hr 100,000.00 130.00

SUB JUMLAH A 24,255.00

B BAHAN
Kaca tebal 12 mm 1.1000 m1 180,000.00 198,000.00
Sealant 0.0700 tube 22,000.00 1,540.00

SUB JUMLAH B 199,540.00

C PERALATAN
-

SUB JUMLAH C -

D JUMLAH (A+B+C) 223,795.00


E Overhead & Profit 10% x D 22,379.50
F HARGA SATUAN PEKERJAAN 246,174.50

Halaman 44
ANALISA HARGA SATUAN PEKERJAAN
(Permen PUPR No. 28/PRT/M/2016)

PEKERJAAN :
LOKASI :

82 Jenis Pekerjaan : Pemasangan Pintu Kaca Tempered tebal 12 mm


Satuan Pembayaran : unit
Standar : -

Harga Total Harga


No. Uraian Kuantitas Satuan Jumlah
(Rp) (Rp)

Pintu Kaca Tempered Uk. 0.9 x 2.2 1.9800 m2/unit 246,174.50 487,425.51
Pintu Kaca Tempered Uk. 0.8 x 2.2 1.7600 m2/unit 246,174.50 433,267.12
Pintu Kaca Tempered Uk. 1.025 x 2.1 2.1525 m2/unit 246,174.50 529,890.61
Pintu Kaca Tempered Uk. 0.75 x 2.1 1.5750 m2/unit 246,174.50 387,724.84
Pintu Kaca Tempered Uk. 0.9 x 2.1 1.8900 m2/unit 246,174.50 465,269.81
Pintu Kaca Tempered Uk. 0.8 x 2.1 1.6800 m2/unit 246,174.50 413,573.16
Pintu Kaca Tempered Uk. 0.9 x 2.05 1.8450 m2/unit 246,174.50 454,191.95
Pintu Kaca Tempered Uk. 0.8 x 2.05 1.6400 m2/unit 246,174.50 403,726.18
Pintu Kaca Tempered Uk. 0.75 x 2.05 1.5375 m2/unit 246,174.50 378,493.29
Pintu Kaca Tempered Uk. 0.7 x 2.05 1.4350 m2/unit 246,174.50 353,260.41

83 Jenis Pekerjaan : Pemasangan 1 Buah Kunci Tanam


Satuan Pembayaran : buah
Standar : A.4.6.2.3

Harga Total Harga


No. Uraian Kuantitas Satuan Jumlah
(Rp) (Rp)

A TENAGA
Pekerja 0.0100 Org/ Hr 75,000.00 750.00
Tukang 0.5000 Org/ Hr 80,000.00 40,000.00
Kepala Tukang 0.0500 Org/ Hr 90,000.00 4,500.00
Mandor 0.0050 Org/ Hr 100,000.00 500.00

SUB JUMLAH A 45,750.00

B BAHAN
Kunci Tanam 2 Slaag 1.0000 bh 334,875.00 334,875.00

SUB JUMLAH B 334,875.00

C PERALATAN
-

SUB JUMLAH C -

D JUMLAH (A+B+C) 380,625.00


E Overhead & Profit 10% x D 38,062.50
F HARGA SATUAN PEKERJAAN 418,687.50

Halaman 45
ANALISA HARGA SATUAN PEKERJAAN
(Permen PUPR No. 28/PRT/M/2016)

PEKERJAAN :
LOKASI :

84 Jenis Pekerjaan : Pemasangan 1 Buah Kunci Kamar Mandi


Satuan Pembayaran : buah
Standar : A.4.6.2.3

Harga Total Harga


No. Uraian Kuantitas Satuan Jumlah
(Rp) (Rp)

A TENAGA
Pekerja 0.0050 Org/ Hr 75,000.00 375.00
Tukang 0.5000 Org/ Hr 80,000.00 40,000.00
Kepala Tukang 0.0500 Org/ Hr 90,000.00 4,500.00
Mandor 0.0030 Org/ Hr 100,000.00 300.00

SUB JUMLAH A 45,175.00

B BAHAN
Kunci Biasa 1.0000 bh 143,000.00 143,000.00

SUB JUMLAH B 143,000.00

C PERALATAN
-

SUB JUMLAH C -

D JUMLAH (A+B+C) 188,175.00


E Overhead & Profit 10% x D 18,817.50
F HARGA SATUAN PEKERJAAN 206,992.50

85 Jenis Pekerjaan : Pemasangan 1 Buah Engsel Pintu


Satuan Pembayaran : buah
Standar : A.4.6.2.5

Harga Total Harga


No. Uraian Kuantitas Satuan Jumlah
(Rp) (Rp)

A TENAGA
Pekerja 0.0150 Org/ Hr 75,000.00 1,125.00
Tukang 0.1500 Org/ Hr 80,000.00 12,000.00
Kepala Tukang 0.0150 Org/ Hr 90,000.00 1,350.00
Mandor 0.0008 Org/ Hr 100,000.00 80.00

SUB JUMLAH A 14,555.00

B BAHAN
Engsel Pintu 4 '' 1.0000 bh 88,000.00 88,000.00

SUB JUMLAH B 88,000.00

C PERALATAN
-

SUB JUMLAH C -

D JUMLAH (A+B+C) 102,555.00


E Overhead & Profit 10% x D 10,255.50
F HARGA SATUAN PEKERJAAN 112,810.50

Halaman 46
ANALISA HARGA SATUAN PEKERJAAN
(Permen PUPR No. 28/PRT/M/2016)

PEKERJAAN :
LOKASI :

86 Jenis Pekerjaan : Pemasangan 1 Buah Engsel Pintu Kaca Tempered


Satuan Pembayaran : buah
Standar : -

Harga Total Harga


No. Uraian Kuantitas Satuan Jumlah
(Rp) (Rp)

A TENAGA
Pekerja 0.0150 Org/ Hr 75,000.00 1,125.00
Tukang 0.1500 Org/ Hr 80,000.00 12,000.00
Kepala Tukang 0.0150 Org/ Hr 90,000.00 1,350.00
Mandor 0.0008 Org/ Hr 100,000.00 80.00

SUB JUMLAH A 14,555.00

B BAHAN
Engsel Pintu Tanam Pintu Kaca Tempered 1.0000 bh 485,000.00 485,000.00

SUB JUMLAH B 485,000.00

C PERALATAN
-

SUB JUMLAH C -

D JUMLAH (A+B+C) 499,555.00


E Overhead & Profit 10% x D 49,955.50
F HARGA SATUAN PEKERJAAN 549,510.50

87 Jenis Pekerjaan : Pemasangan 1 Buah Engsel Jendela


Satuan Pembayaran : buah
Standar : A.4.6.2.6

Harga Total Harga


No. Uraian Kuantitas Satuan Jumlah
(Rp) (Rp)

A TENAGA
Pekerja 0.0100 Org/ Hr 75,000.00 750.00
Tukang 0.1000 Org/ Hr 80,000.00 8,000.00
Kepala Tukang 0.0100 Org/ Hr 90,000.00 900.00
Mandor 0.0005 Org/ Hr 100,000.00 50.00

SUB JUMLAH B 9,700.00

B BAHAN
Engsel Jendela 3 " 1.0000 bh 65,000.00 65,000.00

SUB JUMLAH A 65,000.00

C PERALATAN
-

SUB JUMLAH B -

D JUMLAH (A+B+C) 74,700.00


E Overhead & Profit 10% x D 7,470.00
F HARGA SATUAN PEKERJAAN 82,170.00

Halaman 47
ANALISA HARGA SATUAN PEKERJAAN
(Permen PUPR No. 28/PRT/M/2016)

PEKERJAAN :
LOKASI :

88 Jenis Pekerjaan : Pemasangan 1 Buah Spring Knip


Satuan Pembayaran : buah
Standar : A.4.6.2.8

Harga Total Harga


No. Uraian Kuantitas Satuan Jumlah
(Rp) (Rp)

A TENAGA
Pekerja 0.0150 Org/ Hr 75,000.00 1,125.00
Tukang 0.1500 Org/ Hr 80,000.00 12,000.00
Kepala Tukang 0.0150 Org/ Hr 90,000.00 1,350.00
Mandor 0.0080 Org/ Hr 100,000.00 800.00

SUB JUMLAH A 15,275.00

B BAHAN
Grendel Jendela / Spring Knip 1.0000 bh 33,500.00 33,500.00

SUB JUMLAH B 33,500.00

C PERALATAN
-

SUB JUMLAH C -

D JUMLAH (A+B+C) 48,775.00


E Overhead & Profit 10% x D 4,877.50
F HARGA SATUAN PEKERJAAN 53,652.50

89 Jenis Pekerjaan : Pemasangan 1 Buah Kait Angin


Satuan Pembayaran : buah
Standar : A.6.2.9

Harga Total Harga


No. Uraian Kuantitas Satuan Jumlah
(Rp) (Rp)

A TENAGA
Pekerja 0.0150 Org/ Hr 75,000.00 1,125.00
Tukang 0.1500 Org/ Hr 80,000.00 12,000.00
Kepala Tukang 0.0150 Org/ Hr 90,000.00 1,350.00
Mandor 0.0080 Org/ Hr 100,000.00 800.00

SUB JUMLAH A 15,275.00

B BAHAN
Kait Angin Kualitas Standar 1.0000 bh 16,500.00 16,500.00

SUB JUMLAH B 16,500.00

C UPAH
-

SUB JUMLAH C -

D JUMLAH (A+B+C) 31,775.00


E Overhead & Profit 10% x D 3,177.50
F HARGA SATUAN PEKERJAAN 34,952.50

Halaman 48
ANALISA HARGA SATUAN PEKERJAAN
(Permen PUPR No. 28/PRT/M/2016)

PEKERJAAN :
LOKASI :

90 Jenis Pekerjaan : Pemasangan 1 Buah Handle Pintu


Satuan Pembayaran : buah
Standar : -

Harga Total Harga


No. Uraian Kuantitas Satuan Jumlah
(Rp) (Rp)

A UPAH
Pekerja 0.0150 Org/ Hr 75,000.00 1,125.00
Tukang 0.1500 Org/ Hr 80,000.00 12,000.00
Kepala Tukang 0.0150 Org/ Hr 90,000.00 1,350.00
Mandor 0.0080 Org/ Hr 100,000.00 800.00

SUB JUMLAH A 15,275.00

B BAHAN
Handle Pintu 1.0000 bh 143,800.00 143,800.00

SUB JUMLAH B 143,800.00

C UPAH
-

SUB JUMLAH C -

D JUMLAH (A+B+C) 159,075.00


E Overhead & Profit 10% x D 15,907.50
F HARGA SATUAN PEKERJAAN 174,982.50

91 Jenis Pekerjaan : Pemasangan 1 Buah Handle Jendela


Satuan Pembayaran : buah
Standar : -

Harga Total Harga


No. Uraian Kuantitas Satuan Jumlah
(Rp) (Rp)

A UPAH
Pekerja 0.0150 Org/ Hr 75,000.00 1,125.00
Tukang 0.1500 Org/ Hr 80,000.00 12,000.00
Kepala Tukang 0.0150 Org/ Hr 90,000.00 1,350.00
Mandor 0.0080 Org/ Hr 100,000.00 800.00

SUB JUMLAH A 15,275.00

B BAHAN
Handle jendela 1.0000 bh 195,000.00 195,000.00

SUB JUMLAH B 195,000.00

C UPAH
-

SUB JUMLAH C -

D JUMLAH (A+B+C) 210,275.00


E Overhead & Profit 10% x D 21,027.50
F HARGA SATUAN PEKERJAAN 231,302.50

Halaman 49
ANALISA HARGA SATUAN PEKERJAAN
(Permen PUPR No. 28/PRT/M/2016)

PEKERJAAN :
LOKASI :

92 Jenis Pekerjaan : Pemasangan 1 Buah Door Closer


Satuan Pembayaran : buah
Standar : A.4.6.2.10

Harga Total Harga


No. Uraian Kuantitas Satuan Jumlah
(Rp) (Rp)

A UPAH
Pekerja 0.0500 Org/ Hr 75,000.00 3,750.00
Tukang 0.5000 Org/ Hr 80,000.00 40,000.00
Kepala Tukang 0.0500 Org/ Hr 90,000.00 4,500.00
Mandor 0.0030 Org/ Hr 100,000.00 300.00

SUB JUMLAH A 48,550.00

B BAHAN
Door Closer 1.0000 bh 258,000.00 258,000.00

SUB JUMLAH B 258,000.00

C UPAH
-

SUB JUMLAH C -

D JUMLAH (A+B+C) 306,550.00


E Overhead & Profit 10% x D 30,655.00
F HARGA SATUAN PEKERJAAN 337,205.00

93 Jenis Pekerjaan : Pemasangan Pintu Tipe P1


Satuan Pembayaran : unit

Harga Total Harga


No. Uraian Kuantitas Satuan Jumlah
(Rp) (Rp)

A BAHAN
Gawang Beton 0.2 x 0.35 0.4830 m³ 6,639,710.00 3,206,979.93
Aluminium Composit Panel 2.8000 m² 695,750.00 1,948,100.00
Pintu Kaca Tempered 12 mm 0.9 x 2.2 2.0000 bh 487,425.51 974,851.02
Stiker Kaca Buram 0.9000 m² 32,000.00 28,800.00
Engsel Pintu Kaca Tempered 4.0000 bh 549,510.50 2,198,042.00
Handle Pintu 2.0000 bh 174,982.50 349,965.00
Kunci Pintu 1.0000 bh 418,687.50 418,687.50
Door Closer 2.0000 bh 337,205.00 674,410.00

SUB JUMLAH A 9,799,835.45

B HARGA SATUAN PEKERJAAN 9,799,835.45

94 Jenis Pekerjaan : Pemasangan Pintu Tipe P2


Satuan Pembayaran : unit

Harga Total Harga


No. Uraian Kuantitas Satuan Jumlah
(Rp) (Rp)

A BAHAN
Gawang Beton 0.2 x 0.35 0.4760 m³ 6,639,710.00 3,160,501.96
Aluminium Composit Panel 2.7200 m² 695,750.00 1,892,440.00
Pintu Kaca Tempered 12 mm 0.8 x 2.2 2.0000 bh 433,267.12 866,534.24
Stiker Kaca Buram 0.8000 m² 32,000.00 25,600.00
Engsel Pintu Kaca Tempered 4.0000 bh 549,510.50 2,198,042.00
Handle Pintu 2.0000 bh 174,982.50 349,965.00
Kunci Pintu 1.0000 bh 418,687.50 418,687.50
Door Closer 2.0000 bh 337,205.00 674,410.00

SUB JUMLAH A 9,586,180.70

B HARGA SATUAN PEKERJAAN 9,586,180.70

95 Jenis Pekerjaan : Pemasangan Pintu Tipe P3


Halaman 50
ANALISA HARGA SATUAN PEKERJAAN
(Permen PUPR No. 28/PRT/M/2016)

PEKERJAAN :
LOKASI :

Satuan Pembayaran : unit

Harga Total Harga


No. Uraian Kuantitas Satuan Jumlah
(Rp) (Rp)

A BAHAN
Kusen Aluminium 9.5000 m¹ 161,790.20 1,537,006.90
Pintu Kaca Tempered 12 mm 1.025 x 2.1 2.0000 bh 529,890.61 1,059,781.22
Stiker Kaca Buram 1.0250 m² 32,000.00 32,800.00
Kaca Bening 5 mm 4.2350 m² 152,286.75 644,934.39
Jendela 0.5 x 0.7 2.0000 bh 262,589.25 525,178.50
Engsel Pintu Kaca Tempered 4.0000 bh 549,510.50 2,198,042.00
Handle Pintu 2.0000 bh 174,982.50 349,965.00
Kunci Pintu 1.0000 bh 418,687.50 418,687.50
Engsel Jendela 4.0000 bh 82,170.00 328,680.00
Handle Jendela 2.0000 bh 231,302.50 462,605.00
Grendel Jendela 2.0000 bh 53,652.50 107,305.00
Kait Angin Jendela 4.0000 bh 34,952.50 139,810.00
Door Closer 2.0000 bh 337,205.00 674,410.00

SUB JUMLAH A 8,479,205.51

B HARGA SATUAN PEKERJAAN 8,479,205.51

96 Jenis Pekerjaan : Pemasangan Pintu Tipe P4


Satuan Pembayaran : unit

Harga Total Harga


No. Uraian Kuantitas Satuan Jumlah
(Rp) (Rp)

A BAHAN
Kusen Aluminium 9.5000 m¹ 161,790.20 1,537,006.90
Pintu Kaca Tempered 12 mm 0.75 x 2.1 2.0000 bh 387,724.84 775,449.68
Stiker Kaca Buram 0.7500 m² 32,000.00 24,000.00
Kaca Bening 5 mm 0.9800 m² 152,286.75 149,241.02
Engsel Pintu Kaca Tempered 4.0000 bh 549,510.50 2,198,042.00
Handle Pintu 2.0000 bh 174,982.50 349,965.00
Kunci Pintu 1.0000 bh 418,687.50 418,687.50
Door Closer 2.0000 bh 337,205.00 674,410.00

SUB JUMLAH A 6,126,802.09

B HARGA SATUAN PEKERJAAN 6,126,802.09

97 Jenis Pekerjaan : Pemasangan Pintu Tipe P5


Satuan Pembayaran : unit

Harga Total Harga


No. Uraian Kuantitas Satuan Jumlah
(Rp) (Rp)

A BAHAN
Kusen Aluminium 7.6000 m¹ 161,790.20 1,229,605.52
Pintu Kaca Tempered 12 mm 0.9 x 2.1 1.0000 bh 465,269.81 465,269.81
Stiker Kaca Buram 0.4500 m² 32,000.00 14,400.00
Kaca Bening 5 mm 0.6300 m² 152,286.75 95,940.65
Engsel Pintu Kaca Tempered 2.0000 bh 549,510.50 1,099,021.00
Handle Pintu 1.0000 bh 174,982.50 174,982.50
Kunci Pintu 1.0000 bh 418,687.50 418,687.50
Door Closer 1.0000 bh 337,205.00 337,205.00

SUB JUMLAH A 3,835,111.98

B HARGA SATUAN PEKERJAAN 3,835,111.98

Halaman 51
ANALISA HARGA SATUAN PEKERJAAN
(Permen PUPR No. 28/PRT/M/2016)

PEKERJAAN :
LOKASI :

98 Jenis Pekerjaan : Pemasangan Pintu Tipe P5a


Satuan Pembayaran : unit

Harga Total Harga


No. Uraian Kuantitas Satuan Jumlah
(Rp) (Rp)

A BAHAN

Kusen Aluminium 7.4000 m¹ 161,790.20 1,197,247.48


Pintu Kaca Tempered 12 mm 0.8 x 2.1 1.0000 bh 413,573.16 413,573.16
Stiker Kaca Buram 0.4000 m² 32,000.00 12,800.00
Kaca Bening 5 mm 0.5600 m² 152,286.75 85,280.58
Engsel Pintu Kaca Tempered 2.0000 bh 549,510.50 1,099,021.00
Handle Pintu 1.0000 bh 174,982.50 174,982.50
Kunci Pintu 1.0000 bh 418,687.50 418,687.50
Door Closer 1.0000 bh 337,205.00 337,205.00

SUB JUMLAH A 3,738,797.22

B HARGA SATUAN PEKERJAAN 3,738,797.22

99 Jenis Pekerjaan : Pemasangan Pintu Tipe P6


Satuan Pembayaran : unit

Harga Total Harga


No. Uraian Kuantitas Satuan Jumlah
(Rp) (Rp)

A BAHAN

Kusen Aluminium 7.4000 m¹ 161,790.20 1,197,247.48


Pintu Double Multiplek HPL 0.8 x 2.1 1.0000 bh 1,092,000.00 1,092,000.00
Rangka Multiplek 18 mm Fin. HPL
Kaca Bening 5 mm 0.5600 m² 152,286.75 85,280.58
Engsel Pintu 3.0000 bh 112,810.50 338,431.50
Handle Pintu 1.0000 bh 174,982.50 174,982.50
Kunci Pintu 1.0000 bh 418,687.50 418,687.50
Door Closer 1.0000 bh 337,205.00 337,205.00

SUB JUMLAH A 3,643,834.56

B HARGA SATUAN PEKERJAAN 3,643,834.56

100 Jenis Pekerjaan : Pemasangan Pintu Tipe P7


Satuan Pembayaran : unit

Harga Total Harga


No. Uraian Kuantitas Satuan Jumlah
(Rp) (Rp)

A BAHAN

Kusen Aluminium 5.0000 m¹ 161,790.20 808,951.00


Pintu Double Multiplek HPL 0.8 x 2.1 1.0000 bh 1,092,000.00 1,092,000.00
Rangka Multiplek 18 mm Fin. HPL
Engsel Pintu 3.0000 bh 112,810.50 338,431.50
Handle Pintu 1.0000 bh 174,982.50 174,982.50
Kunci Pintu 1.0000 bh 418,687.50 418,687.50
Door Closer 1.0000 bh 337,205.00 337,205.00

SUB JUMLAH A 3,170,257.50

B HARGA SATUAN PEKERJAAN 3,170,257.50

Halaman 52
ANALISA HARGA SATUAN PEKERJAAN
(Permen PUPR No. 28/PRT/M/2016)

PEKERJAAN :
LOKASI :

101 Jenis Pekerjaan : Pemasangan Pintu Tipe P8


Satuan Pembayaran : unit

Harga Total Harga


No. Uraian Kuantitas Satuan Jumlah
(Rp) (Rp)

A BAHAN

Kusen Aluminium 7.2000 m¹ 161,790.20 1,164,889.44


Pintu Double Multiplek HPL 0.7 x 2.1 1.0000 bh 955,500.00 955,500.00
Rangka Multiplek 18 mm Fin. HPL
Kaca Bening 5 mm 0.4900 m² 152,286.75 74,620.51
Engsel Pintu 3.0000 bh 112,810.50 338,431.50
Handle Pintu 1.0000 bh 174,982.50 174,982.50
Kunci Pintu 1.0000 bh 418,687.50 418,687.50
Door Closer 1.0000 bh 337,205.00 337,205.00

SUB JUMLAH A 3,464,316.45

B HARGA SATUAN PEKERJAAN 3,464,316.45

102 Jenis Pekerjaan : Pemasangan Pintu Tipe P9


Satuan Pembayaran : unit

Harga Total Harga


No. Uraian Kuantitas Satuan Jumlah
(Rp) (Rp)

A BAHAN

Kusen Aluminium 5.0000 m¹ 161,790.20 808,951.00


Pintu PVC 0.7 x 2.1 1.0000 bh 281,325.00 281,325.00
Engsel Pintu 3.0000 bh 152,286.75 456,860.25
Kunci Pintu 1.0000 bh 206,992.50 206,992.50

SUB JUMLAH A 1,754,128.75

B HARGA SATUAN PEKERJAAN 1,754,128.75

103 Jenis Pekerjaan : Pemasangan Pintu Tipe Ps


Satuan Pembayaran : unit

Harga Total Harga


No. Uraian Kuantitas Satuan Jumlah
(Rp) (Rp)

A BAHAN

Kusen Aluminium 3.4000 m¹ 161,790.20 550,086.68


Pintu Aluminium 0.5 x 1.0 1.0000 bh 300,000.00 300,000.00
Engsel Pintu 3.0000 bh 152,286.75 456,860.25
Kunci Pintu 1.0000 bh 206,992.50 206,992.50

SUB JUMLAH A 1,513,939.43

B HARGA SATUAN PEKERJAAN 1,513,939.43

104 Jenis Pekerjaan : Pemasangan Pintu Tipe P10


Satuan Pembayaran : unit

Harga Total Harga


No. Uraian Kuantitas Satuan Jumlah
(Rp) (Rp)

A BAHAN

Pintu Lipat Besi 4.25 x 3.90 1.0000 ls 8,287,500.00 8,287,500.00


Kusen Besi inc. Kunci & aksesoris

SUB JUMLAH A 8,287,500.00

B HARGA SATUAN PEKERJAAN 8,287,500.00

Halaman 53
ANALISA HARGA SATUAN PEKERJAAN
(Permen PUPR No. 28/PRT/M/2016)

PEKERJAAN :
LOKASI :

105 Jenis Pekerjaan : Pemasangan Jendela Tipe J1


Satuan Pembayaran : unit

Harga Total Harga


No. Uraian Kuantitas Satuan Jumlah
(Rp) (Rp)

A BAHAN
Kusen Aluminium 20.8000 m¹ 161,790.20 3,365,236.16
Kaca Bening 5 mm 5.6700 m² 152,286.75 863,465.87

SUB JUMLAH A 4,228,702.03

B HARGA SATUAN PEKERJAAN 4,228,702.03

106 Jenis Pekerjaan : Pemasangan Jendela Tipe J2


Satuan Pembayaran : unit

Harga Total Harga


No. Uraian Kuantitas Satuan Jumlah
(Rp) (Rp)

A BAHAN
Kusen Aluminium 28.5000 m1 161,790.20 4,611,020.70
Kaca Bening 5 mm 8.4000 m² 152,286.75 1,279,208.70

SUB JUMLAH A 5,890,229.40

B HARGA SATUAN PEKERJAAN 5,890,229.40

107 Jenis Pekerjaan : Pemasangan Jendela Tipe J3a


Satuan Pembayaran : unit

Harga Total Harga


No. Uraian Kuantitas Satuan Jumlah
(Rp) (Rp)

A BAHAN
Kusen Aluminium 14.9000 m1 161,790.20 2,410,673.98
Kaca Bening 5 mm 2.4000 m² 152,286.75 365,488.20
Jendela Kaca 0.5 x 0.7 3.0000 bh 262,589.25 787,767.75
Engsel Jendela 6.0000 bh 82,170.00 493,020.00
Handle Jendela 3.0000 bh 231,302.50 693,907.50
Grendel Jendela 3.0000 bh 53,652.50 160,957.50
Kait Angin Jendela 6.0000 bh 34,952.50 209,715.00

SUB JUMLAH A 5,121,529.93

B HARGA SATUAN PEKERJAAN 5,121,529.93

108 Jenis Pekerjaan : Pemasangan Jendela Tipe J3b


Satuan Pembayaran : unit

Harga Total Harga


No. Uraian Kuantitas Satuan Jumlah
(Rp) (Rp)

A BAHAN
Kusen Aluminium 18.4000 m¹ 161,790.20 2,976,939.68
Kaca Bening 5 mm 3.0000 m² 152,286.75 456,860.25
Jendela Kaca 0.5 x 0.7 3.0000 bh 262,589.25 787,767.75
Engsel Jendela 6.0000 bh 82,170.00 493,020.00
Handle Jendela 3.0000 bh 231,302.50 693,907.50
Grendel Jendela 3.0000 bh 53,652.50 160,957.50
Kait Angin Jendela 6.0000 bh 34,952.50 209,715.00

SUB JUMLAH A 5,779,167.68

B HARGA SATUAN PEKERJAAN 5,779,167.68

109 Jenis Pekerjaan : Pemasangan Jendela Tipe J4a


Satuan Pembayaran : unit
Halaman 54
ANALISA HARGA SATUAN PEKERJAAN
(Permen PUPR No. 28/PRT/M/2016)

PEKERJAAN :
LOKASI :

Harga Total Harga


No. Uraian Kuantitas Satuan Jumlah
(Rp) (Rp)

A BAHAN
Kusen Aluminium 21.4400 m¹ 161,790.20 3,468,781.89
Kaca Bening 5 mm 3.9060 m² 152,286.75 594,832.05
Jendela Kaca 1.0 x 0.7 3.0000 bh 525,178.50 1,575,535.50
Engsel Jendela 6.0000 bh 82,170.00 493,020.00
Handle Jendela 3.0000 bh 231,302.50 693,907.50
Grendel Jendela 3.0000 bh 53,652.50 160,957.50
Kait Angin Jendela 6.0000 bh 34,952.50 209,715.00

SUB JUMLAH A 7,196,749.43

B HARGA SATUAN PEKERJAAN 7,196,749.43

110 Jenis Pekerjaan : Pemasangan Jendela Tipe J4b


Satuan Pembayaran : unit

Harga Total Harga


No. Uraian Kuantitas Satuan Jumlah
(Rp) (Rp)

A BAHAN
Kusen Aluminium 21.4400 m¹ 161,790.20 3,468,781.89
Kaca Bening 5 mm 3.9060 m² 152,286.75 594,832.05
Jendela Kaca 1.0 x 0.7 3.0000 bh 525,178.50 1,575,535.50
Engsel Jendela 6.0000 bh 82,170.00 493,020.00
Handle Jendela 3.0000 bh 231,302.50 693,907.50
Grendel Jendela 3.0000 bh 53,652.50 160,957.50
Kait Angin Jendela 6.0000 bh 34,952.50 209,715.00

SUB JUMLAH A 7,196,749.43

B HARGA SATUAN PEKERJAAN 7,196,749.43

111 Jenis Pekerjaan : Pemasangan Jendela Tipe J5a


Satuan Pembayaran : unit

Harga Total Harga


No. Uraian Kuantitas Satuan Jumlah
(Rp) (Rp)

A BAHAN
Kusen Aluminium 15.5000 m¹ 161,790.20 2,507,748.10
Kaca Bening 5 mm 4.2000 m² 152,286.75 639,604.35
Jendela Kaca 1.0 x 0.7 3.0000 bh 525,178.50 1,575,535.50
Engsel Jendela 6.0000 bh 82,170.00 493,020.00
Handle Jendela 3.0000 bh 231,302.50 693,907.50
Grendel Jendela 3.0000 bh 53,652.50 160,957.50
Kait Angin Jendela 6.0000 bh 34,952.50 209,715.00

SUB JUMLAH A 6,280,487.95

B HARGA SATUAN PEKERJAAN 6,280,487.95

Halaman 55
ANALISA HARGA SATUAN PEKERJAAN
(Permen PUPR No. 28/PRT/M/2016)

PEKERJAAN :
LOKASI :

112 Jenis Pekerjaan : Pemasangan Jendela Tipe J5b


Satuan Pembayaran : unit

Harga Total Harga


No. Uraian Kuantitas Satuan Jumlah
(Rp) (Rp)

A BAHAN
Kusen Aluminium 15.5000 m¹ 161,790.20 2,507,748.10
Kaca Bening 5 mm 4.2000 m² 152,286.75 639,604.35
Jendela Kaca 1.0 x 0.7 3.0000 bh 525,178.50 1,575,535.50
Engsel Jendela 6.0000 bh 82,170.00 493,020.00
Handle Jendela 3.0000 bh 231,302.50 693,907.50
Grendel Jendela 3.0000 bh 53,652.50 160,957.50
Kait Angin Jendela 6.0000 bh 34,952.50 209,715.00

SUB JUMLAH A 6,280,487.95

B HARGA SATUAN PEKERJAAN 6,280,487.95

113 Jenis Pekerjaan : Pemasangan Jendela Tipe J6a


Satuan Pembayaran : unit

Harga Total Harga


No. Uraian Kuantitas Satuan Jumlah
(Rp) (Rp)

A BAHAN
Kusen Aluminium 8.4400 m¹ 161,790.20 1,365,509.29
Kaca Bening 5 mm 2.0160 m² 152,286.75 307,010.09
Jendela Kaca 0.96 x 0.7 1.0000 bh 504,171.36 504,171.36
Engsel Jendela 2.0000 bh 82,170.00 164,340.00
Handle Jendela 1.0000 bh 231,302.50 231,302.50
Grendel Jendela 1.0000 bh 53,652.50 53,652.50
Kait Angin Jendela 2.0000 bh 34,952.50 69,905.00

SUB JUMLAH A 2,695,890.74

B HARGA SATUAN PEKERJAAN 2,695,890.74

114 Jenis Pekerjaan : Pemasangan Jendela Tipe J6b


Satuan Pembayaran : unit

Harga Total Harga


No. Uraian Kuantitas Satuan Jumlah
(Rp) (Rp)

A BAHAN
Kusen Aluminium 8.4400 m¹ 161,790.20 1,365,509.29
Jendela Kaca 0.96 x 0.7 3.0000 bh 504,171.36 1,512,514.08
Engsel Jendela 6.0000 bh 82,170.00 493,020.00
Handle Jendela 3.0000 bh 231,302.50 693,907.50
Grendel Jendela 3.0000 bh 53,652.50 160,957.50
Kait Angin Jendela 6.0000 bh 34,952.50 209,715.00

SUB JUMLAH A 4,435,623.37

B HARGA SATUAN PEKERJAAN 4,435,623.37

Halaman 56
ANALISA HARGA SATUAN PEKERJAAN
(Permen PUPR No. 28/PRT/M/2016)

PEKERJAAN :
LOKASI :

115 Jenis Pekerjaan : Pemasangan Jendela Tipe J7


Satuan Pembayaran : unit

Harga Total Harga


No. Uraian Kuantitas Satuan Jumlah
(Rp) (Rp)

A BAHAN
Kusen Aluminium 8.0400 m¹ 161,790.20 1,300,793.21
Jendela Kaca 0.86 x 0.7 3.0000 bh 451,653.51 1,354,960.53
Engsel Jendela 6.0000 bh 82,170.00 493,020.00
Handle Jendela 3.0000 bh 231,302.50 693,907.50
Grendel Jendela 3.0000 bh 53,652.50 160,957.50
Kait Angin Jendela 6.0000 bh 34,952.50 209,715.00

SUB JUMLAH A 4,213,353.74

B HARGA SATUAN PEKERJAAN 4,213,353.74

116 Jenis Pekerjaan : Pemasangan Jendela Tipe J8


Satuan Pembayaran : unit

Harga Total Harga


No. Uraian Kuantitas Satuan Jumlah
(Rp) (Rp)

A BAHAN
Kusen Aluminium 5.6000 m¹ 161,790.20 906,025.12
Kaca Bening 5 mm 1.0750 m² 152,286.75 163,708.26

SUB JUMLAH A 1,069,733.38

B HARGA SATUAN PEKERJAAN 1,069,733.38

117 Jenis Pekerjaan : Pemasangan Jendela Tipe J9a


Satuan Pembayaran : unit

Harga Total Harga


No. Uraian Kuantitas Satuan Jumlah
(Rp) (Rp)

A BAHAN
Kusen Aluminium 10.8300 m¹ 161,790.20 1,752,187.87
Kaca Bening 5 mm 1.2740 m² 152,286.75 194,013.32
Jendela Kaca 0.91 x 0.7 2.0000 bh 477,912.44 955,824.87
Engsel Jendela 4.0000 bh 82,170.00 328,680.00
Handle Jendela 2.0000 bh 231,302.50 462,605.00
Grendel Jendela 2.0000 bh 53,652.50 107,305.00
Kait Angin Jendela 4.0000 bh 34,952.50 139,810.00

SUB JUMLAH A 3,940,426.06

B HARGA SATUAN PEKERJAAN 3,940,426.06

118 Jenis Pekerjaan : Pemasangan Jendela Tipe J9b


Satuan Pembayaran : unit

Harga Total Harga


No. Uraian Kuantitas Satuan Jumlah
(Rp) (Rp)

A BAHAN
Kusen Aluminium 10.8300 m¹ 161,790.20 1,752,187.87
Kaca Bening 5 mm 1.2740 m² 152,286.75 194,013.32
Jendela Kaca 0.91 x 0.7 2.0000 bh 477,912.44 955,824.87
Engsel Jendela 4.0000 bh 82,170.00 328,680.00
Handle Jendela 2.0000 bh 231,302.50 462,605.00
Grendel Jendela 2.0000 bh 53,652.50 107,305.00
Kait Angin Jendela 4.0000 bh 34,952.50 139,810.00

SUB JUMLAH A 3,940,426.06

B HARGA SATUAN PEKERJAAN 3,940,426.06

Halaman 57
ANALISA HARGA SATUAN PEKERJAAN
(Permen PUPR No. 28/PRT/M/2016)

PEKERJAAN :
LOKASI :

119 Jenis Pekerjaan : Pemasangan Jendela Tipe J10


Satuan Pembayaran : unit

Harga Total Harga


No. Uraian Kuantitas Satuan Jumlah
(Rp) (Rp)

A BAHAN
Kusen Aluminium 25.7500 m¹ 161,790.20 4,166,097.65
Kaca Bening 5 mm 5.6000 m² 152,286.75 852,805.80

SUB JUMLAH A 5,018,903.45

B HARGA SATUAN PEKERJAAN 5,018,903.45

120 Jenis Pekerjaan : Pemasangan Jendela Tipe J11


Satuan Pembayaran : unit

Harga Total Harga


No. Uraian Kuantitas Satuan Jumlah
(Rp) (Rp)

A BAHAN
Kusen Aluminium 20.2000 m¹ 161,790.20 3,268,162.04
Kaca Bening 5 mm 1.4000 m² 152,286.75 213,201.45
Jendela Kaca 1 x 0.7 6.0000 bh 525,178.50 3,151,071.00
Engsel Jendela 12.0000 bh 82,170.00 986,040.00
Handle Jendela 6.0000 bh 231,302.50 1,387,815.00
Grendel Jendela 6.0000 bh 53,652.50 321,915.00
Kait Angin Jendela 12.0000 bh 34,952.50 419,430.00

SUB JUMLAH A 9,747,634.49

B HARGA SATUAN PEKERJAAN 9,747,634.49

121 Jenis Pekerjaan : Pemasangan Jendela Tipe J12


Satuan Pembayaran : unit

Harga Total Harga


No. Uraian Kuantitas Satuan Jumlah
(Rp) (Rp)

A BAHAN
Kusen Aluminium 15.3800 m¹ 161,790.20 2,488,333.28
Kaca Bening 5 mm 1.4000 m² 152,286.75 213,201.45
Jendela Kaca 0.86 x 0.7 2.0000 bh 451,653.51 903,307.02
Jendela Kaca 1.0 x 0.7 2.0000 bh 525,178.50 1,050,357.00
Engsel Jendela 8.0000 bh 82,170.00 657,360.00
Handle Jendela 4.0000 bh 231,302.50 925,210.00
Grendel Jendela 4.0000 bh 53,652.50 214,610.00
Kait Angin Jendela 8.0000 bh 34,952.50 279,620.00

SUB JUMLAH A 6,731,998.75

B HARGA SATUAN PEKERJAAN 6,731,998.75

Halaman 58
ANALISA HARGA SATUAN PEKERJAAN
(Permen PUPR No. 28/PRT/M/2016)

PEKERJAAN :
LOKASI :

122 Jenis Pekerjaan : Pemasangan Jendela Tipe J13


Satuan Pembayaran : unit

Harga Total Harga


No. Uraian Kuantitas Satuan Jumlah
(Rp) (Rp)

A BAHAN
Kusen Aluminium 15.3800 m¹ 161,790.20 2,488,333.28
Jendela Kaca 0.96 x 0.7 2.0000 bh 504,171.36 1,008,342.72
Engsel Jendela 4.0000 bh 82,170.00 328,680.00
Handle Jendela 2.0000 bh 231,302.50 462,605.00
Grendel Jendela 2.0000 bh 53,652.50 107,305.00
Kait Angin Jendela 4.0000 bh 34,952.50 139,810.00

SUB JUMLAH A 4,535,076.00

B HARGA SATUAN PEKERJAAN 4,535,076.00

123 Jenis Pekerjaan : Pemasangan Jendela Tipe J14


Satuan Pembayaran : unit

Harga Total Harga


No. Uraian Kuantitas Satuan Jumlah
(Rp) (Rp)

A BAHAN
Kusen Aluminium 12.4800 m¹ 161,790.20 2,019,141.70
Kaca Bening 5 mm 1.8456 m² 152,286.75 281,060.43
Jendela Kaca 0.78 x 0.7 2.0000 bh 409,639.23 819,278.46
Engsel Jendela 4.0000 bh 82,170.00 328,680.00
Handle Jendela 2.0000 bh 231,302.50 462,605.00
Grendel Jendela 2.0000 bh 53,652.50 107,305.00
Kait Angin Jendela 4.0000 bh 34,952.50 139,810.00

SUB JUMLAH A 4,157,880.58

B HARGA SATUAN PEKERJAAN 4,157,880.58

124 Jenis Pekerjaan : Pemasangan Jendela Tipe J15a


Satuan Pembayaran : unit

Harga Total Harga


No. Uraian Kuantitas Satuan Jumlah
(Rp) (Rp)

A BAHAN
Kusen Aluminium 21.4400 m¹ 161,790.20 3,468,781.89
Kaca Bening 5 mm 2.1000 m² 152,286.75 319,802.18
Jendela Kaca 1.0 x 0.7 3.0000 bh 525,178.50 1,575,535.50
Jendela Kaca 0.86 x 0.7 3.0000 bh 451,653.51 1,354,960.53
Engsel Jendela 12.0000 bh 82,170.00 986,040.00
Handle Jendela 6.0000 bh 231,302.50 1,387,815.00
Grendel Jendela 6.0000 bh 53,652.50 321,915.00
Kait Angin Jendela 12.0000 bh 34,952.50 419,430.00

SUB JUMLAH A 9,834,280.09

B HARGA SATUAN PEKERJAAN 9,834,280.09

Halaman 59
ANALISA HARGA SATUAN PEKERJAAN
(Permen PUPR No. 28/PRT/M/2016)

PEKERJAAN :
LOKASI :

125 Jenis Pekerjaan : Pemasangan Jendela Tipe J15b


Satuan Pembayaran : unit

Harga Total Harga


No. Uraian Kuantitas Satuan Jumlah
(Rp) (Rp)

A BAHAN
Kusen Aluminium 21.4400 m¹ 161,790.20 3,468,781.89
Kaca Bening 5 mm 2.1000 m² 152,286.75 319,802.18
Jendela Kaca 1.0 x 0.7 3.0000 bh 525,178.50 1,575,535.50
Jendela Kaca 0.86 x 0.7 3.0000 bh 451,653.51 1,354,960.53
Engsel Jendela 12.0000 bh 82,170.00 986,040.00
Handle Jendela 6.0000 bh 231,302.50 1,387,815.00
Grendel Jendela 6.0000 bh 53,652.50 321,915.00
Kait Angin Jendela 12.0000 bh 34,952.50 419,430.00

SUB JUMLAH A 9,834,280.09

B HARGA SATUAN PEKERJAAN 9,834,280.09

126 Jenis Pekerjaan : Pemasangan Jendela Tipe J16a


Satuan Pembayaran : unit

Harga Total Harga


No. Uraian Kuantitas Satuan Jumlah
(Rp) (Rp)

A BAHAN
Kusen Aluminium 15.1400 m¹ 161,790.20 2,449,503.63
Kaca Bening 5 mm 1.9110 m² 152,286.75 291,019.98
Jendela Kaca 1.0 x 0.7 3.0000 bh 525,178.50 1,575,535.50
Engsel Jendela 6.0000 bh 82,170.00 493,020.00
Handle Jendela 3.0000 bh 231,302.50 693,907.50
Grendel Jendela 3.0000 bh 53,652.50 160,957.50
Kait Angin Jendela 6.0000 bh 34,952.50 209,715.00

SUB JUMLAH A 5,873,659.11

B HARGA SATUAN PEKERJAAN 5,873,659.11

127 Jenis Pekerjaan : Pemasangan Jendela Tipe J16b


Satuan Pembayaran : unit

Harga Total Harga


No. Uraian Kuantitas Satuan Jumlah
(Rp) (Rp)

A BAHAN
Kusen Aluminium 15.1400 m¹ 161,790.20 2,449,503.63
Kaca Bening 5 mm 1.9110 m² 152,286.75 291,019.98
Jendela Kaca 1.0 x 0.7 3.0000 bh 525,178.50 1,575,535.50
Engsel Jendela 6.0000 bh 82,170.00 493,020.00
Handle Jendela 3.0000 bh 231,302.50 693,907.50
Grendel Jendela 3.0000 bh 53,652.50 160,957.50
Kait Angin Jendela 6.0000 bh 34,952.50 209,715.00

SUB JUMLAH A 5,873,659.11

B HARGA SATUAN PEKERJAAN 5,873,659.11

Halaman 60
ANALISA HARGA SATUAN PEKERJAAN
(Permen PUPR No. 28/PRT/M/2016)

PEKERJAAN :
LOKASI :

128 Jenis Pekerjaan : Pemasangan Jendela Tipe J17


Satuan Pembayaran : unit

Harga Total Harga


No. Uraian Kuantitas Satuan Jumlah
(Rp) (Rp)

A BAHAN
Kusen Aluminium 16.0000 m¹ 161,790.20 2,588,643.20
Kaca Bening 5 mm 2.1000 m² 152,286.75 319,802.18
Jendela Kaca 0.5 x 0.7 3.0000 bh 262,589.25 787,767.75
Engsel Jendela 6.0000 bh 82,170.00 493,020.00
Handle Jendela 3.0000 bh 231,302.50 693,907.50
Grendel Jendela 3.0000 bh 53,652.50 160,957.50
Kait Angin Jendela 6.0000 bh 34,952.50 209,715.00

SUB JUMLAH A 5,253,813.13

B HARGA SATUAN PEKERJAAN 5,253,813.13

129 Jenis Pekerjaan : Pemasangan Jendela Tipe J18


Satuan Pembayaran : unit

Harga Total Harga


No. Uraian Kuantitas Satuan Jumlah
(Rp) (Rp)

A BAHAN
Kusen Aluminium 6.1000 m¹ 161,790.20 986,920.22
Kaca Bening 5 mm 0.3500 m² 152,286.75 53,300.36
Jendela Kaca 0.5 x 1.45 3.0000 bh 543,934.88 1,631,804.63
Engsel Jendela 2.0000 bh 82,170.00 164,340.00
Handle Jendela 1.0000 bh 231,302.50 231,302.50
Grendel Jendela 1.0000 bh 53,652.50 53,652.50
Kait Angin Jendela 2.0000 bh 34,952.50 69,905.00

SUB JUMLAH A 3,191,225.21

B HARGA SATUAN PEKERJAAN 3,191,225.21

130 Jenis Pekerjaan : Pemasangan Ventilasi Tipe V1


Satuan Pembayaran : unit

Harga Total Harga


No. Uraian Kuantitas Satuan Jumlah
(Rp) (Rp)

A BAHAN
Kusen Aluminium 12.5000 m¹ 161,790.20 2,022,377.50
Kaca Bening 5 mm 1.4000 m² 152,286.75 213,201.45
Jendela Kaca 1.0 x 0.7 2.0000 bh 525,178.50 1,050,357.00
Engsel Jendela 4.0000 bh 82,170.00 328,680.00
Handle Jendela 2.0000 bh 231,302.50 462,605.00
Grendel Jendela 2.0000 bh 53,652.50 107,305.00
Kait Angin Jendela 4.0000 bh 34,952.50 139,810.00

SUB JUMLAH A 4,324,335.95

B HARGA SATUAN PEKERJAAN 4,324,335.95

Halaman 61
ANALISA HARGA SATUAN PEKERJAAN
(Permen PUPR No. 28/PRT/M/2016)

PEKERJAAN :
LOKASI :

131 Jenis Pekerjaan : Pemasangan Ventilasi Tipe V2a


Satuan Pembayaran : unit

Harga Total Harga


No. Uraian Kuantitas Satuan Jumlah
(Rp) (Rp)

A BAHAN
Kusen Aluminium 9.3200 m¹ 161,790.20 1,507,884.66
Kaca Bening 5 mm 0.7000 m² 152,286.75 106,600.73
Jendela Kaca 1.0 x 0.7 1.0000 bh 525,178.50 525,178.50
Jendela Kaca 0.86 x 0.7 1.0000 bh 451,653.51 451,653.51
Engsel Jendela 4.0000 bh 82,170.00 328,680.00
Handle Jendela 2.0000 bh 231,302.50 462,605.00
Grendel Jendela 2.0000 bh 53,652.50 107,305.00
Kait Angin Jendela 4.0000 bh 34,952.50 139,810.00

SUB JUMLAH A 3,629,717.40

B HARGA SATUAN PEKERJAAN 3,629,717.40

132 Jenis Pekerjaan : Pemasangan Ventilasi Tipe V2b


Satuan Pembayaran : unit

Harga Total Harga


No. Uraian Kuantitas Satuan Jumlah
(Rp) (Rp)

A BAHAN
Kusen Aluminium 9.3200 m¹ 161,790.20 1,507,884.66
Kaca Bening 5 mm 0.7000 m² 152,286.75 106,600.73
Jendela Kaca 1.0 x 0.7 1.0000 bh 525,178.50 525,178.50
Jendela Kaca 0.86 x 0.7 1.0000 bh 451,653.51 451,653.51
Engsel Jendela 4.0000 bh 82,170.00 328,680.00
Handle Jendela 2.0000 bh 231,302.50 462,605.00
Grendel Jendela 2.0000 bh 53,652.50 107,305.00
Kait Angin Jendela 4.0000 bh 34,952.50 139,810.00

SUB JUMLAH A 3,629,717.40

B HARGA SATUAN PEKERJAAN 3,629,717.40

133 Jenis Pekerjaan : Pemasangan Ventilasi Tipe V2c


Satuan Pembayaran : unit

Harga Total Harga


No. Uraian Kuantitas Satuan Jumlah
(Rp) (Rp)

A BAHAN
Kusen Aluminium 9.3200 m¹ 161,790.20 1,507,884.66
Kaca Bening 5 mm 2.0020 m² 152,286.75 304,878.07

SUB JUMLAH A 1,812,762.74

B HARGA SATUAN PEKERJAAN 1,812,762.74

Halaman 62
ANALISA HARGA SATUAN PEKERJAAN
(Permen PUPR No. 28/PRT/M/2016)

PEKERJAAN :
LOKASI :

134 Jenis Pekerjaan : Pemasangan Ventilasi Tipe V3a


Satuan Pembayaran : unit

Harga Total Harga


No. Uraian Kuantitas Satuan Jumlah
(Rp) (Rp)

A BAHAN
Kusen Aluminium 6.5200 m¹ 161,790.20 1,054,872.10
Kaca Bening 5 mm 0.6370 m² 152,286.75 97,006.66
Jendela Kaca 1.0 x 0.7 1.0000 bh 525,178.50 525,178.50
Engsel Jendela 2.0000 bh 82,170.00 164,340.00
Handle Jendela 1.0000 bh 231,302.50 231,302.50
Grendel Jendela 1.0000 bh 53,652.50 53,652.50
Kait Angin Jendela 2.0000 bh 34,952.50 69,905.00

SUB JUMLAH A 2,196,257.26

B HARGA SATUAN PEKERJAAN 2,196,257.26

135 Jenis Pekerjaan : Pemasangan Ventilasi Tipe V3b


Satuan Pembayaran : unit

Harga Total Harga


No. Uraian Kuantitas Satuan Jumlah
(Rp) (Rp)

A BAHAN
Kusen Aluminium 6.5200 m¹ 161,790.20 1,054,872.10
Kaca Bening 5 mm 0.6370 m² 152,286.75 97,006.66
Jendela Kaca 1.0 x 0.7 1.0000 bh 525,178.50 525,178.50
Engsel Jendela 2.0000 bh 82,170.00 164,340.00
Handle Jendela 1.0000 bh 231,302.50 231,302.50
Grendel Jendela 1.0000 bh 53,652.50 53,652.50
Kait Angin Jendela 2.0000 bh 34,952.50 69,905.00

SUB JUMLAH A 2,196,257.26

B HARGA SATUAN PEKERJAAN 2,196,257.26

136 Jenis Pekerjaan : Pemasangan Ventilasi Tipe V4


Satuan Pembayaran : unit

Harga Total Harga


No. Uraian Kuantitas Satuan Jumlah
(Rp) (Rp)

A BAHAN
Kusen Aluminium 6.1400 m¹ 161,790.20 993,391.83
Jendela Kaca 0.86 x 0.7 2.0000 bh 451,653.51 903,307.02
Engsel Jendela 4.0000 bh 82,170.00 328,680.00
Handle Jendela 2.0000 bh 231,302.50 462,605.00
Grendel Jendela 2.0000 bh 53,652.50 107,305.00
Kait Angin Jendela 4.0000 bh 34,952.50 139,810.00

SUB JUMLAH A 2,935,098.85

B HARGA SATUAN PEKERJAAN 2,935,098.85

137 Jenis Pekerjaan : Pemasangan Ventilasi Tipe V5


Satuan Pembayaran : unit

Harga Total Harga


No. Uraian Kuantitas Satuan Jumlah
(Rp) (Rp)

A BAHAN
Kusen Aluminium 8.3000 m¹ 161,790.20 1,342,858.66
Kaca Bening 5 mm 1.6380 m² 152,286.75 249,445.70

SUB JUMLAH A 1,592,304.36

B HARGA SATUAN PEKERJAAN 1,592,304.36

Halaman 63
ANALISA HARGA SATUAN PEKERJAAN
(Permen PUPR No. 28/PRT/M/2016)

PEKERJAAN :
LOKASI :

138 Jenis Pekerjaan : Pemasangan Ventilasi Tipe V6


Satuan Pembayaran : unit

Harga Total Harga


No. Uraian Kuantitas Satuan Jumlah
(Rp) (Rp)

A BAHAN
Kusen Aluminium 3.5200 m¹ 161,790.20 569,501.50
Jendela Kaca 0.96 x 0.7 1.0000 bh 504,171.36 504,171.36
Engsel Jendela 2.0000 bh 82,170.00 164,340.00
Handle Jendela 1.0000 bh 231,302.50 231,302.50
Grendel Jendela 1.0000 bh 53,652.50 53,652.50
Kait Angin Jendela 2.0000 bh 34,952.50 69,905.00

SUB JUMLAH A 1,592,872.86

B HARGA SATUAN PEKERJAAN 1,592,872.86

139 Jenis Pekerjaan : Pemasangan Ventilasi Tipe V7


Satuan Pembayaran : unit

Harga Total Harga


No. Uraian Kuantitas Satuan Jumlah
(Rp) (Rp)

A BAHAN
Kusen Aluminium 6.7000 m¹ 161,790.20 1,083,994.34
Kaca Bening 5 mm 0.7000 m² 152,286.75 106,600.73
Jendela Kaca 1.0 x 0.7 1.0000 bh 525,178.50 525,178.50
Engsel Jendela 2.0000 bh 82,170.00 164,340.00
Handle Jendela 1.0000 bh 231,302.50 231,302.50
Grendel Jendela 1.0000 bh 53,652.50 53,652.50
Kait Angin Jendela 2.0000 bh 34,952.50 69,905.00

SUB JUMLAH A 2,234,973.57

B HARGA SATUAN PEKERJAAN 2,234,973.57

140 Jenis Pekerjaan : Pemasangan Ventilasi Tipe V8


Satuan Pembayaran : Pemasangan unit

Harga Total Harga


No. Uraian Kuantitas Satuan Jumlah
(Rp) (Rp)

A BAHAN
Kusen Aluminium 2.5200 m¹ 161,790.20 407,711.30
Jendela Kaca 0.46 x 0.7 1.0000 bh 241,582.11 241,582.11
Engsel Jendela 2.0000 bh 82,170.00 164,340.00
Handle Jendela 1.0000 bh 231,302.50 231,302.50
Grendel Jendela 1.0000 bh 53,652.50 53,652.50
Kait Angin Jendela 2.0000 bh 34,952.50 69,905.00

SUB JUMLAH A 1,168,493.41

B HARGA SATUAN PEKERJAAN 1,168,493.41

Halaman 64
ANALISA HARGA SATUAN PEKERJAAN
(Permen PUPR No. 28/PRT/M/2016)

PEKERJAAN :
LOKASI :

141 Jenis Pekerjaan : Pemasangan Ventilasi Tipe V9


Satuan Pembayaran : unit

Harga Total Harga


No. Uraian Kuantitas Satuan Jumlah
(Rp) (Rp)

A BAHAN
Kusen Aluminium 3.1000 m¹ 161,790.20 501,549.62
Jendela Kaca 0.8 x 0.65 1.0000 bh 420,142.80 420,142.80
Engsel Jendela 2.0000 bh 82,170.00 164,340.00
Handle Jendela 1.0000 bh 231,302.50 231,302.50
Grendel Jendela 1.0000 bh 53,652.50 53,652.50
Kait Angin Jendela 2.0000 bh 34,952.50 69,905.00

SUB JUMLAH A 1,440,892.42

B HARGA SATUAN PEKERJAAN 1,440,892.42

142 Jenis Pekerjaan : Pemasangan Ventilasi Tipe V10


Satuan Pembayaran : unit

Harga Total Harga


No. Uraian Kuantitas Satuan Jumlah
(Rp) (Rp)

A BAHAN
Kusen Aluminium 6.5200 m¹ 161,790.20 1,054,872.10
Kaca Bening 5 mm 1.3440 m² 152,286.75 204,673.39

SUB JUMLAH A 1,259,545.50

B HARGA SATUAN PEKERJAAN 1,259,545.50

143 Jenis Pekerjaan : Pemasangan Skylight Entrance


Satuan Pembayaran : unit

Harga Total Harga


No. Uraian Kuantitas Satuan Jumlah
(Rp) (Rp)

A BAHAN
Kusen Aluminium 73.9500 m¹ 161,790.20 11,964,385.29
Kaca Bening 5 mm 22.2836 m² 152,286.75 3,393,497.02

SUB JUMLAH A 15,357,882.31

B HARGA SATUAN PEKERJAAN 15,357,882.31

144 Jenis Pekerjaan : Pemasangan Partisi Tipe 1A


Satuan Pembayaran : unit

Harga Total Harga


No. Uraian Kuantitas Satuan Jumlah
(Rp) (Rp)

A BAHAN
Kusen Aluminium 25.2600 m¹ 161,790.20 4,086,820.45
Pintu Multiplek 12 mm 0.8 x 2.05 1.0000 bh -
Kaca Bening 5 mm 8.3150 m² 152,286.75 1,266,264.33
Stiker Kaca Buram 2.8200 m² 32,000.00 90,240.00
Engsel Pintu 3.0000 bh 112,810.50 338,431.50
Handle Pintu 1.0000 bh 174,982.50 174,982.50
Kunci Pintu 1.0000 bh 418,687.50 418,687.50

SUB JUMLAH A 6,375,426.28

B HARGA SATUAN PEKERJAAN 6,375,426.28

Halaman 65
ANALISA HARGA SATUAN PEKERJAAN
(Permen PUPR No. 28/PRT/M/2016)

PEKERJAAN :
LOKASI :

145 Jenis Pekerjaan : Pemasangan Partisi Tipe 1B


Satuan Pembayaran : unit

Harga Total Harga


No. Uraian Kuantitas Satuan Jumlah
(Rp) (Rp)

A BAHAN
Kusen Aluminium 21.3300 m¹ 161,790.20 3,450,984.97
Pintu Kaca Tempered 12 mm 0.9 x 2.05 1.0000 bh 454,191.95 454,191.95
Kaca Bening 5 mm 9.3975 m² 152,286.75 1,431,114.73
Stiker Kaca Buram 2.8263 m² 32,000.00 90,442.08
Engsel Pintu Kaca Tempered 2.0000 bh 549,510.50 1,099,021.00
Handle Pintu 1.0000 bh 174,982.50 174,982.50
Kunci Pintu 1.0000 bh 418,687.50 418,687.50

SUB JUMLAH A 7,119,424.73

B HARGA SATUAN PEKERJAAN 7,119,424.73

146 Jenis Pekerjaan : Pemasangan Partisi Tipe 1C


Satuan Pembayaran : unit

Harga Total Harga


No. Uraian Kuantitas Satuan Jumlah
(Rp) (Rp)

A BAHAN
Kusen Aluminium 14.1000 m¹ 161,790.20 2,281,241.82
Kaca Bening 5 mm 4.5100 m² 152,286.75 686,813.24
Stiker Kaca Buram 1.6500 m² 32,000.00 52,800.00

SUB JUMLAH A 3,020,855.06

B HARGA SATUAN PEKERJAAN 3,020,855.06

147 Jenis Pekerjaan : Pemasangan Partisi Tipe 1D


Satuan Pembayaran : unit

Harga Total Harga


No. Uraian Kuantitas Satuan Jumlah
(Rp) (Rp)

A BAHAN
Kusen Aluminium 33.2200 m¹ 161,790.20 5,374,670.44
Pintu Kaca Tempered 12 mm 0.7 x 2.05 2.0000 bh 353,260.41 706,520.82
Kaca Bening 5 mm 21.5000 m² 152,286.75 3,274,165.13
Stiker Kaca Buram 5.5000 m² 32,000.00 176,000.00
Engsel Pintu Kaca Tempered 4.0000 bh 549,510.50 2,198,042.00
Handle Pintu 2.0000 bh 174,982.50 349,965.00
Kunci Pintu 2.0000 bh 418,687.50 837,375.00

SUB JUMLAH A 12,916,738.38

B HARGA SATUAN PEKERJAAN 12,916,738.38

Halaman 66
ANALISA HARGA SATUAN PEKERJAAN
(Permen PUPR No. 28/PRT/M/2016)

PEKERJAAN :
LOKASI :

148 Jenis Pekerjaan : Pemasangan Partisi Tipe 1E


Satuan Pembayaran : unit

Harga Total Harga


No. Uraian Kuantitas Satuan Jumlah
(Rp) (Rp)

A BAHAN
Kusen Aluminium 21.3300 m¹ 161,790.20 3,450,984.97
Pintu Kaca Tempered 12 mm 0.9 x 2.05 1.0000 bh 454,191.95 454,191.95
Kaca Bening 5 mm 9.3975 m² 152,286.75 1,431,114.73
Stiker Kaca Buram 2.8263 m² 32,000.00 90,442.08
Engsel Pintu Kaca Tempered 2.0000 bh 549,510.50 1,099,021.00
Handle Pintu 1.0000 bh 174,982.50 174,982.50
Kunci Pintu 1.0000 bh 418,687.50 418,687.50

SUB JUMLAH A 7,119,424.73

B HARGA SATUAN PEKERJAAN 7,119,424.73

149 Jenis Pekerjaan : Pemasangan Partisi Tipe 1F


Satuan Pembayaran : unit

Harga Total Harga


No. Uraian Kuantitas Satuan Jumlah
(Rp) (Rp)

A BAHAN
Kusen Aluminium 12.3000 m¹ 161,790.20 1,990,019.46
Kaca Bening 5 mm 4.2350 m² 152,286.75 644,934.39
Stiker Kaca Buram 1.5500 m² 32,000.00 49,600.00

SUB JUMLAH A 2,684,553.85

B HARGA SATUAN PEKERJAAN 2,684,553.85

150 Jenis Pekerjaan : Pemasangan Partisi Tipe 1G


Satuan Pembayaran : unit

Harga Total Harga


No. Uraian Kuantitas Satuan Jumlah
(Rp) (Rp)

A BAHAN
Kusen Aluminium 27.5500 m¹ 161,790.20 4,457,320.01
Kaca Bening 5 mm 11.2200 m² 152,286.75 1,708,657.34
Stiker Kaca Buram 4.1000 m² 32,000.00 131,200.00

SUB JUMLAH A 6,297,177.35

B HARGA SATUAN PEKERJAAN 6,297,177.35

151 Jenis Pekerjaan : Pemasangan Partisi Tipe 1H


Satuan Pembayaran : unit

Harga Total Harga


No. Uraian Kuantitas Satuan Jumlah
(Rp) (Rp)

A BAHAN
Kusen Aluminium 16.0500 m¹ 161,790.20 2,596,732.71
Pintu Kaca Tempered 12 mm 0.8 x 2.05 1.0000 bh 403,726.18 403,726.18
Kaca Bening 5 mm 3.4475 m² 152,286.75 525,008.57
Stiker Kaca Buram 1.8500 m² 32,000.00 59,200.00
Engsel Pintu Kaca Tempered 2.0000 bh 549,510.50 1,099,021.00
Handle Pintu 1.0000 bh 174,982.50 174,982.50
Kunci Pintu 1.0000 bh 418,687.50 418,687.50

SUB JUMLAH A 5,277,358.46

B HARGA SATUAN PEKERJAAN 5,277,358.46

152 Jenis Pekerjaan : Pemasangan Partisi Tipe 1I


Halaman 67
ANALISA HARGA SATUAN PEKERJAAN
(Permen PUPR No. 28/PRT/M/2016)

PEKERJAAN :
LOKASI :

Satuan Pembayaran : unit

Harga Total Harga


No. Uraian Kuantitas Satuan Jumlah
(Rp) (Rp)

A BAHAN
Kusen Aluminium 27.6000 m¹ 161,790.20 4,465,409.52
Kaca Bening 5 mm 8.7725 m² 152,286.75 1,335,935.51
Stiker Kaca Buram 2.9968 m² 32,000.00 95,897.60

SUB JUMLAH A 5,897,242.63

B HARGA SATUAN PEKERJAAN 5,897,242.63

153 Jenis Pekerjaan : Pemasangan Partisi Tipe 1J


Satuan Pembayaran : unit

Harga Total Harga


No. Uraian Kuantitas Satuan Jumlah
(Rp) (Rp)

A BAHAN
Kusen Aluminium 15.4200 m¹ 161,790.20 2,494,804.88
Pintu Kaca Tempered 12 mm 0.9 x 2.05 1.0000 bh 454,191.95 454,191.95
Kaca Bening 5 mm 3.7650 m² 152,286.75 573,359.61
Stiker Kaca Buram 2.0350 m² 32,000.00 65,120.00
Engsel Pintu Kaca Tempered 2.0000 bh 549,510.50 1,099,021.00
Handle Pintu 1.0000 bh 174,982.50 174,982.50
Kunci Pintu 1.0000 bh 418,687.50 418,687.50

SUB JUMLAH A 5,280,167.45

B HARGA SATUAN PEKERJAAN 5,280,167.45

154 Jenis Pekerjaan : Pemasangan Partisi Tipe 1K dan Backdrop Ukuran 6.5 x 2.9 m
Satuan Pembayaran : unit

Harga Total Harga


No. Uraian Kuantitas Satuan Jumlah
(Rp) (Rp)

A BAHAN
Kusen Aluminium 106.6200 m¹ 161,790.20 17,250,071.12
Kaca Bening 5 mm 33.9735 m² 152,286.75 5,173,713.90
Stiker Kaca Buram 33.9735 m² 32,000.00 1,087,152.00
Backdrop uk. 6.5 x 2.9 1.0000 ls 14,137,500.00 14,137,500.00

SUB JUMLAH A 37,648,437.03

B HARGA SATUAN PEKERJAAN 37,648,437.03

155 Jenis Pekerjaan : Pemasangan Partisi Tipe 1L


Satuan Pembayaran : unit

Harga Total Harga


No. Uraian Kuantitas Satuan Jumlah
(Rp) (Rp)

A BAHAN
Kusen Aluminium 131.6400 m¹ 161,790.20 21,298,061.93
Pintu Kaca Tempered 12 mm 0.9 x 2.05 1.0000 bh 454,191.95 454,191.95
Kaca Bening 5 mm 57.8300 m² 152,286.75 8,806,742.75
Stiker Kaca Buram 4.0302 m² 32,000.00 128,966.40
Engsel Pintu Kaca Tempered 2.0000 bh 549,510.50 1,099,021.00
Handle Pintu 1.0000 bh 174,982.50 174,982.50
Kunci Pintu 1.0000 bh 418,687.50 418,687.50

SUB JUMLAH A 32,380,654.03

B HARGA SATUAN PEKERJAAN 32,380,654.03

156 Jenis Pekerjaan : Pemasangan Partisi Tipe 1M


Halaman 68
ANALISA HARGA SATUAN PEKERJAAN
(Permen PUPR No. 28/PRT/M/2016)

PEKERJAAN :
LOKASI :

Satuan Pembayaran : unit

Harga Total Harga


No. Uraian Kuantitas Satuan Jumlah
(Rp) (Rp)

A BAHAN
Kusen Aluminium 13.5880 m¹ 161,790.20 2,198,405.24
Pintu Kaca Tempered 12 mm 0.75 x 2.05 4.0000 bh 378,493.29 1,513,973.18
Kaca Bening 5 mm 30.0100 m² 152,286.75 4,570,125.37
Stiker Kaca Buram 13.2990 m² 32,000.00 425,568.00
Engsel Pintu Kaca Tempered 8.0000 bh 549,510.50 4,396,084.00
Handle Pintu 4.0000 bh 174,982.50 699,930.00
Kunci Pintu 4.0000 bh 418,687.50 1,674,750.00

SUB JUMLAH A 15,478,835.78

B HARGA SATUAN PEKERJAAN 15,478,835.78

157 Jenis Pekerjaan : Pemasangan Partisi Tipe 1N


Satuan Pembayaran : unit

Harga Total Harga


No. Uraian Kuantitas Satuan Jumlah
(Rp) (Rp)

A BAHAN
Kusen Aluminium 21.3200 m¹ 161,790.20 3,449,367.06
Kaca Bening 5 mm 8.3325 m² 152,286.75 1,268,929.34
Stiker Kaca Buram 3.0000 m² 32,000.00 96,000.00

SUB JUMLAH A 4,814,296.41

B HARGA SATUAN PEKERJAAN 4,814,296.41

158 Jenis Pekerjaan : Pemasangan Partisi Tipe 1O


Satuan Pembayaran : Pemasangan unit

Harga Total Harga


No. Uraian Kuantitas Satuan Jumlah
(Rp) (Rp)

A BAHAN
Kusen Aluminium 22.2100 m¹ 161,790.20 3,593,360.34
Pintu Kaca Tempered 12 mm 0.9 x 2.05 1.0000 bh 454,191.95 454,191.95
Kaca Bening 5 mm 13.0325 m² 152,286.75 1,984,677.07
Stiker Kaca Buram 6.1030 m² 32,000.00 195,296.00
Engsel Pintu Kaca Tempered 2.0000 bh 549,510.50 1,099,021.00
Handle Pintu 1.0000 bh 174,982.50 174,982.50
Kunci Pintu 1.0000 bh 418,687.50 418,687.50

SUB JUMLAH A 7,920,216.36

B HARGA SATUAN PEKERJAAN 7,920,216.36

159 Jenis Pekerjaan : Pemasangan Partisi Tipe 1P


Satuan Pembayaran : unit

Harga Total Harga


No. Uraian Kuantitas Satuan Jumlah
(Rp) (Rp)

A BAHAN
Kusen Aluminium 20.5700 m¹ 161,790.20 3,328,024.41
Kaca Bening 5 mm 7.3425 m² 152,286.75 1,118,165.46
Stiker Kaca Buram 2.6850 m² 32,000.00 85,920.00

SUB JUMLAH A 4,532,109.88

B HARGA SATUAN PEKERJAAN 4,532,109.88

160 Jenis Pekerjaan : Pemasangan Partisi Tipe 1Q


Satuan Pembayaran : unit
Halaman 69
ANALISA HARGA SATUAN PEKERJAAN
(Permen PUPR No. 28/PRT/M/2016)

PEKERJAAN :
LOKASI :

Harga Total Harga


No. Uraian Kuantitas Satuan Jumlah
(Rp) (Rp)

A BAHAN
Kusen Aluminium 9.7500 m¹ 161,790.20 1,577,454.45
Pintu Kaca Tempered 12 mm 0.9 x 2.05 1.0000 bh 454,191.95 454,191.95
Kaca Bening 5 mm 3.2425 m² 152,286.75 493,789.79
Stiker Kaca Buram 1.2236 m² 32,000.00 39,156.64
Engsel Pintu Kaca Tempered 2.0000 bh 549,510.50 1,099,021.00
Handle Pintu 1.0000 bh 174,982.50 174,982.50
Kunci Pintu 1.0000 bh 418,687.50 418,687.50

SUB JUMLAH A 4,257,283.83

B HARGA SATUAN PEKERJAAN 4,257,283.83

161 Jenis Pekerjaan : Pemasangan Partisi Tipe 1R


Satuan Pembayaran : unit

Harga Total Harga


No. Uraian Kuantitas Satuan Jumlah
(Rp) (Rp)

A BAHAN
Kusen Aluminium 37.5400 m¹ 161,790.20 6,073,604.11
Pintu Kaca Tempered 12 mm 0.9 x 2.05 1.0000 bh 454,191.95 454,191.95
Kaca Bening 5 mm 17.0750 m² 152,286.75 2,600,296.26
Stiker Kaca Buram 6.8750 m² 32,000.00 220,000.00
Engsel Pintu Kaca Tempered 2.0000 bh 549,510.50 1,099,021.00
Handle Pintu 2.0000 bh 174,982.50 349,965.00
Kunci Pintu 1.0000 bh 418,687.50 418,687.50

SUB JUMLAH A 11,215,765.82

B HARGA SATUAN PEKERJAAN 11,215,765.82

162 Jenis Pekerjaan : Pemasangan Partisi Tipe 1S


Satuan Pembayaran : unit

Harga Total Harga


No. Uraian Kuantitas Satuan Jumlah
(Rp) (Rp)

A BAHAN
Kusen Aluminium 34.8900 m¹ 161,790.20 5,644,860.08
Kaca Bening 5 mm 14.8500 m² 152,286.75 2,261,458.24
Stiker Kaca Buram 5.4250 m² 32,000.00 173,600.00

SUB JUMLAH A 8,079,918.32

B HARGA SATUAN PEKERJAAN 8,079,918.32

Halaman 70
ANALISA HARGA SATUAN PEKERJAAN
(Permen PUPR No. 28/PRT/M/2016)

PEKERJAAN :
LOKASI :

163 Jenis Pekerjaan : Pemasangan Partisi Tipe 1T


Satuan Pembayaran : unit

Harga Total Harga


No. Uraian Kuantitas Satuan Jumlah
(Rp) (Rp)

A BAHAN
Kusen Aluminium 43.6000 m¹ 161,790.20 7,054,052.72
Pintu Kaca Tempered 12 mm 0.9 x 2.05 1.0000 bh 454,191.95 454,191.95
Kaca Bening 5 mm 13.8300 m² 152,286.75 2,106,125.75
Stiker Kaca Buram 5.7225 m² 32,000.00 183,120.00
Engsel Pintu Kaca Tempered 2.0000 bh 549,510.50 1,099,021.00
Handle Pintu 1.0000 bh 174,982.50 174,982.50
Kunci Pintu 1.0000 bh 418,687.50 418,687.50

SUB JUMLAH A 11,490,181.43

B HARGA SATUAN PEKERJAAN 11,490,181.43

164 Jenis Pekerjaan : Pemasangan Partisi Tipe 1U


Satuan Pembayaran : unit

Harga Total Harga


No. Uraian Kuantitas Satuan Jumlah
(Rp) (Rp)

A BAHAN
Kusen Aluminium 43.6000 m¹ 161,790.20 7,054,052.72
Pintu Kaca Tempered 12 mm 0.9 x 2.05 1.0000 bh 454,191.95 454,191.95
Kaca Bening 5 mm 13.8300 m² 152,286.75 2,106,125.75
Stiker Kaca Buram 5.7225 m² 32,000.00 183,120.00
Engsel Pintu Kaca Tempered 2.0000 bh 549,510.50 1,099,021.00
Handle Pintu 1.0000 bh 174,982.50 174,982.50
Kunci Pintu 1.0000 bh 418,687.50 418,687.50

SUB JUMLAH A 11,490,181.43

B HARGA SATUAN PEKERJAAN 11,490,181.43

165 Jenis Pekerjaan : Pemasangan Partisi Tipe 1V


Satuan Pembayaran : unit

Harga Total Harga


No. Uraian Kuantitas Satuan Jumlah
(Rp) (Rp)

A BAHAN
Kusen Aluminium 20.1900 m¹ 161,790.20 3,266,544.14
Kaca Bening 5 mm 9.6525 m² 152,286.75 1,469,947.85
Stiker Kaca Buram 3.5250 m² 32,000.00 112,800.00

SUB JUMLAH A 4,849,291.99

B HARGA SATUAN PEKERJAAN 4,849,291.99

166 Jenis Pekerjaan : Pemasangan Partisi Tipe 2A


Satuan Pembayaran : unit

Harga Total Harga


No. Uraian Kuantitas Satuan Jumlah
(Rp) (Rp)

A BAHAN
Kusen Aluminium 33.9000 m¹ 161,790.20 5,484,687.78
Kaca Bening 5 mm 14.3000 m² 152,286.75 2,177,700.53
Stiker Kaca Buram 5.2000 m² 32,000.00 166,400.00

SUB JUMLAH A 7,828,788.31

B HARGA SATUAN PEKERJAAN 7,828,788.31

167 Jenis Pekerjaan : Pemasangan Partisi Tipe 2B


Halaman 71
ANALISA HARGA SATUAN PEKERJAAN
(Permen PUPR No. 28/PRT/M/2016)

PEKERJAAN :
LOKASI :

Satuan Pembayaran : unit

Harga Total Harga


No. Uraian Kuantitas Satuan Jumlah
(Rp) (Rp)

A BAHAN
Kusen Aluminium 38.2700 m¹ 161,790.20 6,191,710.95
Kaca Bening 5 mm 15.4825 m² 152,286.75 2,357,779.61
Stiker Kaca Buram 5.6350 m² 32,000.00 180,320.00

SUB JUMLAH A 8,729,810.56

B HARGA SATUAN PEKERJAAN 8,729,810.56

168 Jenis Pekerjaan : Pemasangan Partisi Tipe 2C


Satuan Pembayaran : unit

Harga Total Harga


No. Uraian Kuantitas Satuan Jumlah
(Rp) (Rp)

A BAHAN
Kusen Aluminium 37.6000 m¹ 161,790.20 6,083,311.52
Pintu Kaca Tempered 12 mm 0.9 x 2.05 1.0000 bh 454,191.95 454,191.95
Pintu Kaca Tempered 12 mm 0.8 x 2.05 1.0000 bh 403,726.18 403,726.18
Kaca Bening 5 mm 10.2650 m² 152,286.75 1,563,223.49
Stiker Kaca Buram 5.0000 m² 32,000.00 160,000.00
Engsel Pintu Kaca Tempered 4.0000 bh 549,510.50 2,198,042.00
Handle Pintu 2.0000 bh 174,982.50 349,965.00
Kunci Pintu 2.0000 bh 418,687.50 837,375.00

SUB JUMLAH A 12,049,835.14

B HARGA SATUAN PEKERJAAN 12,049,835.14

169 Jenis Pekerjaan : Pemasangan Partisi Tipe 2D


Satuan Pembayaran : unit

Harga Total Harga


No. Uraian Kuantitas Satuan Jumlah
(Rp) (Rp)

A BAHAN
Kusen Aluminium 44.5000 m¹ 161,790.20 7,199,663.90
Pintu Kaca Tempered 12 mm 0.9 x 2.05 1.0000 bh 454,191.95 454,191.95
Kaca Bening 5 mm 17.4050 m² 152,286.75 2,650,550.88
Stiker Kaca Buram 7.0000 m² 32,000.00 224,000.00
Engsel Pintu Kaca Tempered 2.0000 bh 549,510.50 1,099,021.00
Handle Pintu 1.0000 bh 174,982.50 174,982.50
Kunci Pintu 1.0000 bh 418,687.50 418,687.50

SUB JUMLAH A 12,221,097.74

B HARGA SATUAN PEKERJAAN 12,221,097.74

Halaman 72
ANALISA HARGA SATUAN PEKERJAAN
(Permen PUPR No. 28/PRT/M/2016)

PEKERJAAN :
LOKASI :

170 Jenis Pekerjaan : Pemasangan Partisi Tipe 2E


Satuan Pembayaran : unit

Harga Total Harga


No. Uraian Kuantitas Satuan Jumlah
(Rp) (Rp)

A BAHAN
Kusen Aluminium 37.4200 m¹ 161,790.20 6,054,189.28
Pintu Kaca Tempered 12 mm 0.8 x 2.05 1.0000 bh 403,726.18 403,726.18
Kaca Bening 5 mm 13.5675 m² 152,286.75 2,066,150.48
Stiker Kaca Buram 5.5395 m² 32,000.00 177,264.00
Engsel Pintu Kaca Tempered 2.0000 bh 549,510.50 1,099,021.00
Handle Pintu 1.0000 bh 174,982.50 174,982.50
Kunci Pintu 1.0000 bh 418,687.50 418,687.50

SUB JUMLAH A 10,394,020.94

B HARGA SATUAN PEKERJAAN 10,394,020.94

171 Jenis Pekerjaan : Pemasangan Partisi Tipe 2F


Satuan Pembayaran : unit

Harga Total Harga


No. Uraian Kuantitas Satuan Jumlah
(Rp) (Rp)

A BAHAN
Kusen Aluminium 20.7000 m¹ 161,790.20 3,349,057.14
Kaca Bening 5 mm 5.6925 m² 152,286.75 866,892.32
Stiker Kaca Buram 1.9700 m² 32,000.00 63,040.00

SUB JUMLAH A 4,278,989.46

B HARGA SATUAN PEKERJAAN 4,278,989.46

172 Jenis Pekerjaan : Pemasangan Partisi Tipe 2G


Satuan Pembayaran : unit

Harga Total Harga


No. Uraian Kuantitas Satuan Jumlah
(Rp) (Rp)

A BAHAN
Kusen Aluminium 20.7000 m¹ 161,790.20 3,349,057.14
Kaca Bening 5 mm 5.6925 m² 152,286.75 866,892.32
Stiker Kaca Buram 1.9700 m² 32,000.00 63,040.00

SUB JUMLAH A 4,278,989.46

B HARGA SATUAN PEKERJAAN 4,278,989.46

173 Jenis Pekerjaan : Pemasangan Partisi Tipe 2H


Satuan Pembayaran : unit

Harga Total Harga


No. Uraian Kuantitas Satuan Jumlah
(Rp) (Rp)

A BAHAN
Kusen Aluminium 37.4200 m¹ 161,790.20 6,054,189.28
Pintu Kaca Tempered 12 mm 0.8 x 2.05 1.0000 bh 403,726.18 403,726.18
Kaca Bening 5 mm 13.5675 m² 152,286.75 2,066,150.48
Stiker Kaca Buram 5.5395 m² 32,000.00 177,264.00
Engsel Pintu Kaca Tempered 2.0000 bh 549,510.50 1,099,021.00
Handle Pintu 1.0000 bh 174,982.50 174,982.50
Kunci Pintu 1.0000 bh 418,687.50 418,687.50

SUB JUMLAH A 10,394,020.94

B HARGA SATUAN PEKERJAAN 10,394,020.94

174 Jenis Pekerjaan : Pemasangan Partisi Tipe 2I


Halaman 73
ANALISA HARGA SATUAN PEKERJAAN
(Permen PUPR No. 28/PRT/M/2016)

PEKERJAAN :
LOKASI :

Satuan Pembayaran : unit

Harga Total Harga


No. Uraian Kuantitas Satuan Jumlah
(Rp) (Rp)

A BAHAN
Kusen Aluminium 44.5000 m¹ 161,790.20 7,199,663.90
Pintu Kaca Tempered 12 mm 0.9 x 2.05 1.0000 bh 454,191.95 454,191.95
Kaca Bening 5 mm 17.4050 m² 152,286.75 2,650,550.88
Stiker Kaca Buram 7.0000 m² 32,000.00 224,000.00
Engsel Pintu Kaca Tempered 2.0000 bh 549,510.50 1,099,021.00
Handle Pintu 1.0000 bh 174,982.50 174,982.50
Kunci Pintu 1.0000 bh 418,687.50 418,687.50

SUB JUMLAH A 12,221,097.74

B HARGA SATUAN PEKERJAAN 12,221,097.74

175 Jenis Pekerjaan : Pemasangan Partisi Tipe 2J


Satuan Pembayaran : unit

Harga Total Harga


No. Uraian Kuantitas Satuan Jumlah
(Rp) (Rp)

A BAHAN
Kusen Aluminium 29.4000 m¹ 161,790.20 4,756,631.88
Pintu Kaca Tempered 12 mm 0.75 x 2.05 2.0000 bh 378,493.29 756,986.59
Kaca Bening 5 mm 11.1550 m² 152,286.75 1,698,758.70
Stiker Kaca Buram 6.4600 m² 32,000.00 206,720.00
Engsel Pintu Kaca Tempered 4.0000 bh 549,510.50 2,198,042.00
Handle Pintu 2.0000 bh 174,982.50 349,965.00
Kunci Pintu 2.0000 bh 418,687.50 837,375.00

SUB JUMLAH A 10,804,479.16

B HARGA SATUAN PEKERJAAN 10,804,479.16

176 Jenis Pekerjaan : Pemasangan Partisi Tipe 2K


Satuan Pembayaran : unit

Harga Total Harga


No. Uraian Kuantitas Satuan Jumlah
(Rp) (Rp)

A BAHAN
Kusen Aluminium 15.3700 m¹ 161,790.20 2,486,715.37
Pintu Kaca Tempered 12 mm 0.75 x 2.05 2.0000 bh 378,493.29 756,986.59
Kaca Bening 5 mm 6.4950 m² 152,286.75 989,102.44
Stiker Kaca Buram 3.4854 m² 32,000.00 111,532.80
Engsel Pintu Kaca Tempered 4.0000 bh 549,510.50 2,198,042.00
Handle Pintu 2.0000 bh 174,982.50 349,965.00
Kunci Pintu 2.0000 bh 418,687.50 837,375.00

SUB JUMLAH A 7,729,719.20

B HARGA SATUAN PEKERJAAN 7,729,719.20

Halaman 74
ANALISA HARGA SATUAN PEKERJAAN
(Permen PUPR No. 28/PRT/M/2016)

PEKERJAAN :
LOKASI :

177 Jenis Pekerjaan : Pemasangan Partisi Double Multiplek 6 mm Rangka Multiplek 18 mm Fin. HPL Tipe A
Satuan Pembayaran : unit

Harga Total Harga


No. Uraian Kuantitas Satuan Jumlah
(Rp) (Rp)

A BAHAN
Partisi Double Multiplek 4.4100 m² 502,953.00 2,218,022.73
Kaca Bening 5 mm 0.6600 m² 152,286.75 100,509.26

SUB JUMLAH A 2,318,531.99

B HARGA SATUAN PEKERJAAN 2,318,531.99

178 Jenis Pekerjaan : Pemasangan Partisi Double Multiplek 6 mm Rangka Multiplek 18 mm Fin. HPL Tipe B
Satuan Pembayaran : unit

Harga Total Harga


No. Uraian Kuantitas Satuan Jumlah
(Rp) (Rp)

A BAHAN
Partisi Double Multiplek 5.4000 m² 502,953.00 2,715,946.20
Kaca Bening 5 mm 0.8250 m² 152,286.75 125,636.57

SUB JUMLAH A 2,841,582.77

B HARGA SATUAN PEKERJAAN 2,841,582.77

179 Jenis Pekerjaan : Pemasangan Partisi Double Multiplek 6 mm Rangka Multiplek 18 mm Fin. HPL Tipe C
Satuan Pembayaran : unit

Harga Total Harga


No. Uraian Kuantitas Satuan Jumlah
(Rp) (Rp)

A BAHAN
Partisi Double Multiplek 6.3360 m² 502,953.00 3,186,710.21
Kaca Bening 5 mm 0.9810 m² 152,286.75 149,393.30

SUB JUMLAH A 3,336,103.51

B HARGA SATUAN PEKERJAAN 3,336,103.51

180 Jenis Pekerjaan : Pemasangan Partisi Double Multiplek 6 mm Rangka Multiplek 18 mm Fin. HPL Tipe D
Satuan Pembayaran : unit

Harga Total Harga


No. Uraian Kuantitas Satuan Jumlah
(Rp) (Rp)

A BAHAN
Partisi Double Multiplek 4.2480 m² 502,953.00 2,136,544.34
Kaca Bening 5 mm 0.6330 m² 152,286.75 96,397.51

SUB JUMLAH A 2,232,941.86

B HARGA SATUAN PEKERJAAN 2,232,941.86

Halaman 75
ANALISA HARGA SATUAN PEKERJAAN
(Permen PUPR No. 28/PRT/M/2016)

PEKERJAAN :
LOKASI :

181 Jenis Pekerjaan : Pemasangan Partisi Double Multiplek 6 mm Rangka Multiplek 18 mm Fin. HPL Tipe E
Satuan Pembayaran : unit

Harga Total Harga


No. Uraian Kuantitas Satuan Jumlah
(Rp) (Rp)

A BAHAN
Partisi Double Multiplek 5.4000 m² 502,953.00 2,715,946.20
Kaca Bening 5 mm 0.8400 m² 152,286.75 127,920.87

SUB JUMLAH A 2,843,867.07

B HARGA SATUAN PEKERJAAN 2,843,867.07

182 Jenis Pekerjaan : Pemasangan Partisi Double Multiplek 6 mm Rangka Multiplek 18 mm Fin. HPL Tipe F
Satuan Pembayaran : unit

Harga Total Harga


No. Uraian Kuantitas Satuan Jumlah
(Rp) (Rp)

A BAHAN
Partisi Double Multiplek 4.3920 m² 502,953.00 2,208,969.58
Kaca Bening 5 mm 0.6570 m² 152,286.75 100,052.39

SUB JUMLAH A 2,309,021.97

B HARGA SATUAN PEKERJAAN 2,309,021.97

183 Jenis Pekerjaan : Rangka Atap Baja Ringan


Satuan Pembayaran : m2
Standar : -

Harga Total Harga


No. Uraian Kuantitas Satuan Jumlah
(Rp) (Rp)

B TENAGA
Biaya Pemasangan 1.000 ls 25,000.00 25,000.00

SUB JUMLAH A 25,000.00

B BAHAN
Rangka Atap Baja Ringan 1.000 m² 125,000.00 125,000.00
termasuk aksesoris

SUB JUMLAH B 125,000.00

C PERALATAN
-

SUB JUMLAH C -

D JUMLAH (A+B+C) 150,000.00


E Overhead & Profit 10% x D 15,000.00
F HARGA SATUAN PEKERJAAN 165,000.00

Halaman 76
ANALISA HARGA SATUAN PEKERJAAN
(Permen PUPR No. 28/PRT/M/2016)

PEKERJAAN :
LOKASI :

184 Jenis Pekerjaan : Pemasangan 1 m2 Genteng Metal Atap Pelana


Satuan Pembayaran : m2
Standar : A.4.5.2.32

Harga Total Harga


No. Uraian Kuantitas Satuan Jumlah
(Rp) (Rp)

B TENAGA
Pekerja 0.200 Org/ Hr 75,000.00 15,000.00
Tukang 0.100 Org/ Hr 80,000.00 8,000.00
Kepala Tukang 0.010 Org/ Hr 90,000.00 900.00
Mandor 0.001 Org/ Hr 100,000.00 100.00

SUB JUMLAH A 24,000.00

B BAHAN
Atap Genteng Metal 0.35 mm 1.300 bh 95,000.00 123,500.00
Paku Biasa 2" - 5" 0.200 kg 15,000.00 3,000.00

SUB JUMLAH B 126,500.00

C PERALATAN
-

SUB JUMLAH C -

D JUMLAH (A+B+C) 150,500.00


E Overhead & Profit 10% x D 15,050.00
F HARGA SATUAN PEKERJAAN 165,550.00

185 Jenis Pekerjaan : Pemasangan 1 m2 Atap Bitumen Selulosa t = 3 mm


Satuan Pembayaran : m2
Standar : -

Harga Total Harga


No. Uraian Kuantitas Satuan Jumlah
(Rp) (Rp)

B TENAGA
Pekerja 0.140 Org/ Hr 75,000.00 10,500.00
Tukang 0.070 Org/ Hr 80,000.00 5,600.00
Kepala Tukang 0.007 Org/ Hr 90,000.00 630.00
Mandor 0.007 Org/ Hr 100,000.00 700.00

SUB JUMLAH A 17,430.00

B BAHAN
Atap Bitumen Selulosa 40 x 106 cm, t = 3.390 lbr 48,000.00 162,720.00
Sekrup Atap Bitumen 16.900 bh 1,200.00 20,280.00

SUB JUMLAH B 183,000.00

C PERALATAN
-

SUB JUMLAH C -

D JUMLAH (A+B+C) 200,430.00


E Overhead & Profit 15% x D 30,064.50
F HARGA SATUAN PEKERJAAN 230,494.50

Halaman 77
ANALISA HARGA SATUAN PEKERJAAN
(Permen PUPR No. 28/PRT/M/2016)

PEKERJAAN :
LOKASI :

186 Jenis Pekerjaan : Pemasangan 1 m1 Nok Genteng Metal


Satuan Pembayaran : m1
Standar : A.4.5.2.37

Harga Total Harga


No. Uraian Kuantitas Satuan Jumlah
(Rp) (Rp)

B TENAGA
Pekerja 0.140 Org/ Hr 75,000.00 10,500.00
Tukang 0.070 Org/ Hr 80,000.00 5,600.00
Kepala Tukang 0.007 Org/ Hr 90,000.00 630.00
Mandor 0.007 Org/ Hr 100,000.00 700.00

SUB JUMLAH A 17,430.00

B BAHAN
Perabung Genteng Metal Bulat 1.280 bh 26,000.00 33,280.00
Paku Biasa 2" - 3" 0.050 kg 15,000.00 750.00

SUB JUMLAH B 34,030.00

C PERALATAN
-

SUB JUMLAH C -

D JUMLAH (A+B+C) 51,460.00


E Overhead & Profit 10% x D 5,146.00
F HARGA SATUAN PEKERJAAN 56,606.00

187 Jenis Pekerjaan : Pemasangan 1 m1 Nok Atap Bitumen


Satuan Pembayaran : m1
Standar : -

Harga Total Harga


No. Uraian Kuantitas Satuan Jumlah
(Rp) (Rp)

B TENAGA
Pekerja 0.250 Org/ Hr 75,000.00 18,750.00
Tukang 0.150 Org/ Hr 80,000.00 12,000.00
Kepala Tukang 0.015 Org/ Hr 90,000.00 1,350.00
Mandor 0.013 Org/ Hr 100,000.00 1,300.00

SUB JUMLAH A 33,400.00

B BAHAN
Perabung Genteng Bitumen 1.100 lbr 69,000.00 75,900.00
Sekrup Atap Bitumen 10.240 bh 1,200.00 12,288.00

SUB JUMLAH B 88,188.00

C PERALATAN
-

SUB JUMLAH C -

D JUMLAH (A+B+C) 121,588.00


E Overhead & Profit 10% x D 12,158.80
F HARGA SATUAN PEKERJAAN 133,746.80

Halaman 78
ANALISA HARGA SATUAN PEKERJAAN
(Permen PUPR No. 28/PRT/M/2016)

PEKERJAAN :
LOKASI :

188 Jenis Pekerjaan : Pemasangan 1 m1 Listplank Bahan GRC


Satuan Pembayaran : m1
Standar : -

Harga Total Harga


No. Uraian Kuantitas Satuan Jumlah
(Rp) (Rp)

B TENAGA
Pekerja 0.100 Org/ Hr 75,000.00 7,500.00
Tukang 0.200 Org/ Hr 80,000.00 16,000.00
Kepala Tukang 0.020 Org/ Hr 90,000.00 1,800.00
Mandor 0.005 Org/ Hr 100,000.00 500.00

SUB JUMLAH A 25,800.00

B BAHAN
Lisplank GRC 1.000 m¹ 287,500.00 287,500.00

SUB JUMLAH B 287,500.00

C PERALATAN
-

SUB JUMLAH C -

D JUMLAH (A+B+C) 313,300.00


E Overhead & Profit 10% x D 31,330.00
F HARGA SATUAN PEKERJAAN 344,630.00

189 Jenis Pekerjaan : Pemasangan 1 m2 Singap Ukir GRC


Satuan Pembayaran : m2
Standar : -

Harga Total Harga


No. Uraian Kuantitas Satuan Jumlah
(Rp) (Rp)

B TENAGA
Pekerja 0.100 Org/ Hr 75,000.00 7,500.00
Tukang 0.200 Org/ Hr 80,000.00 16,000.00
Kepala Tukang 0.020 Org/ Hr 90,000.00 1,800.00
Mandor 0.005 Org/ Hr 100,000.00 500.00

SUB JUMLAH A 25,800.00

B BAHAN
Singap Ukir GRC 1.000 m² 690,000.00 690,000.00

SUB JUMLAH B 690,000.00

C PERALATAN
-

SUB JUMLAH C -

D JUMLAH (A+B+C) 715,800.00


E Overhead & Profit 10% x D 71,580.00
F HARGA SATUAN PEKERJAAN 787,380.00

Halaman 79
ANALISA HARGA SATUAN PEKERJAAN
(Permen PUPR No. 28/PRT/M/2016)

PEKERJAAN :
LOKASI :

190 Jenis Pekerjaan : Pemasangan 1 Pasang Selembayung GRC


Satuan Pembayaran : psg
Standar : -

Harga Total Harga


No. Uraian Kuantitas Satuan Jumlah
(Rp) (Rp)

B TENAGA
Pekerja 0.100 Org/ Hr 75,000.00 7,500.00
Tukang 0.200 Org/ Hr 80,000.00 16,000.00
Kepala Tukang 0.020 Org/ Hr 90,000.00 1,800.00
Mandor 0.005 Org/ Hr 100,000.00 500.00

SUB JUMLAH A 25,800.00

B BAHAN
Selembayung GRC 1.000 psg 600,000.00 600,000.00

SUB JUMLAH B 600,000.00

C PERALATAN
-

SUB JUMLAH C -

D JUMLAH (A+B+C) 625,800.00


E Overhead & Profit 10% x D 62,580.00
F HARGA SATUAN PEKERJAAN 688,380.00

191 Jenis Pekerjaan : Waterproofing Membran


Satuan Pembayaran : m2
Standar : -

Harga Total Harga


No. Uraian Kuantitas Satuan Jumlah
(Rp) (Rp)

B TENAGA
Pekerja 0.200 Org/ Hr 75,000.00 15,000.00
Mandor 0.010 Org/ Hr 100,000.00 1,000.00

SUB JUMLAH A 16,000.00

B BAHAN
Waterproofing Membran 1.050 m² 35,000.00 36,750.00

SUB JUMLAH B 36,750.00

C PERALATAN
-

SUB JUMLAH C -

D JUMLAH (A+B+C) 52,750.00


E Overhead & Profit 10% x D 5,275.00
F HARGA SATUAN PEKERJAAN 58,025.00

Halaman 80
ANALISA HARGA SATUAN PEKERJAAN
(Permen PUPR No. 28/PRT/M/2016)

PEKERJAAN :
LOKASI :

192 Jenis Pekerjaan : Screed Pelindung Waterproofing


Satuan Pembayaran : m2
Standar : -

Harga Total Harga


No. Uraian Kuantitas Satuan Jumlah
(Rp) (Rp)

B TENAGA
Pekerja 0.200 Org/ Hr 75,000.00 15,000.00
Mandor 0.010 Org/ Hr 100,000.00 1,000.00

SUB JUMLAH A 16,000.00

B BAHAN
Waterproofing Membran 1.050 m² 22,500.00 23,625.00

SUB JUMLAH B 23,625.00

C PERALATAN
-

SUB JUMLAH C -

D JUMLAH (A+B+C) 39,625.00


E Overhead & Profit 10% x D 3,962.50
F HARGA SATUAN PEKERJAAN 43,587.50

193 Jenis Pekerjaan : Pemasangan 1 m2 Paving Blok Berwarna tebal 6 cm


Satuan Pembayaran : m2
Standar : A.4.4.3.66

Harga Total Harga


No. Uraian Kuantitas Satuan Jumlah
(Rp) (Rp)

B TENAGA
Pekerja 0.250 Org/ Hr 75,000.00 18,750.00
Tukang 0.500 Org/ Hr 80,000.00 40,000.00
Kepala Tukang 0.050 Org/ Hr 90,000.00 4,500.00
Mandor 0.001 Org/ Hr 100,000.00 130.00

SUB JUMLAH A 63,380.00

B BAHAN
Paving Blok tebal 6 cm 1.010 m² 98,000.00 98,980.00
Pasir Beton / m³ 0.050 m³ 165,000.00 8,250.00

SUB JUMLAH B 107,230.00

C PERALATAN
Peralatan 10 % 1.000 ls 9,800.00 9,800.00

SUB JUMLAH C 9,800.00

D JUMLAH (A+B+C) 180,410.00


E Overhead & Profit 10% x D 18,041.00
F HARGA SATUAN PEKERJAAN 198,451.00

Halaman 81
ANALISA HARGA SATUAN PEKERJAAN
(Permen PUPR No. 28/PRT/M/2016)

PEKERJAAN :
LOKASI :

194 Jenis Pekerjaan : Pemasangan 1 m1 Kanstin 30x60


Satuan Pembayaran : m2
Standar : -

Harga Total Harga


No. Uraian Kuantitas Satuan Jumlah
(Rp) (Rp)

B TENAGA
Pekerja 0.250 Org/ Hr 75,000.00 18,750.00
Tukang 0.500 Org/ Hr 80,000.00 40,000.00
Kepala Tukang 0.050 Org/ Hr 90,000.00 4,500.00
Mandor 0.001 Org/ Hr 100,000.00 130.00

SUB JUMLAH A 63,380.00

B BAHAN
Kanstin 30x60 1.667 bh 41,000.00 68,333.33

SUB JUMLAH B 68,333.33

C PERALATAN
Peralatan 10 % 1.000 ls 4,100.00 4,100.00

SUB JUMLAH C 4,100.00

D JUMLAH (A+B+C) 135,813.33


E Overhead & Profit 10% x D 13,581.33
F HARGA SATUAN PEKERJAAN 149,394.67

195 Jenis Pekerjaan : Penanaman Rumput


Satuan Pembayaran : m2
Standar : -

Harga Total Harga


No. Uraian Kuantitas Satuan Jumlah
(Rp) (Rp)

B TENAGA
Biaya Penanaman 1.000 m² 4,047.50 4,047.50

SUB JUMLAH A 4,047.50

B BAHAN
Rumput Gajah Mini 1.050 m² 31,700.00 33,285.00
Tanah Hitam 0.050 m³ 143,800.00 7,190.00

SUB JUMLAH B 40,475.00

C PERALATAN
-

SUB JUMLAH C -

D JUMLAH (A+B+C) 44,522.50


E Overhead & Profit 10% x D 4,452.25
F HARGA SATUAN PEKERJAAN 48,974.75

Halaman 82
ANALISA HARGA SATUAN PEKERJAAN
(Permen PUPR No. 28/PRT/M/2016)

PEKERJAAN :
LOKASI :

196 Jenis Pekerjaan : Penanaman Pohon Palem Putri


Satuan Pembayaran : btg
Standar : -

Harga Total Harga


No. Uraian Kuantitas Satuan Jumlah
(Rp) (Rp)

B TENAGA
Biaya Penanaman 1.000 m² 28,047.50 28,047.50

SUB JUMLAH A 28,047.50

B BAHAN
Pohon Palem Putri 1.050 btg 250,000.00 262,500.00
Tanah Hitam 0.125 m³ 143,800.00 17,975.00

SUB JUMLAH B 280,475.00

C PERALATAN
-

SUB JUMLAH C -

D JUMLAH (A+B+C) 308,522.50


E Overhead & Profit 10% x D 30,852.25
F HARGA SATUAN PEKERJAAN 339,374.75

197 Jenis Pekerjaan : Penanaman Pohon Pucuk Merah


Satuan Pembayaran : btg
Standar : -

Harga Total Harga


No. Uraian Kuantitas Satuan Jumlah
(Rp) (Rp)

B TENAGA
Biaya Penanaman 1.000 m² 17,547.50 17,547.50

SUB JUMLAH A 17,547.50

B BAHAN
Pohon Pucuk Merah 1.050 btg 150,000.00 157,500.00
Tanah Hitam 0.125 m³ 143,800.00 17,975.00

SUB JUMLAH B 175,475.00

C PERALATAN
-

SUB JUMLAH C -

D JUMLAH (A+B+C) 193,022.50


E Overhead & Profit 10% x D 19,302.25
F HARGA SATUAN PEKERJAAN 212,324.75

Halaman 83
ANALISA HARGA SATUAN PEKERJAAN
(Permen PUPR No. 28/PRT/M/2016)

PEKERJAAN :
LOKASI :

198 Jenis Pekerjaan : Penanaman Pohon Ketapang


Satuan Pembayaran : btg
Standar : -

Harga Total Harga


No. Uraian Kuantitas Satuan Jumlah
(Rp) (Rp)

B TENAGA
Biaya Penanaman 1.000 m² 28,047.50 28,047.50

SUB JUMLAH A 28,047.50

B BAHAN
Pohon Ketapang 1.050 btg 250,000.00 262,500.00
Tanah Hitam 0.125 m³ 143,800.00 17,975.00

SUB JUMLAH B 280,475.00

C PERALATAN
-

SUB JUMLAH C -

D JUMLAH (A+B+C) 308,522.50


E Overhead & Profit 10% x D 30,852.25
F HARGA SATUAN PEKERJAAN 339,374.75

Halaman 84
ANALISA HARGA SATUAN PEKERJAAN ELEKTRIKAL MEKANIKAL

PEKERJAAN : -
LOKASI : -

No URAIAN PEKERJAAN HARGA JUMLAH TOTAL

199 1 m¹ Memasang Pipa PVC f 4 inch


Upah :
0.0360 Hari Pekerja Rp 75,000.00 Rp 2,700.00
0.0600 Hari Tukang Kayu Rp 80,000.00 Rp 4,800.00
0.0060 Hari Kepala Tukang Rp 90,000.00 Rp 540.00
0.0018 Hari Mandor Rp 100,000.00 Rp 180.00 Rp 8,220.00
Bahan :
1.0500 M1 Pipa PVC 4 inch Rp 64,020.00 Rp 67,221.00
1.0000 Ls Perlengkapan ( 10 % Harga ) Rp 6,402.00 Rp 6,402.00 Rp 73,623.00
Jumlah Bahan + Upah + Peralatan Rp 81,843.00
Overhead + Profit ( 10% ) Rp 8,184.30
Total Harga Satuan Pekerjaan Rp 90,027.30

200 1 m¹ Memasang Pipa PVC f 3 inch


Upah :
0.0360 Hari Pekerja Rp 75,000.00 Rp 2,700.00
0.0600 Hari Tukang Kayu Rp 80,000.00 Rp 4,800.00
0.0060 Hari Kepala Tukang Rp 90,000.00 Rp 540.00
0.0018 Hari Mandor Rp 100,000.00 Rp 180.00 Rp 8,220.00
Bahan :
1.0500 M1 Pipa PVC 3 inch Rp 38,637.50 Rp 40,569.38
1.0000 Ls Perlengkapan ( 10 % Harga ) Rp 3,863.75 Rp 3,863.75 Rp 44,433.13
Jumlah Bahan + Upah + Peralatan Rp 52,653.13
Overhead + Profit ( 10% ) Rp 5,265.31
Total Harga Satuan Pekerjaan Rp 57,918.44

201 1m¹ Memasang Pipa PVC f 2 inch


Upah :
0.0240 Hari Pekerja Rp 75,000.00 Rp 1,800.00
0.0400 Hari Tukang Rp 80,000.00 Rp 3,200.00
0.0040 Hari Kepala Tukang Rp 90,000.00 Rp 360.00
0.0012 Hari Mandor Rp 100,000.00 Rp 120.00 5,480.00
Bahan :
1.0500 M1 Pipa PVC 2 inch Rp 19,635.00 Rp 20,616.75
1.0000 Ls Perlengkapan ( 10 % Harga ) Rp 1,963.50 Rp 1,963.50 Rp 22,580.25
Jumlah Bahan + Upah + Peralatan Rp 28,060.25
Overhead + Profit ( 10% ) Rp 2,806.03
Total Harga Satuan Pekerjaan Rp 30,866.28

202 1 m¹ Memasang Pipa PVC f 1,5 inch


Upah :
0.0240 Hari Pekerja Rp 75,000.00 Rp 1,800.00
0.0400 Hari Tukang Rp 80,000.00 Rp 3,200.00
0.0040 Hari Kepala Tukang Rp 90,000.00 Rp 360.00
0.0012 Hari Mandor Rp 100,000.00 Rp 120.00 5,480.00
Bahan :
1.0500 M1 Pipa PVC 1,5 inch Rp 15,345.00 Rp 16,112.25
1.0000 Ls Perlengkapan ( 10 % Harga ) Rp 1,534.50 Rp 1,534.50 Rp 17,646.75
Jumlah Bahan + Upah + Peralatan Rp 23,126.75
Overhead + Profit ( 10% ) Rp 2,312.68
Total Harga Satuan Pekerjaan Rp 25,439.43

203 1 Unit Pengadaan dan pemasangan jet pump lengkap dengan sumur bor
Bahan :
1.0000 Paket Pompa Jet Pump Rp 5,400,000.00 Rp 5,400,000.00
#REF!
#REF!
1.0000 Unit Sumur Bor Rp 6,500,000.00 Rp 6,500,000.00 Rp 11,900,000.00

Upah :
1.0000 oh Tukang pipa Rp 80,000.00 Rp 80,000.00
1.0000 oh Kepala tukang pipa Rp 90,000.00 Rp 90,000.00
0.5000 oh Mandor Rp 100,000.00 Rp 50,000.00 Rp 220,000.00
Jumlah Bahan + Upah + Peralatan Rp 12,120,000.00
Overhead + Profit ( 10% ) Rp 1,212,000.00
Total Harga Satuan Pekerjaan Rp 13,332,000.00

Halaman 85
ANALISA HARGA SATUAN PEKERJAAN ELEKTRIKAL MEKANIKAL

PEKERJAAN : -
LOKASI : -

No URAIAN PEKERJAAN HARGA JUMLAH TOTAL


204 1 m¹ PIPA POLLYPROPELINE DIA. 2" / PN - 10
Bahan :
1.1000 M Polypropeline dia. 2 ” Rp 127,748.48 Rp 140,523.32
20.0000 % Alat & Material bantu Rp 25,549.70 Rp 25,549.70 Rp 166,073.02

Upah :
0.1667 oh Tukang pipa Rp 80,000.00 Rp 13,333.33
0.0833 oh Kepala tukang pipa Rp 90,000.00 Rp 7,497.69
0.0416 oh Mandor Rp 100,000.00 Rp 4,164.29 Rp 24,995.31
Jumlah Bahan + Upah + Peralatan Rp 191,068.33
Overhead + Profit ( 10% ) Rp 19,106.83
Total Harga Satuan Pekerjaan Rp 210,175.16

205 1 m¹ PIPA POLLYPROPELINE DIA. 1,5" / PN - 10


Bahan :
1.1000 M Polypropeline dia. 1,5 ” Rp 111,748.50 Rp 122,923.35
20.0000 % Alat & Material bantu Rp 22,349.70 Rp 22,349.70 Rp 145,273.05

Upah :
0.1000 oh Tukang pipa Rp 80,000.00 Rp 8,000.00
0.0500 oh Kepala tukang pipa Rp 90,000.00 Rp 4,498.62
0.0250 oh Mandor Rp 100,000.00 Rp 2,498.57 Rp 14,997.19
Jumlah Bahan + Upah + Peralatan Rp 160,270.24
Overhead + Profit ( 10% ) Rp 16,027.02
Total Harga Satuan Pekerjaan Rp 176,297.26

206 1 m¹ PIPA POLLYPROPELINE DIA. 1" / PN - 10


Bahan :
1.1000 M Polypropeline dia. 1 ” Rp 45,119.05 Rp 49,630.96
20.0000 % Alat & Material bantu Rp 9,023.81 Rp 9,023.81 Rp 58,654.77

Upah :
0.0667 oh Tukang pipa Rp 80,000.00 Rp 5,333.33
0.0333 oh Kepala tukang pipa Rp 90,000.00 Rp 2,999.08
0.0167 oh Mandor Rp 100,000.00 Rp 1,665.71 Rp 9,998.12
Jumlah Bahan + Upah + Peralatan Rp 68,652.89
Overhead + Profit ( 10% ) Rp 6,865.29
Total Harga Satuan Pekerjaan Rp 75,518.18

207 1 m¹ PIPA POLLYPROPELINE DIA. 3/4" / PN - 10


Bahan :
1.1000 M Polypropeline dia. 1 ” Rp 35,616.98 Rp 39,178.67
20.0000 % Alat & Material bantu Rp 7,123.40 Rp 7,123.40 Rp 46,302.07

Upah :
0.0500 oh Tukang pipa Rp 80,000.00 Rp 4,000.00
0.0250 oh Kepala tukang pipa Rp 90,000.00 Rp 2,249.31
0.0125 oh Mandor Rp 100,000.00 Rp 1,249.29 Rp 7,498.59
Jumlah Bahan + Upah + Peralatan Rp 53,800.66
Overhead + Profit ( 10% ) Rp 5,380.07
Total Harga Satuan Pekerjaan Rp 59,180.73

208 1 m¹PIPA POLLYPROPELINE DIA. 0,5" / PN - 10


Bahan :
1.1000 M Polypropeline dia. 0,5 ” Rp 29,930.05 Rp 32,923.06
20.0000 % Alat & Material bantu Rp 5,986.01 Rp 5,986.01 Rp 38,909.07

Upah :
0.0333 oh Tukang pipa Rp 80,000.00 Rp 2,666.67
0.0167 oh Kepala tukang pipa Rp 90,000.00 Rp 1,499.54
0.0083 oh Mandor Rp 100,000.00 Rp 832.86 Rp 4,999.06
Jumlah Bahan + Upah + Peralatan Rp 43,908.13
Overhead + Profit ( 10% ) Rp 4,390.81
Total Harga Satuan Pekerjaan Rp 48,298.94

Halaman 86
ANALISA HARGA SATUAN PEKERJAAN ELEKTRIKAL MEKANIKAL

PEKERJAAN : -
LOKASI : -

No URAIAN PEKERJAAN HARGA JUMLAH TOTAL


209 1 m¹ PIPA POLLYPROPELINE DIA. 0,5" / PN - 20
Bahan :
1.1000 M Polypropeline dia. 0,5 ” Rp 35,000.00 Rp 38,500.00
20.0000 % Alat & Material bantu Rp 7,000.00 Rp 7,000.00 Rp 45,500.00

Upah :
0.0333 oh Tukang pipa Rp 80,000.00 Rp 2,666.67
0.0167 oh Kepala tukang pipa Rp 90,000.00 Rp 1,499.54
0.0083 oh Mandor Rp 100,000.00 Rp 832.86 Rp 4,999.06
Jumlah Bahan + Upah + Peralatan Rp 50,499.06
Overhead + Profit ( 10% ) Rp 5,049.91
Total Harga Satuan Pekerjaan Rp 55,548.97

210 1 Bh Ball Tap Plastik dia 1/2"


Bahan :
1.0000 Bh Ball Tap Plastik Rp 100,760.00 Rp 100760
20.0000 % Alat & Material bantu Rp 20,152.00 Rp 20,152.00 Rp 120,912.00

Upah :
0.0333 oh Tukang pipa Rp 80,000.00 Rp 2666.67
0.0167 oh Kepala tukang pipa Rp 90,000.00 Rp 1499.54
0.0083 oh Mandor Rp 100,000.00 Rp 832.86 Rp 4,999.06
Jumlah Bahan + Upah + Peralatan Rp 125,911.06
Overhead + Profit ( 10% ) Rp 12,591.11
Total Harga Satuan Pekerjaan Rp 138,502.17

211 1 Bh Ball Tap Plastik dia 3/4"


Bahan :
1.0000 Bh Ball Tap Plastik Rp 132,770.00 Rp 132770
20.0000 % Alat & Material bantu Rp 26,554.00 Rp 26,554.00 Rp 159,324.00

Upah :
0.0333 oh Tukang pipa Rp 80,000.00 Rp 2666.67
0.0167 oh Kepala tukang pipa Rp 90,000.00 Rp 1499.54
0.0083 oh Mandor Rp 100,000.00 Rp 832.86 Rp 4,999.06
Jumlah Bahan + Upah + Peralatan Rp 164,323.06
Overhead + Profit ( 10% ) Rp 16,432.31
Total Harga Satuan Pekerjaan Rp 180,755.37

212 1 Bh Ball Tap Plastik dia 1 1/4"


Bahan :
1.0000 Bh Ball Tap Plastik Rp 368,500.00 Rp 368500
20.0000 % Alat & Material bantu Rp 73,700.00 Rp 73,700.00 Rp 442,200.00

Upah :
0.0333 oh Tukang pipa Rp 80,000.00 Rp 2666.67
0.0167 oh Kepala tukang pipa Rp 90,000.00 Rp 1499.54
0.0083 oh Mandor Rp 100,000.00 Rp 832.86 Rp 4,999.06
Jumlah Bahan + Upah + Peralatan Rp 447,199.06
Overhead + Profit ( 10% ) Rp 44,719.91
Total Harga Satuan Pekerjaan Rp 491,918.97

213 1 Bh Ball Tap Plastik dia 1 1/2"


Bahan :
1.0000 Bh Ball Tap Plastik Rp 528,440.00 Rp 528440
20.0000 % Alat & Material bantu Rp 105,688.00 Rp 105,688.00 Rp 634,128.00

Upah :
0.0333 oh Tukang pipa Rp 80,000.00 Rp 2666.67
0.0167 oh Kepala tukang pipa Rp 90,000.00 Rp 1499.54
0.0083 oh Mandor Rp 100,000.00 Rp 832.86 Rp 4,999.06
Jumlah Bahan + Upah + Peralatan Rp 639,127.06
Overhead + Profit ( 10% ) Rp 63,912.71
Total Harga Satuan Pekerjaan Rp 703,039.77

Halaman 87
ANALISA HARGA SATUAN PEKERJAAN ELEKTRIKAL MEKANIKAL

PEKERJAAN : -
LOKASI : -

No URAIAN PEKERJAAN HARGA JUMLAH TOTAL


214 1 Bh Ball Tap Plastik dia 2"
Bahan :
1.0000 Bh Ball Tap Plastik Rp 660,220.00 Rp 660220
20.0000 % Alat & Material bantu Rp 132,044.00 Rp 132,044.00 Rp 792,264.00

Upah :
0.0333 oh Tukang pipa Rp 80,000.00 Rp 2666.67
0.0167 oh Kepala tukang pipa Rp 90,000.00 Rp 1499.54
0.0083 oh Mandor Rp 100,000.00 Rp 832.86 Rp 4,999.06
Jumlah Bahan + Upah + Peralatan Rp 797,263.06
Overhead + Profit ( 10% ) Rp 79,726.31
Total Harga Satuan Pekerjaan Rp 876,989.37

215 1 m¹ KABEL TR, NYFGBY 4 X 150 mm2


Bahan :
1.0000 M Kabel NYFGBY 4x150 mm2 Rp 820,000.00 Rp 820,000.00
20.0000 % Alat & Material bantu Rp 164,000.00 Rp 164,000.00 Rp 984,000.00

Upah :
0.1667 oh Tukang Listrik Rp 80,000.00 Rp 13,333.33
0.3333 oh Kepala Tukang Listrik Rp 90,000.00 Rp 30,000.00
0.0333 oh Mandor Rp 100,000.00 Rp 3,333.33 Rp 46,666.67
Jumlah Bahan + Upah + Peralatan Rp 1,030,666.67
Overhead + Profit ( 10% ) Rp 103,066.67
Total Harga Satuan Pekerjaan Rp 1,133,733.33

216 1 m¹ KABEL TR, NYY 4 X 150 mm2


Bahan :
1.0000 M Kabel NYY 4x150 mm2 Rp 610,000.00 Rp 610,000.00
20.0000 % Alat & Material bantu Rp 122,000.00 Rp 122,000.00 Rp 732,000.00

Upah :
0.1667 oh Tukang Listrik Rp 80,000.00 Rp 13,333.33
0.3333 oh Kepala Tukang Listrik Rp 90,000.00 Rp 30,000.00
0.0333 oh Mandor Rp 100,000.00 Rp 3,333.33 Rp 46,666.67
Jumlah Bahan + Upah + Peralatan Rp 778,666.67
Overhead + Profit ( 10% ) Rp 77,866.67
Total Harga Satuan Pekerjaan Rp 856,533.33

217 1 m¹ KABEL TR, NYFGBY 4 X 95 mm2


Bahan :
1.0000 M Kabel NYFGBY 4x95 mm2 Rp 510,000.00 Rp 510,000.00
20.0000 % Alat & Material bantu Rp 102,000.00 Rp 102,000.00 Rp 612,000.00

Upah :
0.1667 oh Tukang Listrik Rp 80,000.00 Rp 13,333.33
0.3333 oh Kepala Tukang Listrik Rp 90,000.00 Rp 30,000.00
0.0333 oh Mandor Rp 100,000.00 Rp 3,333.33 Rp 46,666.67
Jumlah Bahan + Upah + Peralatan Rp 658,666.67
Overhead + Profit ( 10% ) Rp 65,866.67
Total Harga Satuan Pekerjaan Rp 724,533.33

218 1 m¹ KABEL TR, NYFGBY 4 X 35 mm2


Bahan :
1.0000 M Kabel NYFGBY 4x35 mm2 Rp 429,900.00 Rp 429,900.00
20.0000 % Alat & Material bantu Rp 85,980.00 Rp 85,980.00 Rp 515,880.00

Upah :
0.1667 oh Tukang Listrik Rp 80,000.00 Rp 13,333.33
0.1500 oh Kepala Tukang Listrik Rp 90,000.00 Rp 13,500.00
0.0333 oh Mandor Rp 100,000.00 Rp 3,333.33 Rp 30,166.67
Jumlah Bahan + Upah + Peralatan Rp 546,046.67
Overhead + Profit ( 10% ) Rp 54,604.67
Total Harga Satuan Pekerjaan Rp 600,651.33

Halaman 88
ANALISA HARGA SATUAN PEKERJAAN ELEKTRIKAL MEKANIKAL

PEKERJAAN : -
LOKASI : -

No URAIAN PEKERJAAN HARGA JUMLAH TOTAL


219 1 m¹ KABEL TR, NYY 4 X 35 mm2
Bahan :
1.0000 M Kabel NYY 4x35 mm2 Rp 329,900.00 Rp 329,900.00
20.0000 % Alat & Material bantu Rp 65,980.00 Rp 65,980.00 Rp 395,880.00

Upah :
0.1667 oh Tukang Listrik Rp 80,000.00 Rp 13,333.33
0.1500 oh Kepala Tukang Listrik Rp 90,000.00 Rp 13,500.00
0.0333 oh Mandor Rp 100,000.00 Rp 3,333.33 Rp 30,166.67
Jumlah Bahan + Upah + Peralatan Rp 426,046.67
Overhead + Profit ( 10% ) Rp 42,604.67
Total Harga Satuan Pekerjaan Rp 468,651.33

220 1 m¹ KABEL TR, NYY 4 X 16 mm2


Bahan :
1.0000 M Kabel NYY 4x16 mm2 Rp 258,000.00 Rp 258,000.00
20.0000 % Alat & Material bantu Rp 51,600.00 Rp 51,600.00 Rp 309,600.00

Upah :
0.0830 oh Tukang Listrik Rp 80,000.00 Rp 6,640.00
0.0167 oh Kepala Tukang Listrik Rp 90,000.00 Rp 1,503.00
0.0167 oh Mandor Rp 100,000.00 Rp 1,670.00 Rp 9,813.00
Jumlah Bahan + Upah + Peralatan Rp 319,413.00
Overhead + Profit ( 10% ) Rp 31,941.30
Total Harga Satuan Pekerjaan Rp 351,354.30

221 1 m¹ KABEL TR, NYY 4 X 6 mm2


Bahan :
1.0000 M Kabel NYY 4x6 mm2 Rp 122,000.00 Rp 122,000.00
20.0000 % Alat & Material bantu Rp 24,400.00 Rp 24,400.00 Rp 146,400.00

Upah :
0.0830 oh Tukang Listrik Rp 80,000.00 Rp 6,640.00
0.0167 oh Kepala Tukang Listrik Rp 90,000.00 Rp 1,503.00
0.0167 oh Mandor Rp 100,000.00 Rp 1,670.00 Rp 9,813.00
Jumlah Bahan + Upah + Peralatan Rp 156,213.00
Overhead + Profit ( 10% ) Rp 15,621.30
Total Harga Satuan Pekerjaan Rp 171,834.30

222 1 m¹ KABEL TR, NYY 4 X 4 mm2


Bahan :
1.0000 M Kabel NYY 4x4 mm2 Rp 75,000.00 Rp 75,000.00
20.0000 % Alat & Material bantu Rp 15,000.00 Rp 15,000.00 Rp 90,000.00

Upah :
0.0830 oh Tukang Listrik Rp 80,000.00 Rp 6,640.00
0.0167 oh Kepala Tukang Listrik Rp 90,000.00 Rp 1,503.00
0.0167 oh Mandor Rp 100,000.00 Rp 1,670.00 Rp 9,813.00
Jumlah Bahan + Upah + Peralatan Rp 99,813.00
Overhead + Profit ( 10% ) Rp 9,981.30
Total Harga Satuan Pekerjaan Rp 109,794.30

223 1 Bh Lampu Down Light Diameter 5" LED BULB 13 W


Bahan :
1.0000 Bh Lampu DL Rp 192,000.00 Rp 192,000.00
10.0000 % Alat & Material bantu Rp 19,200.00 Rp 19,200.00 Rp 211,200.00

Upah :
0.0333 oh Tukang Listrik Rp 80,000.00 Rp 2,666.67
0.0667 oh Kepala Tukang Listrik Rp 90,000.00 Rp 6,000.00
0.0667 oh Mandor Rp 100,000.00 Rp 6,666.67 Rp 15,333.33
Jumlah Bahan + Upah + Peralatan Rp 226,533.33
Overhead + Profit ( 10% ) Rp 22,653.33
Total Harga Satuan Pekerjaan Rp 249,186.67

Halaman 89
ANALISA HARGA SATUAN PEKERJAAN ELEKTRIKAL MEKANIKAL

PEKERJAAN : -
LOKASI : -

No URAIAN PEKERJAAN HARGA JUMLAH TOTAL


224 1 Bh Lampu Down Light Diameter 4" LED BULB 9 W
Bahan :
1.0000 Bh Lampu DL Rp 162,000.00 Rp 162,000.00
10.0000 % Alat & Material bantu Rp 16,200.00 Rp 16,200.00 Rp 178,200.00

Upah :
0.0333 oh Tukang Listrik Rp 80,000.00 Rp 2,666.67
0.0667 oh Kepala Tukang Listrik Rp 90,000.00 Rp 6,000.00
0.0667 oh Mandor Rp 100,000.00 Rp 6,666.67 Rp 15,333.33
Jumlah Bahan + Upah + Peralatan Rp 193,533.33
Overhead + Profit ( 10% ) Rp 19,353.33
Total Harga Satuan Pekerjaan Rp 212,886.67

225 1 Bh TL LED 2 X 16 W MIRROR


Bahan :
1.0000 Bh TL LED 2 X 16 W Rp 515,000.00 Rp 515,000.00
10.0000 % Alat & Material bantu Rp 51,500.00 Rp 51,500.00 Rp 566,500.00

Upah :
0.0333 oh Tukang Listrik Rp 80,000.00 Rp 2,666.67
0.0667 oh Kepala Tukang Listrik Rp 90,000.00 Rp 6,000.00
0.0667 oh Mandor Rp 100,000.00 Rp 6,666.67 Rp 15,333.33
Jumlah Bahan + Upah + Peralatan Rp 581,833.33
Overhead + Profit ( 10% ) Rp 58,183.33
Total Harga Satuan Pekerjaan Rp 640,016.67

226 1 Bh TL LED 2x8 W MIRROR


Bahan :
1.0000 Bh Lampu TL Rp 455,000.00 Rp 455,000.00
10.0000 % Alat & Material bantu Rp 45,500.00 Rp 45,500.00 Rp 500,500.00

Upah :
0.0333 oh Tukang Listrik Rp 80,000.00 Rp 2,666.67
0.0667 oh Kepala Tukang Listrik Rp 90,000.00 Rp 6,000.00
0.0667 oh Mandor Rp 100,000.00 Rp 6,666.67 Rp 15,333.33
Jumlah Bahan + Upah + Peralatan Rp 515,833.33
Overhead + Profit ( 10% ) Rp 51,583.33
Total Harga Satuan Pekerjaan Rp 567,416.67

227 1 Bh TL 1x36 W TKO


Bahan :
1.0000 Bh Lampu TL Rp 175,000.00 Rp 175,000.00
10.0000 % Alat & Material bantu Rp 17,500.00 Rp 17,500.00 Rp 192,500.00

Upah :
0.0333 oh Tukang Listrik Rp 80,000.00 Rp 2,666.67
0.0667 oh Kepala Tukang Listrik Rp 90,000.00 Rp 6,000.00
0.0667 oh Mandor Rp 100,000.00 Rp 6,666.67 Rp 15,333.33
Jumlah Bahan + Upah + Peralatan Rp 207,833.33
Overhead + Profit ( 10% ) Rp 20,783.33
Total Harga Satuan Pekerjaan Rp 228,616.67

228 1 Bh TL LED 1x16 W Cover ACR + Nicad Batt


Bahan :
1.0000 Bh Lampu TL Rp 800,000.00 Rp 800,000.00
10.0000 % Alat & Material bantu Rp 80,000.00 Rp 80,000.00 Rp 880,000.00

Upah :
0.0333 oh Tukang Listrik Rp 80,000.00 Rp 2,666.67
0.0667 oh Kepala Tukang Listrik Rp 90,000.00 Rp 6,000.00
0.0667 oh Mandor Rp 100,000.00 Rp 6,666.67 Rp 15,333.33
Jumlah Bahan + Upah + Peralatan Rp 895,333.33
Overhead + Profit ( 10% ) Rp 89,533.33
Total Harga Satuan Pekerjaan Rp 984,866.67

Halaman 90
ANALISA HARGA SATUAN PEKERJAAN ELEKTRIKAL MEKANIKAL

PEKERJAAN : -
LOKASI : -

No URAIAN PEKERJAAN HARGA JUMLAH TOTAL


229 1 Bh Stop Kontak 1 Phasa
Bahan :
1.0000 Bh Stop Kontak Rp 28,265.00 Rp 28,265.00
10.0000 % Alat & Material bantu Rp 2,826.50 Rp 2,826.50 Rp 31,091.50

Upah :
0.0800 oh Tukang Listrik Rp 80,000.00 Rp 6,400.00
0.0800 oh Kepala Tukang Listrik Rp 90,000.00 Rp 7,200.00
0.0250 oh Mandor Rp 100,000.00 Rp 2,500.00 Rp 16,100.00
Jumlah Bahan + Upah + Peralatan Rp 47,191.50
Overhead + Profit ( 10% ) Rp 4,719.15
Total Harga Satuan Pekerjaan Rp 51,910.65

230 1 Bh Stop Kontak 1 Phasa AC


Bahan :
1.0000 Bh Stop Kontak Rp 28,265.00 Rp 28,265.00
10.0000 % Alat & Material bantu Rp 2,826.50 Rp 2,826.50 Rp 31,091.50

Upah :
0.0800 oh Tukang Listrik Rp 80,000.00 Rp 6,400.00
0.0800 oh Kepala Tukang Listrik Rp 90,000.00 Rp 7,200.00
0.0250 oh Mandor Rp 100,000.00 Rp 2,500.00 Rp 16,100.00
Jumlah Bahan + Upah + Peralatan Rp 47,191.50
Overhead + Profit ( 10% ) Rp 4,719.15
Total Harga Satuan Pekerjaan Rp 51,910.65

231 1 Bh Sakelar Tunggal


Bahan :
1.0000 Bh Sakelar Tunggal Rp 24,500.00 Rp 24,500.00
10.0000 % Alat & Material bantu Rp 2,450.00 Rp 2,450.00 Rp 26,950.00

Upah :
0.0800 oh Tukang Listrik Rp 80,000.00 Rp 6,400.00
0.0800 oh Kepala Tukang Listrik Rp 90,000.00 Rp 7,200.00
0.0250 oh Mandor Rp 100,000.00 Rp 2,500.00 Rp 16,100.00
Jumlah Bahan + Upah + Peralatan Rp 43,050.00
Overhead + Profit ( 10% ) Rp 4,305.00
Total Harga Satuan Pekerjaan Rp 47,355.00

232 1 Bh Sakelar Ganda


Bahan :
1.0000 Bh Sakelar Ganda Rp 36,595.00 Rp 36,595.00
10.0000 % Alat & Material bantu Rp 3,659.50 Rp 3,659.50 Rp 40,254.50

Upah :
0.0800 oh Tukang Listrik Rp 80,000.00 Rp 6,400.00
0.0800 oh Kepala Tukang Listrik Rp 90,000.00 Rp 7,200.00
0.0250 oh Mandor Rp 100,000.00 Rp 2,500.00 Rp 16,100.00
Jumlah Bahan + Upah + Peralatan Rp 56,354.50
Overhead + Profit ( 10% ) Rp 5,635.45
Total Harga Satuan Pekerjaan Rp 61,989.95

233 1 Bh Instalasi Penerangan NYM 3x2,5 mm2


Bahan :
6.0000 Bh Kabel NYM 3x2,3 mm2 Rp 13,000.00 Rp 78,000.00
5.0000 m¹ Pipa Conduit Rp 5,500.00 Rp 27,500.00
2.0000 bh Socket Pipa Rp 1,500.00 Rp 3,000.00
1.0000 bh Tee Doos Rp 4,400.00 Rp 4,400.00
8.0000 bh Klem Pipa Rp 1,100.00 Rp 8,800.00
6.0000 bh Fhiser Rp 1,100.00 Rp 6,600.00
2.0000 bh Las Doop Rp 1,100.00 Rp 2,200.00
0.0250 bh Isolasi ban Rp 5,000.00 Rp 125.00 Rp 130,625.00

Upah :
0.3000 oh Tukang Listrik Rp 80,000.00 Rp 24,000.00
0.3000 oh Kepala Tukang Listrik Rp 90,000.00 Rp 27,000.00
0.1600 oh Mandor Rp 100,000.00 Rp 16,000.00 Rp 67,000.00
Jumlah Bahan + Upah + Peralatan Rp 197,625.00
Overhead + Profit ( 10% ) Rp 19,762.50
Total Harga Satuan Pekerjaan Rp 217,387.50

Halaman 91
ANALISA HARGA SATUAN PEKERJAAN ELEKTRIKAL MEKANIKAL

PEKERJAAN : -
LOKASI : -

No URAIAN PEKERJAAN HARGA JUMLAH TOTAL


234 1 Bh Instalasi Stop Kontak NYM 3x2,5 mm2
Bahan :
8.0000 Bh Kabel NYM 3x2,3 mm2 Rp 13,000.00 Rp 104,000.00
6.0000 m¹ Pipa Conduit Rp 5,500.00 Rp 33,000.00
2.0000 bh Socket Pipa Rp 1,500.00 Rp 3,000.00
1.0000 bh Tee Doos Rp 4,400.00 Rp 4,400.00
8.0000 bh Klem Pipa Rp 1,100.00 Rp 8,800.00
6.0000 bh Fhiser Rp 1,100.00 Rp 6,600.00
2.0000 bh Las Doop Rp 1,100.00 Rp 2,200.00
0.0250 bh Isolasi ban Rp 5,000.00 Rp 125.00 Rp 162,125.00

Upah :
0.3000 oh Tukang Listrik Rp 80,000.00 Rp 24,000.00
0.3000 oh Kepala Tukang Listrik Rp 90,000.00 Rp 27,000.00
0.1600 oh Mandor Rp 100,000.00 Rp 16,000.00 Rp 67,000.00
Jumlah Bahan + Upah + Peralatan Rp 229,125.00
Overhead + Profit ( 10% ) Rp 22,912.50
Total Harga Satuan Pekerjaan Rp 252,037.50

235 1 Bh Instalasi Exhaust Fan NYM 3x2,5 mm2


Bahan :
3.0000 Bh Kabel NYM 3x2,3 mm2 Rp 13,000.00 Rp 39,000.00
2.0000 m¹ Pipa Conduit Rp 5,500.00 Rp 11,000.00
1.0000 bh Socket Pipa Rp 1,500.00 Rp 1,500.00
1.0000 bh Tee Doos Rp 4,400.00 Rp 4,400.00
2.0000 bh Klem Pipa Rp 1,100.00 Rp 2,200.00
2.0000 bh Fhiser Rp 1,100.00 Rp 2,200.00
1.0000 bh Las Doop Rp 1,100.00 Rp 1,100.00
0.0250 bh Isolasi ban Rp 5,000.00 Rp 125.00 Rp 61,525.00

Upah :
0.1600 oh Tukang Listrik Rp 80,000.00 Rp 12,800.00
0.1600 oh Kepala Tukang Listrik Rp 90,000.00 Rp 14,400.00
0.0800 oh Mandor Rp 100,000.00 Rp 8,000.00 Rp 35,200.00
Jumlah Bahan + Upah + Peralatan Rp 96,725.00
Overhead + Profit ( 10% ) Rp 9,672.50
Total Harga Satuan Pekerjaan Rp 106,397.50

236 1 Bh Instalasi Stop Kontak AC NYM 3x2,5 mm2


Bahan :
9.0000 Bh Kabel NYM 3x2,3 mm2 Rp 13,000.00 Rp 117,000.00
6.0000 m¹ Pipa Conduit Rp 5,500.00 Rp 33,000.00
2.0000 bh Socket Pipa Rp 1,500.00 Rp 3,000.00
1.0000 bh Tee Doos Rp 4,400.00 Rp 4,400.00
8.0000 bh Klem Pipa Rp 1,100.00 Rp 8,800.00
6.0000 bh Fhiser Rp 1,100.00 Rp 6,600.00
2.0000 bh Las Doop Rp 1,100.00 Rp 2,200.00
0.0250 bh Isolasi ban Rp 5,000.00 Rp 125.00 Rp 175,125.00

Upah :
0.3000 oh Tukang Listrik Rp 80,000.00 Rp 24,000.00
0.3000 oh Kepala Tukang Listrik Rp 90,000.00 Rp 27,000.00
0.1600 oh Mandor Rp 100,000.00 Rp 16,000.00 Rp 67,000.00
Jumlah Bahan + Upah + Peralatan Rp 242,125.00
Overhead + Profit ( 10% ) Rp 24,212.50
Total Harga Satuan Pekerjaan Rp 266,337.50

237 1 Bh Outlet Telephone


Bahan :
1.0000 Bh Outlet Telephone Rp 35,000.00 Rp 35,000.00
10.0000 % Alat & Material bantu Rp 3,500.00 Rp 3,500.00 Rp 38,500.00

Upah :
0.0600 oh Tukang Listrik Rp 80,000.00 Rp 4,800.00
0.0600 oh Kepala Tukang Listrik Rp 90,000.00 Rp 5,400.00
0.0250 oh Mandor Rp 100,000.00 Rp 2,500.00 Rp 12,700.00
Jumlah Bahan + Upah + Peralatan Rp 51,200.00
Overhead + Profit ( 10% ) Rp 5,120.00
Total Harga Satuan Pekerjaan Rp 56,320.00

Halaman 92
ANALISA HARGA SATUAN PEKERJAAN ELEKTRIKAL MEKANIKAL

PEKERJAAN : -
LOKASI : -

No URAIAN PEKERJAAN HARGA JUMLAH TOTAL


238 1 Bh Instalasi Telephone
Bahan :
15.0000 Bh Kabel ITC 4x0,6 mm Rp 10,300.00 Rp 154,500.00
13.0000 m¹ Pipa Conduit Rp 2,400.00 Rp 31,200.00
1.0000 bh Socket Pipa Rp 1,500.00 Rp 1,500.00
2.0000 bh Tee Doos Rp 4,400.00 Rp 8,800.00
3.0000 bh Klem Pipa Rp 1,100.00 Rp 3,300.00
6.0000 bh Fhiser Rp 1,100.00 Rp 6,600.00
2.0000 bh Las Doop Rp 1,100.00 Rp 2,200.00
0.2500 bh Isolasi ban Rp 5,000.00 Rp 1,250.00 Rp 209,350.00

Upah :
0.3000 oh Tukang Listrik Rp 80,000.00 Rp 24,000.00
0.3000 oh Kepala Tukang Listrik Rp 90,000.00 Rp 27,000.00
0.1600 oh Mandor Rp 100,000.00 Rp 16,000.00 Rp 67,000.00
Jumlah Bahan + Upah + Peralatan Rp 276,350.00
Overhead + Profit ( 10% ) Rp 27,635.00
Total Harga Satuan Pekerjaan Rp 303,985.00

239 1 Bh Instalasi CCTV


Bahan :
15.0000 Bh Kabel Cat 6 Rp 12,000.00 Rp 180,000.00
13.0000 m¹ Pipa Conduit Rp 2,400.00 Rp 31,200.00
1.0000 bh Socket Pipa Rp 1,500.00 Rp 1,500.00
2.0000 bh Tee Doos Rp 4,400.00 Rp 8,800.00
3.0000 bh Klem Pipa Rp 1,100.00 Rp 3,300.00
6.0000 bh Fhiser Rp 1,100.00 Rp 6,600.00
2.0000 bh Las Doop Rp 1,100.00 Rp 2,200.00
0.2500 bh Isolasi ban Rp 5,000.00 Rp 1,250.00 Rp 234,850.00

Upah :
0.3000 oh Tukang Listrik Rp 80,000.00 Rp 24,000.00
0.3000 oh Kepala Tukang Listrik Rp 90,000.00 Rp 27,000.00
0.1600 oh Mandor Rp 100,000.00 Rp 16,000.00 Rp 67,000.00
Jumlah Bahan + Upah + Peralatan Rp 301,850.00
Overhead + Profit ( 10% ) Rp 30,185.00
Total Harga Satuan Pekerjaan Rp 332,035.00

Halaman 93
DAFTAR HARGA SATUAN BAHAN, UPAH DAN SEWA ALAT

### : #REF!
### : #REF!
### : #REF!

NO URAIAN SATUAN HARGA KET

I UPAH
1 Pekerja Org/ Hr 75,000.00
2 Tukang Org/ Hr 80,000.00
3 Kepala Tukang Org/ Hr 90,000.00
4 Mandor Org/ Hr 100,000.00
5 Operator Alat Berat Org/ Hr 100,000.00
6 Pembantu Operator Alat Berat Org/ Hr 80,000.00
7 Mekanik Org/ Hr 100,000.00
8 Pembantu Mekanik Org/ Hr 80,000.00

II BAHAN BANGUNAN
A BAHAN PASANGAN
9 Air liter 200.00
10 Batu Bata Biasa (5 x 11 x 22) bh 500.00
11 Kerikil / m³ m³ 258,000.00
12 Kerikil (Maks 30 mm) / kg Kg 191.11
13 Pasir Pasang m³ 140,000.00
14 Pasir Urug m³ 120,000.00
15 Pasir Beton / m³ m³ 165,000.00
16 Pasir Beton / kg kg 117.86
17 Semen Portland / Zak sak 70,000.00
18 Semen Portland / kg kg 1,400.00
19 Semen Warna Kg 2,600.00
20 Tanah Urug m³ 80,500.00
21 Tiang Pancang Minipile Beton 25x25 m 205,000.00
22 Paving Blok tebal 6 cm m² 98,000.00
23 Kanstin 30x60 bh 41,000.00

B BAHAN KAYU
24 Kayu/ Papan Klas I m³ 5,000,000.00
25 Kayu/ Papan Klas II m³ 3,300,000.00
26 Kayu 5/7 m³ 3,300,000.00
27 Kayu Papan 3/20 m³ 3,500,000.00
28 Plywood 4 mm lbr 72,000.00
29 Plywood 9 mm lbr 133,000.00
30 Plywood 18 mm lbr 172,000.00
31 Pelapis Kayu Bahan HPL m² 43,000.00
32 Cerucuk Kayu dia. 6 - 8 Panjang 6 m btg 20,000.00
33 Kayu/ Papan Bekisting m³ 2,200,000.00
34 Dolken Kayu Ø (8-10)cm, panjang 4 m btg 15,000.00

Halaman 94
DAFTAR HARGA SATUAN BAHAN, UPAH DAN SEWA ALAT

### : #REF!
### : #REF!
### : #REF!

NO URAIAN SATUAN HARGA KET

B BAHAN BESI
35 Besi Beton Polos kg 12,200.00
36 Besi Beton Ulir kg 13,000.00
37 Baja Struktural / Profil kg 20,800.00
38 Paku Biasa 2" - 3" kg 15,000.00
39 Paku Biasa 2" - 5" kg 15,000.00
40 Paku Sekrup kg 28,000.00
41 Sekrup Fixer bh 500.00
42 Sekrup Atap Bitumen bh 1,200.00
43 Kawat Beton kg 20,000.00
44 Kawat Duri m 3,500.00
45 Kawat Las kg 28,000.00
46 Aluminium Composit Panel m² 550,000.00
47 Railing Tangga Bahan Stainlessteel m¹ 1,150,000.00

D BAHAN MINYAK
48 Minyak Bekisting/ Teak Oil liter 9,500.00
49 Lem Kayu liter 30,000.00
50 Residu liter 11,500.00
51 Meni Besi liter 25,000.00

E BAHAN ATAP
52 Atap Genteng Metal 0.35 mm bh 95,000.00
53 Atap Genteng Metal 0.30 mm bh 80,000.00
54 Atap Bitumen Selulosa 40 x 106 cm, t = 3 mm lbr 48,000.00
55 Perabung Genteng Metal Bulat bh 26,000.00
56 Perabung Genteng Metal Persegi bh 25,000.00
57 Perabung Genteng Bitumen lbr 69,000.00
58 Rangka Atap Baja Ringan m² 125,000.00
59 Lisplank GRC m¹ 287,500.00
60 Singap Ukir GRC m² 690,000.00
61 Selembayung GRC psg 600,000.00
62 Waterproofing Membran m² 35,000.00
63 Sreed Pelindung Waterproofing m² 22,500.00

F BAHAN PLAFOND
64 Gypsum Board 6 mm lbr 76,375.00
65 Gypsum PVC m² 85,000.00
66 Cornest kg 7,500.00
67 Metal stud C 36.7x76x4mm btg 48,000.00
68 List Plafond Gypsum m¹ 28,750.00
69 List Plafond PVC m¹ 25,000.00
70 List Profil m¹ 15,000.00

Halaman 95
DAFTAR HARGA SATUAN BAHAN, UPAH DAN SEWA ALAT

### : #REF!
### : #REF!
### : #REF!

NO URAIAN SATUAN HARGA KET

G BAHAN LANTAI DAN DINDING


71 Granit 60 x 60 bh 80,000.00
72 Granit 40 x 40 bh 35,132.50
73 Granit 30 x 30 bh 25,000.00
74 Granit 30 x 60 bh 31,000.00
75 Keramik 40 X 40 doos 75,000.00
76 Keramik 30 x 60 doos 76,000.00
77 Keramik 30 x 30 doos 75,000.00
78 Keramik 20 x 20 doos 71,000.00
79 Keramik 20 x 25 doos 74,800.00

H BAHAN KACA, JENDELA, PINTU DAN PELENGKAP


80 Kusen Aluminium m¹ 125,000.00
81 Kunci Tanam 2 Slaag bh 334,875.00
82 Kunci Biasa bh 143,000.00
83 Kait Angin Kualitas Standar bh 16,500.00
84 Pintu Double Multiplek Fin. HPL uk. 0.8 x 2.1 bh 1,092,000.00
85 Pintu Double Multiplek Fin. HPL uk. 0.7 x 2.1 bh 955,500.00
86 Pintu Fiber bh 281,325.00
87 Pintu Aluminium 0.5 x 1.0 bh 300,000.00
88 Pintu Lipat Besi uk. 4.25 x 3.90 Kusen Besi bh 8,287,500.00
89 Handle Pintu bh 143,800.00
90 Handle jendela bh 195,000.00
91 Engsel Pintu 4 '' bh 88,000.00
92 Engsel Pintu Tanam Pintu Kaca Tempered bh 485,000.00
93 Engsel Jendela 3 " bh 65,000.00
94 Grendel Jendela / Spring Knip bh 33,500.00
95 Door Closer bh 258,000.00
96 Kaca Polos t = 5 mm m² 111,625.00
97 Kaca Tempered t = 12 mm m² 180,000.00
98 Kaca Rayben t = 5 mm m² 80,000.00
99 Sealant tube 22,000.00
100 Stiker Kaca Buram m² 32,000.00
101 Backdrop uk. 6.5 x 2.9 bh 14,137,500.00

I BAHAN SANITAIR
102 Kloset Jongkok bh 415,000.00
103 Kloset Duduk bh 1,735,000.00
104 Urinoir bh 1,587,000.00
105 Washtafel bh 1,425,000.00
106 Kran Air bh 94,100.00
107 Kran Air Washtafel bh 185,000.00

Halaman 96
DAFTAR HARGA SATUAN BAHAN, UPAH DAN SEWA ALAT

### : #REF!
### : #REF!
### : #REF!

NO URAIAN SATUAN HARGA KET

108 Jet Shower bh 165,000.00


109 Shower bh 250,000.00
110 Floor Drain bh 115,000.00
111 Bak Air Fiber bh 489,800.00
112 Pembatas Urinoir dan Aksesoris bh 325,000.00
113 Cermin bh 225,000.00
114 Kitchen Zink bh 425,000.00
115 Sealtape bh 7,500.00
116 Meja Washtafel bh 750,000.00
117 Meja Pantry bh 850,000.00

J BAHAN FINISHING
118 Cat Minyak kg 85,000.00
119 Cat Air kg 65,000.00
120 Cat Dasar Kayu kg 36,225.00
121 Cat Dasar Tembok kg 15,000.00
122 Cat Menie kg 74,000.00
123 Plamir kg 40,000.00
124 Kuas bh 11,500.00
125 Pengencer kg 28,000.00
126 Amplas lbr 5,000.00

K BAHAN PIPA
127 Pipa PVC 1.5 inch m¹ 15,345.00
128 Pipa PVC 2 inch m¹ 19,635.00
129 Pipa PVC 3 inch m¹ 38,637.50
130 Pipa PVC 4 inch m¹ 64,020.00
131 Pompa Jet Pump, Kap ; 27 ltr/mnt, Head 82 m Paket 5,400,000.00
132 Sumur Bor unit 6,500,000.00
133 Pipa Polypropeline dia. 2 ” / PN - 10 m¹ 127,748.48
134 Pipa Polypropeline dia. 1,5 ” / PN - 10 m¹ 111,748.50
135 Pipa Polypropeline dia. 1 ” / PN - 10 m¹ 45,119.05
136 Pipa Polypropeline dia. 3/4 ” / PN - 10 m¹ 35,616.98
137 Pipa Polypropeline dia. 0,5 ” / PN - 10 m¹ 29,930.05
138 Pipa Polypropeline dia. 0,5 ” / PN - 20 m¹ 35,000.00
139 Ball Tap Plastik dia 1/2" bh 100,760.00
140 Ball Tap Plastik dia 3/4" bh 132,770.00
141 Ball Tap Plastik dia 1 1/4" bh 368,500.00
142 Ball Tap Plastik dia 1 1/2" bh 528,440.00
143 Ball Tap Plastik dia 2" bh 660,220.00
144 Kabel TR, NYFGBY 4 X 150 mm2 m¹ 820,000.00
145 Kabel TR, NYY 4 X 150 mm2 m¹ 610,000.00
146 Kabel TR, NYFGBY 4x95 mm2 m¹ 510,000.00

Halaman 97
DAFTAR HARGA SATUAN BAHAN, UPAH DAN SEWA ALAT

### : #REF!
### : #REF!
### : #REF!

NO URAIAN SATUAN HARGA KET

147 Kabel TR, NYFGBY 4x35 mm2 m¹ 429,900.00


148 Kabel TR, NYY 4x35 mm2 m¹ 329,900.00
149 Kabel TR, NYY 4x16 mm2 m¹ 258,000.00
150 Kabel TR, NYY 4x6 mm2 m¹ 122,000.00
151 Kabel TR, NYY 4x4 mm2 m¹ 75,000.00
152 Kabel NYM 3x2,3 mm2 m¹ 13,000.00
153 Kabel ITC 4x0,6 mm m¹ 10,300.00
154 Kabel Cat 6 m¹ 12,000.00
155 1 Bh Lampu Down Light Diameter 5" LED BULB 13 W bh 192,000.00
156 1 Bh Lampu Down Light Diameter 4" LED BULB 9 W bh 162,000.00
157 1 Bh TL LED 2 X 16 W MIRROR bh 515,000.00
158 1 Bh TL LED 2x8 W MIRROR bh 455,000.00
159 1 Bh TL 1x36 W TKO bh 175,000.00
160 1 Bh TL LED 1x16 W Cover ACR + Nicad Batt bh 800,000.00
161 1 Bh Stop Kontak 1 Phasa bh 28,265.00
162 1 Bh Stop Kontak 1 Phasa AC bh 28,265.00
163 1 Bh Sakelar Tunggal bh 24,500.00
164 1 Bh Sakelar Ganda bh 36,595.00
165 Pipa Conduit m¹ 5,500.00
166 Pipa Conduit m¹ 2,400.00
167 Socket Pipa bh 1,500.00
168 Tee Doos bh 4,400.00
169 Klem Pipa bh 1,100.00
170 Fisher bh 1,100.00
171 Las Doop bh 1,100.00
172 Isolasi ban bh 5,000.00
173 Outlet Telephone bh 35,000.00

L BAHAN LANSEKAP
174 Rumput Gajah Mini m² 31,700.00
175 Pohon Palem Putri btg 250,000.00
176 Pohon Pucuk Merah btg 150,000.00
177 Pohon Ketapang btg 250,000.00
178 Tanah Hitam m³ 143,800.00

III PERALATAN
179 Hydraulic Jacking jam 400,000.00
180 Mesin Las Listrik jam 150,000.00

IV MOBILISASI DAN DEMOBILISASI PERALATAN


181 Hidrolik Jacking Pile unit 26,500,000.00
182 Bulldozer unit 2,500,000.00
183 Water tank truck unit 750,000.00

Halaman 98
DAFTAR HARGA SATUAN BAHAN, UPAH DAN SEWA ALAT

### : #REF!
### : #REF!
### : #REF!

NO URAIAN SATUAN HARGA KET

184 Mesin Beton Molen / Concrete Mixer unit 500,000.00


185 Pompa Air unit 150,000.00
186 Generator Set unit 150,000.00
187 Compressor unit 150,000.00
188 Theodolite unit 75,000.00
189 Mesin Las Listrik unit 250,000.00
190 Concrete Vibrator unit 75,000.00
191 Hand Stamper unit 150,000.00
192 Scafolding unit 2,500.00

Catatan :
- Berat Jenis (BJ) Pasir Cor 1.4 ton/m3
- Berat Jenis (BJ) Batu Pecah 1.35 ton/m4

Halaman 99
DAFTA
DI LINGKUNGAN DIN

NO. JE

I TENAGA KERJA
1 MANDOR
2 KEPALA TUKANG
3 TUKANG
4 PEKERJA
5 OPERATOR
6 PEMBANTU OPERATOR
7 SOPIR
8 PEMBANTU SOPIR
9 MEKANIK
10 PEMBANTU MEKANIK

II BAHAN
A. BAHAN STRUKTUR
1 PASIR URUG
2 PASIR PASANG
3 PASIR BETON / COR
4 TANAH URUG / TIMBUN (TERIMA DITEMPAT)
5 PASIR HALUS
6 KERIKIL / KORAL BETON
7 SIRTU
8 SIRTU GALIAN / GRAVEL
9 BATU PECAH
10 GEOTEXTILE
11 BATU BATA UK. 5 x 10 x 20 CM
12 BATU BATA RINGAN / HEUBEL UK. 10 x 20 x 60 CM
13 SEMEN TYPE PCC (PORTLAND COMPOSITE CEMENT)
14 PORTLAND CEMENT PUTIH
15 PAVING BLOK TEBAL 6 CM
16 CONEBLOCK TEBAL 10X10x20 CM
17 KANSTEEN CONEBLOCK UK. 30 X 60 CM
18 GRASS BLOK TEBAL 6 CM

halaman 100 dari 138


19 BATU KERAWANG BETON
20 BATU SIKAT
21 BUIS BETON DIA. 20
22 BUIS BETON DIA. 40
23 BUIS BETON DIA. 60
24 BUIS BETON DIA. 80
25 BUIS BETON DIA. 100
26 TANAH HITAM
27 RUMPUT GAJAH ( PAITAN )
28 RUMPUT GAJAH MINI
29 ASPAL DRUM
30 ASPAL CURAH
31 BETON READY MIX : MUTU DENGAN MATERIAL KORAL
- K 125
- K 150
- K 175
- K 200
- K 225

halaman 101 dari 138


35 BETON READY MIX : MUTU DENGAN MATERIAL BATU PECAH
- K 225
- K 250
- K 300
- K 350
- K 400
- K 450
- K 500
36 TIANG PANCANG MINIPILE BETON 20X20
37 TIANG PANCANG MINIPILE BETON 25X25
38 TIANG PANCANG BETON PRA TEKAN DIA. 30 CM
39 TIANG PANCANG BETON PRA TEKAN DIA. 35 CM
40 TIANG PANCANG BETON PRA TEKAN DIA. 40 CM

B. BAHAN KAYU
1 KAYU KELAS I
2 KAYU KELAS II
3 KAYU KELAS III
4 KAYU LAMBERZIRING
5 KAYU PIRI-PIRI BIASA
6 KAYU PAPAN
7 TRIPLEKS 3
8 TRIPLEKS 3.6
9 TRIPLEKS 4
10 TRIPLEKS 6
11 TRIPLEKS 6
12 TRIPLEKS 9
13 TRIPLEKS 12
14 TRIPLEKS JATI 4
15 KAYU CEROCOK DIA 5-10 CM
16 KAYU DOLKEN DIA 5-10 CM
17 KAYU PERANCAH / BEKISTING
18 KAYU PROFIL
19 PAPAN LISPLANK UKIRAN (LEBAH BERGAYUT)
20 LISPLANK UKIR (GRC)
21 SINGAP UKIR (PAPAN)
22 SINGAP UKIR (GRC)
23 GRC POLOS (TANPA MOTIF)
24 SELEMBAYUNG UKIR (KAYU)
25 SELEMBAYUNG UKIR (FIBERGLASS)
26 SELEMBAYUNG UKIR (GRC)
27 KAYU BAKAR

halaman 102 dari 138


C. BAHAN BESI
1 BESI BETON BIASA / POLOS
2 BESI BETON ULIR
3 KAWAT IKAT BETON (BENDRAT)
4 KAWAT BRONJONG
5 KAWAT HARMONIKA
6 KAWAT NYAMUK
7 TEMPAT MASAK ASPAL
8 KAWAT DURI
9 BAJA STRUKTURAL/PROFIL (WF, C, H, L...)
10 VERTICAL BLIND
11 BESI PAGAR BRC, P=2.4 M

halaman 103 dari 138


12 BESI PAGAR TERALI (BESI BULAT), T=1.2 M
13 BESI PAGAR TERALI (BESI NAKO), T =1.2 M
14 BESI HOLLOW UK. 40 X 40 MM
15 FOLDING GATE
16 RANGKA ALUMUNIUM
17 ROLLING DOOR

D. BAHAN LANTAI
1 KERAMIK
- KERAMIK UKURAN 60x60
- KERAMIK UKURAN 40x40
- KERAMIK UKURAN 30x30
- KERAMIK UKURAN 25x25
- KERAMIK UKURAN 20x25
- KERAMIK UKURAN 20x20
- PLIN KERAMIK 10X20
- PLIN KERAMIK 10X30
- PLIN KERAMIK 10X40
- PLIN KERAMIK 10X60
- PLIN KERAMIK TANGGA / STEP NOSING
- PLIN KERAMIK KM/WC / WBIS WARNA Uk. 20 CM
- BON-BON KERAMIK
2 GRANIT
- GRANIT UKURAN 80X80
- GRANIT UKURAN 60X60
- GRANIT UKURAN 40X40
- GRANIT UKURAN 20x20
3 MARMER
4 KARPET
5 PARQUET
6 BATU TEMPEL HITAM
7 BATU TEMPEL PALIMANAN
8 BATU TEPLEK
9 VINIL

E. BAHAN ATAP
1 SENG GELOMBANG BJLS 20 K
2 SENG GELOMBANG WARNA BJLS 20 K
3 PERABUNG SENG PLAT BJLS 30 K
4 ATAP BITUMENT GELOMBANG ACRYLIC BACE
5 ATAP GENTENG METAL 0,35 MM
6 ATAP GENTENG METAL 0,30 MM
7 PERABUNG BITUMEN

halaman 104 dari 138


8 PERABUNG GENTENG METAL BULAT
9 PERABUNG GENTENG METAL PERSEGI
10 SENG PLAT BJLS 20 K
11 SENG PLAT ALUMUNIUM 0.3 MM
12 PLASTIK HITAM
13 ASBES
14 ALUMUNIUM FOIL
15 FORMIKA
16 ATAP GENTENG (BETON)
17 NOK ATAP GENTENG (BETON)
18 NOK SAMPING BITUMEN

halaman 105 dari 138


F. BAHAN LANGIT - LANGIT DAN LAP. DINDING
1 GYPSUM 6
2 GYPSUM 9
3 RANGKA FURING
4 LIST PROFIL KAYU
5 LIST PROFIL GYPSUM
6 METAL CLADING
7 PLAFOND AKUSTIK 60X120 CM
8 PLASTER KERAS
9 CORNIS
10 CONWOOD + RANGKA (TERPASANG)
11 ORNAMEN GRC
12 ORNAMEN GRC + RANGKA (TERPASANG)

G. BAHAN PIPA
1 STOPKRAN DIA. 3/4
2 KRAN AIR DIA. 1/2
3 KRAN AIR DIA. 3/4
4 PIPA PVC 1/2
5 PIPA PVC 3/4
6 PIPA PVC 1
7 PIPA PVC 1,5
8 PIPA PVC 2
9 PIPA PVC 3
10 PIPA PVC 4
11 ELBOW PVC 4
12 SOCKET 4
13 PIPA BESI HIGH PRESSURE GIP
14 PIPA BESI HIGH PRESSURE GIP
15 PIPA BESI HIGH PRESSURE GIP
16 PIPA BESI HIGH PRESSURE HITAM 2 "
17 PIPA BESI HIGH PRESSURE HITAM 2,5 "
18 PIPA BESI HIGH PRESSURE HITAM 3 "
19 PIPA BESI HIGH PRESSURE HITAM 4 "
20 PIPA BESI HIGH PRESSURE HITAM 6 "
21 PIPA GALVANIS DIA 1.6"

H. BAHAN SANITAIR
1 KLOSET JONGKOK
2 KLOSET DUDUK
3 FLOOR DRAIN
4 CLEAN OUT 0.2" (SARINGAN AIR KOTOR)

halaman 106 dari 138


5 BAK FIBERGLASS 1 M3
6 WASTAFEL
7 TEMPAT SABUN
8 GANTUNGAN HANDUK
9 KACA KAMAR MANDI
10 MESIN POMPA AIR
11 URINOIR
12 BAK CUCI STAINLESS STEEL / KITCHEN SINK
13 SEAL TAPE
14 BATHTUB KOMPLIT
15 TANKI AIR
16 TANKI AIR
17 IJUK

halaman 107 dari 138


I. BAHAN PAKU
1 PAKU ATAP GENTENG METAL
2 PAKU KAYU
3 PAKU SENG
4 PAKU ASBES
5 PAKU 1"
6 PAKU 2" - 5"
7 PAKU SKRUP + BAUT + KARET DIA. 8"
8 ANGKER BESI
9 BESI STRIP 2"
10 PAKU GYPSUM
11 PAKU TRIPLEKS / TEAKWOOD
12 SKREW ATAP
13 SEKREW GYPSUM/PAKU SEKRUP
14 PAKU RAMSET

J. BAHAN PENGGANTUNG / KUNCI


1 KUNCI 2 SLAAG
2 KUNCI 1 SLAAG
3 KUNCI BIASA
4 GRENDEL PINTU
5 ENGSEL PINTU
6 ENGSEL JENDELA
7 ENGSEL TANAM PINTU
8 GRENDEL JENDELA
9 HAK ANGIN JENDELA
10 HANDLE JENDELA
11 HANDLE PINTU
12 KUNCI GEMBOK
13 KUNCI TANAM ANTIK
14 DOOR CLOSER
15 DOOR STOP

K. BAHAN KACA
1 KACA BENING
2 KACA BENING
3 KACA NAKO (RANGKA 9 DAUN + BESI)
4 KACA BURAM (DOP)
5 KACA BURAM (DOP)
6 KACA BLOK / GLASSBLOCK
7 KACA PATRY TEBAL 8 MM BINGKAI TEMBAGA (3 LAPIS)
8 KACA PATRY TEBAL 16 MM BINGKAI TEMBAGA (3 LAPIS)
9 KACA PATRY TEBAL 17 MM BINGKAI KUNINGAN (3 LAPIS)

halaman 108 dari 138


10 KACA GRAVIR
11 KACA RIBEN

L. BAHAN LISTRIK
1 TITIK LAMPU (KABEL INSTALASI STANDAR PLN)
2 LAMPU PIJAR
3 LAMPU PIJAR
4 LAMPU NEON (JANTUNG) 35 WATT
5 LAMPU TL KOMPLIT
6 LAMPU TL KOMPLIT
7 LAMPU TL KOMPLIT
8 LAMPU TL KOMPLIT
9 LAMPU TL KOMPLIT

halaman 109 dari 138


10 STOP KONTAK (STANDAR PLN)
11 PANEL BOX (STANDAR PLN)
12 PANEL INDUK
13 SAKLAR TRIPLE (STANDAR PLN)
14 SAKLAR GANDA (STANDAR PLN)
15 SAKLAR TUNGGAL (STANDAR PLN)
16 LAMPU SAVE ENERGY 18 WATT
17 LAMPU SAVE ENERGY 25 WATT
18 LAMPU DOWN LIGHT KOMPLIT 20 WATT
19 LAMPU DOWNLIGHT KOMPLIT 18 WATT
20 LAMPU BARET KOMPLIT
21 LAMPU HIAS TANAM KOMPLIT
22 PANEL MCB KOMPLIT (STANDAR PLN)
23 EXHAUSST FAN BESAR
24 EXHAUSST FAN KECIL

M. BAHAN PINTU
1 PINTU PANIL KELAS I
2 PINTU PANIL KELAS II
3 PINTU TERALI BESI dia 12 mm
4 PINTU KACA 10 mm
5 PINTU TEAKWOOD
6 PINTU PLYWOOD
7 PINTU FIBER WARNA
8 PINTU PANIL KACA
9 PINTU ALUMUNIUM KACA (KOMPLIT)
10 PINTU FIBERGLASS MOTIF
11 PINTU BESI ROLLING DOOR

N. BAHAN FINISHING
1 CAT MINYAK
2 CAT TEMBOK
3 CAT VERNISH
4 CAT KAYU DASAR / MENI
5 ALKALI
6 KAPUR TEMBOK
7 MINYAK CAT / THINNER
8 RESIDU
9 DEMPUL
10 PLAMIR
11 KERTAS PASIR / AMPLAS
12 PLITUR
13 TEMPAT ADUKAN CAT

halaman 110 dari 138


14 TEPUNG PENGISI NAT KERAMIK
15 TEPUNG PENGISI NAT GYPSUM / CORNICE
16 KUAS 3"
17 KUAS GULUNG / ROL
18 MINYAK BEKISTING
19 SODA API
20 SABUN
21 LEM
22 LEM KAYU
23 BATACOTE
24 WALLPAPER
25 CAT IMPRA
26 CAT EKSTERIOR (WEATHER SHIELD)

halaman 111 dari 138


O. BAJA RINGAN
1 SUPERTRUSS C75. 100 INT / SETARA
2 SUPERTRUSS C75. 75 INT / SETARA
3 TOPSPAN 40,055 INT
4 WTEKS 12-14 x 20 HWFS CLASS II
5 CSP 10-16 x 16 HWFS CLASS II
6 SG 10 MULTIPLATE

halaman 112 dari 138


DAFTAR HARGA SATUAN UPAH DAN BAHAN
GAN DINAS PERUMAHAN PERMUKIMAN DAN CIPTA KARYA
KOTA PEKANBARU
TAHUN ANGGARAN 2016

JENIS UPAH / BAHAN

halaman 113 dari 138


CM
CM
CM
CM
CM

halaman 114 dari 138


MM
MM
MM
MM
MM LAPIS MIKA
MM
MM
MM

halaman 115 dari 138


halaman 116 dari 138
CM
CM
CM
CM
CM
CM
CM
CM
CM
CM

CM
CM
CM
CM

halaman 117 dari 138


halaman 118 dari 138
MM
MM

"
"
"
"
"
"
"
"
"
"
"
"
1"
3/4 "
1/2 "

halaman 119 dari 138


0.5 M3
1 M3

halaman 120 dari 138


4 "
4 "
3 "

2 "

3 "

3 MM
5 MM

3 MM
5 MM

halaman 121 dari 138


5 MM
5 MM

25 WATT
40 WATT

1X20 WATT TKI 2 X 18


2X20 WATT TK0 2 X 18
1X40 WATT TK0 2 X 30
1X40 WATT TKI 2 X 30

halaman 122 dari 138


20 WATT

halaman 123 dari 138


halaman 124 dari 138
Pekanbaru, September 2016

Plt. Kepala Dinas


DINAS PERUMAHAN PERMUKIMAN DAN CIPT
KOTA PEKANBARU

dto

Ir. S Y A F R I, MT
NIP. 19640128 199203 1 002

halaman 125 dari 138


SATUAN HARGA SATUAN

3 4

HARI 100,000.00
HARI 90,000.00
HARI 80,000.00
HARI 75,000.00
HARI 100,000.00
HARI 80,000.00
HARI 80,000.00
HARI 75,000.00
HARI 100,000.00
HARI 80,000.00

M3 120,000.00
M3 140,000.00
M3 165,000.00
M3 80,500.00
M3 88,125.00
M3 258,000.00
M3 240,000.00
M3 270,000.00
M3 385,000.00
M2 27,000.00
Bh 600.00
Bh 11,515.00
Kg 1,400.00
Kg 2,600.00
Bh 3,500.00
Bh 3,500.00
Bh 41,000.00
Bh 23,500.00

halaman 126 dari 138


Bh 23,500.00
M2 253,000.00
Bh 180,000.00
Bh 264,500.00
Bh 325,000.00
Bh 640,000.00
Bh 680,000.00
M3 143,800.00
M2 23,000.00
M2 31,700.00
Kg 14,000.00
Kg 14,000.00

M3 660,000.00
M3 700,000.00
M3 807,500.00
M3 927,500.00
M3 958,300.00

halaman 127 dari 138


M3 1,034,700.00
M3 1,075,000.00
M3 1,140,800.00
M3 1,171,300.00
M3 1,201,800.00
M3 1,265,000.00
M3 1,391,500.00
M' 182,500.00
M' 240,000.00
M' 810,850.00
M' 860,000.00
M' 1,072,700.00

M3 6,000,000.00
M3 3,500,000.00
M3 2,200,000.00
M3 4,900,000.00
M3 2,200,000.00
M3 2,200,000.00
LBR 58,700.00
LBR 68,000.00
LBR 72,000.00
LBR 95,700.00
LBR 107,000.00
LBR 133,000.00
LBR 175,000.00
LBR 100,000.00
BTG 32,600.00
BTG 25,000.00
M3 2,300,000.00
M' 4,500.00
M' 92,000.00
M' 287,500.00
M2 402,500.00
M2 690,000.00
M' 550,000.00
Bh 345,000.00
Bh 793,500.00
Bh 600,000.00
IKAT 83,375.00

halaman 128 dari 138


Kg 12,200.00
Kg 13,000.00
Kg 20,000.00
Kg 25,000.00
M2 24,000.00
M2 21,500.00
Bh 66,200.00
M' 3,500.00
Kg 20,800.00
M2 150,000.00
Bh 550,000.00

halaman 129 dari 138


M' 350,000.00
M' 400,000.00
M' 74,500.00
M2 850,000.00
M' 57,500.00
M2 695,000.00

M2 175,000.00
M2 92,000.00
M2 75,000.00
M2 74,000.00
M2 74,800.00
M2 71,000.00
Bh 3,000.00
Bh 3,500.00
Bh 5,000.00
Bh 6,000.00
Bh 17,300.00
Bh 9,400.00
M' 8,100.00

Bh 186,900.00
Bh 82,800.00
Bh 35,132.50
Bh 8,100.00
M2 1,250,000.00
M2 17,000.00
M2 238,000.00
M2 230,000.00
M2 175,000.00
M2 74,800.00
M2 34,500.00

LBR 77,000.00
LBR 90,000.00
LBR 31,700.00
M2 180,000.00
M2 95,000.00
M2 80,000.00
LBR 25,000.00

halaman 130 dari 138


LBR 26,000.00
LBR 25,000.00
LBR 55,000.00
LBR 95,000.00
M' 10,000.00
LBR 40,500.00
M2 9,800.00
M2 40,500.00
BH 8,000.00
M' 27,250.00
LBR 25,000.00

halaman 131 dari 138


LBR 76,375.00
LBR 96,000.00
BTG 1,175.00
M' 5,640.00
M' 23,000.00
M2 550,000.00
M2 57,000.00
Rol 10,000.00
Kg 35,000.00
M2 550,000.00
M2 200,000.00
M2 650,000.00

Bh 31,700.00
Bh 27,500.00
Bh 27,500.00
M' 9,125.00
M' 10,375.00
M' 12,000.00
M' 15,440.00
M' 21,300.00
M' 60,400.00
M' 67,300.00
Bh 25,300.00
Bh 19,200.00
M' 49,000.00
M' 35,250.00
M' 21,500.00
M' 60,000.00
M' 70,000.00
M' 80,000.00
M' 140,000.00
M' 193,000.00
BTG 850,000.00

Bh 415,000.00
Bh 1,735,000.00
Bh 327,000.00
Bh 50,000.00

halaman 132 dari 138


Bh 255,000.00
Bh 1,425,000.00
Bh 50,375.00
Bh 100,750.00
Bh 222,075.00
UNIT 1,725,000.00
Bh 1,587,000.00
Bh 385,000.00
Bh 9,025.00
UNIT 6,000,000.00
Bh 850,000.00
Bh 1,552,500.00
Kg 32,000.00

halaman 133 dari 138


Kg 29,900.00
Kg 15,000.00
Kg 28,800.00
Kg 25,300.00
Kg 20,000.00
Kg 15,000.00
Bh 20,000.00
Bh 8,000.00
Kg 14,500.00
Kg 32,400.00
Kg 21,900.00
Bh 700.00
Bh 450.00
Kg 15,000.00

Bh 334,875.00
Bh 232,062.50
Bh 143,000.00
Bh 17,300.00
Bh 88,000.00
Bh 65,000.00
Bh 45,000.00
Bh 33,500.00
Bh 16,500.00
Bh 195,000.00
Bh 143,800.00
Bh 80,000.00
Bh 500,000.00
Bh 258,000.00
Bh 250,000.00

M2 76,375.00
M2 111,625.00
UNIT 211,500.00
M2 133,950.00
M2 135,125.00
Bh 25,000.00
M2 1,900,000.00
M2 2,400,000.00
M2 2,600,000.00

halaman 134 dari 138


M2 1,200,000.00
M2 125,000.00

TITIK 190,000.00
Bh 35,000.00
Bh 45,000.00
Bh 75,000.00
Bh 95,000.00
Bh 150,000.00
Bh 450,000.00
Bh 260,000.00
Bh 400,000.00

halaman 135 dari 138


Bh 50,000.00
Bh 2,000,000.00
Bh 9,500,000.00
Bh 108,000.00
Bh 75,000.00
Bh 47,000.00
Bh 65,000.00
Bh 70,000.00
Bh 220,000.00
Bh 115,000.00
Bh 275,000.00
Bh 2,900,000.00
Bh 180,000.00
UNIT 550,000.00
UNIT 450,000.00

Bh 4,025,000.00
Bh 690,000.00
Bh 1,527,500.00
Bh 2,467,500.00
LBR 684,000.00
LBR 225,000.00
LBR 281,325.00
LBR 1,339,500.00
LBR 2,000,000.00
LBR 500,000.00
M2 700,000.00

Kg 93,000.00
Kg 86,550.00
Kg 60,000.00
Kg 36,225.00
Kg 30,000.00
Kg 88,770.00
LTR 28,000.00
Kg 11,500.00
Kg 29,900.00
Kg 40,000.00
LBR 5,000.00
LTR 46,000.00
Bh 10,000.00

halaman 136 dari 138


Kg 13,000.00
Kg 5,200.00
Bh 11,500.00
Bh 31,700.00
LTR 9,500.00
Kg 11,750.00
Bh 10,000.00
Kg 6,815.00
LTR 30,000.00
Kg 40,000.00
M2 250,000.00
Kg 52,900.00
Kg 100,000.00

halaman 137 dari 138


Kg 35,250.00
Kg 29,375.00
Kg 29,375.00
PC 800.00
PC 600.00
PC 6,250.00

Pekanbaru, September 2016

Plt. Kepala Dinas


ERUMAHAN PERMUKIMAN DAN CIPTA KARYA
KOTA PEKANBARU

dto

Ir. S Y A F R I, MT
NIP. 19640128 199203 1 002

halaman 138 dari 138