Nit
Nit
Nit
Security
2.5 % of tendered value.
Deposit
Certified that this composite NIT contains Page 1 to Page 218 Only.
(Er. S. R. Jaurker)
Chief Engineer (WZ- III)
CPWD, Mumbai
Page No.
S.No. Description
0. Composite NIT 1
1. Index 2–3
4. Part- A 6
63
(Part B)- Civil
5.12 List of approved make of materials and Specialised agencies (Civil Works) 110-116
6.6 Schedule of Quantity for Electrical & Mechanical works (Part A to I) 189-218
Name of work:- Construction of Institute and hostel building (New Institutional complex) of Family
Welfare Training and Research Center (FWTRC), At New Panvel, Navi-Mumbai including internal
water supply, sanitary installation, drainage, development work, Internal electrical
installation,Automatic fire alarm system,Down comer system,SITC of VRF Type Air conditioning ,
D.G. set, Sub station, pump set, street light ,Passenger Lift & Solar water heating system etc.
(BALANCE WORK)
(Er.Ajeet Kumar)
Superintending Engineer (P)
(Er.S. R. Jaurker)
Chief Engineer, WZ-III,
The tender forms and other details can be obtained from the website
www.tenderwizard.com/CPWD or www.cpwd.gov.in. The Press Notice is
also available on www.eprocure.gov.in
____________________________________
Not to be printed below this line
Chief Engineer
WZ- III, CPWD, Mumbai- 20
* to be filled by EE
The Executive Engineer, Mumbai Central Division VI, C.P.W.D., 3rd Floor, Nishtha
Bhavan, (New CGO) Marine Lines, Mumbai- 400 020 on behalf of President of India invites
online percentage rate composite bids on single bid system from contractors of
appropriate class of composite category of CPWD for following work
Earnest Money
Location
NIT No.
S. No.
of bid
bid
1 2 3 4 5 6 7 8
including internal water supply, sanitary
Rs. 24,02,021/-
installation,Automatic
12 Months
(BALANCE WORK)
electrical
+
Mumbai
1.1 Contractors who are registered in cpwd in appropriate class shall be eligible to apply.
Joint ventures are not accepted.
2. The intending bidder must read the terms and conditions of CPWD-6 carefully. He
should only submit his bid if he considers himself eligible and he is in possession of all
the documents required.
3. Information and Instructions for bidders posted on website shall form part of bid
document.
6. Those contractors not registered on the website mentioned above, are required to get
registered beforehand. If needed they can be imparted training on online bidding
process as per details available on the website.
7. The intending bidder must have valid class-III digital signature to submit the bid.
8. On opening date, the contractor can login and see the bid opening process. After
opening of bids he will receive the competitor bid sheets.
9. Contractor can upload documents in the form of JPG format and PDF format.
10. Contractor must ensure to quote rate of each item. The column meant for quoting
rate in figures appears in pink colour and the moment rate is entered, it turns sky
blue. In addition to this, while selecting any of the cells a warning appears that if any
cell is left blank the same shall be treated as “0”. Therefore, if any cell is left blank
and no rate is quoted by the bidder, rate of such item shall be treated as “0”
(ZERO). However if a tenderer quotes nil rates against each item in item rate
tender, the tender shall be treated as invalid and will not be considered as
lowest tenderer.
(Applicable for item rate tender only)
11. The eligible bidder shall quote percentage rate above or below for major component.
For minor component i.e. E & M components, the percentage above or below shall be
quoted separately for each sub work.
(Applicable for percentage rate tender only)
12. The building is targeted for 3 star rating from GRIHA secrateriat. In order to secure
these ratings, a high degree of responsibility and co- operation is necessary from the
contractors. All materials and systems to be used in the project are intended to
maximise energy efficiency for operation of Project throughout service life (substantial
completion to ultimate disposition- reuse, recycling or demolition) with an emphasis
on top quality. Materials and systems are to maximise environmentally- benign
construction techniques including construction waste recycle, reusable delivery
packaging and reusability of selected materials. All vendors/ contractors must adhere
to best practices related to Green Buildings.
13. If any information furnished by the applicant is found incorrect at a later stage, he
shall be liable to be debarred from tendering/ taking up of works in CPWD. The
14. It is mandatory to fill details/ upload scanned copies of documents as stipulated in bid
document. If such documents are not uploaded the bid become invalid and processing
fee if deposited shall not be refunded.
15. The department reserves the right to reject any prospective application without
assigning any reason and to restrict the list of qualified contractors to any number
deemed suitable by it, if too many bids are received satisfying the laid down criterion.
16. After submission of the bid the contractor can resubmit revised bid any number of
times but before last date of submission of bid.
Executive Engineer,
Mumbai Central Division VI,
C.P.W.D., 3rd Floor, Nishtha Bhavan,
Mumbai- 400 020
1. The Executive Engineer, Mumbai Central Division-VI CPWD, 3rd Floor Nishtha
Bhavan( New CGO Bldg) 48, New Marine Lines Mumbai-400020 (Ph. No. 022-
22003209/ Fax No. 022-22018140 e-mail: eemcd6@gmail.com) invites on
behalf of President of India on line percentage rate composite bids on single
bid system from eligible contractors of composite category of CPWD for
following work: NIT No.:- 09/CE/WZ-III/EE/MCD VI/2017-18, Name of work:
Construction of Institute and hostel building (New Institutional complex) of
Family Welfare Training and Research Center (FWTRC), At New Panvel, Navi-
Mumbai including internal water supply, sanitary installation, drainage,
development work, Internal electrical installation,Automatic fire alarm
system,Down comer system,SITC of VRF Type Air conditioning , D.G. set, Sub
station, pump set, street light ,Passenger Lift & Solar water heating system
etc. (BALANCE WORK)
2. The enlistment of the contractors should be valid on the last date of submission of
bids. In case the last date of submission of bid is extended, the enlistment of
contractor should be valid on the original date of submission of bids.
Intending bidders is eligible to submit the bid provided he has definite proof from the
appropriate authority, which shall be to the satisfaction of the competent authority, of
having satisfactorily completed similar works of magnitude specified below:
3. Agreement shall be drawn with the successful bidders on prescribed Form No. CPWD-
7 which is available as a Govt. Of India Publication and also available on website
www.cpwd.gov.in. Bidders shall quote his rates as per various terms and conditions of
the said form which will form part of the agreement.
4. The time allowed for carrying out the work will be 12 (Twelve) Months from the date
of start as defined in schedule ‘F’ or from the first date of handing over of the site,
whichever is later, in accordance with the phasing, if any, indicated in the bid
documents.
5.
i) The site for the work is available.
ii) The architectural drawings for the work are available.
iii) The structural drawings shall be made available, as per requirement of the
same as per approved programme of completion submitted by the contractor
after award of work.
8. While submitting the revised bid, contractor can revise the bid percentage
above/below of civil and electrical components any number of times but before last
time and date of submission of bid as notified.
9. When the bids are invited in three stage system and if it is desired to submit revised
financial bid then it shall be mandatory to submit revised financial bid. If not
submitted then the bid submitted earlier shall become invalid.
9 (A) The contractor registers prior to 1/4/2015 on e-Tendering portal of CPWD shall have
to deposit tender processing fees at existing rates, or they have option to switch
over to the new registration system without tender processing fees at any time
10. Earnest Money of Rs.24,02,021/- in the form of Treasury Challan or Demand Draft
or Pay order or Banker‘s Cheque or Deposit at Call Receipt or Fixed Deposit Receipt
(drawn in favour of Executive Engineer, Mumbai Central Division VI, CPWD, Mumbai)
shall be scanned and uploaded to the e-Tendering website within the period of bid
submission. The original EMD should be deposited either in the office of Executive
engineer inviting bid or division office of any Executive Engineer CPWD within the
period of bid submission.(The EMD document shall only be issued from the place in
which the office of receiving division office is situated) The EMD receiving Executive
Engineer shall issue a receipt of deposition of earnest money deposit to the bidder in
a prescribed format(enclosed)uploaded by the tender inviting EE in the NIT.
This receipt shall also be uploaded to the e-tendering website by the
intending bidder upto the specified bid submission date and time.
A part of earnest money is acceptable in the form of bank guarantee also. In such
case, minimum 50% of earnest money or Rs. 20 lac, whichever is less, shall have to
be deposited in shape prescribed above, and balance may be deposited in shape of
Bank Guarantee submitted as part of earnest money of any scheduled bank having
validity for Ninety Days for single bid works and 120 days for two bid systems or
more from the last date of receipt of bids which is to be scanned and uploaded by the
intending bidders.
Copy of Enlistment Order and other documents as specified in the bidding document
shall be scanned and uploaded to the e-Tendering website within the period of bid
submission.
However, certified copy of all the scanned and uploaded documents as specified in the
bidding document shall have to be submitted by the lowest bidder only within a week
physically in the office of tender opening authority.
Online bid documents submitted by intending bidders shall be opened only of those
bidders, whose EMD deposited with any division office of CPWD and other document
scanned and uploaded are found to be in order.
The contractors registered prior to 01/04/2015 on the e-tendering portal will have
option to continue by paying tender processing fee up to one year from the date of
registration, or to switch over to (new) registration without tender processing fee any
time. All new registrations from 01.04.2015 will be without tender processing fee.
11. The bid submitted shall become invalid and e-Tender processing fee shall not be
refunded if:
(i) The bidder is found ineligible.
12. The contractor whose bid is accepted will be required to furnish performance
guarantee of 5% (Five Percent) of the bid amount within the period specified in
Schedule F. This guarantee shall be in the form of cash (in case guarantee amount is
less than Rs. 10000/-) or Deposit at Call receipt of any scheduled bank/Banker’s
cheque of any scheduled bank/Demand Draft of any scheduled bank/Pay order of any
Scheduled Bank of any scheduled bank (in case guarantee amount is less than Rs.
1,00,000/-) or Government Securities or Fixed Deposit Receipts or Guarantee Bonds
of any Scheduled Bank or the State Bank of India in accordance with the prescribed
form. In case the contractor fails to deposit the said performance guarantee within
the period as indicated in Schedule ‘F’, including the extended period if any, the
Earnest Money deposited by the contractor shall be forfeited automatically without
any notice to the contractor. The earnest money deposited along with bid shall be
returned after receiving the aforesaid performance guarantee. The contractor whose
bid is accepted will also be required to furnish either copy of applicable
licenses/registrations or proof of applying for obtaining labour licenses, registration
with EPFO, ESIC and BOCW Welfare Board including provident fund Code No.if
applicable and also ensure the compliance of aforesaid provisions by the sub
contractors, if any engaged by the contractor for the said work and program chart (
time and progress) within the period specified in schedule ‘F’( modified vide OM
No.DG/MAN/342 dt. 22-12-2016)
Intending Bidders are advised to inspect and examine the site and its surroundings
and satisfy themselves before submitting their bids as to the nature of the ground and
sub-soil (so far as is practicable), the form and nature of the site, the means of
access to the site, the accommodation they may require and in general shall
themselves obtain all necessary information as to risks, contingencies and other
circumstances which may influence or affect their bid. A bidders shall be deemed to
have full knowledge of the site whether he inspects it or not and no extra charge
consequent on any misunderstanding or otherwise shall be allowed. The bidders shall
be responsible for arranging and maintaining at his own cost all materials, tools &
plants, water, electricity access, facilities for workers and all other services required
for executing the work unless otherwise specifically provided for in the contract
documents. Submission of a bid by a bidders implies that he has read this notice and
14. The competent authority on behalf of the President of India does not bind itself to
accept the lowest or any other bid and reserves to itself the authority to reject any or
all the bids received without the assignment of any reason. All bids in which any of
the prescribed condition is not fulfilled or any condition including that of conditional
rebate is put forth by the bidders shall be summarily rejected.
16. The competent authority on behalf of President of India reserves to himself the right
of accepting the whole or any part of the bid and the bidders shall be bound to
perform the same at the rate quoted.
17. The contractor shall not be permitted to bid for works in the CPWD Circle (Division in
case of contractors of Horticulture/Nursery category) responsible for award and
execution of contracts, in which his near relative is posted a Divisional Accountant or
as an officer in any capacity between the grades of Superintending Engineer and
Junior Engineer (both inclusive). He shall also intimate the names of persons who are
working with him in any capacity or are subsequently employed by him and who are
near relatives to any gazetted officer in the Central Public Works Department or in the
Ministry of Urban Development. Any breach of this condition by the contractor would
render him liable to be removed from the approved list of contractors of this
Department.
19. The bid for the works shall remain open for acceptance for a period of
Ten/Fifteen/Thirty/Forty five/sixty (10/15/30/45/60) days from the date of
opening of bid in case of single bid system. If any bidders withdraws his bid before
the said period or issue of letter of acceptance, whichever is earlier, or makes any
modifications in the terms and conditions of the bid which are not acceptable to the
department, then the Government shall, without prejudice to any other right or
remedy, be at liberty to forfeit 50% of the said earnest money as aforesaid. Further
the bidders shall not be allowed to participate in the rebidding process of the work.
20. This notice inviting Bid shall form a part of the contract document. The successful
bidders/contractor, on acceptance of his bid by the Accepting Authority shall within 15
days from the stipulated date of start of the work, sign the contract consisting of:-
(a) The Notice Inviting Bid, all the documents including additional conditions,
specifications and drawings, if any, forming part of the bid as uploaded at the time of
invitation of bid and the rates quoted online at the time of submission of bid and
acceptance thereof together with any correspondence leading thereto.
(b) Standard C.P.W.D. Form 7 or other Standard C.P.W.D. Form as applicable.
20.1.1 The Executive Engineer in charge of the major component will call bids for the
composite work. The Earnest Money will be fixed with respect to the combined
estimated cost put to tender for the composite bid.
20.1.4 After acceptance of the bid by competent authority, the EE in charge of major
component of the work shall issue letter of award on behalf of the President of
India. After the work is awarded, the main contractor will have to enter into one
agreement with EE in charge of major component and has also to sign two or more
copies of agreement depending upon number of EE's/DDH in charge of minor
components. One such signed set of agreement shall be handed over to EE/DDH in
charge of minor component(s). EE of major component will operate Part A and Part
B of the agreement. EE/DDH in charge of minor component(s) shall operate Part C
along with Part A of the agreement.
20.1.5 Entire work under the scope of composite bid including major and all minor
components shall be executed under one agreement.
20.1.6 Security Deposit will be worked out separately for each component corresponding
to the estimated cost of the respective component of works.
20.1.7 Running payment for the major component shall be made by EE of major discipline
to the main contractor. Running payment for minor components shall be made by
the Engineer-in-charge of the discipline of minor component directly to the main
contractor.
Executive Engineer
MCD VI, CPWD, Mumbai
GOVERNMENT OF INDIA
CENTRAL PUBLIC WORKS DEPARTMENT
Tender for the work:- Construction of Institute and hostel building (New Institutional
complex) of Family Welfare Training and Research Center
(FWTRC), At New Panvel, Navi-Mumbai including internal water
supply, sanitary installation, drainage, development work, Internal
electrical installation,Automatic fire alarm system,Down comer
system,SITC of VRF Type Air conditioning , D.G. set, Sub station,
pump set, street light ,Passenger Lift & Solar water heating system
etc. (BALANCE WORK)
TENDER
I/ We have read and examined the notice inviting tender, schedule, A, B, C, D, E & F
Specifications applicable, Drawings & Designs, General Rules and Directions, Conditions of
Contract, of 2014 with amendments up to the last date of submission of bid, clauses of
contract, Special conditions, Schedule of Rate & other documents and Rules referred to in
the conditions of contract and all other contents in the tender document for the work
Name of work:- Construction of Institute and hostel building (New Institutional complex)
of Family Welfare Training and Research Center (FWTRC), At New Panvel, Navi-Mumbai
including internal water supply, sanitary installation, drainage, development work, Internal
electrical installation,Automatic fire alarm system,Down comer system,SITC of VRF Type Air
conditioning , D.G. set, Sub station, pump set, street light ,Passenger Lift & Solar water
heating system etc. (BALANCE WORK) I/ We hereby tender for the execution of the work
specified for the President of India within the time specified in Schedule ‘F’ viz., schedule of
quantities and in accordance in all respect with the specifications, designs, drawing and
instructions in writing referred to in Rule-1 of General Rules and Directions and in Clause
11 of the Conditions of contract of 2014 with amendments up to the last date of submission
of bid with such materials as are provided for, by, and in respect of accordance with, such
conditions so far as applicable.
We agree to keep the tender open for FORTY (45) days from the date of opening of bid
and not to make any modification in its terms and conditions.
I/We agree that President of India or the successors representatives in office shall without
prejudice to any other right or remedy available in law, be at liberty to forfeit the said
earnest money and the performance guarantee absolutely, otherwise the said earnest
money shall be retained by him towards security deposit to execute all the works referred
to in the tender documents upon the terms and conditions contained or referred to those in
excess of that limit at the rates to be determined in accordance with the provision
contained in Clause 12.2 and 12.3 of the tender form.
I/ We undertake and confirm that eligible similar work(s) has/have not been got executed
through another contractor on back to back basis. Further that, if such a violation comes to
the notice of Department, then I/We shall be debarred for tendering in CPWD in future for
ever. Also, if such a violation comes to the notice of Department before date of start of
work, the Engineer-in-Charge shall be free to forfeit the entire amount of Earnest Money
Deposit/ Performance Guarantee.
I/We hereby declare that I/We shall treat the tender documents drawings and other
records connected with the work as secret/confidential documents and shall not
communicate information/derived there from to any person other than a person to whom
I/We am/are authorized to communicate the same or use the information in any manner
prejudicial to the safety of the State.
Witness: ***
ACCEPTANCE
The above tender (as modified by you as provided in the letters mentioned hereunder) is
accepted by me for an on behalf of the President of India for a sum of Rs..………*……….……..
(Rupee………..………………………………………*……………………………………………………………………….....………
………...).
The letters referred to below shall form part of this contract agreement:-
(a) *
(b) *
(c) *
Signature ………………………………………
To,
………………………..,
………………………..,
………………………..
Dear Sir,
The subject Notice Inviting Tender (NIT) is an invitation to offer made on the
condition that the Bidder will sign the integrity Agreement, which is an integral part of
tender/bid documents, failing which the tenderer/bidder will stand disqualified from the
tendering process and the bid of the bidder would be summarily rejected.
This declaration shall form part and parcel of the Integrity Agreement and signing of
the same shall be deemed as acceptance and signing of the Integrity Agreement on behalf
of the CPWD.
Yours faithfully,
Executive Engineer
To,
Executive Engineer,
………………………..,
………………………..
Dear Sir,
I/We agree that the Notice Inviting Tender (NIT) is an invitation to offer made on
the condition that I/We will sign the enclosed integrity Agreement, which is an integral part
of tender documents, failing which I/We will stand disqualified from the tendering process.
I/We acknowledge that THE MAKING OF THE BID SHALL BE REGARDED AS AN
UNCONDITIONAL AND ABSOLUTE ACCEPTANCE of this condition of the NIT.
I/We confirm acceptance and compliance with the Integrity Agreement in letter and
spirit and further agree that execution of the said Integrity Agreement shall be separate
and distinct from the main contract, which will come into existence when tender/bid is
finally accepted by CPWD. I/We acknowledge and accept the duration of the Integrity
Agreement, which shall be in the line with Article 1 of the enclosed Integrity Agreement.
I/We acknowledge that in the event of my/our failure to sign and accept the
Integrity Agreement, while submitting the tender/bid, CPWD shall have unqualified,
absolute and unfettered right to disqualify the tenderer/bidder and reject the tender/bid is
accordance with terms and conditions of the tender/bid.
Yours faithfully,
INTEGRITY AGREEMENT
BETWEEN
(Name of Division)
(Address of Division)
AND
...............................................................................................................................
.......
Preamble
WHEREAS the Principal / Owner has floated the Tender (NIT No……………….
...............................................................................................................................
......
(Name of work)
AND WHEREAS the Principal/Owner values full compliance with all relevant laws of the land,
rules, regulations, economic use of resources and of fairness/transparency in its relation
with its Bidder(s) and Contractor(s).
NOW, THEREFORE, in consideration of mutual covenants contained in this Pact, the parties
hereby agree as follows and this Pact witnesses as under:
1) The Principal/Owner commits itself to take all measures necessary to prevent corruption
and to observe the following principles:
(b) The Principal/Owner will, during the Tender process, treat all Bidder(s) with equity
and reason. The Principal/Owner will, in particular, before and during the Tender
process, provide to all Bidder(s) the same information and will not provide to any
Bidder(s) confidential / additional information through which the Bidder(s) could
obtain an advantage in relation to the Tender process or the Contract execution.
(c) The Principal/Owner shall endeavor to exclude from the Tender process any person,
whose conduct in the past has been of biased nature.
2) If the Principal/Owner obtains information on the conduct of any of its employees which
is a criminal offence under the Indian Penal code (IPC)/Prevention of Corruption Act, 1988
(PC Act) or is in violation of the principles herein mentioned or if there be a substantive
suspicion in this regard, the Principal/Owner will inform the Chief Vigilance Officer and in
addition can also initiate disciplinary actions as per its internal laid down policies and
procedures.
b) The Bidder(s)/Contractor(s) will not enter with other Bidder(s) into any undisclosed
agreement or understanding, whether formal or informal. This applies in particular
to prices, specifications, certifications, subsidiary contracts, submission or non-
submission of bids or any other actions to restrict competitiveness or to cartelize in
the bidding process.
c) The Bidder(s)/Contractor(s) will not commit any offence under the relevant IPC/PC
Act. Further the Bidder(s)/Contract(s) will not use improperly, (for the purpose of
competition or personal gain), or pass on to others, any information or documents
provided by the Principal/Owner as part of the business relationship, regarding
plans, technical proposals and business details, including information contained or
transmitted electronically.
d) The Bidder(s)/Contractor(s) of foreign origin shall disclose the names and addresses
of agents/representatives in India, if any. Similarly Bidder(s)/Contractor(s) of Indian
Nationality shall disclose names and addresses of foreign agents/representatives, if
any. Either the Indian agent on behalf of the foreign principal or the foreign principal
directly could bid in a tender but not both. Further, in cases where an agent
participate in a tender on behalf of one manufacturer, he shall not be allowed to
quote on behalf of another manufacturer along with the first manufacturer in a
subsequent/parallel tender for the same item.
e) The Bidder(s)/Contractor(s) will, when presenting his bid, disclose (with each tender
as per proforma enclosed) any and all payments he has made, is committed to or
intends to make to agents, brokers or any other intermediaries in connection with
the award of the Contract.
3) The Bidder(s)/Contractor(s) will not instigate third persons to commit offences outlined
above or be an accessory to such offences.
4) The Bidder(s)/Contractor(s) will not, directly or through any other person or firm indulge
in fraudulent practice means a willful misrepresentation or omission of facts or
submission of fake/forged documents in order to induce public official to act in
reliance thereof, with the purpose of obtaining unjust advantage by or causing
damage to justified interest of others and/or to influence the procurement
process to the detriment of the Government interests.
5) The Bidder(s)/Contractor(s) will not, directly or through any other person or firm use
Coercive Practices (means the act of obtaining something, compelling an action or
influencing a decision through intimidation, threat or the use of force directly or indirectly,
where potential or actual injury may befall upon a person, his/ her reputation or property
to influence their participation in the tendering process).
Without prejudice to any rights that may be available to the Principal/Owner under
law or the Contract or its established policies and laid down procedures, the
Principal/Owner shall have the following rights in case of breach of this Integrity Pact by
the Bidder(s)/Contractor(s) and the Bidder/ Contractor accepts and undertakes to respect
and uphold the Principal/Owner’s absolute right:
1) The Bidder declares that no previous transgressions occurred in the last 5 years with
any other Company in any country confirming to the anticorruption approach or with
Central Government or State Government or any other Central/State Public Sector
Enterprises in India that could justify his exclusion from the Tender process.
2) If the Bidder makes incorrect statement on this subject, he can be disqualified from the
Tender process or action can be taken for banning of business dealings/ holiday listing
of the Bidder/Contractor as deemed fit by the Principal/ Owner.
3) If the Bidder/Contractor can prove that he has resorted / recouped the damage caused
by him and has installed a suitable corruption prevention system, the Principal/Owner
may, at its own discretion, revoke the exclusion prematurely.
2) The Principal/Owner will enter into Pacts on identical terms as this one with all
Bidders and Contractors.
3) The Principal/Owner will disqualify Bidders, who do not submit, the duly signed Pact
between the Principal/Owner and the bidder, along with the Tender or violate its provisions
at any stage of the Tender process, from the Tender process.
This Pact begins when both the parties have legally signed it. It expires for the
Contractor/Vendor 12 months after the completion of work under the contract or till the
continuation of defect liability period, whichever is more and for all other bidders, till the
Contract has been awarded.
If any claim is made/lodged during the time, the same shall be binding and continue
to be valid despite the lapse of this Pacts as specified above, unless it is
discharged/determined by the Competent Authority, CPWD.
1) This Pact is subject to Indian Law, place of performance and jurisdiction is the Head
quarters of the Division of the Principal/Owner, who has floated the Tender.
2) Changes and supplements need to be made in writing. Side agreements have not been
made.
3) If the Contractor is a partnership or a consortium, this Pact must be signed by all the
partners or by one or more partner holding power of attorney signed by all partners and
consortium members. In case of a Company, the Pact must be signed by a representative
duly authorized by board resolution.
4) Should one or several provisions of this Pact turn out to be invalid; the remainder of this
Pact remains valid. In this case, the parties will strive to come to an agreement to their
original intensions.
5) It is agreed term and condition that any dispute or difference arising between the parties
with regard to the terms of this Integrity Agreement / Pact, any action taken by the
Owner/Principal in accordance with this Integrity Agreement/ Pact or interpretation
thereof shall not be subject to arbitration.
All rights and remedies of the parties hereto shall be in addition to all the other legal
rights and remedies belonging to such parties under the Contract and/or law and the same
shall be deemed to be cumulative and not alternative to such legal rights and remedies
aforesaid. For the sake of brevity, both the Parties agree that this Integrity Pact will have
precedence over the Tender/Contact documents with regard any of the provisions covered
under this Integrity Pact.
IN WITNESS WHEREOF the parties have signed and executed this Integrity Pact at the
place and date first above mentioned in the presence of following witnesses:
...............................................................
.................................................................
WITNESSES:
1. ..............................................
2. ...............................................
Place:
Dated :
SCHEDULE ‘A’
SCHEDULE 'B'
NIL
SCHEDULE 'C'
NIL
SCHEDULE ‘D’
SCHEDULE ‘E’
Name of Work Name of work:- Construction of Institute and hostel building (New
Institutional complex) of Family Welfare Training and Research Center
(FWTRC), At New Panvel, Navi-Mumbai including internal water
supply, sanitary installation, drainage, development work, Internal
electrical installation,Automatic fire alarm system,Down comer
system,SITC of VRF type Air conditioning , D.G. set, Sub station, pump
set, street light, passenger lift & Solar water heating system etc.
(BALANCE WORK)
9(ii) Standard CPWD Contract Form CPWD Form 7 & GCC 2014 as modified &
GCC 2014 corrected up-to last date of submission of
tender.
Clause 1
Amount to be with-held
Sl. Description of Milestone (Physical) Time in
( All floor levels are with reference to
No lower most allowed in case of non achievement
Ground level) months of each of the mile stone
(% of tendered amount
(from date of
Civil and relevant E&M
component)
of start)
1. Completion of RCC Works upto Terrace 6 Months 1.00 %
Authority to decide:
Clause 6, 6A
Gross work to be done together with net : Rs. 89 Lacs for Civil work
payment / adjustment of advances for
material collected, if any, since the last
such payment for being eligible to interim
payment
Clause 7A
List of testing equipment’s to be provided by the: As per TABLE-1, Page no. 36-37
contractor at site lab
Clause 10C
Sl. Material covered Nearest Materials (other Base Price and its corresponding
No. under this clause than cement, period of all the materials covered
reinforcement bars and under clause 10 CA
structural steel) for
which all India
Wholesale Price Index to
be followed.
Base Price Corresponding
Period
1 Ordinary Portland Rs 6250/- Per MT June 2017
Cement (OPC)53
GRADE
2 Reinforcement bars
TMT-500D Rs 44560/- Per MT June 2017
(Primary
manufacturer)
3 Structural steel Rs 41000/- Per MT June 2017
Schedule of component of other materials, Labour, POL etc. for price escalation:-
Component of civil (Except materials covered under clause 10CA) /
expressed as percent of total value of civil work Xm ----
Component of labour expressed as percent of total value of work. ----
Component of P.O.L. expressed as percent of total value of work. ---- Nil
(a) Specifications to be followed for execution of CPWD Specifications 2009 volume-I &
Civil work II with corrections slips issued upto last
date of receipt of tender.
(b) Specifications to be followed for execution of As per Schedule F of Part C of bid
E & M work document
Clause 12
Clause 16
Clause 25
Clause36 (i)
Requirement of Technical Representative(s) and Recovery Rates
Requirement of Technical Rate at which
Staff recovery shall be
Minimum
Qualification Number made from the
experience in
Designation contractor in the
Construction
event of not fulfilling
(For Major Component) (Years)
provisions of clause
36(i)
I. Project Manager
with degree in
Principal Technical
corresponding 1 10 Years Rs. 30,000 per month
representative
decipline of
Engineering
II Graduate Engineer Technical
1 5 Years Rs. 25,000 per month
(Civil) Representative
III Graduate Engineer 2 21. Years Project/Site
Or Engineer & Project Rs. 15,000 per month
Diploma Engineer 2 5 Years planning/ Billing Per Person
(Civil) Engineer
Assistant Engineers retired from Government services who are holding Diploma will be
treated at par with Graduate Engineers. Diploma holder with minimum 10 year relevant
experience with a reputed construction company can be treated at par with Graduate
Engineers for the purpose of such deployment subject to the condition that such diploma
holders should not exceed 50% of requirement of degree engineers.
The contractor shall submit a certificate of employment of the technical representative(s)
(in the form of copy of Form -16 or CPF deduction issued to the Engineers employed by
him) along with every account bill/final bill and shall produce evidence if at any times so
required by the Engineer-in-charge.
Clause 42
(i) (a) Schedule/statement for determining DSR 2014 with correction slips upto
theoretical quantity of cement & bitumen last date of submission of tender
on the basis of Delhi Schedule of Rates
(ii) Variations permissible on theoretical
(a) quantities:
Cement
For works with estimated cost put to 2% plus / minus.
tender more than Rs. 5 lakh.
Bitumen for all works 2.5% plus only and nil on minus side.
(b) Steel Reinforcement and structural steel 2% plus / minus
sections for each diameter, section and
(c) category
All other materials Nil
All necessary equipment for conducting all necessary tests shall be provided at the site in
the well-furnished site laboratory of minimum size 25 feet x 15 feet by the contractor at his
own cost The following minimum laboratory equipment’s shall be set up at site office
laboratory:-
2. Slump cone, steel plate, tamping rod, steel scale, scoop 5 (each)
9. Sets of sieves
ieves of 200 mm internal dia for fine
ine aggregate
agregate 1
[4.75mm; 2.36mm; 1.18mm; 600 microns; 300 microns & 150
micron , with lid and pan]
15. Spatula 100mm & 200mm with long blade wooden 1 each
handle
25. Iron Weight of 5 kg, 2 kg, 1 kg, 500 gm, 200 gm, 100 gm 1 each
Numbers
Sl. No. Equipment (Minimum)
2. Needle Vibrators. 6
3. Plate Vibrators. 2
4. Dumper. 1
8. Total station. 1
Note: If the number is less than that required, then reasons shall be
recoded.
SEALED with the Common Seal of the said Bank this ……………….. day of ……………… 20…….
(1) If after Tender opening the Contractor withdraws, his Tender during the period of
validity of Tender (including extended validity of Tender) specified in the Form of
Tender;
(2) If the contractor having been notified of the acceptance of his Tender by the
Engineer-in-Charge:
(a) fails or refuses to execute the Form of Agreement in accordance with the
Instructions to contractor, if required; OR
(b) fails or refuses to furnish the Performance Guarantee, in accordance with the
provisions of Tender document and Instructions to contractor, OR
(c) fails or refuses to start the work, in accordance with the provisions of the
contract and Instructions to contractor, OR
(d) fails or refuses to submit fresh Bank Guarantee of an equal amount of the Bank
Guarantee, against Security Deposit after award of contract.
The Guarantee will remain in force up to and including the date* ……………………….. after the
deadline for submission of Tender as such deadline is stated in the Instructions to
contractor or as it may extended by the Engineer-in-Charge, notice of which extension (s)
to the Bank is hereby waived. Any demand in respect of this Guarantee should reach the
Bank not later than the above date.
DATE …………………. SIGNATURE OF THE BANK
PART– B
(iv) General Conditions of Contract for CPWD works and CPWD Specifications.
1.2 The work shall be carried out in accordance with the Architectural drawings and
structural drawings, to be issued from time to time, by the Engineer-in-Charge.
Before commencement of any item of work, the contractor shall correlate all the
relevant architectural and structural drawings issued for the work and satisfy himself
that the information available there from is complete and unambiguous. The
discrepancy, if any, shall be brought to the notice of the Engineer-In-Charge before
execution of the work. The contractor alone shall be responsible for any loss or
damage occurring by the commencement of work on the basis of any erroneous and
or incomplete information.
1.3 Existing drains, pipes, cables, over-head wires, sewer lines, water lines and similar
services encountered in the course of the execution of work shall be protected
against the damage by the contractor, at his own expense, for which nothing is
payable. The contractor shall not store materials or otherwise occupy any part of the
site in a manner likely to hinder the operation of such services.
1.4 The contractor shall be responsible for the watch and ward / guard of the buildings,
safety of all fittings and fixtures including sanitary and water supply fittings and
fixtures provided by him against pilferage and breakage during the period of
installations and thereafter till the building is physically handed over to the
department. No extra payment shall be made on this account.
1.5 The entire work up to the plinth level, as required for obtaining approval of the
plinth from the local authority, shall be completed by level approval shall be
obtained by him from local body within the prescribed time, if any. the Contractor
and plinth Work above plinth shall be allowed to be carried out only after obtaining
approval from the local body. No delay shall be allowed on this ground and also no
claim whatsoever on account of any delay in approval at plinth level by the local
body shall be entertained from the Contractor. Nothing extra shall be payable on
this account.
1.7 For works below ground level the contractor shall keep that area free from water. If
dewatering or bailing out of water is required the contractor shall do it and nothing
extra shall be paid except otherwise provided in the items of schedule of quantities.
1.8 Results of sub-surface investigations conducted at site are indicated in extracts of
the report attached. This information about the soil and sub-soil water conditions is
being made available to the Contractor, in good faith, for guidance only and the
Contractor is advised to obtain details directly as may be considered necessary by
him before quoting rates in the tender. No claim whatsoever on account of any
discrepancy between the sub-surface strata conditions that may be actually
encountered at the time of execution of the work and those given in these tender
documents, in-accuracy or interpretation thereof shall be entertained from the
Contractor under any circumstances. The ground water table is a variable condition
and the information given in the report is only indicative and it may vary from time
to time.
1.9 Any legal or financial implications resulting out of disposal of earth shall be sole
responsibility of the contractor. Nothing extra over the schedule shall be paid on this
account.
1.10 The Contractor shall keep himself fully informed of all acts and laws of the Central &
State Governments, all orders, decrees of statutory bodies, tribunals having any
jurisdiction or authority, which in any manner may affect those engaged or
employed and anything related to carrying out the work. All the rules & regulations
and bye-laws laid down by Collector / NMMC / CIDCO and any other statutory bodies
shall be adhered to, by the contractor, during the execution of work. The Contractor
shall also adhere to all traffic restrictions notified by the local authorities. It is
clarified that the extra sewerage charges (one time charges for commencement of
work) required to be paid to the Municipal Corporation / other statutory bodies shall
be paid by the department and need not be considered by the contractor. The water
charges (for municipal water connection as well as tanker water) shall be borne by
the contractor. Also, if the contractor obtains water connection for the drinking
purposes from the municipal authorities or any other statutory body, the consequent
sewerage charges shall be borne by the contractor. All statutory taxes, levies,
charges (including water and sewerage charges, charges for temporary service
connections and / or any other charges) payable to such authorities for carrying out
the work, shall be borne by the Contractor. The Contractor shall arrange to give all
notices as required by any statutory / regulatory authority and shall pay to such
authority all the fees that is required to be paid for the execution of work. He shall
protect and indemnify the Department and its officials & employees against any
claim and /or liability arising out of violations of any such laws, ordinances, orders,
decrees, by himself or by his employees or his authorized representatives. Nothing
extra shall be payable on these accounts. The fee payable to statutory authorities
for obtaining the various permanent service connections and Occupancy Certificate
for the building shall be borne by the Department.
1.11 Royalty at the prevalent rates shall be paid by the Contractor or the RMC supplier as
per the terms of supply between them on all materials such as boulders, metals,
1.13 The Contractor shall conduct his work so as not to interfere with or hinder the
progress of the work being performed by other Contractors or by the Engineer-in-
Charge. As far as possible, he shall arrange his work and place, so as not to
interfere with the operations of other Contractors or shall arrange his work with that
of the others, in an acceptable and coordinated manner and shall perform it in
proper sequence
1.14 The Contractor shall assume all liability, financial or otherwise in connection with
this contract and shall protect and indemnify the Department from any and all
damages and claims that may arise on any account. The Contractor shall indemnify
the Department against all claims in respect of patent rights, royalties, design,
trademarks of name or other protected rights, damages to adjacent buildings, roads
or members of public, in course of execution of work or any other reasons
whatsoever, and shall himself defend all actions arising from such claims and shall
indemnify the Department in all respect from such actions, costs and expenses.
Nothing extra shall be payable on this account.
1.15 The Contractor shall make all necessary arrangements for protecting from rains, the
work already executed and for carrying out the further work, during monsoon
including providing and fixing temporary shelters, protections etc. Nothing extra
shall be payable on this account. Also, no claims for hindrance shall be entertained
on this account.
1.16 In case of flooding of site on account of rain or any other cause and any consequent
damage, whatsoever, no claim financially or otherwise shall be entertained not
withstanding any other provisions elsewhere in the contract agreement. Also, the
Contractor shall make good, at his own cost, the damages caused, if any.
1.17 The Contractor shall take all necessary precautions to prevent any nuisance or
inconvenience to the owners, tenants or occupants of the adjacent properties and to
the public in general .The Contractor shall take all care, as not to damage any other
adjacent property or other services running adjacent to the plot. If any damage is
done, the same shall be made good by the Contractor at his own cost and to the
entire satisfaction of the Engineer-in-Charge. The Contractor shall use such
methodology and equipments for execution of the work, so as to cause minimum
environmental pollution of any kind during construction, to have minimum
construction time and minimum inconvenience to road users and to the occupants of
the buildings on the adjacent plot and public in general, etc. He shall make good at
his own cost and to the entire satisfaction of the Engineer in Charge any damage to
roads, paths, cross drainage works or public or private property whatsoever caused,
due to the execution of the work or by traffic brought thereon, by the Contractor.
Further, the Contractor shall take all precautions to prevent any pollution of streams
and waterways. All waste or superfluous materials shall be carted away by the
Contractor, entirely to the satisfaction of the Engineer-in-Charge. Utmost care shall
be taken to keep the noise level to the barest minimum so that no disturbance as far
1.18 No accommodation is available at the site of work. The labour huts shall not be
erected on the plot and the Contractor shall make his own arrangements to provide
such accommodation as per the rules of the local bodies. He shall make his own
arrangements for stores, field office etc. Before tendering, he shall visit the site and
assess the manner in which he is able to arrange the above facilities. The Engineer-
in-Charge shall in no way be responsible for any delay on this account and no claim,
whatsoever, on this account shall be entertained. Nothing extra shall be payable on
this account.
1.19 All ancillary and incidental facilities required for execution of work like labour camp,
stores, fabrication yard, offices for Contractor, watch and ward, temporary ramp
required to be made for working at the basement level, temporary structure for
plants and machineries, water storage tanks, installation and consumption charges
of temporary electricity, telephone, water etc. required for execution of the work,
liaison and pursuing for obtaining various No Objection Certificates, completion
certificates from local bodies etc., protection works, barricading, testing facilities /
laboratory at site of work, facilities for all field tests and for taking samples etc.
during execution or any other activity which is necessary (for execution of work and
as directed by Engineer-in-Charge), shall be deemed to be included in rates quoted
by the Contractor, for various items in the schedule of quantities. Nothing extra
shall be payable on these accounts. Before start of the work, the Contractor shall
submit to the Engineer-in-Charge, a site / construction yard layout, specifying areas
for construction, site office, positioning of machinery, material yard, cement and
other storage, steel fabrication yard, site laboratory, water tank, etc.
1.20 The Contractor shall display all permissions, licenses, registration certificates, bar
charts, other statements etc under various labour laws and other regulations
applicable to the works, at his site office.
1.21 No tools and plants including any special T&P etc. shall be supplied by the
Department and the Contractor shall have to make his own arrangements at his own
cost. No claim of hindrance (or any other claim) shall be entertained on this account.
The Contractor shall cooperate with and provide the facilities to the sub-Contractors
and other agencies working at site for smooth execution of the work. The
Contractor shall
(c) Provide control lines and benchmarks to his Sub-Contractors and the other
Contractors.
(f) Co-ordinate with other Contractors for leaving inserts, making chases,
alignment of services etc. at site.
(h) Resolve the disputes with other Contractor amicably and the Engineer-in-
Charge shall not be made intermediary or arbitrator. The contractor shall
indemnify the Department against any claim(s) arising out of such disputes.
1.22 On completion of work, the contractor shall submit four prints of “as built” drawings
to the Engineer-In-Charge. These drawings shall have the following information:
a) Run off for all piping and their diameters including soil, waste pipes and
vertical stacks.
b) Ground and invert level of all drainage pipes together with locations of all
manholes and connections, up to outfall.
c) Run off for all water supply lines with diameters location of control valves,
access panels etc.
The security deposit shall not be released to the contractor until the aforesaid
drawings are submitted to the Engineer-in-Charge.
1.23 Contractor has to engage at his own cost plumbing consultant / designer to make
the water supply to the occupants all the times during the construction of work and
to engage plumbing labour for disconnecting and connecting of water supply lines
with new / old water supply lines to make the continuous water supply to the
occupants.
1.24 Contractor shall obtain necessary permission from Local Body for plying the vehicles
to carry out materials for construction and disposal and to follow the restrictions of
time given by the concerned authorities.
1.25 Architectural drawings are submitted to local body for approval. The date of start
shall be reckoned from the issue of approved drawing / handing over of site
whichever is later.
1.26 The work is consisting of two buildings. Viz. 1 Institute building (Ground + 2 upper
floors and hostel building (Ground + 1) Institute building is constructed upto plinth
level with few colums extended upto 1 to 2 metres above plinth level and RCC
structure of hostel building is completed. The work is needed to start above these
stages.
1.27 Malba/ building rubbish/ surplus earth/ obtained from the work is to be disposed off
at approval dumping ground of CIDCO/NMMC and recipt of the same is to be
produce as documentary evidence. Nothing shall be paid extra on account.
2.0 PROGRAM /SCHEDULE
2.2 Apart from the above integrated program chart, the contractor shall be required to
submit monthly progress report of the work in a computerized form. The progress
report shall contain the following, apart from whatever else may be required as
specified:
(i) Construction schedule of the various components of the work through a bar
chart for the next three quarters (or as may be specified), showing the
milestones, targeted tasks and up to date progress.
(ii) Progress chart of the various components of the work that are planned and
achieved, for the month as well as cumulative up to the month, with reason
for deviations, if any in a tabular format.
(iii) Plant and machinery statement, indicating those deployed in the work.
(iv) Man-power statement, indicating individually the names of all the staff
deployed on the work, along with their designations.
(v) Financial statement, indicating the broad details of all the running account
payment received up to date, such as gross value of work done, advances
taken, recoveries effected, amount withheld, net payments details of cheque
payment received etc.
2.3 For completing the work in time, the Contractor might be required to work in two or
more shifts (including night shifts). No claim whatsoever shall be entertained on
this account, not with-standing the fact that the Contractor may have to pay extra
amounts for any reason, to the labourers and other staff engaged directly or
indirectly on the work according to the provisions of the labour and other statutory
bodies regulations and the agreement entered upon by the Contractor with them.
2.4 The contractor shall arrange at site at least 1000 sqm of centering and shuttering
before start of the work. In case the completion schedule requires more quantity of
centering and shuttering, the contractor shall do so at no extra cost to the
department.
2.7 The contractor shall conduct his work, so as not to interfere with or hinder the
progress or completion of the work being performed by other contractor(s) or by the
Engineer-In-Charge and shall as far as possible arrange his work and shall place and
dispose off the materials being used or removed so as not to interfere with the
operations of other contractor or he shall arrange his work with that of the others in
an acceptable and in a proper co -ordination manner and shall perform it in proper
sequence to the complete satisfaction of others.
2.8 The Contractor shall do proper sequencing of the various activities by suitably
staggering the activities within various pockets in the plot so as to achieve early
completion. The agency may deploy adequate equipment, machinery and labour as
required for the completion of the entire work within the stipulated period specified.
Also ancillary facilities shall be provided commensurate with requirement to
complete the entire work within the stipulated period. Nothing extra shall be payable
on this account. Adequate number/sets of equipment in working condition, along
with adequate stand-by arrangements, shall be deployed during entire construction
period. It shall be ensured by the Contractor that all the equipment, Tools & Plants,
machineries etc. provided by him are maintained in proper working conditions at all
times during the progress of the work and till the completion of the work. Further,
all the constructional tools, plants, equipment and machineries provided by the
Contractor, on site of work or his work shop for this work, shall be exclusively
intended for use in the construction of this work and they shall not be shifted /
removed from site without the permission of the Engineer-in-Charge.
2.9 To avoid delay, contractor should submit samples as stated above well in advance
so as to give timely orders for procurement.
2.10 All material shall only be brought at site as per program finalized with the Engineer-
in-Charge. Any pre-delivery of the material not required for immediate consumption
shall not be accepted and thus not paid for.
3.3 The Contractor shall submit, immediately after the award of work, a detailed and
complete method statement for the execution, testing and Quality Assurance, of
such items of works, as directed by the Engineer-in-Charge. All the materials to be
used in the work, to give the finished work complete in all respects, shall comply
with the requirements of the specifications and shall pass all the tests required as
per specifications as applicable or such specifications / standards as directed by the
Engineer-in-Charge. However, keeping the Quality Assurance in mind, the
Contractor shall submit, on request from the Engineer-in-Charge, his own Quality
Assurance procedures for basic materials and such items, to be followed during the
execution of the work, for approval of the Engineer-in-Charge.
3.4 All materials and fittings brought by the contractor to the site for use shall conform
to the samples approved by the Engineer-in-charge which shall be preserved till the
completion of the work. If a particular brand of material is specified in the item of
work in Schedule of Quantity, the same shall be used after getting the same
approved from Engineer-In-Charge. Wherever brand / quality of material is not
specified in the item of work, the contractor shall submit the samples as per
suggested list of brand names given in the tender document / particular
specifications for approval of Engineer-In-Charge. For all other items, materials and
fittings of ISI Marked shall be used with the approval of Engineer-In-Charge.
Wherever ISI Marked material / fittings are not available, the contractor shall
submit samples of materials / fittings manufactured by firms of repute conforming to
relevant specifications or IS codes and use the same only after getting the approval
of Engineer-In-Charge.
3.5 The Contractor shall procure and provide all the materials from the manufacturers /
suppliers as per the list attached with the tender documents, as per the item
description and particular specifications for the work. The equivalent brand for any
item shall be permitted to be used in the work, only when the specified make is not
available. This is, however, subject to documentary evidence produced by the
contactor for non availability of the brand specified and also subject to independent
verification by the Engineer-in-Charge. In exceptional cases, where such approval is
required, the decision of Engineer-in-Charge as regards equivalent make of the
material shall be final and binding on the Contractor. No claim, whatsoever, of any
kind shall be entertained from the Contractor on this account. Nothing extra shall
be payable on this account. Also, the material shall be procured only after written
approval of the Engineer-in-Charge.
3.6 All materials whether obtained from Govt. stores or otherwise shall be got checked
by the Engineer-in-Charge or his authorized supervisory staff on receipt of the same
at site before use.
3.7 The tests, as necessary, shall be conducted in the laboratory approved by the
Engineer–in-Charge. The samples shall be taken for carrying out all or any of the
tests stipulated in the particular specifications and as directed by the Engineer-in-
Charge or his authorized representative.
3.8 The Contractor shall at his own risk and cost make all arrangements and shall
provide all such facilities including material and labour, the Engineer-in-Charge may
require for collecting, preparing, forwarding the required number of samples for
testing as per the frequency of test stipulated in the contract specifications or as
(i) By the contractor, if the results show that the material does not conform to
relevant specifications and BIS codes.
(ii) By the department, if the results show that the material conforms to relevant
specifications and BIS codes.
3.11 In case there is any discrepancy in frequency of testing as given in list of mandatory
tests and that in individual sub-heads of work as per CPWD Specifications, higher of
the two frequencies of testing shall be followed and nothing extra shall be payable
on this account.
3.12 The contractor has to establish field laboratory at site including all necessary
equipment for field tests as given in appendix D of sub head 5.0 of CPWD
specifications (vol-1) 2009 at his own cost.
3.13 All the hidden items such as water supply lines, drainage pipes, conduits, sewers
etc. are to be properly tested as per the design conditions before covering.
3.14 Water tanks, taps, sanitary, water supply and drainage pipes, fittings and
accessories should conform to byelaws and municipal body / corporation where
CPWD Specifications are not available. The contractor should engage licensed
plumbers for the work and get the materials (fixtures/fittings) tested by the
Municipal Body/Corporation authorities wherever required at his own cost.
3.15 The contractor shall give performance test of the entire installation(s) as per the
standing specifications before the work is finally accepted and nothing extra
whatsoever shall be payable to the contractor for the test.
3.16 The contractor shall have to execute guarantee bonds in respect of water proofing
work and acrylic paint work as per performa enclosed.
3.17 The Contractor shall depute Site Engineer & skilled workers as required for the
work. He shall submit organization chart along with details of Engineers and
supervisory staff. It shall be ensured that all decision making powers shall be
available to the representatives of the Contractor at Mumbai itself to avoid any likely
delays on this account. The Contractor shall also furnish list of persons for
specialized works to be executed for various items of work. The Contractor shall
identify and deploy key persons having qualifications and experience in the similar
and other major works, as per the field of their expertise. If during the course of
execution of work, the Engineer-in-Charge is of the opinion that the deployed staff is
not sufficient or not well experienced; the Contractor shall deploy more staff or
better-experienced staff at site to complete the work with quality and in stipulated
time limit.
(a) Before commencing the execution of work, the Contractor shall, without in any way
limiting his obligations and liabilities, insure at his own cost and expense against any
damage or loss or injury, which may be caused to any person or property, at site of
work. The Contractor shall obtain and submit to the Engineer-in-Charge proper
Contractor All Risk Insurance Policy for an amount 1.25 times the contract amount
for this work, with Engineer-in-Charge as the first beneficiary. The insurance shall
be obtained in joint names of Engineer-in-Charge and the Contractor (who shall be
second beneficiary). Also, he shall indemnify the Department from any liability
during the execution of the work. Further, he shall obtain and submit to the
Engineer-in-Charge, a third party insurance policy for maximum 10 lakh for each
accident, with the Engineer-in-Charge as the first beneficiary. The insurance shall
be obtained in joint names of Engineer-in-Charge and the Contractor (who shall be
second beneficiary).
(b) The Contractor shall, from time to time, provide documentary evidence as regards
payment of premium for all the Insurance Policies for keeping them valid till the
completion of the work. The Contractor shall ensure that Insurance Policies are also
taken for the workers of his Sub-Contractors / specialized agencies also. Without
prejudice to any of its obligations and responsibilities specified above, the Contractor
shall within 10 days from the date of letter of acceptance of the tender and
thereafter at the end of each quarter submit a report to the Department giving
details of the Insurance Policies along with Certificate of these insurance policies
being valid, along with documentary evidences as required by the Engineer-in-
Charge. No work shall be commenced by the Contractor unless he obtains the
Insurance Policies as mentioned above. Also, no payment shall be made to the
Contractor on expiry of insurance policies unless renewed by the Contractor. Nothing
extra shall be payable on this account. No claim of hindrance (or any other claim)
shall be entertained from the contractor on these accounts.
4.2 Temporary Barricading
(a) Proper temporary barricading by fencing with G.I. sheets, shall be carried out by the
Contractor at the start of work to physically define the boundaries of the plot for
restricted entry to only those involved in the work and also to prevent any
accidents, at the same time without causing any inconvenience to the traffic and the
users of the buildings in the adjacent plots. It shall be done by providing, erecting,
maintaining temporary protective barricading, 2.5 meters in height, made in panels,
with each panel having MS frames / MS scaffolding pipes of suitable size and
stiffness, with 24 gauge thick GI corrugated sheet or suitably stiffened plain GI
sheet fixed on frames. Such panels shall be suitably connected to each other for
stability with nuts and bolts, hooks, clamps etc. and fixed firmly to the ground at
(b) Contractor shall take all precautionary measures to avoid any damage to adjoining
property. All necessary arrangement shall be made at his own cost.
The Contractor shall provide and erect a display board of size and shape as required
and paint over it, in a legible and workman like manner, the details about the salient
features of the project, as required by the Engineer-in-Charge. The Contractor shall
fabricate and put up a sign board in an approved location and to an approved design
indicating name of the project, client / owner, architects, structural consultants,
Department etc. besides providing space for names of other Contractors, Sub-
Contractors and specialized agencies. Nothing extra shall be payable on this
account.
4.5 Necessary protective and safety equipments shall be provided to the Site Engineer,
Supervisory staff, labour and technical staff of the contractor by the Contractor at
his own cost and used at site.
4.6 No inflammable materials including P.O.L shall be allowed to be stored in huge
quantity at site. Only limited quantity of P.O.L may be allowed to be stored at site
subject to the compliance of all rules / instructions issued by the relevant authorities
and as per the direction of Engineer -in- Charge in this regard. Also all precautions
and safety measures shall be taken by the Contractor for safe handling of the P.O.L
products stored at site. All consequences on account of unsafe handling of P.O.L
shall be borne by the Contractor.
6.2 The contractor shall make arrangement for Helmets and leather shoes (meant of
construction work at sites) for all field staff of the department during the entire
period of construction for safety reasons. One helmet and two pairs of shoes per
staff member (maximum ten members) of the departments per year shall be
arranged by the contractor.
6.3 The Contractor shall arrange for two number computers along with printer,
necessary peripherals and including broadband connection with one number
computer operator at the disposal of Engineer-in-charge. The computer shall be
provided with MS-project & the computer operator shall be fully conversant with Ms-
word, Excel, Power-point, & Ms-Project. Nothing extra shall be paid on this account.
6.4 The Contractor shall give the Engineer-in-charge on the 4th day of each month, a
progress report along with pictorial photographs of the work done during the
previous month. The progress of work will be reviewed periodically by the Engineer-
in charge with the contractor and shortfalls, if any, sorted out. The contractor shall
there upon take such action as may be necessary to bring back his work to schedule
without additional cost to the department.
(a) The Contractor shall be responsible for maintenance and watch and ward of
the complete installation and water / electricity meter and shall also be
responsible for any pilferage, theft, damage, penalty etc. in this regard. The
(b) The Department shall in no way be responsible for either any delay in getting
electric and/or water and/or telephone connections for carrying out the work
or not getting connections at all. No claim of delay or any other kind,
whatsoever, on this account shall be entertained from the Contractor. Also
contingency arrangement of stand-by water & electric supply shall be made
by the Contractor for commencement and smooth progress of the work so
that work does not suffer on account of power failure or disconnection or not
getting connection at all. No claim of any kind whatsoever shall be
entertained on this account from the Contractor. Nothing extra shall be
payable on this account.
(c) The Contractor shall arrange electricity at his own cost for testing of the
various electrical installations as directed by Engineer-in-Charge and for the
consumption by the contractor for executing the work. Also all the water
required for testing various electrical installations, fire pumps, wet riser / fire
fighting equipments, fire sprinklers etc. and also testing water supply,
sanitary and drainage lines, water proofing of under ground sump, over head
tanks, water proofing treatment etc. shall be arranged by the contractor at
his own cost. Nothing extra shall be payable on this account.
8.1 The composite tender comprises of two main components: viz. civil work and E & M
works. The list of Specialized Agencies for certain items in case of Civil works and E
& M works have been approved by the Department and given in the tender
documents. The tenderer shall select one of the approved Specialized Agencies for
the specified items of the Civil work and for each E & M package for executing the
work and furnish the name of Specialized Agencies for various works at the time of
submission of tender. The Specialized Agencies selected by the tenderer may attend
the pre-bid meeting, after careful study of contract conditions, specifications,
drawings & schedule of quantities for different Packages of work for meaningful
discussion in the meeting.
8.2 It shall be the responsibility of main contractor to sort out any dispute / litigation
with the Specialized Agencies without any time & cost overrun to the Department.
The main contractor shall be solely responsible for settling any dispute / litigation
arising out of his agreement with the Specialized Agencies. The contractor shall
ensure that the work shall not suffer on account of litigation/ dispute between him
and the specialized agencies / sub-contractor(s). No claim of hindrance in the work
shall be entertained from the Contractor on this account. No extension of time shall
be granted and no claim what so ever, of any kind, shall be entertained from the
Contractor on account of delay attributable to the selection/rejection of the
Specialized Agencies.
8.3 The main contractor cannot work as a specialized Agency unless his name is already
included in the list of Approved specialized Agencies.
9.3 The site of work shall be always kept clean due to constraints of space and to avoid
any nuisance to the users of buildings in the adjacent plots. The Contractor shall
take all care to prevent any water- logging at site. The wastewater, slush etc. shall
not be allowed to be collected at site. It may be directly pumped into the natural
drain with prior approval of the concerned authorities. For discharge into public
drainage system, necessary permission shall be obtained from relevant authorities
after paying the necessary charges, if any, directly to the authorities. The work
shall be carried out in such a way that the area is kept clean and tidy. All the
fees/charges in this regard shall be borne by the Contractor. Nothing extra shall be
payable on this account.
In event of any restriction being imposed by the Department, traffic or any other
statutory authority having control over the project, on the working or movement of
Labour, materials, etc., the Contractor shall strictly follow all such restrictions or
instructions issued regarding the same and nothing extra shall be payable to the
Contractor on account of such restrictions or instructions. No delay or claims of any
kind shall be entertained from the Contractor on this account. The loss of time on
this account, if any, shall have to be made up by the contractor by generating and
deploying additional resources etc. Nothing extra shall be payable on this account.
11.0 DOCUMENTATION
The Contractor shall render all help and assistance in documenting the total sequences of this
project by way of photography, slides, audio / video recording etc. Nothing extra shall be
payable to Contractor on this account. However, cost of photographs, slides, audio / video
graph etc. shall be borne by the Department. The original films shall be the property of the
Department. No copy shall be prepared without the prior approval of the Engineer- in –
Charge.
1.1 The Contractor shall carry out survey of the work area, at his own cost, setting out
the layout and fixing of alignment of the pile work, building in consultation with the
Engineer-in-Charge & proceed further. Any discrepancy between the architectural
drawings and actual layout at site shall be brought to the notice of the Engineer-in-
charge. It shall be responsibility of the Contractor to ensure correct setting out of
alignment. Total station survey instruments only shall be allowed to be used for
layout, fixing boundaries, centre lines, etc., along with theodolites. Nothing extra
shall be payable on this account.
1.2 The Contractor shall establish, maintain and assume responsibility for grades, lines,
levels and benchmarks. He shall report any errors or inconsistencies regarding
grades, lines, levels, dimensions etc. to the Engineer-in-Charge before commencing
work. Commencement of work shall be regarded as the Contractor’s acceptance of
such grades, lines, levels, and dimensions and no claim shall be entertained at a
later date for any errors found.
1.3 If at any time, any error in this regard appears during the progress of the work, the
Contractor shall, at his own expense rectify such error, if so required, to the
satisfaction of the Engineer-in-Charge. Nothing extra shall be payable on this
account.
1.4 Though the site levels are indicated in the drawings the Contractor shall ascertain
and confirm by him, the site levels with respect to benchmark from the concerned
authorities. The Contractor shall protect and maintain temporary/permanent
benchmarks at the site of work throughout the execution of work. These
benchmarks shall be got checked by the Engineer-in-Charge or his authorized
representatives. Nothing extra shall be payable on this account.
1.5 The work at different stages shall be checked with reference to bench marks
maintained for the said purpose. The cost of carrying out lay outs at all stages
including marking of reference points, center lines of the building etc. including
construction/maintenance of said bench marks shall be deemed to be included in
quoted rates quoted for various items. Nothing extra shall be payable on this
account.
1.6 The entire work up to the plinth level, as required for obtaining approval of the
plinth from the local authority, shall be completed by the Contractor at the same
time. The Contractor shall also extend all co-operation and liaison with the local
body for approval of plinth. Nothing extra shall be payable on this account. Work
above plinth shall be allowed to be carried out only after obtaining approval from the
local body. No delay shall be allowed on this ground and also no claim whatsoever
on account of any delay in approval at plinth level by the local body shall be
entertained from the Contractor. Nothing extra shall be payable on this account.
1.7 The approval by the Engineer-in-Charge, of the setting out by the Contractor, shall
not relieve the Contractor of any of his responsibilities and obligation to rectify the
errors/ defects, if any, which may be found at any stage during the progress of the
work or after the completion of the work.
1.9 The rates quoted by the Contractor are deemed to be inclusive of site clearance,
setting out work, profile, establishment of reference bench mark(s), taking spot
levels, construction of all safety and protection devices, barriers, preparatory works,
working during monsoon, working at all depths, height and location etc. and any
other incidental works required to complete this work. Nothing extra shall be
payable on this account.
1. (a) The CPWD/Contractor shall procure IS marked TMT bars of various grades
from the steel manufacturers or their authorised dealers (as per following
selection criteria) having valid BIS license for IS:1786-2008 (amendment -1
November 2012)
The procured steel should have following qualities:-
i) Excellent ductility, bend ability and elongation of finished product due to
possible refining technology.
ii) Consumption of steel should be accurate as per design.
iii) Steel should have no brittleness problem in finished product.
iv) Steel should carry the quality of corrosion and earthquake resistance.
v) Quality steel with achievement of proper level of sulphur and phosphorus as
per IS:1786-2008.
(b) Selection Criteria of steel manufacturers
The supply of reinforcement steel for all CPWD works should have following
selection criteria of steel manufacturers:-
Steel producers of any capacity using iron ore/processed iron ore as the basic raw
material adopting advanced refining technologies as given hereunder,
(i) DRI-EAF=Direct Reduced iron-Electric arc furnace.
Or
(ii) BF-BOF=Blast furnace-Basic oxygen furnace
Or
(iii) COREX-BOF=COREX-Basic oxygen furnace
For production of liquid steel to finish product at single/multiple locations with NABL
or any other similarly placed accrediting Governmnet body which operates in accordance
with ISO/IEC17011 and accredits labs as per ISO/IEC 17025 conforming to IS:1786-2008
(Amendment1 November 2012). The check list for incorporation any quality steel producer
is enclosed for technical assessment is given in Annexure-1.
Chief Engineer / CPM / PM shall approve the steel manufactures for projects under
their jurisdiction. NIT approving authority shall specify the manufacturers in the tender
document.
1. Contractor shall have to obtain and furnish test certificates to the Engineer-in-
charge in respect of all supplies of steel brought by him to the site of work.
2. Samples shall also be taken and got tested by the Engineer-in-Charge as per the
provisions in this regard in relevant BIS codes. In case the test results indicate that
the steel arranged by the Contractor does not conform to the specifications
mentioned in IS 1786-2008 pertaining to Fe 500D, the same shall stand rejected
and it shall be removed from the site of work by the Contractor at his cost within a
week time on written orders from the Engineer-in-Charge to do so.
3. The steel reinforcement bars shall be brought to the site in bulk supply of 10 tonnes
or more or as decided by the Engineer-in-Charge.
4. The steel reinforcement bars shall be stored by the Contractor at site of work in
such a way as to prevent their distortion and corrosion and nothing extra shall be
paid on this account. Bars of different sizes and lengths shall be stored separately
to facilitate easy counting and checking.
5. For checking nominal mass, tensile strength, bend test, re-bend test etc. specimens
of sufficient length shall be cut from each size of the bar at random, and at
frequency not less that specified below:
Under 10mm One sample for each 25 tonnes of One sample for each 40
dia bars part thereof tonnes part thereof.
10mm to One sample for each 35 tonnes or One sample for each 45
16mm dia bars par++t thereof tonnes part thereof.
Over 16mm dia One sample for each 45 tonnes of One sample for each 60
bars part thereof. tonnes part thereof.
6. The Contractor shall supply free of charge the steel required for testing including its
transportation to testing laboratories. The cost of tests shall be borne by the
contractor.
7. The actual issue of consumption of steel on work shall be regulated and proper
accounts maintained as provided in clause 10 of the contract. The theoretical
consumption of steel shall be worked out as per procedure prescribed in clause 42 of
the contract and shall be governed by conditions laid therein. In case the
consumption is less than theroretical consumption including permissible variations
recovery at the rate so prescribed shall be made. In case of excess consumption no
adjustment need to be made.
8. The steel bought to site and steel remaining unused shall not be removed from site
without the written permission of the Engineer-in-Charge.
(i) By the Contractor, if the results show that the cement does not conform to
(ii) By the Department, if the results show that the cement conforms to relevant
BIS Codes.
5. The actual issue and consumption of cement on work shall be regulated and proper
accounts maintained as provided in clause 10 of the contract. The theoretical
consumption of cement shall be worked out as per procedure prescribed in clause 42
of the contract and shall be governed by conditions laid therein. In case the cement
consumption is less than theoretical consumption including permissible variation,
recovery at the rate so prescribed shall be made. In case of excess consumption no
adjustment need to made.
6. Cement brought to site and cement remaining unused after completion of work shall
not be removed from site without written permission of the Engineer-in-Charge.
7. The damaged cement shall be removed from the site immediately by the contractor
on receipt of a notice in writing from the Engineer-in-Charge. If he does not do so
within 3 days of receipt of such notice, the Engineer-in-Charge shall get it removed
at the cost of the contractor.
1. SITE
1.1.1 The contractor shall ensure that adequate measures are taken for the prevention of
erosion of the topsoil during the construction phase. The contractor shall implement
the Erosion and Sedimentation Control Plan (ESCP) to be prepared by him and
approved by the Engineer in Charge as part of the larger Construction Management
Plan (CMP). The contractor shall obtain the Erosion and Sedimentation Control Plan
(ESCP) Guidelines from the Engineer in Charge and then prepare working plan for
the following month’s activities as a CAD drawing showing the construction
management, staging & ESCP. At no time soil should be allowed to erode away from
the site and sediments should be trapped where necessary.
The contractor shall ensure that all the top soil excavated during construction works
is neatly stacked and is not mixed with other excavated earth. The contractors shall
take the clearance of the Engineer in Charge before any excavation. Top soil should
be stripped to a depth of 20 cm (centimeters) from the areas to be disturbed, for
example proposed area for buildings, roads, paved areas, external services and area
required for construction activities etc. It shall be stockpiled to a maximum height of
40 cm in designated areas, covered or stabilized with temporary seeding for erosion
prevention and shall be reapplied to site during plantation of the proposed
vegetation. Top soil shall be separated from subsoil, debris and stones larger than
50 mm (millimeter) diameter. The stored top soil may be used as finished grade for
planting areas.
1.1.2 The Contractor should follow the construction plan as proposed by the Architect
/Engineer in Charge to minimize the site disturbance such as soil pollution due to
spilling. Use staging and spill prevention and control plan to restrict the spilling of
the contaminating material on site. Protect top soil from erosion by collection
storage and reapplication of top soil, constructing sediment basin, contour
trenching, mulching etc.
1.1.3 No excavated earth shall be removed from the campus unless suggested otherwise
by Engineer in Charge. All subsoil shall be reused in backfilling/landscape, etc. as
per the instructions of the Engineer in Charge. The surplus excavated earth shall be
disposed of by the contractor at his own cost for reuse. A certificate of reuse as
required by the Engineer-in-Charge shall be submitted by the contractor.
1.1.4 The contractor shall not change the natural gradient of the ground unless specifically
instructed by the Engineer in Charge. This shall cover all natural features like water
bodies, drainage gullies, slopes, mounds, depressions, etc. Existing drainage
patterns through or into any preservation area shall not be modified unless
specifically directed by the Engineer-in-charge.
1.1.5 The contractor shall not carry out any work which results in the blockage of natural
drainage.
1.1.6 The contractor shall ensure that existing grades of soil shall be maintained around
existing vegetation and lowering or raising the levels around the vegetation is not
allowed unless specifically directed by the Engineer-in-charge.
1.1.7 Contractor shall reduce pollution and land development impacts from automobiles
use during construction.
Paints
Non-flat - 150 g/L
Sealers
Waterproofing sealer - 250 g/L
Sanding sealer - 275 g/L
Other sealers - 200 g/L
The VOC (Volatile Organic Compounds) content of adhesives and sealants used must
be less than VOC content limits mentioned:
Architectural Applications VOC Limit (g/l less water)
1.2.20 Wherever required, Contractor shall meet and carry out of all activities on site,
supplementation of information, and submittals in accordance with IGBC LEED India
New Construction v1.0 & GRIHA program standards and guidelines.
Towards meeting the aforementioned building environmental rating standard(s)
expert assistance shall be provided to him up on request.
1.2.21 Water Use during Construction
Contractor should spray curing water on concrete structure and shall not allow free
flow of water. Concrete structures should be kept covered with thick cloth/gunny
bags and water should be sprayed on them. Contractor shall do water poundings on
all sunken slabs using cement and sand mortar.
1.2.22 The Contractor shall remove from site all rubbish and debris generated by the Works
and keep Works clean and tidy throughout the Contract Period. All the serviceable
and non-serviceable (malba) material shall be segregated and stored separately.
The malba obtained during construction shall be collected in well-formed heaps at
properly selected places, keeping in a view safe condition for workmen in the area.
Materials which are likely to cause dust nuisance or undue environmental pollution
in any other way, shall be removed from the site at the earliest and till then they
shall be suitable covered. Glass & steel should be dumped or buried separately to
prevent injury. The work of removal of debris should be carried out during day. In
1.2.29 EQUIPMENT
(a) To ensure energy efficiency during and post construction all pumps, motors
and engines used during construction or installed, shall be subject to
approval and as per the specifications of the Engineer in Charge.
(b) All lighting installed by the contractor around the site and at the labour
quarters during construction shall be LED bulbs of the appropriate
illumination levels. This condition is a must, unless specifically prescribed.
The contractor is expected to go through all other conditions of the LEED & GRIHA
rating stipulations. Failure to adhere to any of the above mentioned items, without
approval of the Engineer in Charge, shall be deemed as a violation of contract and
the contractor shall be held liable for penalty as per terms of the agreement.
1.3 Wherever any reference to any Indian Standards occurs in the documents relating to
this contract, the same shall be inclusive of all amendments issued thereto or
revisions thereof, if any, upto the date of receipt of tenders.
1.4 Unless otherwise specified in the schedule of quantities, the rates for all items of
work shall be considered, as inclusive of pumping out or bailing out water, if
required through out the construction period for which no extra payment shall be
made. This shall also include water encountered from any source such as rains,
floods, sub soil water table being high and/or due to any other cause whatsoever.
1.5 The work shall be executed and measured as per metric dimensions given in the
Schedule of quantities, drawings etc. (F.P.S. units wherever indicated are for
guidance only).
(a) All stone aggregate and stone ballast shall be of hard stone variety to be
obtained from approved quarries at Navi Mumbai or any other source to be
got approved from the Engineer-in-charge.
(b) Coarse sand should be obtained from Vaitarna / Mahad or any other source
to be got approved from the Engineer-in-charge. The coarse sand shall be
screened before using, if required. The same shall be clean and sharp angular
grit type. If the sand brought to site is dirty, it must be washed in clean water
to bring the sand to the required specifications. Nothing extra shall be payable
on this account.
(c) Fine sand should be obtained from Vaitarna /Mahad or any other source to
be got approved from the Engineer-in-charge. The fine sand shall be screened,
if required. The same shall be clean and sharp angular grit type. If the sand
brought to site is dirty, it must be washed in clean water to bring the sand to
the required specifications. Nothing extra shall be payable on this account.
(b) All the materials shall be procured and delivered in sealed containers with
labels legible and intact.
(c) All the chemicals (polymers, epoxy, water proofing compound, plasticizer,
chloropyrifos etc.) shall be procured in convenient packs say 20 litres (Kgs.)
capacity packing only or as approved by the Engineer-in-Charge, and not in
bigger capacity containers, say 200 litre (Kgs.) drums unless otherwise
specifically permitted by the Engineer-in-Charge. One sample from each lot of
the chemical procured by the contractor shall be tested in a laboratory as
approved by the Engineer – in – Charge.
(d) All material required for the execution of the work shall be got approved,
procured and deposited with the Departmental supervisory staff. The materials
shall be kept in joint custody of the contractor and the Department. The watch
and ward of such material shall, however, remain to be the responsibility of
the contractor and no claim, whatsoever, on this account shall be entertained.
Different containers of each chemical shall be serially numbered on packing
and also consumed in that order. Day-to-Day account of receipt, issue and
balance shall be regulated by the Department and proper account shall be
maintained at site of work in the prescribed form as per the standard practice.
(e) All the chemicals shall be procured by the contractor directly from the
manufacturer. In exceptional circumstances, the contractor may be allowed to
procure the materials from the authorized dealers of the manufacturers, if
specifically permitted by the Engineer-in-Charge.
(f) The original copies of challan / cash memos towards the quantity of various
chemicals procured shall be made available by the contractor at the request
from the Engineer-in-Charge and a copy of the same shall be kept in record.
(j) Empty containers of the chemicals should not be removed from site till the
completion of work and shall be removed only with the written approval of
the Engineer-in-Charge.
(k) All arrangements for measuring, dosing and mixing of material / chemicals at
site have to be made by the contractor.
(l) Contractor shall suitably advise his site Engineer and all the workers as
regards safe handling of chemicals. Necessary protective and safety
equipments in form of hand gloves, goggles etc. shall be provided by the
contractor and be also used at site.
(m) All incidental charges of any kind including cartage, storage and wastage and
safe custody of material etc. shall be borne by the contractor and no claim,
whatsoever, shall be entertained on this account.
(n) The chemicals shall be tested in an independent laboratory as approved by the
Engineer-in-Charge at the frequency as specified. If required, more samples
may have to be tested as per the directions of the Engineer-in-Charge. Nothing
extra shall be payable on this account. However testing charges shall be
borne by the department of the samples satisfy the requirements specified in
the tender.
2.2 De-watering shall be carried out by suitable means with adequate stand-by
arrangements of pumps etc. and it shall be ensured that its disposal is carried out as
per the regulations of the local bodies. The water / slush / muck etc. shall not be
disposed off into the public drainage system of sewer manhole or storm water drain,
but shall be pumped off into the creek close to the plot or disposed by any other
manner, subject to the approval of the local bodies in this regard. The agencies are,
therefore, advised to inspect and acquaint themselves of the site and location of
disposal point(s) of water / slush and satisfy themselves as regards method of
pumping and disposal required to be adopted. Any default or failure on the part of
the Contractor to acquaint him with the aforesaid aspect of work shall not absolve
him from his responsibility for the execution / performance of this contract. Also, all
permissions in this regard, to be taken from local authorities, shall be obtained by
the Contractor. Nothing extra shall be payable on these accounts.
2.3 In trenches where surface water is likely to get into cut / trench during monsoons, a
ring bund of puddle clay or by any other means shall be formed outside, to the
required height, and maintained by the Contractor. Also, suitable steps shall be
taken by the Contractor to prevent back flow of pumped water into the trench.
Nothing extra shall be payable on this account.
2.4 Unless otherwise provided in the item of schedule of quantity the cost of de watering
or working under water and / or liquid mud for execution of all the items for the
work is deemed to be included in quoted rates of the respective items and shall not
be measured separately for payment. Nothing extra shall be payable for de watering
in this work, irrespective of whether specified or not, in the item descriptions or in
the specifications / conditions in this contract agreement.
The cover blocks, wherever used, for proper cover & to avoid displacement of
reinforcement bars shall be manufactured in factory. Nothing extra shall be paid for
providing such cover blocks in the work.
Nothing extra shall be paid for the centering & shuttering circular in shape wherever the
form work is having a mean radius exceeding 6m in plan.
The bulk of concrete of required mix shall be arranged from RMC plant and smaller
quantities in lintel band, sill band etc. similar locations will be allowed for production at site
for contractor shall be required to install automatic batching plant of minimum 5 cum per
hour capacity. For design mix, provisions of IS: 456-2000 – Latest Edition shall be
followed. Following parameters shall be adopted for mix design as per IS-456-2000.
The concrete mix design with and without admixture will be carried out by the contractor,
at his own cost, through one of the following laboratories/Test houses to be approved by
Engineer-in-charge:-
In the event of all the four laboratories being unable to carry out the requisite
design/testing, the contractor shall have to get the same done from any other reputed
laboratory with prior approval of the Engineer-in-Charge.
The various ingredients for mix design/laboratory tests shall be sent to the approved
lab/test houses through the Engineer-in-charge and the samples of such ingredients sent
shall be preserved at site by the contractor till completion of work or change in Design Mix
whichever is earlier. The sample shall be taken from the approved materials which are
proposed to be used in the work.
The Contractor shall submit the mix design report from approved laboratory for approval of
Engineer-in-Charge within 45 days from the date of issue of letter of acceptance of the
tender. No concreting shall be done until the mix design is approved by Engineer-incharge.
The contractor shall make cubes of trial mixes as per approved mix design at site
laboratory for all grades of concrete in presence of the Engineer in charge using same
ingredients as adopted for design mix, prior to commencement of concreting and get them
tested in presence of Engineer-in-charge. The testing and the acceptance of the trial mixes
shall be as per CPWD Specifications. The conformity of mix design should be established by
conducting three repeat trial mix tests. In each repeat trial mix test six cubes of standard
size 15 cm x 15 cm x 15 cm shall be cast, out of which three cubes shall be tested after 7
days & 3 cubes shall be tested after 28 days. This provision shall be as per relevant paras
of CPWD specifications 2009.
90% of the total trial mix tests shall be done in the laboratory established at site by the
contractor and remaining 10% in any government laboratory or government engineering
college situated in Mumbai/ Navi Mumbai or in any other laboratory as directed by
For each change of source or quality / characteristic properties of the ingredients from that
approved & used in the concrete mix during the work, a fresh mix design shall be got done
by the contractor. However, maximum two such changes shall be permitted in the whole
work. For any change, the Contractor shall bear the cost of fresh Mix Design. Revised trial
mix tests shall be conducted at laboratory established at site or Engineer-in-Charge may
order for testing of these cubes from the independent laboratory and shall be submitted by
the contractor as per the direction of the Engineer-in-charge.
The cost of packaging, sealing, transportation, loading, unloading, cost of samples and the
testing charges for mix design in all cases shall be borne by the contractor.
The mix design shall be done considering the degree of quality control as “Good” in all
cases.
The mix design for a specified grade of concrete shall be done for target mean compressive
strength - Tck = fck + 1.65 S
Where: fck = characteristic compressive strength at 28 days.
S = Standard deviation which depends on degree of quality control.
The degree of quality control for this work shall be “Good” for which the standard deviation
(s) for different grades of concrete as per IS456-2000 shall be followed. Standard deviation
calculations of test results shall also be done as per clause 9.2.4 of IS456-2000 for
maintaining the quality control.
The mix design shall be carried out generally in accordance with the provisions made in
CPWD specification and IS 456-2000 read along with the provisions mentioned in this
document.
Acceptance criteria for trial Mix:- Average of all the cubes tested at 28 day shall be more
than target mean strength (i.e. fck + 1.65 S). No individual cube shall be less than 0.85
times the target mean strength.
Work Strength Test & Acceptance criteria:- Work strength Test for strength of concrete
shall be carried out as per para 5.8.12.2 of CPWD specifications 2002, relevant paras of
CPWD specifications 2009 will superceed. 90% of the total work strength tests shall be
done at the laboratory established at site by the contractor and remaining 10% in the
laboratory of Central Design Organization, CPWD or in any other laboratory as directed by
Engineer in Charge. The testing charges would be governed by para 39.0 of special
conditions. The acceptability criterion given in para 5.8.4.1 of CPWD specifications 2002,
relevant paras of CPWD specifications 2009 will superceed shall be read along with
following :-
In case four consecutive tests results (as per para 5.8.4.1 of CPWD specification) are not
available in one day’s concreting the standard deviation for purpose of acceptance of
concrete shall be calculated on the basis of all the cube test results of that particular day of
concreting.
If the cube results of individual cube do not comply with the condition mentioned in column
3 of Table 6 of para 5.8.4.1 of CPWD specification 2002, relevant paras of CPWD
specifications 2009 will superceed but the test results satisfy the requirement of mean
compressive strength as mentioned in column 2 of above table the concrete represented by
the cube not meeting the requirements shall be at risk. The Engineer-in-Charge reserves
the right to reject the said concrete or to accept it at reduced rates subject to establishing
the structural adequacy by means of additional tests and suitable remedial measures as
directed by Engineer-in-Charge.
The contractor shall have to arrange bulk of quantity of Ready MIX concrete (RMC) from
the RMC producing plants supplying concrete in Navi Mumbai/ Mumbai.
The contractor shall, within 15 days of award of the work, submit the details of RMC
producers, out of list specified in the contract document including details and number of
transit mixers & pumps etc. to be deployed indicating name of owner/company, its location.
Text of MOU proposed to be entered between purchaser (the contractor) and supplier (RMC
producer) to the Engineer-in-Charge. Engineer-in-Charge shall give approval in writing. The
contractor shall draw the MOU with approved RMC producer and submit to Engineer-in-
Charge with in a week of such approval. The contractor will not be allowed to use ready
mixed-concrete without completion of above stated formalities.
1.5.3.1 For all purposes, the contractor shall carry out fully, the responsibilities of
the “placement contractor” and the “manufacturer of concrete”.
The Engineer-in-Charge will reserve right to inspect at any stage and reject the concrete if
he is not satisfied about quality of product at the user’s end.
Ingredients water and admixtures purchased , stored and to be used in the concrete
including conducting of tests for checking quality of materials, recording of test results and
declaring the materials fit or unfit for use in production of mix.
Weight and quantity check on the ingredients, water and admixtures added for batch
mixing.
Testing of fresh concrete, recordings of results and declaring the mix fit or
unfit for use. This will include continuous control on the workability during
production and taking corrective action, if required.
The contractor should therefore draw MOU/agreement with RMC producer very
carefully keeping in view all terms and conditions/specifications forming part of
this tender document.
OPC Cement (Conforming to IS 456 Code) fly ash confirming to grade I of IS 3812
(Part I) brand/make/source as
approved by Engineer-in-Charge shall only be used for production of concrete
for the work.
It shall be the responsibility of the contractor to ensure that RMC producer provides
all necessary testing equipments and takes all necessary measures to ensure Quality
Control of ready mixed concrete. In general the required measures shall be :-
(I) Control of purchased material quality RMC producer shall ensure that all the
materials purchased and used in the production of concrete conform to the
stipulation of the relevant agreed standards and the requirements of the concrete
mix design and quality control procedures. This shall be accomplished by visual
checks, sampling and testing, certification from material supplier and
information/data from material supplier. Necessary equipment for the testing of all
material shall be provided and maintained in calibrated condition at the plant by the
RMC producer.
(II) Control of material storage Adequate and effective storage arrangement shall
be provided by RMC producer at RMC plant for reliable transfer and feed systems,
drainage of aggregates, prevention of freezing or excessive solar heating of
aggregate, prevention of contamination etc.
(III)Record of mix design and mix design modification RMC producer shall
ensure that record of mix design and mix design modification is readily available in
his computer at RMC plant for inspection of Engineer-in-Charge or his authorised
representative at any time. Any modification in mix design shall be done only after
the approval of Engineer-in-Charge.
(IV) Transfer and weighing equipment RMC producer shall ensure that a
documented calibration procedure is in place. Proper calibration records shall be
made available indicating date of next calibration due & corrective action taken. RMC
producer shall ensure additional calibration checks whenever required by E-in-C in
writing to contractor. RMC producer shall also maintain a daily production record
including details of customers to whom RMC was supplied including details of mixes
supplied. Record shall also be maintained of the material used for each day’s
production including water and admixtures.
The accuracy of measuring equipment shall be within +2% of quantity of cement &
+3% of quantity of aggregate, admixture and water being measured.
(V) Maintenance of Plant, Trucks, Mixers and Pumps: Plant, Truck Mixers and
Pumps should be well maintained so as not to hamper any operation of production,
transportation and placement of concrete.
Weighing (correct reading of batch data and accurate weighing) :-For each load,
written, printed or graphical records shall be made of the weights of the materials
batched, the estimated slumps, the total amount of water added to the load, the
delivery tickets, serial number of load and time of loading of concrete into the truck.
(XI) Control of designed and the prescribed mixes : A quality control system
shall be operated to control the strength of designed mixes to the required
levels. The system shall include continuous analysis of results from cube
tests.
All Ready Mixed Designed concrete from plant shall be laid with the help of concrete
pump of adequate capacity for which nothing extra shall be paid over and above the
quoted rates in relevant items. However, small quantity can be allowed without pump
with prior written approval of Engineer-in-charge as per site requirement.
NOTE: - In case cement content as per the approved design mix is less than the
cement content specified in the nomenclature of the item, financial adjustment at Rs.
6520/-per M.T of cement shall be done.
Minimum Quality Assurance Plan
The contractor has to comply with the minimum quality assurance plan, as
follows:-
Lot size, number of required tests and frequency of testing shall be conducted as per
CPWD specification and BIS Code and manufacturer’s certificate.
All the relevant and applicable codes, specification and standards, as well as the
acceptance criteria for various items of work, workmanship, materials & process
employed should be made available at site office by contractor.
All the register of tests carried out at Construction site or in outside laboratories shall
be maintained by the contractor which shall be issued to the contractor by Engineer –
in – Charge.
All samples of materials including cement concrete cubes shall be taken jointly with
contractor by JE and out of this at least 50% samples shall be taken in presence of AE
incharge. If there is no JE, all samples of materials including cement concrete cubes
shall be taken by AE jointly with contractor. All the necessary assistance shall be
All the test in field lab setup at construction site shall be carried out by the Engineering
staff deployed by the contractor which shall be 100% witnessed by JE and 50% of tests
shall be witnessed by AE incharge. At least 10% of the tests are to be witnessed by the
Executive Engineer.
All the entries in the registers will be made by the designated Engineering staff of the
contractor and same should be regularly reviewed by JE/ AE/ EE. Contractor shall be
responsible for safe custody of all the test register. Submission of copy of all test
registers, material at site register and hindrance register alongwith each alternate
Running Account Bill and Final Bill shall be mandatory. These registers should be duly
checked by AE (P) in Division Office and receipt of registers should also be
acknowledged by AAO by signing the copies.
All the MAS registers including cement and steel register shall be maintained by
contractor which shall be issued to the contractor by Engineer- in- charge.
Each of the entry of receipt of material at site shall be test checked 100% by the J.E. or
by AE if there is no JE.
Cement register and other registers shall be reviewed by EE at least once in a month.
The contractor shall make his own arrangement of water for construction and drinking
purpose as well for electricity and its distribution at his own cost. The department will
render only assistance to the contractor for making application to Local body/
authorized Electric supply agency, if required. All the fees and charges including
consumption charges shall be borne bythe contractor. The contractor can make deep
well boring at site. The water should be as per CPWD specifications, 2009 and
necessary test shall be conducted as per CPWD specification.
The contractor shall ensure quality control measures on different aspects of construction
materials, workmanship and correct construction methodologies to be adopted. All the
registers of tests carried out at Construction Site or in outside laboratories shall be
maintained by the contractor which shall be issued to the contractor by Engineer-in-
Charge.
The contractor shall submit samples of various materials to be used for the approval of
the Engineer-in-charge out of the brands provided in the agreement.
The contractor shall submit drawings of shuttering arrangement etc. for the approval of
Engineer-in-Charge. The contractor shall also submit bar bending schedule for approval
of Engineer-in- Charge before execution.
The contractor shall establish a site laboratory & make arrangement of Engineers /
Technicians for testing of materials as per specification and maintain the record of test
results in required Performa as per direction of engineer-in-charge. A tentative list of
minimum equipment’s for site laboratory, to be established by the contractor at site is
as mentioned in part A.
2.
SIGNED FOR AND ON BEHALF OF THE PRESIDENT OF INDIA BY
____________________________________in the presence of:
1.
2.
NOW THE GURANTOR hereby guarantee that Acrylic painting done by him will
remain non flaking and uniform colouring without patches and the minimum guarantee
period of such painting shall be three years to be reckoned form the date of the completion
of work.
Provided that the guarantor will not be responsible for damage caused due to
earthquake or misuse of buildings or alteration and for such purpose. The decision of the
Engineer-in-Charge with regard to cause of damage shall be final and binding.
During this period of guarantee the guarantor shall make good all defects to the
satisfaction of the Engineer-in-Charge at his cost and shall commence the work for such
rectification within seven days from the date of issue of he notice from the Engineer-in-
Charge calling upon him to rectify the defects failing which the work shall be got done by
the Department by some other contractor at the GUARANTOR’S Cost and risk. The decision
of the Engineer-in-Charge as to the cost, payable by the guarantor shall be final and
binding.
That if the guarantor fails to make good the defects or commits breach there under
then the guarantor will indemnify the principal and his successors against all loss, damage
cost, expenses or otherwise which may be incurred by him by reasons of any default on the
part of GUARANTOR in performance and observance of this supplementary agreement. As
to the amount of loss and / or damage and / or cost incurred by the Government and the
decision of the Engineer-in-Charge will be final and binding on both the parties.
IN WITNESS WHEROF these presents have been executed by the obligator ------------ and by ----------------
------ and for and on behalf of the PRESIEDENT OF INDIA on the day, month and year first above written.
The work of Aluminium doors / windows etc. as per item No. 17.1,17.2 & 19.1 to
19.5 shall be guaranteed for a period of 2 (Two) years as per enclosed guarantee bond
against structural stability, water leakage, faulty materials, workmanship and defective
anodized finish, on notification by the Engineer-in-Charge of any compliance to be
performed under this guidance by the contractor, the contractor shall immediately supply
labour / materials and rectify all the defects notified by the Engineer-in-Charge to perform
this guarantee at no additional cost and to ensure that the defects are fully rectified. 1
(one) % of the amount of the aluminium work as per item No. 17.1,17.2 & 19.1 to 19.5
shall be withheld on this account, which shall be refunded under the expiry of the
guarantee period if no defects are observed in the said period or if the defects have been
rectified in pursuant in the agreement to the entire satisfaction of the Engineer-in-Charge.
The agreement made this…..day of……one thousand nine hundred and ………between
(hereinafter called the GUARANTOR of the one part) and the PRESIDENT OF INDIA
(hereinafter called the GOVERNMENT of the other part).
AND WHEREAS THE GUARANTGOR agreed to give a guarantee to the effect that the
said work will remain structurally stable, completely leak-proof and guaranteed against
faulty material and workmanship, defective anodizing, colouring and finishing from two
years from the date of completion of work.
NOW THE GUARANTOR hereby guarantees that work executed by him will remain
structurally stable, completely leak proof and guaranteed against faulty material and
workmanship, defective anodizing and colouring for a minimum life of two years to be
reckoned from the date after the maintenance period prescribed in the contract.
The decision of the Engineer-in-Charge with regard to the cause of defect shall be
final.
During this period of guarantee the guarantor shall make good all defects to the
satisfaction of the Engineer-in-Charge at his cost and commence the work for such
rectification within seven days from the date of issue of notice from the Engineer-in-Charge
calling upon him to rectify the defects failing which the work shall be got done by the
Department by some other contractor at the GUARANTOR’s Cost and risk. The decision of
the Engineer-in-Charge as to the cost, payable by the GUARANTOR shall be final and
binding.
1.
2.
Signed for and on behalf of THE PRESIDENT OF INDIA BY ------------------in the presence
of:
1.
2.
1.1 The contractor shall be fully responsible for and shall guarantee proper performance
of the entire waterproofing system for a period of 10 (Ten) years from the final
completion of works. In addition, specific 10 years written guarantee (to be
furnished in a non-judicial stamp paper of value not less than Rs.100/-) in approved
proforma shall be submitted for the performance of the system, before final
payment and shall not in any way limit any other rights the Employer may have
under the contract.
1.2 All water-proofing work shall be carried out through approved specialist agency as
per method of working approved by the Engineer-in-charge. However the
Contractors shall be solely responsible for waterproofing treatment until the expiry
of the above guarantee period.
1.3 Ten years guarantee in prescribed proforma attached shall be given by the
contractor for the water proofing treatment. In addition 10% (ten percent) of the
cost of these items of water proofing under this sub head shall be retained as
guarantee to watch the performance of the work executed. However, half of this
amount (withheld) would be released after five years from the date of completion of
the work, if the performance of the waterproofing works is satisfactory. The
remaining withheld amount shall be released after completion of ten years from the
date of completion of work, if the performance of the waterproofing work is
satisfactory. If any defect is noticed during the guarantee period, it should be
rectified by the contractor within seven days of issuing of notice by the Engineer-in-
Charge and, if not attended to, the same shall be got done through other agency at
the risk and cost of the contractor and recovery shall be effected from the amount
retained towards guarantee. In any case, the contractor and the specialist agency,
during the guarantee period, shall inspect and examine the treatment once in every
year and make good any defect observed and confirm the same in writing. The
security deposit can be released in full, if bank guarantee of equivalent amount,
valid for the duration of guarantee period, is produced and deposited with the
Department.
1. All purchase of paint shall be made directly from the manufacturers on their
authorized dealers. The delivery challan shall be issued by the manufacturers store
yard directly with full description of the work for which the purchases is being made.
The condition shall be applicable for all from purchases is being made. The condition
shall be applicable for all from purchases for 100 litres or more in a work.
3. The materials shall be Premium Acrylic Smooth Exterior paint with silicone additives
“ Snowcryl 1 – XT, Of M/s Snowcem India Ltd.. or equivalent like (a) Weather Coat
Smooth “ of M/s Berger Paint India Ltd (b) “ Dulux – Weather Shield” of M/S . ICI (
India) Paints (c) Apex Ultima“ of M/s Asian Paints.
4. The base for painting (Acrylic) be prepared by cleaning, scaling mosses etc. with wire
brushes and cleaning with water etc. complete for which no extra payment shall be
made.
*to be filled by EE
3. Unless otherwise specified, the brand / make of the material as specified in the item
nomenclature, in the particular specifications and in the list of approved materials
attached in the tender, shall be used in the work.
4. In case of non-availability of the brand specified in the contract the Contractor shall
be allowed to use alternate equivalent brand of the material subject to submission
of documentary evidence of non - availability of the specified brand. The necessary
cost adjustments on account of above change shall be made for the material.
A. MATERIALS:
• KAJARIA
NITCO,
11 HARDENERS • IRONITE, FERROK,
• HARDONATE.
12 AAC BLOCKS • ULTRA TECH
• BILT
• SIPOREX
• SNEH INDUSTRIES
13 FLUSH DOORS • ARCHID PLY
• KANARA WOOD AND
PLYWOOD INDUSTRIES
• KUTTY FLUSH DOORS
14 NATURAL WOOD VEENERS • ARCHID PLY,
• DURIAN
• KANARA WOOD AND
PLYWOOD INDUSTRIES LTD.
49 PVC water storage Tanks (ISI Marked only) SINTEX, NATIONAL PLASTIC,
KAVERI
50 Centrifugally Cast Spun Iron Pipes (ISI Marked NECO, Kapilansh, Bengal Iron
only) Corporation
51 UPVC Rain Water Pipes (ISI Marked only)(IS Astron Fittings (14375),
:13592) Finolex Supreme, Prince
Polytuf
Polytuf
NEROLAC
NEROLAC
NEROLAC
NEROLAC
NEROLAC
NEROLAC
NEROLAC
Ultratech,
Structural Drawings
1. 170/TC/1 Details of column and foundation OF Institute building
2. 170/RB/1 Details of column and foundation OF Residential building
3. 170/RB/2 Schedule of plinth beam of residential building
Institute building
4. 170/TC/2 Details of grade beam of
5. 170/TC/3 Layout of first floor
6. 170/ST/1,2,3 Staircase details
Residential building
9 FLOORING 10766225.00
10 ROOFING 973923.00
11 FINISHING 3474330.00
16 DRAINAGE 233167.00
10,63,38,741.00
Total (1 to 20 above)
Say 10,63,38,741
Name of work: Construction of Institute and hostel building (New Institutional complex) of
Family Welfare Training and Research Center (FWTRC), At New Panvel, Navi-Mumbai including
internal water supply, sanitary installation, drainage, development work, Internal
electrical installation,Automatic fire alarm system,Down comer system,SITC of VRF type Air
Conditioning D.G. set, Sub station, pump set, street light, passenger lift & Solar water heating system
etc.
(BALANCE WORK)
Sub-Total 260461.00
2 CONCRETE WORK
2.1 Providing and laying in position cement
concrete of specified grade excluding the
cost of centering and shuttering - All
work up to plinth level
2.1.3 Extra for laying cement concrete above 176 cum 699.70 123147
plinth and up to floor V level
Sub-Total 3340611
3.1.2 Walls (any thickness) including attached 640 sqm 463.90 296896
pilasters, butteresses, plinth and string
courses etc.
3.1.4 Lintels, beams, plinth beams, girders, 3140 sqm 427.00 1340780
bressumers and cantilevers
3.1.5 Columns, Pillars, Piers, Abutments, Posts 2190 sqm 582.90 1276551
and Struts
3.1.8 Weather shade, Chajjas, corbels etc., 295 sqm 633.00 186735
including edges
3.4 Add for plaster drip course/ groove in 770 metre 39.50 30415
plastered surface or moulding to R.C.C.
projections.
3.5.1 Providing M-30 grade concrete instead of 620 cum 98.40 61008
M-25 grade BMC/ RMC. (Note:- Cement
content considered in M-30 is @ 340
kg/cum)
3.6.1 All works upto plinth level 115 cum 8435.70 970106
3.6.2 All works above plinth level upto floor V 505 cum 9359.40 4726497
level
Sub-Total 19223193.39
4 BRICK WORK
4.1 Providing and laying autoclaved aerated 1150 Cum 7526.90 8655935
cement blocks masonry with 150
mm/230 mm / 300mm thick AAC blocks
in super structure above plinth level upto
floor V level with RCC Band at Sill level
and lintel level with approved block
laying polymer modified adhesive mortar
all complete as per direction of Engineer-
in-Charge. (The payment of RCC Band &
rainforcement shall be made for
seperately.
Sub-Total 8655935
5.2.1 Cement mortar 1:6 (1 cement : 6 coarse 115 cum 5997.60 689724
sand)
Sub-Total 1168287
6 MARBLE WORK
6.1.1.1 Area of slab upto 0.50 sqm 450 sqm 4970.50 2236725
6.1.1.2 Area of slab over 0.50 sqm 205 sqm 5023.70 1029859
6.2 Extra for fixing marble /granite stone, 70 metre 318.10 22267
over and above corresponding basic
item, in facia and drops of width upto
150 mm with epoxy resin based
adhesive, including cleaning etc.
complete.
Sub-Total 3349700
7.13.1 Two track two panels sliding window 155 sqm 7710.80 1195174
made of (big series) frame 67x50 mm &
sash 46x62 mm both having wall
thickness of 2.3 ± 0.2 mm and single
glazing bead of appropriate dimension.
(Area of window above 1.75 sqm upto
2.50 sqm)
7.12.1. Three track three panels sliding window 104 sqm 9118.30 948303
2 made of (big series) frame 116 x 45 mm
& sash 46 x 62 mm both having wall
thickness of 2.3 ± 0.2 mm and single
glazing bead / double glazing bead of
appropriate dimension. (Area of window
above 1.75 sqm)
7.14 Extra for providing lipping with 2nd class 535 sq mtr 470.40 251664
teak wood battens 25mm minimum
depth on all edges of flush door shutters
(overall area of shutter to be measured)
Sub-Total 8141205
8 STEEL WORK
8.1 Supplying and fixing rolling shutters of
approved make, made of required size
M.S. laths, interlocked together through
their entire length and jointed together
at the end by end locks, mounted on
specially designed pipe shaft with
brackets, side guides and arrangements
for inside and outside locking with push
and pull operation complete, including
the cost of providing and fixing
necessary 27.5 cm long wire springs
manufactured from high tensile steel
wire of adequate strength conforming to
IS: 4454 - part 1 and M.S. top cover of
required thickness for rolling shutters.
8.2 Providing and fixing ball bearing for 6 Each 564.40 3386
rolling shutters.
8.4 Providing and fixing circular/ Hexagonal 129 Each 183.80 23710
cast iron or M.S. sheet box for ceiling
fan clamp, of internal dia 140 mm, 73
mm height, top lid of 1.5 mm thick M.S.
sheet with its top surface hacked for
proper bonding, top lid shall be screwed
into the cast iron/ M.S. sheet box by
means of 3.3 mm dia round headed
screws, one lock at the corners. Clamp
shall be made of 12 mm dia M.S. bar
bent to shape as per standard drawing.
Sub-Total 2603370
9 FLOORING
9.1 Chequerred precast cement concrete
tiles 22 mm thick in footpath &
courtyard, jointed with neat cement
slurry mixed with pigment to match the
shade of tiles, including rubbing and
cleaning etc. complete, on 20 mm thick
bed of cement mortar 1:4 (1 cement: 4
coarse sand).
9.1.1 Ordinary cement without any pigment 205 sqm 846.20 173471
9.3 Providing and laying rectified Glazed 283 sqm 1298.00 367334
Ceramic floor tiles of size 300x300 mm
or more (thickness to be specified by the
manufacturer), of 1st quality conforming
to IS : 15622, of approved make, in all
colours, shades, except White, Ivory,
Grey, Fume Red Brown, laid on 20 mm
thick Cement Mortar 1:4 (1 Cement : 4
Coarse sand), including pointing the
joints with white cement and matching
pigments etc., complete.
9.4 Crazy ceramic tile flooring,with under 1816 sqm 600.40 1090326
layer 12mm thick cement mortar 1:4 (1
cement 4 coarse sand), with joints not
exceeding 5mm, including filling the
gaps with ordinary cement mixture &
mixing with synthetic polyester flore,
triangular in shape having specific
gravity of 1.34 to 1.40, cross section
size ranging from 10 to 40 micron &
length upto 6mm, mixing fibre @125
grams per 50 kg of cement in cement
mortar, including providing and mixing
water proofing material in mortar @1kg
per 50 kg of cement , all complete as
per direction of Engineer-in-charge.
9.8 Deduct for not grouting the joints with 3030 sqm -10.90 -33027
white cement and matching pigment in
the items of fixing of vitrified tiles.
Sub-Total 10766225
10 ROOFING
10.1 Providing and fixing on wall face
unplasticised Rigid PVC rain water pipes
conforming to IS : 13592 Type A,
including jointing with seal ring
conforming to IS : 5382, leaving 10 mm
gap for thermal expansion, (i) Single
socketed pipes.
Sub-Total 973923
11 FINISHING
11.3.1 New work (two or more coats) over and 9760 sqm 115.30 1125328
including water thinnable priming coat
with cement primer
11.5.1 New work (Two or more coat applied @ 4000 sqm 122.10 488400
1.43 ltr/10 sqm over and including
priming coat of exterior primer applied
@ 2.20kg/10 sqm)
11.6.1 With ready mixed pink or Grey primer of 290 sqm 42.40 12296
approved brand and manufacture on
wood work (hard and soft wood)
11.7.1 Two or more coats on new work 800 sqm 103.50 82800
11.8.1 Two or more coats on new work 1015 sqm 95.70 97136
11.9 Providing and applying white cement 10560 sqm 115.30 1217568
based putty of average thickness 1 mm,
of approved brand and manufacturer,
over the plastered wall surface to
prepare the surface even and smooth
complete.
Sub-Total 3474330
Sub-Total 103796
13 ROAD WORK
13.1 Providing and fixing concertina coil 130 metre 369.10 47983
fencing with punched tape concertina
coil 600 mm dia 10 metre openable
length ( total length 90 m), having 50
nos rounds per 6 metre length, upto 3 m
height of wall with existing angle iron 'Y'
shaped placed 2.4 m or 3.00 m apart
and with 9 horizontal R.B.T. reinforced
barbed wire, stud tied with G.I. staples
and G.I. clips to retain horizontal,
including necessary bolts or G.I. barbed
wire tied to angle iron, all complete as
per direction of Engineer-in-charge, with
reinforced barbed tape(R.B.T.) / Spring
core (2.5mm thick) wire of high tensile
strength of 165 kg/ sq.mm with tape
(0.52 mm thick) and weight 43.478 gm/
metre (cost of M.S. angle, C.C. blocks
shall be paid separately)
13.2 Providing and laying at or near ground 16.65 cum 6808.90 113368
level factory made kerb stone of M-25
grade cement concrete in position to the
required line, level and curvature,
jointed with cement mortar 1:3 (1
cement: 3 coarse sand), including
making joints with or without grooves
(thickness of joints except at sharp
curve shall not to more than 5mm),
including making drainage opening
wherever required complete etc. as per
direction of Engineer-in-charge (length
of finished kerb edging shall be
measured for payment). (Precast C.C.
kerb stone shall be approved by
Engineer-in-charge).
Sub-Total 1988999
14 SANITARY INSTALLATIONS
14.7.1. Centrifugally cast (spun) iron socket & 290 metre 1180.00 342200
1 spigot (S&S) pipe as per IS: 3989
14.7.2. Centrifugally cast (spun) iron socketed 320 metre 1017.40 325568
1 pipe as per IS: 3989
14.9.1.1 Sand cast iron S&S as per IS – 3989 50 Each 495.90 24795
14.9.2 75 mm dia
14.9.2.1 Sand cast iron S&S as per IS – 3989 52 Each 409.50 21294
14.11.1. Sand cast iron S&S as per IS : 3989 50 Each 431.70 21585
1
14.11.2 75 mm dia
14.11.2. Sand cast iron S&S as per IS -3989 56 Each 319.90 17914
1
14.12 Providing and fixing double equal
junction of required degree with access
door, insertion rubber washer 3 mm
thick, bolts and nuts complete :
14.12.1 100x100x100x100 mm
14.12.1. Sand cast iron S&S as per IS - 3989 28 Each 980.90 27465
1
14.12.2 75x75x75x75 mm
14.12.2. Sand cast iron S&S as per IS - 3989 28 Each 767.90 21501
1
14.13 Providing and fixing single equal plain
junction of required degree with access
door, insertion rubber washer 3 mm
thick, bolts and nuts complete.
14.13.1 100x100x100 mm
14.13.1. Sand cast iron S&S as per IS - 3989 21 Each 802.00 16842
1
14.13.2 75x75x75 mm
14.14.1 100 mm
14.14.1. Sand cast iron S&S as per IS - 3989 25 Each 558.60 13965
1
14.14.2 75 mm
14.14.2. Sand cast iron S&S as per IS - 3989 15 Each 476.70 7151
1
14.15 Providing lead caulked joints to sand
cast iron/centrifugally cast (spun) iron
pipes and fittings of diameter :
14.16.1. Sand Cast Iron S&S as per IS: 3989 96 Each 1263.30 121277
1
14.16.2 100 mm inlet and 75 mm outlet
14.16.2. Sand cast iron S&S as per IS - 3989 48 Each 1312.60 63005
1
Sub-Total 1334600
15 WATER SUPPLY
15.1 Providing and fixing Chlorinated
Polyvinyl Chloride (CPVC) pipes, having
thermal stability for hot & cold water
supply, including all CPVC plain & brass
threaded fittings, including fixing the
pipe with clamps at 1.00 m spacing. This
includes jointing of pipes & fittings with
one step CPVC solvent cement and
testing of joints complete as per
direction of Engineer in Charge.
External work
15.3.1 50 mm dia nominal bore 95 metre 513.60 48792
15.4 Fixing water meter and stop cock in G.I. 1 Each 405.60 406
pipe line including cutting and threading
the pipe and making long screws etc.
complete (cost of water meter and stop
cock to be paid separately).
15.7 Providing and placing on terrace (at all 8000 per litre 9.30 74400
floor levels) polyethylene water storage
tank, ISi : 12701 marked, with cover
and suitable locking arrangement and
making necessary holes for inlet, outlet
and overflow pipes but without fittings
and the base support for tank.
Sub-Total 928055
16.3.1. With common burnt clay F.P.S. (non 15 Each 2020.20 30303
1 modular) bricks of class designation 3.5
Sub-Total 233167
17.2.1 With float glass panes of 6.0 mm 570 sqm 1355.40 772578
thickness
17.3.1 With stainless steel cover plate minimum 8 Each 2621.50 20972
1.25 mm thickness
17.5 Providing and fixing 100mm brass locks 16 Each 538.30 8613
(best make of approved quality) for
aluminium doors including necessary
cutting and making good etc. complete.
Sub-Total 1895593
18.4.1 With average thickness of 120 mm and 1816 sqm 1310.20 2379323
minimum thickness at khurra as 65 mm.
Sub-Total 2689914
19.4 Extra for openable side / top hung vision 75 sqm 3937.10 295283
glass panels (IGUs) including providing
and supplying at site all accessories and
hardwares for the openable panels as
specified and of the approved make such
as heavy duty stainless steel friction
hinges, min 4 -point cremone locking
sets with stainless steel plates, handles,
buffers etc. including necessary stainless
steel screws/ fasteners, nuts, bolts,
washers etc. all complete as per the
Architectural drawings, as per the
approved shop drawings, as specified
and as directed by the Engineer- in-
Charge.
Sub-Total 6509988
20.5 Random rubble masonry with old hard 55 cum 3961.90 217905
stone in foundation and plinth including
levelling up with cement concrete 1:6:12
(1 cement : 6 coarse sand : 12 graded
stone aggregate 20 mm nominal size)
upto plinth level with Cement mortar 1:6
(1 cement : 6 coarse sand) ( old hard
stone receveid from dismentling issued
free of cost)
20.8 Providing and fixing Granite stone slab 94 Sqm 2572.50 241815
18 mm thick in shelves, working tables,
plateform and the like on all floors and
all levels making chases in walls
wherever required and making good the
same after fixing by cement mortar 1 : 3
( 1 cement : 3 fine sand ) joint with grey
cement slurry mixed with pigment to
match the colour of the slab
etc.complete as per direction of engineer
incharge including the following
operations and conditions
20.10 Providing and laying machine cut pre- 127 sqm 3202.40 406705
mirror polished granite stone in required
design and patterns, wherever required,
in combination with granite stones of
different colours and shades of any size
as by the engineer incharge in skirtting
risers and step and dadoes over 12mm
thick cement mortar 1:3( 1 Cement :
Course sand) ) including jointing with
grey cement slurry at the rate 3.3 kg/
sqm including pointing in white cement
mixed with pigment of mathing shead
complete ( Single piece to be used in
risers)
20.11 Finishing wall s with exterior acrylic 2800 sq mtr 499.90 1399720
plaster consisting of 1 st coat with
texture plaster @50 kg/10 sq mtr with
minimum 2mm thick. Allow the plaster
to dry for 16 to 18 hrs 2nd coat with
exterior wall primer @50 kg /sq mtr mix
ed with water @1ltre primer with 800 ml
to 1000 ml water. All ow the primer to
dry for 4 hrs. Apply two coat exteria
exterior emulsion paint @2.15 ltr /10 sq
mtr with a gap of 4 to 6 hrs between to
coats including cleaning & washing the
surface complete
20.13 Providing and fixing CP bras bottle trap 69 EACH 1350.25 93167
(with internal partition)32mm size with
300mm and 190mm long wall
connection pipes and wall flange and for
wash basins and sink item code no ALD-
769L of Jaquar or equivalent
20.15 Providing and fixing C.P brass concealed 31 EACH 9592.25 297360
body single lever high flow bath and
shower mixture wall mounted model
with button spout( composite one piece
body) item code no KUB-35137F OF
Jaquar or equivalent.
20.16 Providing and fixing in wall lining using 126 sqm 1212.85 152819
12mm thick Commercial ply IS 303
marke to frame, backing or studing with
screws etc complete( frames. Backing or
studing to be paid seprately)
20.17 Providing and laying 23 cm thick stone 360 Cum 1491.78 537041
soling with boulders by hand packing
with smaller stone filling gaps with stone
dust ramming watering consolidating
with road roller etc complete.
20.18 Providing and fixing white vitreous china 60 Each 30656.65 1839399
wall mounting square rimless water
closet of size 560X370mm INSPIRIA
series, item code no RS346537000 of
Roca or equivalent including slendra
concealed flushing cistern (Item Code
No. RA890031410) with slendra Wall
plate square knob of Roca item code no
RE890195001 & slendra installation
frame Item Code No. RA89008312 of
Roca or equivalent including cutting and
making good the wall etc complete.
20.19 Providing and fixing white vitreous china 21 Each 31131.68 653765
back inlet urinal of size
273/405mmx700 mm of site range item
code no RS35960ROOO of Roca or
equivalent fixed with fitting set, waste
pipe,flexible tube, elbow joint and
connector and concealed urinal sensor
powered by 220 volts-AC item code no
RT5X9215E00 of Roca or equivalant
including cutting and making the wall
good etc complete.
20.21 Providing and fixing white vitreous china 34 Each 18051.36 613746
Oval shaped counter top wash basin of
Roca INSPIRA series item code
no.RS327530000 or Equivalent of Size
500X370MM with 15 mm C.P. brass
aerator pillar cock with 200mm
extension body and base flange of
Jaquar item code no KUB-35021F or
Equivalent 32 mm C.P. brass waste half
threaded with 80mm height item code
no ALD-729of Jaquar or equivalant
including cutting and making holes for
fixtures as directed by the Engineer-in-
charge.
20.22 Providing and fixing 40mm dia PVC rigid 100 mtr 136.40 13640
pipe including clamps for waste line for
wash basin etc all complete as per
direction of engineer incharge
20.25.1.1 Granite stone of any colour and shade 318 sqm 3577.20 1137550
20.27 Providing and fixing C.P. brass bib cock 66 Each 1695.80 111923
with flange item code no. KUB-35037F
OF Jaquar or equivalant 15mm Nominal
bore
20.28 Providing and fixing CP brass anglular 189 Each 1449.00 273861
stop cock with flange item code no. KUB-
35053F Of Jaquar or equivalant with
15mm Nominal bore
20.31 Providing and fixing soap dispenser with 60 Each 1449.55 86973
glass bottle Kubix prime series of Jaquar
item code no AKP-35735P orequivalant
20.33 Providing and laying tactile tile (for 25 sqm 2479.15 61979
vision impaired as per standards) of size
300X300X15mm having with water
absorption less than 0.5% and
confirming to IS 15622 of approved
make and in all colours and shades in for
outdoor floors such as footpath, court
yard,multi modals locationetc laid on
20mm thick cement morter 1:4(1
cement 4 coarse sand)in all shapes and
patterns including grouting the joints
with white cementmixed with with
matching pigmentsetc complete as per
direction of Engineer in charge
20.40 Providing and fixing white vitreous china 1 Each 35385.50 35386
pedestal type water closet (European
type W.C. pan) with all fittings and
fixtures complete, including cutting and
making good the walls and floors
wherever required: Vitreous china close-
coupled WC with vertical outlet (item
code No. RS342237), Dual flush 6/3L
W.C. cistern with bottom inlet (item
code No.RS 341231 and seat and cover
with opening (item code No.RA801230)
of parryware or equivalent
20.45 Providing & applying One coat of Alkaline 200 Sq Mt 99.70 19940
Rust converting primer FEOVERT @ 0.17
Ltr per sqm per Coat of M/s. Krishna
Conchem Product Pvt.Ltd. or equivalent
product of approved manufacture
conforming to ASTM-B-117, to exposed
existing rebars after reoving & cleaning
loose rust by wire brush and leave it for
6-8 hours.
20.46 Providing & applying Two coats of Anti 200 Sq Mt 213.20 42640
Corrosive protective coating IP Net RB
(CBRI/CSIR technology) @ 0.4 ltr per
sqm per sqm for 2 coats of M/s.Krishna
Conchem Product Pvt.Ltd. or equivalent
product of approved manufacture for
reinforcement bars by brush. Sprinkle
dry sand when second coat is tacky so
as to get rough surface.
20.48 Grouting Injecting slow setting very low 2750 Kg 974.20 2679050
viscosity grout EPCO KP HP 250 SSLV by
pressure and using injector with
accessories till nozzles refused to accept
the grout, Including. Mixing of
materials; Mixing material components
part a and part b required quantities as
per mfg insrtruction by weigh batching
Grouting; Fill the grouting gun with
monopol. Maintain desired pressure in
the gun by air compressor maintain the
pressure at exit (3 to 4 kg/Cm2) by
monitoring pressure guage at exit.
Grout the material through prefixed
nozzlewith EPCO 1010 putty after the
refusal. Monitor leakages through other
nozzles while grouting and seal them as
per the requirement.
a)For RCC Columns-2 Units in a single
drilled hole at a spacing of 500mm c/c
from two opposite faces in staggered
fashion.
20.49 Providing & fixing cement concrete 1200 sqm 1030.70 1236840
designer wall tile approved colour &
design on wall upto 10 meter height with
the help of approved adhrsive applying
at the rate of 2.5 kg per sq mt over
existing plastered surface and grouting
the joints etc complete and as per
direction of Engineer- in- charge
20.52 Providing and fixing high grade AISI 130 Each 5769.55 750042
316 225mm(9’’) satin finished stainless
steel mortice latch and lock ( item code
no MLB9S) a pair of handles (item
code no .MH1965S) and round key hole
( item code no. EEP55S) with necessary
screws of Kich or equivalant.
20.55 Providing and fixing satin finished 130 Each 128.45 16699
stainless steel (SS316) door stopper
with necessary screws item code no
DSTRS of Kich or equivalant
20.56 Providing and fixing satin finished CP 25 Each 332.65 8316
brass door eye item code no NEVBS of
Neki or equivalant
Sub-Total
28697389
Executive Engineer
MCD – VI , Central P.W.D.
Mumbai
PART C
(Electrical & Mechanical)
Name of work: Construction of Institute and hostel building (New Institutional complex)
of Family Welfare Training and Research Center (FWTRC), At New Panvel, Navi-Mumbai
including internal water supply, sanitary installation, drainage,development work, Internal
electrical installation,Automatic fire alarm system,Down comer system, SITC of VRF type
Air conditioning, D.G. set, Sub station, pump set, street light,Passenger Lift & Solar water
heating system etc. (BALANCE WORK)
Certified that this Part of the tender Document (Part C of three parts viz. A,
B & C) contains pages from page 164 to 218 pages.
Executive Engineer,
MCD VI ,CPWD, Mumbai 20.
SCHEDULE ‘A’
SCHEDULE 'B'
I The following material shall be issued to the contractor at the store at CGO
Building Belapur.
Sr.No. Description of Material Qty Unit Issue Panel Rate at which recovery
Rate will be made, if the unused
materials not returned by
II Recovery shall be made for using conduit for wiring work which is already laid in
slab.
III The following material shall be issued to the contractor at free of cost at store at
CGO Building Belapur.
SCHEDULE 'C'
Tools and plants to be hired to the contractor
S. No. Description Hire charges per day Place of issue
1 2 3 4
---------------------NIL-------------------
SCHEDULE ‘D’
Extra schedule for specific requirements/document for the work, if any - As per schedule ”A”
SCHEDULE ‘E’
Earnest Money
As specified in Part A
Performance Guarantee
As specified in Part A
Security Deposit
As specified in Part A
SCHEDULE “F”
Definitions:
Clause 1
Maximum allowable extension with late fee @ 0.1% per As specified in Part A
day of Performance Guarantee amount beyond the period
provided in (i) above
Clause 2
Clause 2A
Clause 5
Authority to decide:
Clause 6, 6A
Clause 7
Gross work to be done together with net Rs. 30 lakhs, for electrical work and part
there of as per discretion of Engineer- in-
payment /adjustment of advances for material
Charge
collected, if any, since the last such payment for
being eligible to interim payment
Clause 7A
Clause 10A
List of testing equipment to be provided by the contractor at site lab: As specified in Part A
Clause 10C
1
2
Clause 10CC
Schedule of component of other materials, Labour, POL etc. for price escalation:-
Component of labour expressed as percent of total value of work. ---- As specified in Part A
Component of P.O.L. expressed as percent of total value of work. ---- As specified in Part A
Clause 11
Clause 12
12.2, 12.3
Clause 16
Clause 18
List of mandatory machinery, tools & plants to be deployed by the contractor at site:- As specified in
Part- A
Clause 36 (i)
Experience
Technical Technical / Minimum event of not fulfilling provision of
Number
Representative Representative) clause 36 (i)
Figures in In Words
Rs.
Assistant Engineers retired from Government services that are holding Diploma will be
treated at par with Graduate Engineers.
Clause 42
3. All MCCB’S shall be with (Ics=100% Icu) rating. All MCCBS shall be provided with spreader
links, operating handle with door interlock assembly within tender cost.
4. LED Fittings
4.1 The technical specification of LED fittings are enclosed. All the LED fittings shall be under the
comprehensive warranty of 3 year from OEM from the date of completion of work.
Beam Angle 120 degree minimum lenses for directing light beam
CRI >80
1.1 The system should be able to detect any type of smoke, fire and heat in the respective site
area.
1.2 The detectors shall be Addressable Intelligent optical/ Thermal / multi sensor type as
specified in the BOQ.
1.3 The number of detectors and location shall confirm to relevant standards. Addressable
intelligent optical smoke detectors shall be used in the general office areas / lobby;
Addressable intelligent multi-sensor(optical cum thermal) detectors in the basements areas
and Addressable intelligent heat detectors in the electrical shafts. The detectors shall give
the visual and audible alarm at the control Panel. The panel shall be located in the upper
Basement floor control room
1.4 Addressable Control Modules shall be provided in suitable location for the purpose of
shutting off Fire Dampers/ AC indoor units on detection of smoke within its zone and for
switching-on exhaust / ventilation fans in the event of fire.
1.5 Monitoring modules shall be provided to monitor and address contact-type input devices like
flow switch.
1.6 The fire alarm panel shall operate 240V+ 10% 50Hz. The FDAS shall also be provided
with a dedicated stand by power supply system (battery and charger) capable of
maintaining the system for a period of not ess than 24 hours after failure of ac power
supply after which sufficient battery shall remain to provide full load operation for at least
30 minutes in line with IS 2189.
2.1 An Intelligent Modular/ Expandable Fire Alarm System (IFAS) shall be provided to effect
total control over the life safety services required in the building.
2.2 The system shall be provided with Addressable fire alarm initiating, annunciating and
control devices.
2.3 The addressable and intelligent system shall be such that smoke sensors, thermal sensors,
manual call points, etc., can be identified with point address.
2.4 The FAS shall be able to recognize normal and alarm conditions, below normal sensor
values that reveal trouble condition, and above normal values that indicate either an alarm
condition or the need of maintenance.
2.5 Read-out or address an actual detector location. The operator shall also be able to adjust
alarm and alarm thresholds and other parameters for the smoke sensors.
2.6 Provide a maintenance/pre-alert/fault alarm capability at smoke sensors to prevent
the detectors from indicating a false alarm due to dust, dirt etc
2.7 Provide alarm verification of individual smoke sensors. Systems that perform alarm
verification on a zone basis shall not be acceptable. Alarm verification shall be printable on
the printer to enhance system maintenance and identify possible problem areas.
2.8 Provide local alpha-numeric point address of device and current condition of the point.
2.9 Each detector shall use state-of-the-art Microprocessor Circuitry with error, detector self-
diagnostics and supervision programs.
2.10 The detection of the fire shall be taken at the detector level.
The System Alarm LED on the main fire alarm control panel shall flash.
2.11 Provide outputs that are addressable, i.e. outputs shall have point address. The
operator shall be able to command such points manually or assign the points to Logical
Point Groups (Software Zones) for preprogrammed operation.
2.12 In the event of a fire alarm, but not in a fault condition, the following action shall be
performed automatically
3 FIRE ALARM CONTROL PANEL (FACP) The Fire Alarm control panel shall have the
following features:
3.1 FACP shall have its own microprocessor, software and memory.
3.2 The panel should be modular microprocessor based in nature and shall be expandable from
Single loop to 32 loops.
3.3 FACP shall supervise detection circuits and shall generate an alarm in case of abnormal
conditions.
3.4 FACP shall provide general purpose inputs for monitoring such functions as low battery or AC
power failure. FACP shall provide tamper protection and commendable outputs, which can
operate relays or logic level devices.
3.6 6 It shall be possible for the panel to have a loop length with different modules offering 1
km Loop Length of devices from the panel.
3.7 FACPs shall provide monitoring and control of one floor or area or for multiple floors or areas.
3.8 FACPs shall meet the following requirements to assure the integrity and reliability of the
system.
a. The FACP shall be UL / VdS listed independently as a fire alarm control panel.
b. The FACP should have integrated power distribution module and fixed cabling done
internally to guarantee a clear and tidy cable feed.
c. The panel should have a minimum 600 character display with white background lighting and
keypad. The display should enable a flexible design of the operating menu with variable
keys and message windows.
d. FACP should have menu Based operation.
e. All materials and components used in the panel are specified as per UL / VdS or higher.
f. The panel should have a 230V AC power supply unit in plug-in design with rack and panel
connector and a 24VDC/6A output power supply. The module should be protected against
overvoltage and reverse polarity. The output voltage is monitored and regulated
externally.
g. LCD display at the FACP shall be provided to indicate point in alarm or trouble. In such
systems,means for manually scanning the points in trouble shall be provided and a
trouble and alarm LED shall be used to indicate that there are points in alarm/trouble.
The alarm/trouble LED shall only extinguish when all alarm/troubles are cleared from the
loop.
h. It shall be possible to command test, reset and alarm silence from the FACP. FACP should
have freely configurable detector zone displays.
i. FACP should have a programmable software timer for automatic switching of day
operation mode to night operation mode, switching of mode of operation of automatic
multi-criteria fire Detectors.
j. FACP should have at least 1000 history logs.
3.9 FACP switches shall allow authorized personnel to accomplish the following :
3.13 The display on FACP shall provide indication for AC Power, System Alarm, System
Trouble/Security Alarm, Display Trouble and Signal Silence. This would mean that in the event
of change of any logic, detector / zone sequence alteration, the operator can initiate these by
i. The main power supply shall be 230 VAC±10%, 50 Hz±3% and shall in turn provide all
necessary power of the FACP.
iii. For ease of service, all wiring terminal blocks shall be plug-in type.
b) Maintenance: All detectors shall be fitted either with plug-in system or bayonet type
connections only, from the maintenance and compatibility point of view.
c) Construction: The components of the detectors must not be damaged by static over
voltage
a)) Smoke detectors shall be addressable devices, and shall connect with two wires to one of
The Fire Alarm Control Panel loops. Minimum 250 devices should connect to one loop.
The detectors shall be ceiling mounted type
c) The area covered by each smoke/heat detector shall be as per UL/EN - 54 guidelines.
d) Each detector shall have in built fault isolation unit or the contractor shall provide
one independent fault isolator module for every twenty addressable devices
without any additional cost.
4.3.1 Thermal detectors shall be intelligent and addressable devices, and shall connect with
twoWires to one of the Fire Alarm Control Panel loops.
4.3.2 The detectors shall use an electronic detector to measure thermal conditions caused by a fire
and shall, on command from the control panel, send data to the panel. Each detector shall
have in built fault isolation unit or the contractor shall provide one fault isolator module for
every twenty addressable devices without any additional cost.
4.4 Addressable Manual Stations
a) Addressable manual stations shall be provided to connect to the Fire Alarm Control
Panel loops.
b) The manual stations shall on command from the Control Panel send data to the panel
representing the state of the manual station.
Remote Response Indicator shall be installed outside the areas normally kept closed to
identify the detectors response even if the room is locked. These indicators shall be able to
indicate the status of the corresponding detectors in these areas.
a)The Microprocessor Based Fire Alarm Repeater Panel shall have the following
features.
b) It shall display events as in the main panel.
c) It shall have features for acknowledgement, silence, reset of alarm/trouble.
d) Navigational keys shall be available for scrolling and selecting required menu.
e) It shall have system status LEDs.
f) The repeater panel shall function by drawing its required power from the Main Fire alarm
control panel or it shall have its own separate power supply unit with battery back-up.
a) It shall display the alarm status of the detectors, manual call points
b) It shall check, display and log the health of different components in the
system.
c) It shall be able to generate and print alarm status reports, fault status reports.
d) It shall have facility for alarm acknowledgement, reset and test functions.
e) It shall facilitate the programming of the fire detection and alarm panel and
other components.
f) It shall be possible to program and display different messages of normal, fault
and alarm conditions.
4.11 1)Installation:
a) Installation shall be in accordance with the IS 2189, NEC, NFPA 72, EN 54,local and
state codes, and as recommended by the major equipment manufacturer.
b) All fire detection and alarm system devices, control panels and remote annunciators
shall be flush mounted or surface mounted as per direction given by E-in-C.
c) Manual fire alarm boxes shall be suitable for surface mounting or semi-flush
mounting.
5 The Fire extinguishers of ABC class shall have warrantee from OEM of 5 years
from date of completion of work.
The Scope of this section comprises the supply, erection, testing and commissioning of
Variable Refrigerant Volume Air conditioning unit, conforming to these Specifications and
in accordance with requirements of drawings and of the bill of Quantities.
6.1 GENERAL
a) Outdoors units of the VRF system shall be compact air cooled type.
b) All the compressors of the outdoor units must be hermetically sealed type.
c) The maximum number of units for outdoor units should be limited to 4 Nos. Only so
a) Installation manual
b) Operation Manual
c) Connection Pipes
d) Clamps
1.3.1 These units shall be suitable for wall mount with suitable supports to take care of
operating weight of the unit, without causing any excessive vibration & noise.
1.3.2 The cold air supplied by these units will be supplied to the area to be air conditioned.
1.3.3 Each indoor unit must have electronic expansion valve operated by microprocessor
thermostat based temperature control to deliver cooling/ heating as per the heat load
of the room.
1.3.4 The operating noise level of unit at the highest operating level shall not exceed 45
dB(A), at a distance of 1.5 m Unit must have Thermal Fuse for fan motor protection, in
case of motor heating.
1.3.5 The unit will be connected in series to a suitable outdoor unit & it must be possible
to operate the unit independently, through corded/ cordless remote specified in the bill
of quantities.
1.3.6 The unit should be suitable for further connection to Intelligent Building Management
System / Central Room Controller & it shall be possible to operate the unit through this
IBMS system / Central Controller.
1. Commercial Conditions:
This specification covers manufacture testing as may be necessary before dispatch, delivery
at site all preparatory work, assembly and installation, commissioning putting into operation,
final testing & handing over as reqd.
In addition to supply and/or, installation, testing & commissioning of all the equipment &
materials as per the schedule of work, the following works shall be deemed to be included
within the scope of work to be executed by the contractor, whether or not explicitly indicated
in the schedule work.
i) Minor building works, necessary for installation of equipment viz. making opening in the
walls or in floors & restoring them to their original condition/ finish.
iv) Watch & ward of the equipment & materials, during supply & installation, till their handing
over to the department duly installed & commissioned.
v) All conduits, supports for pipes and anti-vibrations pads etc. as are necessary i/c grouting
them as reqd.
The tenderer shall be deemed to have examined the tender documents, detailed specifications,
data etc, & to have visited the site & ascertained all relevant details for offering suitable
equipment & for installation work.
4. Whenever the items are ready for inspection, the firm shall give due notice period of at least
15 days for enabling the department to depute its representative for inspecting the item before
5. The rates for all items are applicable for all heights of the work to be done as per drawing (or)
as directed by the Engineer-in-charge & no extra on this account will be entertained.
6. It shall be responsibility of the contractor to obtain the approval of drawings & to get the
installation inspected & passed by the concerned agencies, as may be necessary as per local
bylaws. Any fee payable to the local bodies for each activity shall also be borne by the
contractor.
7 All the materials to be used in the work are to be got approved by the Engineer-in –charge
before using in the work.
8. Drawings & Manuals to be furnished by the contractor. offer shall have complete detailed
technical literature, performance data i/c test certificate along with operation, maintenance
manual & spares manuals.
9. The contractor shall submit in duplicate the following drawings within a fortnight of the award of
work for approval by the department.
ii) Details of foundations for the equipment & weight of assembled equipment.
iii) Plumbing layout compete with details of all accessories for all circuits.
v) Electrical layout & schematic & physical arrangement drawings of switch/ control boards i/c size
& capacity of the equipment/ cables used.
10. Before commencement of the installation the above drawings with observations of the
department duly incorporated, shall be submitted to the Engineer-in-charge in triplicate along
with any special instructions with regard to handling, storage & installation well before the
installation.
Copies of all routine & test certificate of the equipment carried at the manufacturer's premises or
otherwise shall be furnished to the purchaser & Consignee.
The contractor shall guarantee the entire installation as per specifications both for components &
for systems as a whole. All equipment shall be guaranteed for one year from the date of
acceptance against unsatisfactory performance or break down due to defective materials, design,
manufacture and / or installation. The work shall be covered by the condition that the whole
installation or any part/ material thereof found defective within one year from the date of taking
over shall be replaced or repaired by the contractor free of charge as decided by the department.
13. Tenderer must visit the site before filling the tender. Total space available must be verified
by the tenderer before quoting rate.
14. Total proposed capacity is 2 nos. of 300 LPD capacity of solar water heating system.
16. Successful bidder shall give two sets of instruction manual to the department without any extra
cost. Instruction manual shall contain the following details:
a) Schematic diagram of the solar collector and a domestic hot water system.
b) Instructions for installation (including mounting details) and use and safety precautions.
c) Instructions for repair and maintenance including causes for common failures, such as, dust
ingress on glass cover, peeling of paint, scaling, damaged sealant, gasket and grommets and
their remedies.
17. The firms shall furnish complete and satisfactory type test certificates for each size/type of solar
flat plate collector as per specification from any MNRE approved govt. laboratory.
3 Collector Specifications
Glazing & Features Frosted glass – Most advanced Solar glass to provide
better performance even in cloudy weather. High
transmitivity, Low iron, texture toughened glass/ Plain
float glass for Safety, high efficiency & ruggedness
ensured.
Riser & Features 99.9% Pure Industrial grade Copper – Dia 12.7 mm –
Pure Copper – Best Quality Assured
Inlet Header & Features 99.9% Pure Industrial grade Copper – Dia 25.4 mm –
Pure Copper – Best Quality Assured
Grommet EPDM
11 Absorber – Riser Bonding Ultrasonic / LASER welding – Maximum heat transfer and
efficiency ensured
12 Anti-fogging natural breather Provided in the collector to prevent fogging inside the
device collector, ensures better efficiency and avoids corrosion
of the absorber plates
14 Flange Sliding Arrestor cum Provided with every collector to ensure no heat loss,
insulator ensures collector weldng joints are safe in transit
15 Ease of maintenance Company Service personnel can open the collectors for
servicing, unlike many sealed collectors in the market
16 Finish (Power coating) Golden Yellow for Frame, Black for Glass Retaining Angle
20 Terminatioin & its features 59mm Dia Brass Flange with 04 Holes of ǿ7mm at PCD
45mm, EPDM gasket & 04 Nos of M6 x 20 SS 304 Bolts.
Pure Brass Flanges are corrosion resistant as against MS
flanges, ensures durability
The contractor shall use any of the makes for use in work as mentioned below after
confirming the approval of Engineer-in-Charge.
1. PVC conduit pipe (ISI mark) & Precision/ Asian/ AKG duly ISI mark
accessories
2. PVC insulated copper wire (FRLS) Finolex/ Havells/ RR Kable / Polycab duly ISI marked
3. Modular Switches & Sockets, Fan Legrand-Myrius / Schneider – Vivace/ MK-
Regulator, RJ-45(cat-6)/including Blenze/Crab Tree-Athena/kolors-Krest/Precision-Blue
modular boxes & plates Era
4. MCBs / RCBO /MCB Siemens/ ABB/ Legrand/ Schneider /L & T
DBs/V.TPN DB, Industrial Sockets,
cable end box and accessories.
5. MCCB’S Siemens/ ABB Legrand/ Schneider Electric / L&T/
6. Piano type Switches, Sockets, Bell Kolors, Ancher, leader, elleys/ Precision
Push ect
7. Batten/ Angle Holderl & Buzzer Any ISI Marked.
8. Cat-6 LAN Cable/ Jack Panel Legrand/Mollex/AMP(Tyco)/Systimax/Panduit/Beldon.
9. Light Fittings Wipro/ Philips/ GE/ TRILUX
10. Panel Meters (Only Digital type) Conserve/AE/L&T
11. Gl Pipes-ISI Mark TATA/Jindal/Zenith duly ISI mark
12. LT XLPE armoured Havells / Finolex / RR Kabel/ RPG / Polycab duly ISI
Aluminum/copper XLPE Cable marked.
13. Telephone cable (FR grade) Finolex/ RR Kable / Delton / Schneider/Polycab Duly
ISI mark
14. 1.1 KV XLPE Cable/ PVC insulated Finolex / Havells / Universal / RR Kabel duly ISI
copper conductor armoured control mark
15. cable
Energy Efficient (5 star) rated Orient/Crompton/Havells
ceiling fans- 1200mm
16. Exhaust fans/ Fresh Air Fans Crompton /Almonard/ Bajaj/Usha/ Khaitan
17. T5 Lamps, /LED Lamps Philips/Osram/Bajaj/Halonix/GE
18. CTs Kappa/AE/L&T/C&S
19. Panel Boards Neptune / Abak / Tricolite / Adlec/BSPL, Bhopal /
Pristine Switch gear / P & I / Advance Panels &
Switch gear
20. Cable gland/ lugs Comet/Jainson/Braco/Dowells
21. Selector switch Kaycee/BCH/ L & T/ Siemens
22. Indicating Lamp Siemens/ L & T/ BCH/ Schneider
23. Connector/ Terminal blocks Elmex/ connectwell/ Essen/ Wago
24. G. I. Pole Bajaj / walmont/ NOVA/SCHIREDER
25. Street Light fittings Havells/ Philips/ Wipro/ Crompton
26. FRP Pole Box Hensel / Sintex
27. DWC Pipe Duraline/ Rex duly ISI mark
49.. Hose coupling / Branch pipe & Omex / Superx / Newage / Getech / Safeguard /
Nozzle Padmini / Fire Guard / Safex / Minimax
50. Reinforced Rubber lined Canvas Omex / Superx / Newage / Getech / Safeguard /
Hose Padmini / Exflame / Fire Guard (ISI Marked)
ABSTRACT OF COST
Name of work: Construction of Institute and hostel building (New Institutional complex)
of Family Welfare Training and Research Center (FWTRC), At New Panvel, Navi-Mumbai
including internal water supply, sanitary installation, drainage,development work, Internal
electrical installation,Automatic fire alarm system,Down comer system,SITC of VRF type Air
conditioning, D.G. set, Sub station, pump set, street light, Passenger Lift & Solar water
heating system etc. (BALANCE WORK)
Sl.
SUB WORKS Total
No.
Sub work :- A
SH: Providing Internal EI,Power outlets and Telephone 6801200
conduits
Sub work:- B
SH:- Providing and installation of automatic fire
alarm system. 1975569
Sub work:-C
SH:- Providing Down comer system 623968
Sub work:-D
SITC of VRF type Air conditioning. 10313182
Sub work:- E
SH:- Supplying, Installation, testing, commissioning of 11 KV substation
equipments. 8887678
Sub work:- F
SH:-SITC of D.G. SET 2593787
Sub work:-G
SH :- Providing Drinking water pump set . 381683
Sub work:-H
SH:- Street light for family walfare, Panvel, Navi Mumbai. 334752
Sub work:-I
SH:- SITC of Passenger Lift 1498500
Sub work:-J
SH:- Solar water heating system 453100
a) 1 or 2 Module (75mmX75mm)
46 Each 175 8050
(For Telephone & bell push)
3877277
Total of Sub-Head II Rs.
Sl.
TOTAL OF SUB WORK A – (Sub Head I+II+III) 6801200
No.
(c) 100 A rating 4 strip tinned Al. sleeved bus bar- 1 set
(f) Indication lamps (RYB) with control HRC fuse with fuse
fitting
a 6.4 mm dia with 13mm thick nitrile rubber insulation 200 Mt 386 77200
b 9.52 mm dia with 13mm thick nitrile rubber insulation 180 Mt 718 129240
c 12.7 mm dia with 13mm thick nitrile rubber insulation 180 Mt 828 149040
d 15.88 mm dia with 13mm thick nitrile rubber insulation 125 Mt 1012 126500
e 19.05 mm dia with 13mm thick nitrile rubber insulation 172 Mt 1242 213624
f 22.2 mm dia with 19mm thick nitrile rubber insulation 150 Mt 1343 201450
g 28.58 mm dia with 19mm thick nitrile rubber insulation 100 Mt 1601 160100
h 34.92 mm dia with 19mm thick nitrile rubber insulation 90 Mt 1877 168930
i 41.1 mm dia with 19mm thick nitrile rubber insulation 80 Mt 2429 194320
2 TRANSFORMER : -
SUB-HEAD II : MV EQUIPMENT
Main Board
1 (L.T. panels)
1) Incomer :
2) Bus couplers:
3) OUTGOING
4) Busbar Ratings
B) Essential Panel
1) Incoming :
a) 400A FP 36KA MCCB MOCROPROCESSOR BASED
RELEASE O/L & S/C PROTECTION WITH SPREADER
LINK, ROHM & MECHANICAL KEY INTERLOCK - 2 Nos
2) OUTGOING
3) Busbar Ratings
2 APFC PANELS
(Sintex / Birla )
f) Providing and fixing HT danger notice plate 250 mm x
200 mm made of mild steel at least 2 mm thick and
vitreous enamelled white on both sides with inscription
in signal red colour at front side as required. 10 Each 163 1630
1) SH-I (EQUIPMENTS)
a) Providing, Installing, Testing and Commissioning of
‘Silent Type’ Diesel Generating set along with having
Prime Power Rating of 200 KVA, 415 volts at 1500 RPM,
0.9 lagging power factor at 415 V suitable for 50 Hz, 3
phase system & for 0.85 Load Factor and consisting of
the followings
b) Diesel Engine: Diesel engine 4 stroke water cooled,
electric start, of suitable BHP at 1500 RPM suitable for
above output of alternator at 40 Degree C, 50% RH & at
1000 Meter MSL and conforming to BS 5514, BS649, IS
10000, capable of taking 10% over loading for one hour
after 12 hours of continuous operation. The engine will
be fitted complete with all the required accessories.
c) Engine mounted Instrument Panel fitted with and having
digital display for following (i) Start-stop switch with
key (ii) Water temperature indication (iii) Lubrication oil
pressure indication (iv) Lubrication oil temperature
indication (v) Battery charging indication (vi) RPM
indication (vii) Over speed indication (viii) Low lub. oil
trip indication (ix) Engine Hours indication
2593787
Total of work -F
9) Pump Panel.
Incoming
381683
Total of work -G
Type of doors :
Car :- Power operated Centre opening horizontal
sliding stainless steel scratch resistant ( honey comb
finish ) doors.
Executive Engineer,
MCD VI ,CPWD, Mumbai 20.