Installation Report Coaxial
Installation Report Coaxial
Installation Report Coaxial
For
Submitted By
1
This Document Contains
2
INSTALLATION REPORT
DATE:
CUSTOMER NAME : Food Corporation of India
ADDRESS : FCI, FSD,KC DEPOT.
Consul
3 UPS-1 KVA without battery COMPLETE
Neowatt
Battery:60min battery
4 Quanta
backup for above 1KVA COMPLETE
Coaxial cable - RG 11
Master
5 Coaxial Copper Cable ISI
flex COMPLETE
mark
3
PVC Pipe - 80 mm PVC Pipe
11 COMPLETE
Heavy ISI Marked
GI Pipe - 50 mm GI pipe
13 COMPLETE
medium ISI Mark
Supply of 12 V Power
Adaptors 4 AMP SMPS,
Input Voltage -90 to 285,
17 Cp Plus COMPLETE
Voltage variation + _ 10%,
over voltage & short circuit
protection
Supply& Installation of L
Shape Angles Iron Bracket
of required specifications
18 with provision of mounting Local COMPLETE
bullet cameras on the gate,
weighbridge and godown
walls
4
8 Channel Video to Fiber
23 Converter TX
COMPLETE
31
Power Distribution Board COMPLETE
27U Rack for manager room
32
for L2, M/C,& PSUs
(600mm*600mm)
VGA / HDMI cable (15mtrs
33
Length) COMPLETE
35
DVR Switcher for Monitor COMPLETE
5
INSTALLATION DETAILS:
Contact Person
6
WORK COMPLETION/ COMMISSIONING REPORT
TIME FIRE
CCTV
ATTENDANCE ALARM
INTRUDER ACCESS
OTHERS
ALARM CONTROL
TYPE OF WORK
INSTALLATION
TESTING
COMMISSIONING
SERVICING MAINTENANCE SUPPLY
OTHERS
SYSTEM IS FUNCTIONING
YES NO
7
TRAINING & HANDOVER CERTIFICATE
THE TRAINING& HANDOVER ON THE ABOVE MENTIONED SYSTEM HAS BEEN CARRIED
OUT ON DATED AS PER YOUR SATISFACTION.
1) MR.
2) MR.
3) MR.
FOR CMS
FOR FCI MANAGER (Depot)
8
PROJECT HANDOVER FORM
Hereby it is certified that the above PROJECT has achieved practical completion of
Installation and Commissioning of CCTV System.
Project Handover has been accepted by the customer as indicated by the signatures below.
9
CUSTOMER SATISFACTION SURVEY:COMMISSIONING
BROADCAST ENGINEERING CONSULTANTS INDIA LIMITED
Your valuable feedback will help us to improve our system and service to serve you better.
A B C D E NA
VERY BELOW NOT
How would you rate? GOOD
GOOD ADEQUATE
AVERAGE
POOR
APPLICABLE
1 Erection/Installation supervision
Thanks for sparing your valuable time. We will surely share your views with our project commissioning team for
improvements.