MULTIPLE CHOICE
2. Decision variables
a. tell how much or how many of something to produce, invest, purchase, hire, etc.
b. represent the values of the constraints.
c. measure the objective function.
d. must exist for each constraint.
ANS: A PTS: 1 TOP: Objective function
3. Which of the following is a valid objective function for a linear programming problem?
a. Max 5xy
b. Min 4x + 3y + (2/3)z
c. Max 5x2 + 6y2
d. Min (x1 + x2)/x3
ANS: B PTS: 1 TOP: Objective function
5. A solution that satisfies all the constraints of a linear programming problem except the nonnegativity
constraints is called
a. optimal.
b. feasible.
c. infeasible.
d. semi-feasible.
ANS: C PTS: 1 TOP: Graphical solution
6. Slack
a. is the difference between the left and right sides of a constraint.
b. is the amount by which the left side of a £ constraint is smaller than the right side.
c. is the amount by which the left side of a ³ constraint is larger than the right side.
d. exists for each variable in a linear programming problem.
ANS: B PTS: 1 TOP: Slack variables
7. To find the optimal solution to a linear programming problem using the graphical method
a. find the feasible point that is the farthest away from the origin.
b. find the feasible point that is at the highest location.
c. find the feasible point that is closest to the origin.
d. None of the alternatives is correct.
ANS: D PTS: 1 TOP: Extreme points
8. Which of the following special cases does not require reformulation of the problem in order to obtain a
solution?
a. alternate optimality
b. infeasibility
c. unboundedness
d. each case requires a reformulation.
ANS: A PTS: 1 TOP: Special cases
9. The improvement in the value of the objective function per unit increase in a right-hand side is the
a. sensitivity value.
b. dual price.
c. constraint coefficient.
d. slack value.
ANS: B PTS: 1 TOP: Right-hand sides
10. As long as the slope of the objective function stays between the slopes of the binding constraints
a. the value of the objective function won't change.
b. there will be alternative optimal solutions.
c. the values of the dual variables won't change.
d. there will be no slack in the solution.
ANS: C PTS: 1 TOP: Objective function
11. Infeasibility means that the number of solutions to the linear programming models that satisfies all
constraints is
a. at least 1.
b. 0.
c. an infinite number.
d. at least 2.
ANS: B PTS: 1 TOP: Alternative optimal solutions
13. Whenever all the constraints in a linear program are expressed as equalities, the linear program is said
to be written in
a. standard form.
b. bounded form.
c. feasible form.
d. alternative form.
ANS: A PTS: 1 TOP: Slack variables
14. All of the following statements about a redundant constraint are correct except
a. A redundant constraint does not affect the optimal solution.
b. A redundant constraint does not affect the feasible region.
c. Recognizing a redundant constraint is easy with the graphical solution method.
d. At the optimal solution, a redundant constraint will have zero slack.
ANS: D PTS: 1 TOP: Slack variables
15. All linear programming problems have all of the following properties except
a. a linear objective function that is to be maximized or minimized.
b. a set of linear constraints.
c. alternative optimal solutions.
d. variables that are all restricted to nonnegative values.
ANS: C PTS: 1 TOP: Problem formulation
16. If there is a maximum of 4,000 hours of labor available per month and 300 ping-pong balls (x1) or 125
wiffle balls (x2) can be produced per hour of labor, which of the following constraints reflects this
situation?
a. 300x1 + 125x2 > 4,000
b. 300x1 + 125x2 < 4,000
c. 425(x1 + x2) < 4,000
d. 300x1 + 125x2 = 4,000
ANS: B PTS: 1 TOP: Problem formulation
17. In what part(s) of a linear programming formulation would the decision variables be stated?
a. objective function and the left-hand side of each constraint
b. objective function and the right-hand side of each constraint
c. the left-hand side of each constraint only
d. the objective function only
ANS: A PTS: 1 TOP: Problem formulation
18. The three assumptions necessary for a linear programming model to be appropriate include all of the
following except
a. proportionality
b. additivity
c. divisibility
d. normality
ANS: D PTS: 1 TOP: Problem formulation
20. A variable added to the left-hand side of a less-than-or-equal-to constraint to convert the constraint into
an equality is
a. a standard variable
b. a slack variable
c. a surplus variable
d. a non-negative variable
ANS: B PTS: 1 TOP: Slack variables
TRUE/FALSE
1. Increasing the right-hand side of a nonbinding constraint will not cause a change in the optimal
solution.
2. In a linear programming problem, the objective function and the constraints must be linear functions of
the decision variables.
4. Only binding constraints form the shape (boundaries) of the feasible region.
5. The constraint 5x1 - 2x2 £ 0 passes through the point (20, 50).
7. Because surplus variables represent the amount by which the solution exceeds a minimum target, they
are given positive coefficients in the objective function.
8. Alternative optimal solutions occur when there is no feasible solution to the problem.
9. A range of optimality is applicable only if the other coefficient remains at its original value.
10. Because the dual price represents the improvement in the value of the optimal solution per unit
increase in right-hand-side, a dual price cannot be negative.
12. No matter what value it has, each objective function line is parallel to every other objective function
line in a problem.
13. The point (3, 2) is feasible for the constraint 2x1 + 6x2 £ 30.
15. The standard form of a linear programming problem will have the same solution as the original
problem.
16. An optimal solution to a linear programming problem can be found at an extreme point of the feasible
region for the problem.
17. An unbounded feasible region might not result in an unbounded solution for a minimization or
maximization problem.
18. An infeasible problem is one in which the objective function can be increased to infinity.
20. It is possible to have exactly two optimal solutions to a linear programming problem.
SHORT ANSWER
1. Explain the difference between profit and contribution in an objective function. Why is it important for
the decision maker to know which of these the objective function coefficients represent?
ANS:
Answer not provided.
PTS: 1 TOP: Objective function
ANS:
Answer not provided.
3. Create a linear programming problem with two decision variables and three constraints that will
include both a slack and a surplus variable in standard form. Write your problem in standard form.
ANS:
Answer not provided.
ANS:
Answer not provided.
5. Use a graph to illustrate why a change in an objective function coefficient does not necessarily lead to
a change in the optimal values of the decision variables, but a change in the right-hand sides of a
binding constraint does lead to new values.
ANS:
Answer not provided.
ANS:
Answer not provided.
PROBLEM
6x + 2y = 50
2x + 4y = 20
ANS:
x = 8, y = 1
ANS:
x = 4, y = 4
Max 8x + 7y
s.t. 15x + 5y £ 75
10x + 6y £ 60
x+ y£8
x, y ³ 0
ANS:
a.
b. The optimal solution occurs at the intersection of constraints 2 and 3. The point is x = 3,
y = 5.
c. The value of the objective function is 59.
4. For the following linear programming problem, determine the optimal solution by the graphical
solution method
Max -x + 2y
s.t. 6x - 2y £ 3
-2x + 3y £ 6
x+ y£3
x, y ³ 0
ANS:
x = 0.6 and y = 2.4
a. Which area (I, II, III, IV, or V) forms the feasible region?
b. Which point (A, B, C, D, or E) is optimal?
c. Which constraints are binding?
d. Which slack variables are zero?
ANS:
Min 5x + 6y
s.t. 3x + y ³ 15
x + 2y ³ 12
3x + 2y ³ 24
x,y³0
ANS:
s.t. 2x + 3y £ 30
2x + 5y £ 40
6x - 5y £ 0
x,y³ 0
ANS:
Max 2x + 3y
s.t. 4x + 9y £ 72
10x + 11y £ 110
17x + 9y £ 153
x,y³0
ANS:
The complete optimal solution is x = 4.304, y = 6.087, s1 = 0, s2 = 0, s3 = 25.043, obj. func. = 26.87
Min 3x + 3y
s.t. 12x + 4y ³ 48
10x + 5y ³ 50
4x + 8y ³ 32
x,y³0
ANS:
10. For the following linear programming problem, determine the optimal solution by the graphical
solution method. Are any of the constraints redundant? If yes, then identify the constraint that is
redundant.
Max x + 2y
s.t. x+ y£3
x - 2y ³ 0
y£1
x, y ³ 0
ANS:
x = 2, and y = 1 Yes, there is a redundant constraint; y £ 1
11. Maxwell Manufacturing makes two models of felt tip marking pens. Requirements for each lot of pens
are given below.
ANS:
s.t. 3F + 4T £ 36
5F + 4T £ 40
5F + 2T £ 30
F,T³0
b.
12. The Sanders Garden Shop mixes two types of grass seed into a blend. Each type of grass has been
rated (per pound) according to its shade tolerance, ability to stand up to traffic, and drought resistance,
as shown in the table. Type A seed costs $1 and Type B seed costs $2. If the blend needs to score at
least 300 points for shade tolerance, 400 points for traffic resistance, and 750 points for drought
resistance, how many pounds of each seed should be in the blend? Which targets will be exceeded?
How much will the blend cost?
Type A Type B
Shade Tolerance 1 1
Traffic Resistance 2 1
Drought Resistance 2 5
ANS:
Let A = the pounds of Type A seed in the blend
Let B = the pounds of Type B seed in the blend
Min 1A + 2B
s.t. 1A + 1B ³ 300
2A + 1B ³ 400
2A + 5B ³ 750
A, B ³ 0
The optimal solution is at A = 250, B = 50. Constraint 2 has a surplus value of 150. The cost is 350.
13. Muir Manufacturing produces two popular grades of commercial carpeting among its many other
products. In the coming production period, Muir needs to decide how many rolls of each grade should
be produced in order to maximize profit. Each roll of Grade X carpet uses 50 units of synthetic fiber,
requires 25 hours of production time, and needs 20 units of foam backing. Each roll of Grade Y carpet
uses 40 units of synthetic fiber, requires 28 hours of production time, and needs 15 units of foam
backing.
The profit per roll of Grade X carpet is $200 and the profit per roll of Grade Y carpet is $160. In the
coming production period, Muir has 3000 units of synthetic fiber available for use. Workers have been
scheduled to provide at least 1800 hours of production time (overtime is a possibility). The company
has 1500 units of foam backing available for use.
ANS:
Let x = the number of rolls of Grade X carpet to make
Let y = the number of rolls of Grade Y carpet to make
14. Does the following linear programming problem exhibit infeasibility, unboundedness, or alternate
optimal solutions? Explain.
Min 1x + 1y
s.t. 5x + 3y £ 30
3x + 4y ³ 36
y£7
x,y³0
ANS:
The problem is infeasible.
Min 3x + 3y
s.t. 1x + 2y £ 16
1x + 1y £ 10
5x + 3y £ 45
x,y³0
ANS:
The problem has alternate optimal solutions.
16. A businessman is considering opening a small specialized trucking firm. To make the firm profitable, it
is estimated that it must have a daily trucking capacity of at least 84,000 cu. ft. Two types of trucks are
appropriate for the specialized operation. Their characteristics and costs are summarized in the table
below. Note that truck 2 requires 3 drivers for long haul trips. There are 41 potential drivers available
and there are facilities for at most 40 trucks. The businessman's objective is to minimize the total cost
outlay for trucks.
Capacity Drivers
Truck Cost (Cu. Ft.) Needed
Small $18,000 2,400 1
Large $45,000 6,000 3
Solve the problem graphically and note there are alternate optimal solutions. Which optimal solution:
a. uses only one type of truck?
b. utilizes the minimum total number of trucks?
c. uses the same number of small and large trucks?
ANS:
a. 35 small, 0 large
b. 5 small, 12 large
c. 10 small, 10 large
s.t. x + 3y ³ 9
6x - 2y = 12
x + 2y £ 10
x, y ³ 0
ANS:
S.T. x + 3y - s1 = 9
6x - 2y = 12
x + 2y + s3 = 10
x, Y, s1, s3 ³ 0
b. Line segment of 6x - 2y = 12 between (22/7,24/7) and (27/10,21/10).
c. Extreme points: (22/7,24/7) and (27/10,21/10). First one is optimal; obj. func. = 336.
Max 5x + 7y
s.t. x £6
2x + 3y £ 19
x+ y£8
x, y ³ 0
ANS:
From the graph below we see that the optimal solution occurs at x = 5, y = 3, obj. func. = 46.
PTS: 1 TOP: Graphical solution procedure
Solve the problem graphically. How many extreme points exist for this problem?
ANS:
Two extreme points exist (Points A and B below). The optimal solution is x = 10, y = 6, and obj. func.
= 2760 (Point B).
PTS: 1 TOP: Graphical solution procedure
Max 4x + 5y
s.t. x + 3y £ 22
-x + y £ 4
y£6
2x - 5y £ 0
x, y ³ 0
ANS:
Two extreme points exist (Points A and B below). The optimal solution is x = 10, y = 6, and obj. func.
= 2760 (Point B).
PTS: 1 TOP: Graphical solution procedure