Aace International Scheduling: Making Time Calculations
This document discusses scheduling techniques for projects, including activity coding, work breakdown structures (WBS), and forward and backward passes. It explains that the WBS provides a hierarchical structure to organize project activities from high level summaries to detailed tasks. Each activity is assigned a unique code corresponding to its place in the WBS. Calculating early and late start/finish dates involves performing forward and backward passes through the network to determine the earliest and latest possible schedules.
Aace International Scheduling: Making Time Calculations
This document discusses scheduling techniques for projects, including activity coding, work breakdown structures (WBS), and forward and backward passes. It explains that the WBS provides a hierarchical structure to organize project activities from high level summaries to detailed tasks. Each activity is assigned a unique code corresponding to its place in the WBS. Calculating early and late start/finish dates involves performing forward and backward passes through the network to determine the earliest and latest possible schedules.
bered 21000 and 22000. Summarizing on WBS 2, where the
first digit is equal to 2, provides the total project process In addition to the previous construction example, Figure information. 13.12 is provided to display a nonconstruction WBS example. The lowest level of any WBS of the project constitutes the SCHEDULING TECHNIQUES detailed work activities. Higher levels constitute summaries of the detailed activities. Making Time Calculations Once a network has been created and the duration of each Activity Coding activity has been established, both the total time required to Table 13.3 illustrates a listing of detailed schedule activities. reach project completion and the individual start and finish Included in Table 13.3 is the process WBS coding. The code times for each activity can be calculated. The four time values for each WBS can be input into one of many activity code as associated with each activity are Early Start (ES), Early fields when using computer-based project management sys- Finish (EF), Late Start (LS), and Late Finish (LF). tems. It is necessary that every activity have a unique alphanumeric identifier. It is generally better to use the The computations required to calculate the above times process-based WBS since it is usually the most detailed WBS. involve simple addition and subtraction. Manual computa- tion is easy and logical, but it can become tedious and time The WBS for any particular project is usually prepared by proj- consuming when done for large networks. ect control personnel. However, project control personnel do not perform the actual work. Consequently, it is imperative Forward and Backward Pass that project control personnel and the project personnel who The forward pass through the network determines each actually do the work reach an agreement concerning the WBS. activity’s ES and EF and the project’s duration or the earliest Table 13.3—Detailed Activity List with WBS Coding date a project can finish. The backward pass through the net- work determines each activity’s LS and LF. The calculations assume that activities begin on the morning of the scheduled start date and end in the evening of the scheduled finish date and that an event or milestone occurs on the evening of the day its last predecessor finished.
Before starting the network calculation, the precedence net-
work list of activities is revisited to include the activity dura- tion as shown in Table 13.4. The activity duration is the