STD 137 PDF
STD 137 PDF
FOR RESTRICTED
CIRCULATION
Prepared by
COMMITTEE ON
INSPECTION AND MAINTENANCE OF ELECTRICAL EQUIPMENT
The Co-ordinator,
Committee on
“Inspection & Maintenance of Electrical Equipment”
OIL INDUSTRY SAFETY DIRECTORATE
7th Floor, ‘New Delhi House’
27, Barakhamba Road
New Delhi – 110 001
.
COMMITTEE ON PROCESS INSPECTION AND
MAINTENANCE OF ELECTRICAL EQUIPMENT.
LIST OF MEMBERS
----------------------------------------------------------------------------------------------------------------------------
Name Designation / Organisation Position in
Committee
----------------------------------------------------------------------------------------------------------------------------
S/Shri
SECTION
1.0 Introduction
2.0 Scope
3.0 Definitions
4.0 Permit-to-work(Electrical)
8.0 Documentation
10.0 References
ANNEXURES
I Protective relay inspection & test record
II Maintenance card of transformer & breaker
SECTION
iii) At times, different agencies area called i) This Clearance shall be taken by
upon to work on same equipment. UIC EIC, from Permit Issuing Authority
shall ensure that Work Permits of all (Electrical), wherever earth
the agencies are closed before excavation is to be carried out.
recharging the equipment. Similarly, Without such clearance, if excavation
the equipment may have more than is carried out, especially over
the one source of electric supply. energised underground electrical
Before issuing any Permit to EIC, UIC facilities it may cause fatal accidents
shall arrange through Electrical-in- to the personnel, besides adversely
charge for: affecting the plant operation due to
possible damage of such
(a) Positive Electrical Isolation (by underground facilities (e.g. piercing
disconnection of all sources of the insulation of live cable through
electric power supply) and sharp tool like pickaxe).
obtaining Electrical Isolation Line
Clearance. ii) After first obtaining permission from
UIC for the work, Earth Excavation
(b) Effective earthing of line/ Line Clearance shall be taken by EIC
equipment (Isolated section) from Permit-Issuing Authority
(Electrical) in an approved format to
iv) After completion of the work, EIC shall be developed by individual
arrange to deenergise and remove all organisations depending on the type
temporary installations, construction of installations and administrative set
materials, debris and withdraw up. While designing the format, the
personnel from site, and returns Work need of owner-in-charge concept
Permit/Clearances to UIC. UIC shall shall also be taken care of, as
arrange for safe charging of the defined in OISD-STD-105 (Work
equipment after obtaining Electrical Permit System).
Energisation Line Clearances.
iii) Permit-Issuing Authority (Electrical)
v) Throughout the work, Authorised shall spell out the precautions to be
Person shall ensure that the switches taken, while carrying out such earth
excavation, in the Clearance itself. Failures of electrical equipment gives rise
Prior to issue of Clearance, he shall to any or all the following hazards:
ensure that the proposed excavation
does not interfere with existing i) Fatal accidents due to electric shock.
underground electrical facilities such
as power (H.T & L.T), telephone, fire ii) Fire accidents and burn injuries due to
alarm, lighting, and control cables, electric arcs/sparks/hot surfaces
earthing, and cathodic protection
installations etc., iii) Abrupt interruption in plant operation..
iv) EIC shall ensure compliance of all the The failures of electrical equipment can be
safety measures including those attributed to:
stipulated in the Clearance and
provide supervision throughout the i) Imposed external conditions such as
work for safe excavation and deterioration of enclosure, insulation
protection of the underground facilities and operating mechanism by
from any damage due to excavation. environment conditions like heat,
He shall promptly report to Permit- moisture, dust, chemical attack and dirt.
Issuing Authority (Electrical) any
damage to underground facilities even ii) Quality of power supply (like
if it be of minor nature, and shall undervoltage, powerdips, unbalanced
proceed with the excavation work only voltage, frequently failures of power
after complying with further supply etc.)
instructions, as endorsed in Permit, if
any. iii) Overloading due to any reason.
v) Irrespective whether mentioned or not iv) Internal faults in the equipment itself
in the Clearance, whenever mainly due to manufacturing defects,
bricklayer, tiles or cables sleeves are or those crept in during installation,
encountered during the excavation maintenance and repairs.
work (which confirm electrical
facilities below), EIC, after stopping v) Inferior quality of work due to factors
excavation work, shall inform of the like poor workmanship by
same to Permit-issuing Authority unqualified/unskilled and untrained
(Electrical) and obtain further workers, inadequate or incompetent
instructions to proceed. supervision, non-compliance of
safety and statutory requirements,
vi) The Earth Excavation Line Clearance adoption of incorrect procedures, and
shall be issued only after EIC first usage of poor quality of tools and
obtains Work Permit from UIC for his tackles.
work in the particular location of the
unit. vi) Usage of substandard materials and
equipment not in conformity with
vii) UIC shall ensure that EIC closes main original design specifications.
Work Permit only after his first
closing Earth Excavation Line vii) Design deficiencies in the technical
Clearance, and obtaining Clearance specifications, improper sizing and
from Permit-Issuing Authority layout of installations and lack of total
(Electrical) which shall confirm that system concept.
the excavation was carried out safely,
trenches backfilled, the construction viii) Bypassing of protective and
materials and debris cleared, and interlocking devices/circuits during
personnel withdrawn from the site. operation though originally designed
for the system.
5.0 BASIS AND TYPES OF
INSPECTION ix) Inability for carrying out shutdown
inspection/tests on the equipment in
time, as required by maintenance
5.1 BASIS OF INSPECTION inspection schedules, due to
difficulties in taking the equipment out without any downtime of unit operation.
of service. The standby rotary equipment shall
additionally be checked at least once
Inspection programmed on electrical every two months for-
equipment and associated circuits shall be
devised on the basis that the inspection a) Free rotation of shaft
results will be able to pinpoint the trouble b) Proper functioning of space heater
spots in the installations, well in advance, circuit
allowing ample time for the maintenance c) Weather protection.
personnel to take remedial measures, so d) Insulation resistance of motor with
as to prevent failure of equipment leading cable.
to unsafe conditions and hazards as
mentioned above. No equipment shall be If, however, standby equipment was not
operated beyond its safe life period energised earlier, all applicable
assessed on the basis of inspections from Precommissioning checks, as detailed in
time to time and optimum replacement Section 9.0 shall be carried out before
schedule shall be followed. Manufacturer’s taking it into service.
recommendation shall prevail wherever
available. The spare parts shall be inspected to
ensure compliance with original
5.2 TYPES OF INSPECTION specifications as per manufacturers’
catalogue number.
The field inspection of electrical equipment
in an operating unit is classified into 6.0 FREQUENCY OF
following three types: INSPECTION
i) ONSTREAM INSPECTION The inspection scheme given in the
following tabular format shall be followed
This covers audio visual inspection items as minimum requirement for the items to
(instrument aided or otherwise) for be inspected. Frequencies of inspection in
checking of general equipment conditions, this format have been arrived at,
while the equipment is in operation. (e.g. considering a typical installation and
an abnormal nose or vibration of motor, therefore shall be treated as guidelines.
leakage of transformer oil or overheating Depending on specific requirements of the
of equipment etc., can be assessed installation, considering severity of usage,
through such inspections). criticality of equipment, environmental
conditions and such other factors,
ii) SHUTDOWN INSPECTION individual organisations shall review and
develop own inspection frequency
This covers those inspection items for standards which shall be strictly followed.
checking conditions of equipment and
systems which cannot be revealed through The frequency of inspection for new or
Onstream Inspection (such as internal special equipment, where previous
condition of equipment). This inspection experience is not available, shall be
shall be carried out after taking the reviewed by the concerned organisation,
shutdown of the related equipment after after one or two inspections and
obtaining the Electrical Line Clearance, reconsidered whether the interval could be
and Work Permit, requirements of which lengthened safely or should be shortened.
are detailed in Section 4.0 and in OISD- care shall be taken against the bad effects
STD-105 (Work Permit System) of over maintenance especially for
flameproof and such critical installations.
iii) INSPECTION OF STANDBY No attempt should be made to replace or
EQUIPMENT AND SPARE repair a glass in a flameproof enclosure
PARTS (e.g. in lighting fixture or the parts) except
with the complete assembly or part
The standby electrical equipment electrical obtainable from the manufacturer for
equipment shall be inspected on the same which the flameproof certificate from the
basis and schedule applicable under item competent authority shall be obtained to
(ii) above, so that changeover from normal confirm its flame proofness.
to standby equipment shall be possible
For inspection procedures, Section 7.0 vii) Surface overheating F
shall be referred. The safety Electrical viii) Ventilation F
Line Clearances as required in Section 4.0 ix) Abnormal noise F
shall be obtained for work where Electrical x) Functioning of meters F
Isolation is needed or when any work is to xi) Corrosion effects (external M
be carried out in close proximity to bare xii) Provision of Guards to M
energised electrical circuits. moving parts
xiii) any other inspection
Insulation resistance, earth resistance and recommended by the
continuity tests, when required to be manufacturer
carried out in an hazardous area, shall be Note:
carried out only with certified intrinsically
safe insulation/earth tester suitable for use For critical generators such as for Captive
in classified hazardous area, after taking plants, the frequency of inspection shall be
the shutdown of the related equipment Daily (D) basis for all items, except for
through permit system. items (XIII) and (XIV).
x) * Insulation deterioration
(Polarisation Index Test) Y
Note :
Note:
--Space heater
--Temperature detector
--Interlocks,/trips
--Annunciation circuits
vi) Availability of all protective
devices and circuits in line
as per design, and all in
operating condition.
vii) Condition of remote tripping
devices & limit switches
viii) Limit & torque switches (in
the case of motor operated
valves) for proper
functioning.
ix) Oil level in lubricating
gearcase.
x) “Moisture absorption ( Di-
electric Absorption Test)
xi) Insulation deterioration
(Polarisation Index Test)
“ Items (x) and (xi) are needed for critical The following shall be Shutdown
high voltage equipment only. Inspection items:
Note:
iii)
Float voltage & charging W
current
iv) Overheating W
v) External damages W
Notes:
6.2.5. U.P.S/Invertor
i) General cleanliness,
(accumulation of dust, and
dirt on contactors, diodes,
thristors, transformers and
other components) and
external damages W
i) Internal damages HY
6.2.6 Reactor and Capacitor ii) Oil level and oil leakage D
i) Operation of switchyard
The following shall be Shutdown equipment with control,
Inspection items: trip, and annunciation
circuits HY
i) Insulation resistance Q
ii) Internal damages HY
ii) Discolouration on cable
connector clamps Q iii) Condition of insulators
HY
iii) Earth resistance Q iv) Alignment between
contacts HY
iv) Operation of protective
devices Q v) Insulation resistance HY
--Cleanliness
viii) Any other inspection
recommend by the --Breakages (of glass cover etc.)
manufacturer
-- Calibration test, and other safety checks
6.2.8 Lighting Fixture & Junction-box before use as per manufacturer’s
(installed for plant/yard/street and recommendation
building lighting.)
--Zero setting, errors
The following shall be Onstream
Inspection items; --Bent pointers, sticky or jerky movement
v) Earth resistance on
The following shall be Shutdown individual electrodes once
Inspection items: in dry and one in wet HY
weather
i) Trip circuit operation
(simulation test) TA vi) Continuity of earthing
conductors Y
ii) Relay operation under fault
conditions simulated vii) Bonding and earthing of
(primary injection) TA all metallic structures, pipe
racks, armour of cables,
iii) Changeover circuit and electrical equipment
operation HY enclosures Y
vii) Voltage drop at the farthest end iv) Mechanical protection to under
of tracer M ground and overhead cables
(especially for energised
viii) Tightness of connections M cables) HY
Notes:
1. It shall be checked (through random viii) Infringement and growth
trial pits) that the underground cables of vegetation M
are protected with sand and bricks
thoughout and ensure that the cables ix) Any damages to
are not exposed at any location. Also insulators and other
armouring, pipe sleeves and such other devices M
mechanical protection requirements
shall be inspected. x) Earthing of staywire M
II) Manufacturer’s test certificates shall The items listed below shall be
be obtained(for the successful checked/tested before start up:
passing of shop tests.
I) Mechanical and electrical checks as per
III) Installations conform to acceptable IS: 900
engineering standards and are
appropriate to the respective ii)Cleanliness (free from dirt, dust and
hazardous area classifications (as moisture)
per ISI-NEC-1985). Installations
with all individual Isolating devices iii)Insulation resistance (before and after
(for safe disconnection of electrical connection of the power cables)
circuits) shall be easily accessible
for regular and emergency operation iv)D.C. resistance of stator and rotor
and maintenance. windings(This should not differ from
manufacturers’ data by more than 2%)
9.1 ROTATING MACHINERY
v) Polarisation Index and Dielectric e) Vibration
Absorption tests (for critical equipment f) No load current
only) g) Speed
xxi) Control supply availability ix) Explosion vent diaphragm not having
any dents, accumulation of any
xxii) Provision of fire fighting equipment oil/air(whether released)
suitable for electrical fires.
x) Buchholz relay (frinctionless movement
xxiii) Electrical & manual closing and and floats)
tripping of all circuit breakers (remote
and local) xi)Protective checks on tips and alarms
(simulation)
xxiv) Provision of phase barriers and
partitions (to avoid inadvertent xii) Polarity and ration tests
contact with live parts.
xiii) Arcing gaps for the bushings
xxv) Corrosion effects (whether to be
painted) xiv) Earthing connections for the surge
divertor
xxvi) Condition of supporting structure
xiv) Operation of the tap changer circuits
xxvii)Earthing connections/resistance on all the tap positions (simulation)
The following checks/tests shall be carried xvii) Operation of tap changer limit switch
out: on the maximum tap positions.
xxvii) Vermin & dust proofness and earth viii) Spillage of electrolyte
connections of bus ducts
ix) Tightness of wiring connections
xxviii) Busduct supports
x) provision of required protective devices
xxix) Expansion joints and flexible and annunciations.
connection of busduct
9.2.5 Lighting System
xxx) Cable terminations
The following shall be checked/tested:
xxxi) Provision of caution boards
I) Installation and components meet the
After commissioning the requirements set by environmental
transformer, the following pints shall be conditions and conform to approved
observed, and recorded: drawings/specifications
vii) Current, voltage, and temperature vi) Tightness of wiring connections at the
readings (hourly for 24 hours when terminals
transformer is loaded)
vii) Cable terminals
viii) Cables end boxes for any overheating
viii) Ratings of fuses, MCBS and switches
9.2.4 Battery & Charger
ix) Insulation resistance between phases
The items listed below shall be and between phases & earth.
checked/ensured:
x) Weatherproofing and vermin proofness
I) Battery not affected by sunlight.
xi)Earthing connection/earth resistance
ii) Proper ventilation and provision of acid values
proof flooring in the battery room.
xii) Size and type of cables, wires and
iii)Conformity of electrolyte to IS:266 & its conduits used
level
xiii)Painting (corrosion effect
xiv) Functional checks of lighting circuits ix) Continuity of core to confirm no open
for operation circuit.
xvii) Available illumination levels areawise I) Indian Electricity (i.E) Rules 1956/Act-
to confirm operation and safety 1910
requirements through field ii) Bureau of Indian Standards-ISI:s
inspection with UIC) publication: IS:2705, IS:3156, IS:3043,
IS:1554, IS:2309, IS:5216, IS:335,
xviii) Circuit identifications and markings in IS:266, IS:900, IS:3156, IS:10029,
the field. IS:1255, IS:732, IS:5572, IS:2148,
IS:7389, IS:3072, IS:4770, IS:10118,
9.2.6 CABLES IS:1866, IS:2516, IS:5124,
The items listed below shall be iii) ISI-national Electrical Code, 1985
checked/ensured:
iv) Model code of safe practice Electrical-
I) Identification of the cable with equipment Part 1, 1974 (Institute of Petroleum
tag no., circuit inscription, provision of publication)
cable route markers and joint
location markers. v) Guide for Inspection of Refinery
Equipment-Chapter XIV-Electrical
ii) Depth of laying and spacing between System-(API-Publication) 1976
cables of different voltage grades
(random checks on trial pit basis). vi) OISD-STD-105 (Work Permit system),
1988
iii) Voltage rating, size and type of the
cable (to ensure correct specifications) vii) British Standard Code of Practice BS-
6651, CP-1013
iv) Cable support/clamping arrangement
viii) Regulations for the electrical
v) Cable terminals (especially for equipment of buildings. Fifteenth
flameproof, watertight terminaitions) eidtion 1976 (Institution of Electrical
Engineers - IEE’s publication)
vi) Armour earthing and bonding
ix) Oil Mine Regulation 1984
vii) Cable sleeves (whenever crossing the
roads, walls etc.,) x) Petroleum Rules 1976
viii) Insulation resistance of every circuit xi) Asian Electricity Journal, Oct 96.
(phase to phase, phase to ground and
armour)
ANNEXURE I
MANUFACTURER___________TYPE__________STYLE NO._________FUNCTION______
RELAY INSPECTION
DATE
COVER
GLASS TIGHT
GLASS CLEAN
GASKET TIGHT
RELAY CONDITION
DUST
RUST
IRON FILINGS
BEARINGS STICKY
SHORTCOMING
BARS IN PLACE
CONNECTIONS
TIGHT
CONTACTS
DIRTY
PITTED
OPERATIONS
INDICATOR
ARMATURE FREE
TARGET FREE
INSTANTANEOUS
ATTACHMENT
ARMATURE FREE
TARGET FREE
DISC.RUBBING
INSPECTION
ANNEXURE III
________________
_______________________________
CARD NO.
INSTALLATION.......................................................
UNIT _________________________ EQUIPMENT TAG NO.:___________
DATE______________
------------------------------------------------------------------------------------------------------------------------------------------
1. Present Failure/Abnormality Last Failure/Abnormality
Date: Date:
Nature: Nature:
Signature/name/Designation
(of the Officer preparing the
Report)
ANNEXURE VI
------------------------------------------------------------------------------------------------------------------------------------------
Signature/name/Designation
(of the Officer preparing the
Report)
ANNEXURE VII
CABLE FAULT DETECTION
(Ref.Asian Electricity Journal Oct. ‘86)
GENERAL
Fault locating procedure:
The use of particular fault finding equipment • Through diagnosis
depends on the factors such as type of fault, • Accurate route measurement
length of cable, location of cable, cable • Trustworthy pre-location (i.e correct
construction and, very important, funds instrument)
available for procurement.
(a) Contact fault:
Broad guidelines for methods and
equipment necessary Pulse Echo Set if fault resistance is
suitable. If not, H.V. Or High Resistance bridge
The methods and equipment necessary are: or Impulse current set can be used.