Heat protection measures at ZZ2

• Cooling room - Halliburton 20ft container is air conditioned and was


operational.
• Drinking water – Provided along with ice and available in 2 coolers.
• Shade – Cooling room as above.
• Work during peak temperature hours – Not avoided due to short
timeline and conducted at Peak hours.
• Resting and cycling crew – Only one crew available for rig up and rig
down.