Location via proxy:   [ UP ]  
[Report a bug]   [Manage cookies]                

ECC Template

Download as doc, pdf, or txt
Download as doc, pdf, or txt
You are on page 1of 5

CLASSIFICATION

Environmental Clearance Certification

Instructions for Completion


General
This form (AB081) will be used by proponents responsible for conducting projects/activities on Defence land that require an Environmental
Clearance Certificate (ECC).
 An ECC is required where:
- a project/activity is beyond the scope of approved RSO’s, SI’s, SOP’s or other documented systems and associated instructions;
- the project/activity is undertaken on the Defence Estate (eg. construction or maintenance) by external agencies (eg. powerlines operators);
- a project/activity has any likelihood of causing significant environmental impact in the absence of strict controls;
- project/activity is a controlled action under the EPBC Act (the ECC will be issued to ensure the conditions of approval are communicated,
understood and complied with).
 Proponents will take a precautionary approach, and discuss the project/activity with the SEM/REO to determine if an ECC is required.
 The ECC is used to identify project/activity risks and applicable mitigation measures and environmental conditions.
 The ECC records that project/activity risks and mitigations have been identified, and implementing the project/activity in accordance with the ECC is
unlikely to cause significant environmental impacts under the EPBC Act.
- The ECC can be tailored to meet activity requirements in consultation with the SEM/REO.
- ECC’s are modified to enforce conditions and responsibilities in Range Standing Orders or Management Plans for major activities.
 ECC’s will be issued where no extant policies or procedures already exist.
- The Base or Training Area SEM/REO should be consulted as early as possible and can assist with risk identification and the development of
appropriate mitigation measures, so that activity can proceed with minimal restrictions and delays.
- An approved ECC issued by the REO and countersigned (approved) by the SEM provides a record that the environmental impacts of a
Defence action have been identified and has been assessed as not likely to cause significant environmental impacts under the EPBC Act.
Completing the ECC
The ECC will be completed by the Action Authority (i.e. the proponent) in consultation with the SEM/REO to identify all environmental impacts and
mitigation measures for the proposed activity. Upon completion of Sections A and B, the SEM/REO and responsible Defence person will agree on the
mitigation measures and conditions of approval, and sign that only the proposed action described in the certificate is to take place.

Activity
Step 1 - Appoint an Environmental Liaison Officer (ELO)
 The ELO will be responsible for liaison with the SEM/REO and ensuring that the ECC requirements are communicated to all personnel involved
in the project/activity, incident control and post-activity reporting.
Step 2 - Contact the SEM/REO to discuss the proposed activity, and to arrange a meeting if required
 Initial contact with the SEM/REO should be made no later than 10 working days prior to a proposed activity if possible.
 For larger activities, (eg. Major Ex’s, Major Capital Facilities), the SEM/REO should be contacted at the earliest opportunity (eg. Facility concept
planning, Ex planning), and no later than 20 working days prior to the proposed start date.
Step 3 - Section A - Proposed Action
Fill in Section A , including:
 Description of the proposed action:
- Provide information on the location of all activity components, examples are given.
 Mitigation Measures:
- The Action Authority shall insert mitigation measures that will be implemented to manage project/activity risks.
- In some cases the Action Authority will be directed to develop an Environmental Management Plan (EMP) outlining site specific mitigation
measures, responsibility, personnel responsible, timeframes for implementation, monitoring and reporting.
- This section can cross reference an EMP and other standards/procedures where relevant instead of repeating information.
Step 4 - Section B - Clearance
 Email the ECC form with completed Section A to the SEM/REO along with all reference documentation i.e. EMP.
 The SEM/REO will review the proposal and mitigation measures, and specify conditions in the ECC.
 The SEM/REO will then consult with the Defence person responsible for the activity and when both parties are satisfied the SEM/REO will sign
the ECC and return to the Action Authority.
 Project/Activity now provided with environmental approval to proceed.
Step 5 - Section C - Commitment to Comply
 The Action Authority or appointed representative is to review the ECC conditions and sign Section C Commitment to Comply.
 The Project Manager/Contractor must then Email or Fax the fully signed form back to the SEM/REO.
Step 6 - Undertake all activities in accordance with conditions of the ECC.
Step 7 - Section D - Post Activity Report
 Upon completion of the activity, complete the Section D Post Activity Report (PAR) provided with the ECC and submits to the SEM/REO within
10 working days of activity completion.
Note: conditions within the ECC and PAR may require a SEM/REO to be on site when Section D is being completed.
 The SEM/REO or their delegate must counter sign Section D provided the activity is deemed complete and the conditions of the ECC have
been met.
Security Classification

Version No. 1.2


Issue Date February 2015 CLASSIFICATION
Review Date February 2016 Page 1 of 5
CLASSIFICATION

Environmental Clearance Certification

When certificates are rendered on classified equipment or when details of a classified nature are included, the certificate is to be given an appropriate
classification marking.

Version No. 1.2


Issue Date February 2015 CLASSIFICATION
Review Date February 2016 Page 2 of 5
CLASSIFICATION

Environmental Clearance Certification

Section A – Proposed Action (To be completed by Action Authority)

Service, Group or Organisation Unit File Reference (Defence to insert)

Description of the proposed action: (refer to attachments if necessary): eg. Exercise instructions, Project/Activity, description,
Location of all activity components (eg. Grid Refs), Timings, Personnel, Vehicle Details (number by type), and Earthmoving (eg. m 3 of
earth excavated, m2 land cleared) etc…

Title:

Location:

Date/Duration:

Project/Activity:

Contact Officer’s Name Contact Officer’s Phone no. Contact Officer’s email address

Mitigation Measures

Section B – Clearance (To be completed by Defence Senior Environment Manager/Regional Environmental


Officer)

1. The proposal has been assessed and is considered not likely to cause any significant environmental impacts on the
environment, or any matters of national environmental significance, under the EPBC Act. The proposal may proceed
subject to the following conditions:

2. This Certificate applies only to the proposed action as described in Section A and mitigation measures in Section B.
Signature Senior Environmental Manager (SEM) / Printed Name Title or Rank Date
Regional Environmental Officer (REO)

Signature Senior Manager/Commanding Officer Printed Name Title or Rank Date

Version No. 1.2


Issue Date February 2015 CLASSIFICATION
Review Date February 2016 Page 3 of 5
CLASSIFICATION

Environmental Clearance Certification

Section C – Commitment to Comply (To be signed by the Action Authority or Subcontractor following
completion of Section B and before Proposed Action undertaken)

I have read and I understand the conditions and will ensure full compliance.
(To be signed by the Action Authority)
Signature Action Authority Printed Name Title or Rank Appointment Date

or

I have read and I understand the conditions and will ensure full compliance.
(To be signed by the Subcontractor)
Signature Subcontractor Printed Name Title or Rank Appointment Date

Company

Version No. 1.2


Issue Date February 2015 CLASSIFICATION
Review Date February 2016 Page 4 of 5
CLASSIFICATION

Environmental Clearance Certification

Section D - Post Activity Report


(To be completed by Action Authority and submitted to the Senior Environmental Manager (SEM)/Regional Environmental
Officer (REO) within 10 working days following completion of activity and remediation)

1. The proposal requires a post activity report  Yes  No

Service, Group or Organisation Unit File Reference

Mitigation Measures & Conditions (as per Section A & Section B) Check Comment

A post activity report will be required at the completion of this activity.

Record any environmental incidents (unintentional fire, injury/death


of fauna, damage to flora, spills, bogging etc)

2. This confirms that only the proposed action identified in Section A has been undertaken, and that measures identified in
Section A, and conditions in Section B have been implemented according to the claims above. Any lessons learnt or
suggestions for an improved environmental outcome identified during this activity have also been recorded.

Signature Action Authority Printed Name Title or Rank Date

Signature Senior Environmental Manager Printed Name Title or Rank Date


(SEM) / Regional Environmental Officer (REO)

Version No. 1.2


Issue Date February 2015 CLASSIFICATION
Review Date February 2016 Page 5 of 5

You might also like