Material Requirements Planning System
Material Requirements Planning System
Material Requirements Planning System
Day : 0 1 2 3 4 5 6 7 8
X Gross requirements 150
LT=1 Scheduled receipts
Proj. Avail. Balance 20 20 20 20 20 20 20 20 20
Net requirements 130
On - Hand Planned order receipts 130
20 Planner order release 130
A Gross requirements 520
LT = 2 Scheduled receipts
Proj. Avail. Balance 40 40 40 40 40 40 40 40
Net requirements 480
On - Hand Planned order receipts 480
40 Planner order release 480
B Gross requirements 520
LT = 2 Scheduled receipts
Proj. Avail. Balance 10 10 10 10 10 10 10 10
Net requirements 510
On - Hand Planned order receipts 510
10 Planner order release 510
C Gross requirements 4800
LT = 3 Scheduled receipts
Proj. Avail. Balance 60 60 60 60 60 60
Net requirements 4740
On - Hand Planned order receipts 4740
60 Planner order release 4740
D 2400
Gross requirements
LT = 4 2040
Scheduled receipts
20 20 20 20 20 20
Proj. Avail. Balance
20 20 20 20 20 0
2380
Net requirements
2040
2380
Planned order receipts
2040
On - Hand 2380
Planner order release
20 2040
Gross requirements 4080
E Scheduled receipts
LT = 5 Proj. Avail. Balance 10 10 10 10 10 10
Net requirements 4070
On - Hand Planned order receipts 4070
10 Planner order release 4070
F Gross requirements 1020
LT = 3 Scheduled receipts
Proj. Avail. Balance 0 0 0 0 0 0
Net requirements 1020
On - Hand Planned order receipts 1020
0 Planner order release 1020