MS CCTV Se0001 00
MS CCTV Se0001 00
MS CCTV Se0001 00
Townhouses(Package-15)
Project Name:
MUROOJ AL FURJAN (Package 15)
Method Statement Title:
Method statement for Installation of CCTV and ANPR cameras with cabling
METAC PRODUCED/APPROVED
DISTRIBUTION
Page: 1 of 11
Murooj Al furjan Villas &
Townhouses(Package-15)
Index
1. Purpose
2. Scope of Work
3. References
4. Definition
5. Procedure
5.1 Pre-Construction Activity
5.2 Construction activity
5.3 Post Construction Activity
6. Material, Tools & Equipment
7. Personnel Responsibilities
8. Health, Safety & Environment
9. Training
10. Appendix
10.1 Check list
10.2 Inspection Test Plan (ITP)
10.3 Risk Assessment
1.Purpose
The purpose of this method statement is to outline the materials and labour required to
undertake the works during Installation of CCTV and ANPR cameras.
The method statement shall be briefed to all appropriate operatives to ensure that they are
aware of the sequence of activities and any Client/Engineer project specific requirements.
A constant monitoring and supervision duty shall be undertaken by World security to ensure work
activities are carried out in accordance with the method statement. Any irregularities shall be
immediately action.
2.Scope of Work
The Method statement describes the methodology that will be used for during Installation of CCTV
and ANPR cameras in overall project site.
Page: 2 of 11
Murooj Al furjan Villas &
Townhouses(Package-15)
3. References
4. Definition
MS - Method Statement
QMS - Quality Management System
ITP - Inspection and Test Plan
IR - Inspection Request
Client - Nakheel
Consultant - LACASA / Arif & Bintoak
Contractor - METAC
Subcontractor -World security
5. Procedure
• Ensure that the clearance for the area/handhole is received to start the cable installations.
• Ensure that the work area/handhole is ready and safe to start the installation.
Page: 3 of 11
Murooj Al furjan Villas &
Townhouses(Package-15)
• Prior to start the cable installation, refer to the approved shop drawings related to the area of
installation and ensure that required materials are available at site as per approved material
submittals.
• Ensure that proper safety precautions are taken; safety clearance (Permit to Work) is obtained
prior to start the installation works.
• All required storage precautions shall be implemented at site.
• Prior to Commencement of work, areas and access will be inspected to confirm that Site is
safe and ready to commence the work.
• Make sure pull rope is available in the 50mm upvc duct before starting the cable installation.
• Make sure there should be labelling on the cables.
• Cables should not exceed 90m if Cat6A.
• Cat6A cables and fiber cables should pass through 50mm duct from MDF room to respective
IDF’s.
• Power cables can be either buried/run in a 50mm duct from feeder pillar to respective IDF.
• Make sure the ducts are free from damage.
• Ensure the location of the bullet camera is as per an approved shop drawing.
• The Pole mounted fixed bullet camera shall be installed with the base bracket.
• Make 25mm hole on the pole in 3m height for CCTV cable entry.
• Fix the base bracket to the desirable surface by drilling four holes and fastening it with
screws.
• Pass all the Cat6A cables through the 25mm hole on pole and then pass the cable
through rubber bush into the centre hole of base bracket.
• Terminate the RJ45 connector to the cable using a crimping tool. Connect the cable to
the camera.
• Insert screws through the bracket’s screw holes and tighten screws into the
corresponding hole of the adaptor metal.
• Complete Surface Installation.
• Install the bullet camera with 4 screws onto base bracket.
• Give cable and camera identification labels as per approved shop drawings.
• Mark the location to install the dome camera as per approved shop drawing and
prepare the ceiling or ceiling tile mount.
• All the above false ceiling camera cables should have the facility to be accessed for
future maintenance.
• For the CCTV camera which needs to be fixed on the false ceiling, mark with exact
dimension and holes/cutting to be done at site prior to installation.
Page: 4 of 11
Murooj Al furjan Villas &
Townhouses(Package-15)
• Ensure the wall-mounted dome camera location and height are as per approved shop
drawings.
• Using the template provided as an accessory, drill the screw installation hole, and
firmly insert the plastic anchor provided as an accessory to the end.
• Connect and arrange the necessary cables lest that they should be damaged or
twisted while installing the camera.
• Terminate the RJ45 connector to the cable using a crimping tool. Connect the cable to
the camera.
• Install the dome camera on the ceiling and close the camera cover.
• Ensure the location of the ANPR camera is as per the approved shop drawing.
• Mark the approved installation height of the ANPR Camera and the enclosure on the
pole.
• Mark the pole bracket template to drill the wall fixing points and cable entry.
• Terminate /Connect the Cat6A cable and power cable.
• Mount the camera on the Pole with the proper fixing bolt or screws.
• Mount the ANPR enclosure on the wall with the C channel.
• Mark the approved installation height for the installation of wall enclosure, use the
drill to make 4 hole and install the enclosure on the C-channel support if required.
• Upon completion of installation, inspection shall be offered for consultant approvals.
Page: 5 of 11
Murooj Al furjan Villas &
Townhouses(Package-15)
• Complete labelling of all proposed ANPR equipment as per the approved labelling
scheme.
• Loop cutting is made by marking as per site condition from camera location.
• Loop cable will be installed through loop cutting and will be connected to Loop
detector inside enclosure which will be installed in nearby location.
• ANPR will be connected via ANPR server which will be installed inside Rack in
equipment room.
Inspections
Equipment: -
• Toolbox
• Ladders
• Scaffolding items
• Pulling spring
• Cable ties
• Fluke Machine
• OTDR Machine
• Labelling machine
7.Personnel Responsibilities
A full and detailed description of the roles and responsibilities of all World security staff is included
within the Project Quality Plan. For the works as covered by this method statement, the following
personnel have specific duties.
Page: 6 of 11
Murooj Al furjan Villas &
Townhouses(Package-15)
HSE Officers
Specific responsibilities include:
• Assisting in the production of any health, safety and environmental documents.
• Monitoring the implementation of health, safety and environmental requirements.
• Ensure the areas are barricaded, walkaways and permit systems are in place.
Supervisor(s)/ Forman’s
Specific responsibilities include:
• To ensure that all operatives and appropriate subcontractors have been briefed as to the content
of the method statement and the works.
• To adequately control the works as required.
• To ensure the works are undertaken in a safe manner.
• To ensure all operatives are adequately training in their respective works.
• Reporting any un-safe practices on site to the METAC site team.
Page: 7 of 11
Murooj Al furjan Villas &
Townhouses(Package-15)
• Ensuring that materials are inspected when delivered to ensure they comply with the various
specifications.
• Maintaining a record of all QA/QC activities on site.
• Controlling and ensuring all measuring and test equipment on site is properly calibrated.
• Controlling all non-conforming products or workmanship, and implementing the required
preventive actions.
• Ensuring that corrective and preventive actions are taken when required.
• Ensuring that the required testing is undertaken by approved independent laboratories, and that
all test results are reviewed.
• Undertake audits to ensure conformance to agreed Standards, Legislation and project specific
requirements.
• Ensuring that staff are aware of their responsibilities in respect of quality issues.
• Assisting and reporting to the QA/QC Manager as required
Safety: -
• As per the Dubai Municipality Regulation
• All personnel of World security shall be provided with the following safety gears.
▪ Safety helmets.
▪ Industrial protection goggles.
▪ Safety Vest.
▪ Gloves.
▪ Safety shoes.
▪ Company’s identified uniforms
The METAC Project Safety Plan shall be strictly enforced. All works shall be regularly monitored to
ensure full compliance.
Resources – World security shall resource as appropriate the supervision of the works.
Permits – Where required, permits to work will be provided prior to commencement of works.
Permits shall be issued by suitably trained and experienced HSE personnel only.
PPE – All required PPE shall be issued. Constant monitoring and supervision of the works shall
ensure that always the appropriate PPE is worn by affected operatives.
Page: 8 of 11
Murooj Al furjan Villas &
Townhouses(Package-15)
Access and Egress – Routine access and egress will be provided for materials and operatives at
all times; where emergency routes are required, these shall be determined and arranged, and
instructions given prior to commencement of the works.
Supervision – METAC supervision shall ensure that all material deliveries are coordinated, and all
vehicles are parked in a position where they present no additional risk to the general public or people
associated with this project. Where vehicles are offloaded from public areas, the activity shall be
supervised, and a dedicated offloading/storage area shall be provided.
Plant – All plant associated with this activity shall be inspected prior to the works commencing and
at regular periods during the works to ensure that all required certification is current and that the
plant is maintained in a safe and suitably working manner.
Lighting – At all times, appropriate and suitable lighting shall be provided to ensure the works can
be undertaken in a safe and competent manner.
Housekeeping – At all times, METAC supervision shall monitor the works so as to reduce as far as
reasonably practical the storage of rubbish, waste materials and debris at the workface. All waste
materials shall be removed from the workplace to a suitable area.
Risk assessment has been prepared and signed off by METAC Safety Manager
9 Training
METAC shall identify the particular needs for training and/or certification of personnel to ensure that
suitable levels of proficiency are attained and maintained in order to meet the specified requirements
of the project.
METAC shall:
• Determine the necessary competence for personnel performing work affecting its quality.
• Provide training or take other actions as to satisfy those needs.
• Evaluate the effectiveness of action taken.
• Ensure that its personnel are aware of the relevance and importance of their activities and
how they contribute to the achievement of the product.
Prior to these works commencing, a review of the activities shall be undertaken in association with
the operatives undertaking the duties. This will identify where additional training over, and above
existing knowledge or experience is required.
Page: 9 of 11
Murooj Al furjan Villas &
Townhouses(Package-15)
This Method Statement shall be communicated to appropriate personnel connected with the
undertaking of these works. This is essential to the safe and successful completion of the operation.
The method statement shall be signed every time the operatives are briefed.
10. Appendix
Page: 10 of 11
Murooj Al furjan Villas &
Townhouses(Package-15)
Page: 11 of 11
Al furjan Package 15
INSPECTION & TEST PLAN
Prepared by Checked by Approved By Sr
Activity
(QA/QC Dept) (QA/QC Dept) Project Mnager
Hold Point: Stop work until inspected and QA documents approved. Surveillance: Ensure the activity is reviewed to allow work to continue
Witness Point: Inspection Requested - work can continue Review Point: Results to be reviewed by a 2nd party.
SHOP DRAWING APPROVAL FOR CCTV and ANPR. ONCE SHOP DRAWINGS SUBMITTAL HOLD HOLD
Method Statement approval of Installation of CCTV and ANPR camera system ALL AREAS INSPECTION REQUEST HOLD SURVEILLANCE
INSPECTION FOR INSTALLATION OF CCTV AND ANPR CAMERA ALL AREAS INSPECTION REQUEST HOLD SURVEILLANCE
JOB CARD FOR COMPLETION OF WORK ALL AREAS METHOD STATEMENT SURVEILLANCE REVIEW
This work has been undertaken and completed in accordance with this ITP and all associated reference documents.
Page 1 of 1
Alfurjan Villas & Townhouses-Package 15
CHECK SHEET
Installation of Cables for CCTV camera , ANPR system & Cable testing
Checksheet: WS-CS-CCTV-0001
Check the equipment are clean and without any physical damage.
Check the Installation of Cameras and ANPR Camera, as per approved drawing.
Check the readiness of the security control room/Equipment room before installation of head end
devices
Check the provisions for the Indoor/outdoor cameras are ready for the installation.
Ensure the installation of CCTV camera is as per the approved location and design.
Ensure CAT-6 A Cable terminated and tested prior to install the camera
Ensure the correct conduit and backbox size are installed as per the approved typical installation
detail.
Page 1 of 1 419
Ref. No. GEN-WS-HSE-FOR-012
Date: 25-11-2023
RISK ASSESSMENT
MAINACTIVITY: Installation of CCTV camera,ANPR with cabling RA No
AL FURJAN PACKAGE 15
LOCATION: Landscape area, Control room PROJECT: DATE: 25/11/2023
EQUIPMENT TO BE USED SUBSTANCES TO BE USED REVISION STATUS
• Technician Tools Box. REVISED DATE
• Mobile Ladder /Scaffold / Measuring tape
Step Ladders if required. Scaffolding materials,
• Wiring spring.
Ladder
• Screwdriver sets. First Issue
Cat6A and Fiber cables 00
Wire Stripers/cutter
Fluke tester and OTDR
tester equipment’s
POTENTIAL HAZARDS / CONDITIONS CONSIDERED (TICK BOX) PERSONS AT RISK (TICK BOX)
☒WORKING FROM HEIGHT ☒ ELECTRICITY ☒ HAND TOOLS ☒MATERIAL ☒CONFINED SPACE ☒EXCAVATION/BACK FILLING ☒EMPLOYEES ☐PUBLIC
HANDLING
☒FALLING MATERIALS ☒ MANUAL HANDLING ☒PEDESTRIAN ☒NOISE & VIBRATION ☒ HAZARDOUS SUBSTANCES
☒FATIGUE ☒SUBCONTRACTORS ☐VISITORS
☒MACHINERY/EQUIPMENT ☒ SLIPS / TRIPPING ☒ SITE VEHICLE ☐ HEAT EXHAUSTION ☒ENVIRONMENTAL
☒SECURITY (Use Environmental Impact-
☒FIRE RISK ☒ACCESS/EGRESS ☒MATERIAL STORAGE Severity Rating Section for these
☒ADVERSE WEATHER ☐STAKE HOLDERS ☐OTHERS
☐ LIFTING HAZARDS)
OPERATION
MANDATORY HSE REQUIREMENTS (TICK BOX)
☒ ADEQUATE ☒WORK PERMIT
☒SAFETY INDUCTION ☒PROPER TOOLS / EQUIPMENT ☒SUPERVISION
VENTILATION
☒TOOLBOX TALK ☒TASK-SPECIFIC PPE ☒BARRICADES, WARNING SIGNS IN THE AFFECTED AREA
☒DUST CONTROL ☒TASK LIGHTING
Date: 25-11-2023
Demonstrated
Potential Residual Risk
Risk H / M / H/M/
ALARP
L With no Existing Barrier or L
Cause Consequences controls in with controls
Job Step Hazard Controls Recommended Controls
Sequence of place in place
# Possible causes The harm which Action By
working The potential to cause Describe all existing Describe additional controls that
that will could possibly
activities harm. Health, Injury, barriers /controls for are required
potentially occur
Property damage, each hazard Yes\
release a hazard S P PR S P RR
environment etc. No
1. Fatality, partial or Personnel 3 2 6 • All workers must be • Proper coordination and PE/SE/ 3 1 3 YES
permanent injury, Head adequately HSE necessary permission shall be Sup
disability inducted with proper obtained with concerned prior
Injury, fracture,
Eye injury, Hand TBT and awareness. to bring the vehicle inside the
Vehicle incidents due to Injury • Ensure all vehicles have site.
vehicle forward/ Reverse Major/Minor access pass for entering Restrict the trailer/heavy vehicle
movements. the site. movement inside the project site
injury near duty start / finish times,
Ensure separate way for
vehicles /equipment’s and breaks, restrooms, and main exits,
pedestrians. particularly when the flow of
workers on foot is at a peak (such
as at the end of a shift or during
breaks).
Access to
Personnel • Designated materials • Work area to be kept clear of
Worksite and
injury, Head storage area and non-essential tools &
Work Area
Injury, fracture, pedestrian access. equipment.
, Hand Injury • Sufficient light on traffic • Access to be clear from any
Major/Minor ways and sign boards. obstruction.
injury • Ensure PPE (safety shoes,
Slip, Trip & Fall Minor injury, cut/ helmet, jacket, safety glasses, PE/SE/
2 2 4 2 1 2 YES
bruises. gloves etc.) worn for the Sup
workplace.
• Ensure the method of statement
& risk assessment briefing to all
workers.
Ensure competent supervision and
competent operatives are in place.
Personnel • Ensure Pre – task briefing. YES
Personal injuries, injury, Head • Vehicle must be • All vehicle/heavy equipment shall
Delivery of Falling of objects. PE/SE/
2. damage to Injury, fracture, 3 2 6 registered and driver be fitted with reverse alarm. 3 1 3
materials. Sup
property Eye injury, Hand license to be ensured. • Follow vehicle routes and speed
Injury limits.
Date: 25-11-2023
Date: 25-11-2023
Eye injury, Hand as well job task specific • All sharp object must be covered
Injury training. or eliminate before starting the
Major/Minor Permit to work must be in work.
place • Where the size, surface texture
injury
or nature of a load makes it
difficult to grasp consideration
should be given to the handles.
• TBT must be conducted with
proper manual handling
briefings.
Use EN standard hand gloves.
Personnel • Ensure proper material stacking YES
injury, Head necessary support and make sure
Injury, fracture, • Ensured job-oriented no any heavy material stored
Fall hazards due to Minor injuries, training to workforce and over shoulder level.
Eye injury, Hand PE/SE/
improper material cut, abrasion, mandatory HSE induction All Workers assigned for this task
Injury 3 2 6 must be safety inducted also they Sup 2 1 2
stacking minor or major for entire crew.
Major/Minor will have to attend specific
injuries • Permit to work should be
injury. training which will include the
in place.
standard operating procedures,
types of potential or actual
hazards peasant.
• All Workers assigned for this task YES
must be safety inducted also they
will have to attend specific
Storage of
training which will include the
material, lifting,
standard operating procedures,
shifting
3. Personnel types of potential or actual
(Manually and
mechanically) injury, hazards peasant.
Back pain, • Ensured job-oriented • All work crew assigned for task
Sprain, training to workforce and must be trained with manual
Improper work poster fracture, Hand mandatory HSE induction handling and competent.
Strain, sprain to PE/SE/
during manual handling muscles Injury
3 2 6
for entire crew. • In case mechanical handling Sup
2 1 2
Date: 25-11-2023
Date: 25-11-2023
Date: 25-11-2023
Date: 25-11-2023
Date: 25-11-2023
Date: 25-11-2023