Wong Shyang Jian
Wong Shyang Jian
Wong Shyang Jian
Date : _____________________________________
Date : _____________________________________
JUNE 2015
DECLARATION
“I admit that this report is the result of my own but summarizes and quotes that for
everything I have explained the source.”
Signature :…………………………………
Name :…………………………………
Date :…………………………………
ACKNOWLEDGEMENT
I would like to thank the following people for their role in making this study possible:
IR. BUDIONO HARDJONO, my supervisor, for being there from the first to finish,
providing me with valuable guidance and advice. I am especially grateful to him for
correct me to the right path.
DR. YUSRI BIN ARSHAD, my panel, for her valuable comments and suggestions
and for accepting the way I work with grace and patience.
My course mate, for their moral support and shares the knowledge to make the
whole study more effective.
At last, are my family members who support of my studies. Without the stability and
security provided by them, this study would not have been possible.
DEDICATION
This thesis is dedicated to my father, Wong Kah Chan and my mother Chong Sok
Choo, who taught me the value of education and who made sacrifices for us, so that I
have the opportunity that finished my research.
ABSTRACT
CONTENTS
DECLARATION ii
ACKNOWLEDGEMENT iii
DEDICATION iv
ABSTRACT v
ABSTRAK vi
CONTENTS vii
LIST OF TABLES x
LIST OF FIGURES xi
CHAPTER 1 INTRODUCTION 1
REFERENCES 49
APPENDIX
x
LIST OF TABLES
LIST OF FIGURES
APPENDICES LIST
APPENDIX TITLE
1.0 Questionnaires
1
CHAPTER 1
INTRODUCTION
Formworks systems are used to hold and stable the construction reinforced concrete
works in place until it completely hardens to form the desired shape. The constructions
formworks can be made up from different materials. One of the most common used
formwork in worldwide is plywood formwork. Plywood is pieces of wood made of three or
more layers of surface joined with chemical glue, and almost always an odd number of plies
are used to provide balancing of construction work. (Nemati, 2007)
IBS is not new in Malaysia construction industry but it is not fully implemented by
the contractors. The current construction formworks trends in Malaysia are still using the
conventional formwork system which is plywood formwork. Most of the housing contractor
dare not to adopt the others materials of formworks such as Steel Formworks and Plastic
Formworks because of the costing. (Muhammad Hassan, 2009)
2
IBS formwork system brings a lot of benefits to the construction industry. Reduction
of site labor and materials, reduce the wastage, cleaner environment, controlled quality,
higher productivity, neater and safer construction site, faster project completion and the last
also the most important advantage which is lower the total construction cost.
According to the industry interview with Project Manager of Oriental Max Group, the
construction site faced many of the problem by using the conventional formwork building
system.
First of all, the installation of the plywood formwork is difficult. The unskilful
foreigner workman might spoil the plywood formworks. Besides, the scale and the
installation method need a lot of manpower. Once the incorrect scale or uneven installation
may causes the leakage of cement.
Safety problem occur as the conventional formwork system need a lot of nails to
install. Nails will cut or injured the manpower while they installing the formwork system.
Workman safety issue unprotect able in using conventional formwork system.
The formwork system occupied highly cost of the total construction cost. The
conventional building formworks materials is cheaper than the IBS formwork materials in
term of per square feet (psf) but the IBS product life period is longer than conventional
system.
Besides that, the timing of preparation of polymer formwork system is faster than the
plywood, it is because by providing formwork measurement to formwork engineer, polymer
formwork will be prepared well when concrete work is ready. Next is the durability of
polymer is longer than the plywood. According to the project manager of Oriental Max
Group of Company, plywood formwork can be reuse up to 4 times only. But polymer
formwork can be reuse up to 150 times. This mean the total cost of the formwork system will
be reduce due to the reuse of polymer formwork system.
This research is focus on the materials of formwork system. Here come the following
research questions.
1. How can the schedule time of the civil project be reduced by using Polymer
Formwork System?
2. How can quality of the civil project execution be improved by using Polymer
Formwork System?
3. How can the cost of the civil project execution be reduced by using Polymer
Formwork System?
4
The research objectives are designed to improve the efficiency and effectiveness in an
organization which using the right Formwork System. Below are the objectives:
1. To identify the reducing time resulted from the use of right Formwork System
in civil project execution.
2. To identify the quality improvement resulted from the use of right
Formwork System in civil project execution.
3. To identify the cost reduction resulted from the use of right Formwork System in
Civil project execution.
This research is focus to the selection of the formwork materials. The conventional
formwork is made up by plywood and the IBS formwork is made up by recyclable materials.
In this research, we will only focus on two materials from IBS which is steel formwork
system and plastic formwork system.
Steel formwork system and plastic formwork system is not new in Malaysia, but not
fully implement. This research will bring an outcome to the most effective and most cost
saving formwork system.
This research is included the price, usage, quality, specification, durability and the
uniqueness. The information will be collected from the interview and questionnaires.
The research is within 2014 and 2015. Therefore, the technology of the formwork
system in before and after the research period is uncounted in this research. In this research,
researcher assume that respondents given the honest answer; assume a good cooperation of
respondents; assumption of research is practical useful for company.
5
The selection of the formwork materials between conventional systems of IBS are the
aimed to an organization. The final result is to select the most cost saving system and higher
performance. This study is benefits to the research and organization in both.
1.6.1 Organisation
In this research, the outcome and result will help the construction industry companies
to have a clear vision to how to select the better performance formwork system. The
construction quality is the key to leads to the said performance. Besides that, organization is
also will get the information on which formwork system is most cost saving. The price per
unit and the formwork durability will help the organization to select the formwork materials.
1.6.2 Researcher
In this research, the researcher will gain a lot of knowledge of the construction
formwork system. Research can be making himself a minor expertise on this research to give
some opinion upon formwork materials. Besides that, research can build a relationship in the
construction industry while doing interview and questionnaires. In future, researcher can be
easily to work in this industry.
1.7 Summary
CHAPTER 2
LITERATURE REVIEW
2.1 Introduction
New formwork system is not only helps to save our forests, but also save labour,
material, time and capital for construction. It also helps improve the quality of the
construction performance and most important, improve company profit by reducing cost.
In construction industry, building construction project normally consists of four major
stages. Survey and setting is the first stage. In this stage, the entire boundary and all the
building pegs are being identified in order to determine the building foundation is same with
the building plan. Secondly, is building structural works. Building structural works involve in
piling work which is depends on soil condition follow by excavations for foundation works.
In Malaysia, most of the buildings are construct by reinforced concrete (RC) structural work.
RC structural work is the backbone of the building which is very important factor that will
influence the building quality. In this stage, the formwork system also plays an important role
in order to commence the building structural works which will be discussed further in this
study.
The final stage is the building external works that involve sewerage system and water
reticulation work and road and drainage work.
7
According to Hadi (2011), Malaysia has approximately 1.9 million foreign workers
spread across sectors such as manufacturing (39%), construction (19%), plantation (14%),
housemaids (12%), and services (10%), with the rest in agriculture. The contributing
countries by rank are: Indonesia (50.9%), Bangladesh (17.4%), Nepal (9.7%), Myanmar
(7.8%), India (6.3%), and the rest from Vietnam. These figures are excluding the illegal
foreign workers.
Malaysia Construction industry employs 1,214,000 or about 10% of our country total
employment 12,116,600. However, around 70% - 80% of construction labours are occupied
by foreigners. Due to the influx of foreign workers, the employers are reluctant to employ
locals since the wages paid to foreign workers are much less as compared to the locals. (DSM,
2011)
The limitation of using conventional construction method are divided into three main
categorize. Quality of the building is usually most concern by developers and end users. Most
of the foreign workers of construction in Malaysia are form from semi-skilled worker and
low-skilled worker. This will bring an impact towards the quality of works directly; safety of
the construction site is also concern by the employer and employee. Workers having high
percentage of being harm by the wastes of the conventional construction method; highly
construction cost of conventional method is also a limitation. Main of construction cost are
come from labours cost and materials cost. Conventional formwork system occupied a high
percentage of the total construction cost.
Formworks systems are used to hold and stable the construction reinforced concrete
works in place until it completely hardens to form the desired shape. The constructions
formworks can be made up from different materials. One of the most common used
formwork in worldwide is plywood formwork. Plywood is pieces of wood made of three or
more layers of surface joined with chemical glue, and almost always an odd number of plies
are used to provide balancing of construction work.
8
Plywood formwork system are the system that used by majority of contractors in
Malaysia. The figure 1.0 below shows the plywood formwork system. It shows the ground
beam formwork system that ready to casting of cement. The Reinforced Cement (RC) Shear
wall formwork system also shows in figure 1.1 as below.
Besides than the plywood formwork system, Steel formwork system is also being
famous in this industrialised building system. Steel formwork system is made up from the
thin pieces of steel. Steel formwork system is also needed back ridge to support the structural
9
shape. Steel formworks are installed with the supportive back ridge while ready to casting
cement. Steel formwork of RC shear wall and RC columns are shows in figure 1.2 and figure
1.3 respectively.
Polymer formwork system is the minority known in Malaysia. This formwork system
is not fully using polymer to implement. Polymer formwork is made up of plastic and the
back ridge can either choose of plywood or steel ridge. Polymer formwork is able to expose
to direct sunlight. Figure below shows the plastic formwork system of shear wall (Figure 1.4)
and columns (Figure 1.5).