Method Statement For Structured Cabling System & Accessories Installation
Method Statement For Structured Cabling System & Accessories Installation
Method Statement For Structured Cabling System & Accessories Installation
REVISION RECORD
This cover page is a record of all revisions of the document identified above by number and title. All previous cover pages are
hereby superseded and are to be destroyed.
CONTENTS
1.0 PURPOSE
2.0 SCOPE
3.0 REFERENCES
4.0 DEFINITIONS
5.0 RESPONSIBILITIES
6.0 EQUIPMENT
7.0 PROCEDURE
8.0 ATTACHMENTS
Project Name
TITLE Ref. No. :
Method Statement For REV. No. 0
Date :
Structured Cabling System & Accessories Installation
Page 4 of 32
1.0 PURPOSE
This procedures defines the methods to be adapted for the installation structural cabling system solution.
This documents ensures the work to be conducted at site are compliance with approved architecture
diagram and material submittal.A work method statement is prepared for each task on a particular
worksite; the group of work method statements are then packaged and included in the overall
Construction Safety Plan. This method statement deal with Structural Cabling system solution, SCS will
be implemented to support data, voice, and video services under a common physical infrastructure.
2.0 SCOPE
This document details the SCS Installation procedures, for Implementation proposed to Petrolleum
instiute research Centre. The document details solution on installation related activities that will be
carried out during the project as per the solution proposal.
3.0 REFERENCE
4.0 DEFINITIONS:
FP : Face Plate
D/V : Data & voice
MDF : Main distributing Frame
IDF : Intermediate Distribution Frame
CCTV : Close Circuit Television
BOQ : Bill Of Quantity
ELV : Extra Low Voltage
P.P. : Patch Panel
SCS : Structural Cabling system
5.0 RESPONSIBILITIES:
Responsibilities for ensuring that the steps in this procedure shall be carried out are specified at relevant
steps in the procedure:
- Project Manager.
- Construction manager
- QA/QC Engineer
- Site Engineer
- HSE officer
- SK
- Project Manager is the overall responsible for the project in terms of work execution, safety, planning &
quality. The Project Manager will maintain the planning progress and coordination of works with the
main contractor.
- The work progress shall be carried out as per planned program and all the equipment’s required to
execute the works shall be available and in good condition as per project planned.
- Specific attention is paid to all safety measures and quality control in coordination with Safety
Engineer and QA/QC Engineer and in line with PSP and PQP.
- The method of statement to the system shall be implemented according to the Consultant project
specifications and approved shop drawings.
- Provision of all necessary information and distribution of responsibilities to his Construction team.
- The work progress shall be monitored in accordance with the planned work program and he will
provide reports to his superiors.
- The constant coordination with the Safety Engineer to ensure that the works are carried out in safe
Project Name
TITLE Ref. No. :
Method Statement For REV. No. 0
Date :
Structured Cabling System & Accessories Installation
Page 6 of 32
working atmosphere.
- The constant coordination with the QA/QC Engineer for any works to be carried out and initiate for
the Inspection for the finished works.
- He will ensure the implementation of any request that might be raised by the Consultant.
- Efficient daily progress shall be obtained for all the equipment and manpower.
- He will engage in the work and check the same against the daily report received from the Foremen.
- The passage of all the revised information to the Foremen and ensure that it’s being carried out
properly.
- The monitoring of executions of works at site and should be as per the approved shop drawings and
project specifications.
- Ensure WIRs and MIRs are being raised for activities in timely manner and inspected by the
Consultant.
- Check and insure that all activities / work done / completed prior to offer for consultant inspection.
- He will follow and carried out all the relevant tests as per project specifications.
- Obtain the required clearance prior to Consultant’s inspections.
- Should acquire any necessary civil works clearances and coordination.
- Coordinate with site construction team.
- One who will assist the Consultant Engineer / Inspector during inspection?
- The carrying-out of work and the proper distribution of all the available resources in coordination
with the Site Engineer on a daily basis.
- Daily reports of the works are achieved and coordinated for the future planning with the Site
Engineer.
- Incorporate all the QA/QC and Safety requirements as requested by the concerned Engineer.
- Meeting with any type of unforeseen incident or requirement and reporting the same to the Site
Engineer immediately.
- The implementation of all safety measures in accordance with the HSE plan and that the whole work
force is aware of its proper implementation.
- The implementation of safety measures is adequate to maintain a safe working environment on the
work activity.
- Inspection of all the site activities and training personnel in accident prevention and its proper
reporting to the Construction Manager and the Project Manager.
- The site is maintained in a clean and tidy manner.
- Ensure only trained persons shall operate the power tools.
- Ensure all concerned personals shall use PPE and all other items as required.
- Ensure adequate lighting is provided in the working area at night time.
- Ensure high risk elevated areas are provided are barricade, tape, safety nets and provided with
Project Name
TITLE Ref. No. :
Method Statement For REV. No. 0
Date :
Structured Cabling System & Accessories Installation
Page 7 of 32
ladders.
- Ensure service area/inspection area openings are provided with barricade, tape, and safety nets.
- Ensure safe access to site work at all times.
- Responsible for overall Store operations in making sure to store the material delivery to the site and
keep it in suitable area that will keep the material in safe from rusty and damage.
- One who will acknowledge the receiving of materials at site in coordination with QA/QC and
concerned Engineer.
- Technicians will be on site doing the installation of the SCS as per the BOQ, approved drawings &
Schematic Diagram. After that they will start labeling the system cables and test the system ports.
- The blow table explains the manpower used for the successful completion of the project.
- Project Engineer: One Engineer.
- Supervisor: one-two as per the site requirement.
- Technician: 10 - 20 as per the site requirement.
6.0 EQUIPMENTS
Pulling Spring
Cabling Punching tools
Screw drivers
Hack saw
Jig saw
Wire cutters
Hammer
Crimping tools
Tracers
Fluke testing tools.
Measuring Wheel.
Drilling tools.
Ladders.
Scaffolding (to be provided by the contractor for the High level Area).
Safety requirements tools such as safety shoes, safety helmet, safety glasses, fluorescent
vest, and safety gloves to insure maximum ability of safe work and dust mask when
Project Name
TITLE Ref. No. :
Method Statement For REV. No. 0
Date :
Structured Cabling System & Accessories Installation
Page 8 of 32
required.
7.0 PROCEDURE
- Persons engaged with Installation have to be skilled and have received proper and adequate training
on safety and should be maintained in safe condition and the installation methods not to create
danger either for the operator or for other persons or livestock.
- Necessary PPE to be worn while working in energized to be worn while working in energized
circuits.
- Ensure adequate lighting is provided in the working area at night time and if inside the building area
to be well illuminated.
- Ensure service area/work area openings are provided with barricade, tape, safety nets and warning
signage to be provided.
- Ensure LOTO procedure to be followed and implement comprehensive logout & tag out during
execution of work.
- Emergency evacuation plan and procedure to be developed prior to start of testing.
- PTW to be applied and obtained to start work on the required area.
- Calibrated Instruments only to be used.
- In order to ensure safe conditions during Installation the following points must be taken to account.
- A safe work environment is much more likely when each worker makes ensuring workplace safety a
part of the job. Do not depend only on the efforts of others to ensure job safety.
- When working, try to consider the possible effects of every action. This is especially important for
actions which could have consequences in remote locations (for example, turning power on or off or
activating distant machinery).
- All telephony installation technicians should be capable of providing:
- First aid is the emergency aid or treatment given before medical services can be obtained. Training in
first aid prepares individuals to act properly and help save lives in the event of an emergency.
- CPR is the emergency procedure used on a person who is not breathing and whose heart has stopped
beating (cardiac arrest).
- When there is an emergency there is no time to ask questions or learn from mistakes. There is only
one chance to make the correct choice to save a life. An untrained rescuer will often become a victim
of the situation that caused the emergency. For example, if a rescuer attempts to assist an
unconscious victim who is lying across an energized electrical circuit, the rescuer can become part of
the circuit and a victim.
- Training in emergency rescue and first aid are often combined into one comprehensive course.
Project Name
TITLE Ref. No. :
Method Statement For REV. No. 0
Date :
Structured Cabling System & Accessories Installation
Page 9 of 32
- There are few basic steps to safely assist others without endangering yourself:
- Survey the scene—check for fire, toxic fumes, heavy vehicle traffic, live electrical wires, a ladder, or
swift-moving water. If the victim is conscious, ask questions to get information.
- Notify someone—it is imperative to let someone know that you need help and where you are. If you
attempt a rescue alone and become overwhelmed from smoke, electrocution, or unseen gases, you
will need help.
- Communication is an important part of any safety program. Attend and pay close attention to all
safety meetings and safety equipment training. Ask questions. On the job, Telephony installers must
communicate freely and clearly with everyone affected by their work and those whose work may
affect them.
On receipt of the material and accessories at site, necessary precautions shall be taken for unloading,
shifting and storage, as follows:
A. Overview
- Pulling cable for telecommunications installations inside of buildings requires using many
techniques. Some cables are very large and heavy, disguising the fact that the pairs inside the cable
are actually very fragile. Be prepared to learn the correct way to handle the cable so that the
installation will meet specifications.
- Setting up, or getting ready, is the proper way to ensure a smooth job of pulling cable. These pre-
cable pulling tasks are essential:
The work area must be secured (cleared of pedestrian traffic) for safe conditions to exist for
everyone.
Equipment for supporting the cable reels must be in place.
Equipment for pulling the cable must be available.
Equipment for temporarily holding the cable in place must be available.
Correct lengths of cable must be on hand.
Project Name
TITLE Ref. No. :
Method Statement For REV. No. 0
Date :
Structured Cabling System & Accessories Installation
Page 10 of 32
Before the pull begins, locations for accessing and pulling the cable should be identified.
Adequate manpower must be available.
Equipment allowing cabling installers to communicate must be on hand.
Set up cones, signs, barricades, and/or caution tape in work areas to alert everyone of danger in the
area.
Place caution tape across the entrance to the area to restrict access to anyone other than cabling
installers or other authorized personnel.
Notify appropriate personnel that work is beginning.
For large cable reels, set up a jack stand or reel dolly. A reel dolly is basically a jack stand with
wheels that allows easy relocation of the assembly.
Find out if the cable reel being installed is so large and heavy that a jack stand or reel dolly is
required.
Many contractors use jack stands for holding the reels of cable off the floor. Sometimes this
equipment is made from homemade supports and a pipe is used to appropriately suspend the reel.
Select a location that is large enough for the number of spools needed.
Set up the jacks stand inside the telecommunications closet if there is room for it or set it up in the
area just outside the closet.
Place a pipe or crossbar (known as a mandrel) through the center hole in the reel. Get help from
co-workers to lift the spool onto the jack stand. Jack stands used for placing larger cables usually
have a mechanical ratcheting or hydraulic lift mechanism to assist in lifting the reels into place for
pulling.
Project Name
TITLE Ref. No. :
Method Statement For REV. No. 0
Date :
Structured Cabling System & Accessories Installation
Page 11 of 32
Make sure the mandrel can support the weight of the cable reel(s).
In some pulling operations, reel brakes may be needed to control the pay out of the cable.
Cable trees are used when there are multiple small spools of cable being pulled at the same time.
Select the spools of cable that will be needed for the job. Cable can be ordered with various put up
lengths. Usually put ups are 305 m (1000 ft), 457 m (1500 ft), and 1524 m (5000 ft).
Select a location near the cable feed point that is large enough for the cable tree.
Bring in the cable tree and set it up inside the closet if there is room, or in an area outside the
telecommunications closet, such as in the hallway.
Mount the spools on the cable tree.
Find the end of each cable reel and bring them together, through the guide hole on the pay-out end
of the cable tree.
Select one of the cables in the group as a guide cable.
Take the next two cables and tape them to the guide cable approximately 76 mm (3 in) behind the
guide cable. Continue attaching cable to the bundle in groups of two until all cables are attached to
the bundle.
Prepare the guide cable for attachment to the pull string.
Even smaller amounts of cable, set up a cable pay-out pack.
Knock a hole in the top of the pack or remove the plastic insert to expose the cable inside.
Cable is shipped in several different containers:
– Pay-out-pack
– Reel-in-a-box
– Spool
The pay-out packs and the reel-in-a-box are convenient and require no rack to hold them. For
pulling multiple strands of cable, the packs can be stacked and numbered sequentially for proper
labeling later.
Find the end of the cable and thread it out through the hole in the top of the pack.
Keep the wire free from any obstruction that would crimp or bend it, causing damage.
Set up pull string or pull rope. If no pull string or pull rope exists, and it is required in the conduit
system, one must be installed.
Determine the distance of the complete cable run. Ensure the distance does not exceed 90 m (295
ft). Take care to identify the changes in direction, vertically or horizontally. These changes in
direction may cause the run to exceed the 90 m (295 ft) limit.
Take note of the number and locations of bends and identify where to feed the cable around sharp
bends or turns. Pulley hangers may be used at some points to save manpower.
Allow no more than two 90-degree bends per 30 m (98 ft) cable pull.
Divide the total cable run distance into segments where each segment is less than the maximum of
30 m (98 ft), including end measurements.
Project Name
TITLE Ref. No. :
Method Statement For REV. No. 0
Date :
Structured Cabling System & Accessories Installation
Page 12 of 32
Identify a pull point, where necessary, for accessing and handling the cable.
Where possible, minimize the number of pull points, since each pull point requires an additional
person, a pulley, or a separate pull.
A. Overview
- Horizontal cable is installed between the telecommunications closet and the work area outlets for
workstations. It supports many different kinds of information for its users:
Voice communications
Data communications
Other building information systems (such as CATV, IPCCTV)
- Pulling horizontal cabling is one of the most important jobs of a successful installation. Because the
cable seems bulky and well protected, some cabling installers incorrectly believe that it is almost
indestructible. Cable must never be bent or kinked excessively.
- Conduit installations are usually designed to be parallel or perpendicular to the external walls of the
building. No one conduit segment will be more than 30 m (98 ft) in length and no more than two 90-
degree bends are allowed in one segment. Exceeding these limits increases the coefficient of friction
and can possibly stretch the cable and damage it.
- A pull string is a thin cord used to pull cable through the conduit. The pull string must extend
through the entire length of the conduit before cable can be pulled.
- This can be done by a manual method using fishtape or by pressurized air methods using a foam rat
or a foam ball attached to a pull string. Fishtape passes through the conduit to reach the pull string
attached to the cable at the far end. Some fishtapes have swivel-type clips on the end for attaching to
objects that need to be pulled back through the conduit. Fishtape is used to pull the string through the
conduit, not for pulling the actual cable. Some pull string is designed to break if excessive tension is
placed on the cable.
- Horizontal cabling in conduit may require the use of a lubricant. This is necessary only for high-pair-
count cable. Many products are available for lubricating the cable as it enters the conduit to assure a
smooth pull.
- Always label cables and their reels prior to pulling cable into place. It is easier to identify and label
the cables before they are pulled through the conduit.
- The building plans or blueprints are the record of what is in the building. After the installation is
complete, the building owner has the as-built plans to refer to for future work. It is a lasting record of
cable information that documents the placing of cables.
Estimate length of run by walking off the distance or using a measuring wheel.
Find the area on the floor that is just below the location in the ceiling where the conduit run is
located.
Walk the distance of the cable run, noting where the conduit bends and pull boxes are.
Estimate the distance walked and allow for all changes in elevation. (e.g., include the distance
from conduits to floors or ceilings).
Project Name
TITLE Ref. No. :
Method Statement For REV. No. 0
Date :
Structured Cabling System & Accessories Installation
Page 13 of 32
NOTE: A common general practice is to count ceiling tiles of known lengths, such as 0.6 m (2 ft) by 0.6
m (2 ft) lay-in or 0.6 m (2 ft) by 0.6 m (2 ft) decorator tile.
Ensure each cable dispenser has enough cable to reach the full length of the run.
Place an identification label on each cable end.
Label each cable dispenser and cable a few feet back from the cable’s bitter end. Do not put the
label too close to the end or the tape will cover the label.
Determine the length of fishtape required. After estimating the length of the run, add a few feet to
each end to be sure enough fishtape is available.
Feed fish tape through conduit.
Put on all necessary personal safety equipment.
Feed the fishtape into the end of the nearest conduit.
Do not force the fishtape if the conduit contains existing cables.
If there is a metallic tab on the end of the fishtape, cover it with electrical tape to prevent snagging
other cable already in the conduit.
Never feed a fishtape into a conduit without knowing where it may go. It could accidentally be fed
into a live electrical junction box.
Push the fishtape through the conduit until it comes out the far end of the conduit.
Attach pull string to fishtape.
Go to the far end of the conduit where the end of the fishtape is now located.
The end of the fishtape will have a hook, a ring, or some type of attachment device.
Attach the end of the fishtape to the pull string to be pulled through the conduit securely to prevent
it from coming off during the pulling operation.
If the clip at the end of the tape has been removed, secure the attachment by wrapping a piece of
electrical tape around the pull string and the fishtape.
Pull the fishtape out of the conduit.
Go back to the other end of the conduit.
Slowly rewind the fishtape reel to retrieve the pull string from the far end of the conduit, storing
the fishtape in the holder as it is taken up.
Detach the fishtape from the pull string.
If there will be a delay prior to cable-pulling efforts, tie off the pull string at both ends. This will
prevent accidentally pulling the string back into the conduit and the need to re-fish the conduit.
Put the fishtape away.
Overcoming pulling problems.
Feed out a few meters (feet) of cable to prepare for entering the conduit.
Arrange the cable(s) to form a smooth transition from a single cable to a larger bundle. Tape
cables as necessary to hold them in place while the pull string
Attach the pull string using a rolling hitch (three half hitches and a clove hitch). Each half-hitch
will bite into the cables and prevent them from slipping. The clove hitch is of little importance as
long as a tight knot is placed around the cables after each half-hitch. Place electrical tape over the
knots to prevent them from slipping or becoming caught during the pull.
Attach a trailer string to the cables to provide a string for future pulls.
As the cable is being pulled through the conduit, keep slack available at the entrance so the cable
Project Name
TITLE Ref. No. :
Method Statement For REV. No. 0
Date :
Structured Cabling System & Accessories Installation
Page 14 of 32
C. Pull cable.
Maintain proper bend radius of four times the diameter of the 4-pair cable.
Monitor pull force closely during installation to be sure that the manufacturer’s specifications are
never exceeded.
Maximum pull force for one 4 pair, 24 AWG cable is 110 N (25 lbf ). Bends and lubricants also
affect performance.
Avoid excessive tension and deforming of the cable when going around corners or bends.
Consider using a 11 kg (25 lb) breakaway swivel attached between the pull rope and the
unshielded twisted-pair (UTP) cable to ensure that no more than 11 kg (25 lb) of tension is exerted
on the pulled cable.
Leave enough slack in the TC to reach the furthest corner and add the distance from floor to
ceiling. This allows service slack to be stored within the closet for any possible mistakes or future
reconfigurations.
Most optical fiber distribution cabinet manufacturers require an additional 3 m (10 ft) of slack
within their cabinets in addition to the service slack described above.
Allow enough slack to ensure a minimum of 0.3 m (1 ft) of slack for copper conductor cables and
1 m (3.3 ft) of slack for optical fiber cables at the work area after termination.
Tie off both ends of the trailer string.
D. Identify cables.
Once the amount of required service slack has been determined, mark the cable prior to cutting it
off the cable dispenser.
The cable label shall be a unique identifier that is clearly visible on each end of the cable after the
pull is complete. If this is a temporary label, ensure that the person who follows can understand it.
A. Overview
- Backbone cable in the vertical riser shaft may be high-pair-count cable, which is extremely heavy, or
high strand count optical fiber cable. Therefore, several considerations must go into deciding the best
method for making this kind of installation. The cable may be placed vertically directly in an open
riser shaft, through cores, sleeves or slots, or within a large conduit.
- The cabling installer must determine the size and type of reel onto which the cable is to be loaded.
These reels may be steel which must be returned to the factory, or wood which is disposable. The
size of the reel is dependent on the size and quantity of the cable. High-pair-count cable can be
loaded onto reels that are up to 2.1 m (7 ft) high and 1.5 m (5 ft) wide.
- Cables should be ordered with a factory-equipped pulling eye. If this is not possible, a substitute can
be installed prior to placing the cable.
- During pulling operations, a reel must be situated in a location that provides enough slack for the top
floor once the placing operations are complete.
- Pulleys may be needed to handle the cable from the reel location to the point where it will be
dropped down to lower floors. These pulleys can be attached to the overhead structure in the building
and provide a pathway for the cable as it is being placed.
- In the closet where the cable will enter the vertical pathway, a bull-wheel will be required to ensure
that the jacket is not damaged as it enters the pathway.
- Situate the bull-wheel so that it will allow the cable to drop vertically into the pathway. Bull-wheels
must be attached to the building structure, thereby preventing any lateral movement. Any lateral
movement will cause the cable to become misaligned with the vertical pathway and will damage the
outer jacket.
- Cabling installers should be located on each floor through which the cable will pass as well as the
floor where it will terminate. They must be equipped with the proper tools to perform critical tasks
during the placing operation. Some of the tools include:
Personal protection equipment such as safety glasses, hardhats, gloves, etc.
Communication equipment such as portable, handheld radios.
Temporary restraining devices for the cable. Cable type and size will determine the necessary
Project Name
TITLE Ref. No. :
Method Statement For REV. No. 0
Date :
Structured Cabling System & Accessories Installation
Page 16 of 32
restraining devices. One of the most common methods of temporarily restraining cable is the use
of a large hemp or manila rope equipped with an eyelet.
- Move cable reels to the upper floor of the vertical feed point.
- Set up the cable pulling area and put reels on a jack stand or reel dolly. Secure the work area.
- Attach a reel brake to the cable reel.
- Install and attach guide rope to cable lead. This pull rope helps to guide the cable as it descends.
A. Overview
- Optical Fiber is one of four types of cable suitable for backbone systems. Optical Fiber cable is more
rugged than generally perceived; however, just as with copper cable, care must be taken when
pulling optical Fiber so as not to exceed the manufacturer’s recommended pulling tension. Most
optical Fiber cable manufacturers provide maximum pulling tension based on cable construction.
- There is an increased use of optical Fiber cable to the desktop as the need for increased bandwidth to
serve imaging and other services develop in the marketplace. Within buildings, the predominant
placement of optical Fiber cable is in the backbone between telecommunications closets.
- Regardless of the application, whether it be backbone or horizontal, optical Fiber cables may be
installed in inner-ducts as an indicator that Fiber cable is present.
- This method of installation also tends to reduce the pulling tension required, especially when
multiple inner-ducts are installed in conduit.
- Plenum and non-plenum rated inner-ducts are available in a variety of colors though usually
purchased with a pull rope preinstalled inside for attaching the Fiber cable to be pulled, they are also
available without pull ropes. The pathway of a Fiber cable must be free of sharp bends and turns.
Normally, inner-ducts are inside conduit, through sleeves, or placed in cable trays. Care should be
taken to ensure that the properly rated inner-duct is being installed.
- As in copper cable installations, communication among co-workers is essential to ensure the pulling
function progresses properly without excessive stress or tension on the cable.
- Complete the pull and route the cable to the closets; identify and document cable information.
Project Name
TITLE Ref. No. :
Method Statement For REV. No. 0
Date :
Structured Cabling System & Accessories Installation
Page 18 of 32
- Ensure that only tested and accepted lengths of optical Fiber cable are installed.
Verify that there is Fiber continuity while the cable is on the reel. In order to do so, the cable must
be ordered with access to both ends of the Fiber on the reel.
Test the optical Fiber cable for continuity. This can be done by shining a light source (such as a
flashlight) into the Fiber cable or using a power meter and light source or optical time domain
reflecto-meter (OTDR). A bare-Fiber adapter or mechanical reusable splice is necessary to connect
either the power meter and light source or OTDR to the un-terminated Fiber on the reel.
In those instances where optical Fiber cable is installed without an inner-duct, care must be taken
to ensure that the run is as straight as possible.
At transitions, be sure that a co-worker is placed at such points to relieve excessive tension during
the pull. This ensures that the optical Fiber cable does not rub against obstructions which can nick
or cut the jacket.
- Pull Fiber.
Feed the optical Fiber cable into the inner-duct. Normally the optical Fiber cable can be pulled by
Project Name
TITLE Ref. No. :
Method Statement For REV. No. 0
Date :
Structured Cabling System & Accessories Installation
Page 19 of 32
hand.
Do not exceed the recommended pull tension or the recommended bend radius of the optical Fiber
cable.
The service loop is used to relieve all tension on the optical Fiber cable and provide slack for
future moves or changes.
Always bring the optical Fiber cable with the inner-duct into a point of termination using the
grommets provided in the optical Fiber cabinet.
The optical cable should be secured to the cabinet, ladder rack, cable tray, or backboard. The
optical Fiber strands should be stored and dressed inside the cabinet.
The optical Fiber cable service loop should be long enough to reach the other side of the wiring
closet in case relocated or additional equipment is encountered in the future and the Fiber must be
relocated within the closet. The service slack stored inside the cabinet should be 3 m (10 ft).
All Fiber cables should be anchored in the termination cabinet by using the aramid yarn of the
cable to act as a strain relief, as stated in the manufacturer’s instructions.
Care should be taken to not overtighten tie wraps around optical Fiber cable when dressing. Keep
them loose enough that they can be turned from side to side using finger pressure.
For instance, the bend radius requirements of some optical Fiber cables are 10 times the cable’s
outside diameter when the cables are at rest and 20 times the cable’s outside diameter while the
cables are under stress. These values may be 15 times and 30 times the cable’s outside diameter
for some cables.
- Identify cables.
Place a unique identification number (from the installation drawings) at each end of the cable
showing the point of origin and destination.
A. Overview
Project Name
TITLE Ref. No. :
Method Statement For REV. No. 0
Date :
Structured Cabling System & Accessories Installation
Page 20 of 32
- Cable termination involves the organizing of cables by destination, forming and dressing cables, and
proper labelling, as well as actually creating a connection with a copper or Fiber conductor.
- Proper cable termination practices are vital for the complete and accurate transfer of both analog and
digital information signals. Insulation Displacement Connection (IDC) termination is the
recommended method of copper termination recognized by ANSI/TIA/EIA-568-B for UTP cable
terminations. This method removes or displaces the conductor’s insulation as it is seated in the
connection. The specific tools designed for making these connections are required. During
termination, the cable is pressed between two edges of a metal clip displacing the insulation and
exposing the copper conductor. The copper conductor is held tightly within the metal clip, ensuring a
solid connection.
- Screw-type terminal faceplates commonly used in voice applications are not recommended by
ANSI/TIA/EIA-568-B for UTP terminations and should not be used.
- Wire wrap is another method of terminating copper conductors. This procedure wraps the bare
conductor around an appropriate terminal post on a terminal block. If done properly, this makes a
good electrical connection that is resistant to corrosion and loosening. Copper wire wrap termination
is usually practiced in a central office or special application locations. It is not found in structured
wiring and will not be covered in this chapter.
- There are several different applications relative to the termination of a cable.
- This Cable Termination Practices will address the following:
Termination blocks
Patch panels
Work area outlets
Optical Fiber
- The following types of cable currently recognized by the ANSI/TIA/EIA-568-B for use in the
premises cabling will be covered:
100 Unshielded twisted-pair copper cable (UTP)
Optical Fiber cable
- Determine method and length of sheath removal. Sheath removal can be performed in three ways:
Ringing tool
- The ringing tool contains a razor blade which is set to a depth that allows the sheath to be slit deep
enough to separate the sheath but not nick the inner pairs. To properly use this tool to the greatest
surety, insert approximately 13 mm to 19 mm (0.5 in to 0.75 in) of the cable into the tool. Turn the
tool and then remove the severed sheath with electrician snips.
Electrician snips
- Using the electrician snips carefully cut into the sheathing to a depth that exposes the rip-cord. Using
the rip-cord, pull down the sheathing until the proper length of sheath is ready to be removed. Then
remove the severed sheath with the electrician snips.
Project Name
TITLE Ref. No. :
Method Statement For REV. No. 0
Date :
Structured Cabling System & Accessories Installation
Page 21 of 32
Slitter tool
- The slitter tool is carefully inserted between the cable sheath and the pairs. Slide the tool carefully
down the sheathing until the proper amount of sheathing has been prepared for removal. Remove the
severed sheath using the electrician snips.
- Using a proper sheath removal tool, remove the cable sheath in accordance with ANSI/TIA/EIA-
568-B standards and the termination equipment manufacturer’s specifications.
Remove only as much of the sheath as is necessary to terminate the cable pairs and ensure that the
twist of the pairs is maintained.
- A common fallacy in the industry is that only 50 to 76 mm (2 to 3 in) of sheath should be removed
from the cable. This requirement can vary depending on the block, type, and size of the cable and
type of IDC termination hardware manufacturer.
- Separate, identify, and tie off binder groups.
Binder groups are associated with 50 pair and larger pair-count cables.
A unique colour code identifies each binder group. Cables are grouped in 25-pair increments with
each 25-pair group (or subgroup) individually wrapped with a fabric or plastic tape to identify the
groupings. See the following color-code chart for clarification.
Dependent upon manufacturer, 25-pair binder groups are combined into identifiable master
groups.
Tie off binder groups to keep them identified until ready to terminate.
NOTE: One helpful hint is to use a copper pair of the same color as the binder group. Twist it snugly,
but not tightly to both the sheath end and the outside end of the unsheathed cable binder group. This
helps to identify binder groups. It also keeps the binder groups together during termination, allowing for
easier housekeeping.
Fan out and form cable pairs from each binder group.
Cable pairs should be uniformly placed so as to be not only aesthetically pleasing, but also, pairs
should not cross or interfere with any other pairs.
Wire pairs should be parallel with no tension at the point of connection, and equal tension on all
connections.
- The 110-style IDC termination hardware is used in both voice and data cabling applications.
Backbone cabling is commonly terminated on wall- or rack mounted 110 termination blocks in
increments of 50, 100, or 300 pairs as well as on a 900-pair wall mount.
- The majority of patch panels are wired in specific configurations (i.e.,T568A, T568B, USOC) and
are mainly constructed with 110-style connectors. In addition, work area outlet terminations are
manufactured with 110-style hardware.
- Cables are routed through the middle pathway of the 110 wiring block from either the top or bottom,
and fanned into the wire way from alternate sides. The block wire way is designed such that one row
is terminated on the wiring block by punching down from the bottom up. The next row is terminated
from the top down. For the specific location of each termination refer to the telecommunications
designer’s layout.
Project Name
TITLE Ref. No. :
Method Statement For REV. No. 0
Date :
Structured Cabling System & Accessories Installation
Page 22 of 32
- It should be noted that the 110-style wiring block contains no IDC. The IDC for this type of
termination application is in the C-3 (3-pair), C-4 (4-pair), and C-5 (5-pair) connector block that is
punched down on top of the 110-wiring block to permit cross connection.
- The connecting block pair count is determined by the application (i.e., 4-pair horizontal cabling is
terminated on a C-4 (4-pair) connecting block; trunk cables in 25-pair increments are terminated on
5-pair connecting blocks).
- The designation strips are then placed in the holder which covers the terminated cables.
- Data and voice patch panels are available from various manufacturers and in many different styles
and wiring configurations.
- Patch panels are available which feature 110, BIX, and LSA connections. Common configurations
are 24-, 48-, and 96-port.
- To properly terminate a 4-pair horizontal cable onto a patch panel, keep sheath removal to the
minimum amount required. Category 5 cable pairs must remain twisted to within 13 mm (0.5 in) of
the point of termination.
- Strain relief of the cables is accomplished by the use of tie wraps or hooks and loop straps installed
on a cable management bar which is installed at the rear of the patch panel.
- Care should be taken prior to actual termination to verify that the work area outlet wiring scheme
(T568A or T568B) matches the patch panel wiring configuration (T568A or T568B), to ensure
proper functioning. Identify patch panel termination locations in the space allocated on the patch
panel. The manner of labeling patch panels will be provided by the telecommunications designer.
- Many different styles of outlets are provided for work areas. Drywall offices can be terminated in
single- or double-gang faceplates with jack inserts ranging from low density single-port to high
density eight-port devices.
- Several manufacturers provide specially designed inserts for modular furniture in multiple jack
configurations. These inserts are designed to fit in a specific model of furniture.
- Termination of work area outlets should be completed by removing the minimum required amount of
the sheath, according to the manufacturer’s specifications. Follow the manufacturer’s specifications
for proper termination techniques, being careful to ensure the 13 mm (0.5 in) maximum amount of
untwisting of the cable pairs to maintain Category 5 compliance. Carefully coil the remaining slack
(minimum of 300 mm [12 in]) into the termination box. Do not kink the cable or exceed the bend
radius of four times the cable diameter.
- It is always advisable to utilize the same manufacturer’s patch panels and work area outlets at a
given job site. This will minimize the possibility of component mismatch, especially when cabling
for ANSI/TIA/EIA-568-B compliance and meeting the TIA/EIA TSB-67 requirements for basic link
performance. Another aspect of component mismatch is the warranty issue for manufacturer
compliant installation practices. Additionally, all patch cords should be obtained from one source
and pre-tested, as well as certified Category 5 by the manufacturer.
Project Name
TITLE Ref. No. :
Method Statement For REV. No. 0
Date :
Structured Cabling System & Accessories Installation
Page 23 of 32
deformed or crushed.
- It is at this stage that the cabling designer’s splice plan must be fully understood and followed, (i.e.,
which Fibers from which cable are to be spliced together). The proper subunits must be routed to the
correct corresponding trays, (i.e., in a through splice, Fibers 1-12 from cable1 are routed to the same
splice tray as Fibers 1-12 from cable 2).
- Continue securing the subunits to the splice trays and dressing the Fibers in the tray, until the entire
cable is stripped and loaded into the splice trays.
- A number of fusion Splicers are available on the market which provides special tools and
procedures. Familiarize yourself with the manufacturer’s instructions prior to beginning the splicing
operation. While most fusion Splicers have some degree of automation, this section on single-Fiber
automatic fusion Splicers is dedicated to Splicers which automatically position the Fibers in the X-
Y-Z axis and also provide automatic splice loss measurements.
- There are basically two distinct types of automatic fusion Splicers: the local injection detection
(LID) method and the profile alignment system (PAS) method.
- While these two distinct methods exist, they follow the same basic procedures and steps which these
are explained below:
- Most automatic fusion Splicers are menu driven and allow for various degrees of automation;
however, these procedures are based on full automation. Most automatic fusion Splicers furnish their
own Fiber cleaver design; however, an alternate cleaver can be used if care is taken in following the
prescribed cleave length.
- Open the fusion splicer and connect it to an approved power source.
- Some Splicers are equipped with either an internal or external battery supply normally capable of
eight hours of operation.
- Turn on the fusion splicer per the manufacturer’s instructions. Most units will go through some sort
of internal diagnostics. Depending on the machine and the power supply, some machines have an
automatic cut-off function to conserve battery power.
- Most machines will have some sort of parameter-setting capability.
- Specifically, choose whether the splicer is to be set up for multimode or single mode operation.
While a number of parameters are available for changing, it is suggested that the cabling installer
initially try splicing with the manufacturer’s default settings.
- Select fully automatic, semi-automatic, or manual operation. It is suggested that fully automatic
should be used unless some special circumstance exists.
- Some fusion Splicers may or may not have different sized V-grooves used for alignment based on
250 μm coated or 900 μm buffered Fibers. Ensure that the proper V-groove is used, based on the
type Fibers being spliced.
- Wipe the filling compound from the Fibers with a lint-free tissue soaked in isopropyl alcohol (99
percent pure).
- If using heat-shrink tubing for mechanical protection of the completed splice, slide the tubing over
one of the two Fibers to be spliced.
- Strip the coating or buffer from the Fiber to the required length, using the cable manufacturer’s
Project Name
TITLE Ref. No. :
Method Statement For REV. No. 0
Date :
Structured Cabling System & Accessories Installation
Page 25 of 32
recommended Fiber stripper. For 250 μm coated Fibers, the most commonly used tool is the Miller
tool. For 900 μm buffered Fiber either the Miller tool or a No-Nik® tool may be required. The
proper strip length is determined by the fusion splicer and the cleaver being used; however, 25 to 50
mm (1 to 2 in) is typically all that is necessary.
- Gently wipe the Fiber with a lint-free tissue soaked in isopropyl alcohol (99 percent pure). This
removes any fragments of dirt remaining on the Fiber. This is an important step because the Fibers
are aligned within the V-grooves of the fusion splicer in relation to the outside dimension of the
stripped Fiber.
- Cleave the Fiber to the prescribed length for the splice, using the cleaving tool. A number of
different cleaving tools could be used for this operation. Follow the manufacturer’s instructions. It is
important that tools remain clean and in proper working order. Observe the manufacturer’s length
recommendations closely, because this ensures that the Fibers have enough travel in the fusion
splicer to select the proper Z-gap and to butt against each other during splicing.
- Discard the broken Fiber stub properly.
- Open the flaps over the electrode and the Fiber-holding V-grooves.
- Grasp the Fiber by the coating next to the bare Fiber; place the Fiber into the fusion splicer. Some
units may mark the V-grooves where the end of the coating or buffer should be placed. Typically, the
end of the Fiber is placed so that it stops between, but not past, the upper and bottom electrodes.
- Close the Fiber holding V-groove flap but not the electrode flap.
- Repeat Steps 7 through 16 for the second Fiber to be spliced.
NOTE: If using heat-shrink tubing for protection, only one tube is needed per Fiber splice, (i.e., it is not
needed on the second Fiber). If the first Fiber was inserted into the left-hand side of the splicer, the
second Fiber is inserted into the right-hand side or vice versa.
8.0 ATTACHMENTS