01-6 QCS 2014
01-6 QCS 2014
01-6 QCS 2014
Page 1
ca
tio
ns
20
14
at
ar
on
st
ru
ct
io
Sp
ec
ifi
6
6.1
6.1.1
6.2
6.2.1
6.2.2
6.3
6.3.1
6.3.2
6.4
6.4.1
6.4.2
6.5
6.5.1
6.5.2
6.6
6.6.1
QCS 2014
Page 2
PROJECT MEETINGS
6.1
GENERAL
6.1.1
Scope
This Part specifies the meetings that will take place before, during and after the construction
of the Works.
6.2
PRE-CONSTRUCTION MEETING
6.2.1
General
A pre-construction meeting shall be held at the Site. The Engineer shall set the date and time
of the meeting and shall notify the Contractor accordingly.
The Owner, the Engineer and the Contractor and their respective representatives shall attend
this meeting.
The Engineer shall provide the agenda a minimum of three (3) working days prior to the
meeting.
6.2.2
Contractual topics of discussion will include, but not necessarily be limited to, the following:
20
ns
ca
tio
ifi
ec
Sp
(b)
Contract sum.
(c)
Starting instructions.
(d)
Commencing date.
(e)
Contract Period.
(f)
on
ct
ru
st
Maintenance period.
Penalties.
ar
Contractors Obligation topics of discussion will include, but not necessarily be limited to, the
following:
at
Q
3
io
(a)
(g)
2
14
(a)
Performance Bond.
(b)
Programme of Works.
(c)
Insurance.
Site related topics of discussion will include, but not necessarily be limited to, the following:
(a)
(b)
(c)
(d)
QCS 2014
Page 3
Traffic diversions.
(f)
(g)
(h)
(i)
(j)
(k)
Progress photographs.
(l)
(m)
Quality assurance.
(n)
Environmental Considerations.
(o)
Site personnel.
(p)
Site inspections.
(q)
(r)
Engineers overtime.
(s)
(t)
Co-ordination.
Sp
ec
ifi
ca
tio
ns
20
14
(e)
Drawing and communication topics of discussion will include, but not necessarily be limited
to, the following:
io
Project correspondence.
(b)
Project Documentation.
(c)
Daily reports.
(d)
Weekly reports.
(e)
Monthly reports.
ru
st
on
Method statements.
(f)
ct
(a)
Progress meetings.
(h)
Material approvals.
(i)
Submittals.
at
ar
(g)
Miscellaneous topics of discussion will include, but not necessarily be limited to, the following:
(a)
(b)
(c)
Variations.
(d)
QCS 2014
Page 4
PROGRESS MEETINGS
6.3.1
General
Progress meetings shall be held once a month. Where possible and practicable, progress
meetings shall be held at the same time, day of the month and location.
The Engineer shall prepare the agenda and submit it to the Contractor a minimum of three
(3) working days prior to the meeting.
Progress Meetings shall be attended by the Engineer and his representatives and the
Contractor and his representatives. Sub-contractors may attend when involved in the matters
to be discussed or resolved but only when requested by the Engineer. In addition to the
attendees named herewith, the meeting shall be attended by representatives of utility owners,
Government departments and authorities and any other regulatory agencies having
jurisdiction over the Project, if required, and such other persons the Engineer may designate.
The time and location of the progress meetings shall be as directed by the Engineer. The
Engineer shall chair the meetings.
The Contractor shall submit the information itemised below to the Engineer at least three (3)
working days prior to each progress meeting:
A list of completed activities.
(b)
(c)
A list of changes to planned starting dates and durations for all outstanding activities.
(d)
(e)
(f)
(g)
st
ru
ct
io
Sp
(a)
If the Contractor requires additional Progress Meetings he shall submit his request in writing
to the Engineer. For any such additional meeting:
on
ec
ifi
ca
tio
ns
20
14
6.3
(b)
The Contractor shall provide the names of all personnel who are required to attend.
(c)
at
ar
(a)
6.3.2
Topics of discussion will include but not necessarily be limited to the following:
(a)
Actual start and finish dates for activities completed during the update period.
(b)
Remaining durations and percentage completion for all activities not completed.
(c)
Logic, activity duration and cost data for Variation Order work that will be
incorporated into the construction schedule.
QCS 2014
(d)
Page 5
Contractors proposed measures to recover lost time and place the Project back on
schedule by increasing manpower, materials and equipment resources and working
extended hours, additional shifts, etc.
PRE-START UP MEETING
6.4.1
General
A pre-start up meeting is required prior to starting up any major plant component, sub-system
or system.
Pre-start up meetings shall be attended by the Engineer and his representatives and the
Contractor and his representatives. If necessary, equipment manufacturers and/or suppliers
shall also attend.
The agenda for the meeting shall be provided by the Engineer a minimum of three (3)
working days prior to the meeting.
6.4.2
Topics for discussion will include but not necessarily be limited to the following:
ec
ifi
ca
tio
ns
20
14
6.4
(b)
(c)
Temporary connections.
(d)
(e)
(f)
ru
ct
io
Sp
(a)
POST-CONSTRUCTION MEETING
6.5.1
General
A post construction meeting shall be held prior to final inspection of the Work.
Post-construction meetings shall be attended by the Engineer, the Contractor and their
respective representatives.
on
ar
The Agenda for the meeting shall be provided by the Engineer a minimum of three (3)
working days prior to the meeting.
at
st
6.5
6.5.2
Topics for discussion will include but not necessarily be limited to the following:
(a)
(b)
(c)
(d)
QCS 2014
Page 6
(e)
(f)
RECORD OF MEETINGS
6.6.1
Minutes of Meeting
A copy of the minutes shall be furnished to the Contractor within four (4) working days.
If the Contractor has any objections to the minutes he shall submit them in writing to the
Engineer not more than two (2) days after they are presented to him. In the absence of any
objection, it shall be understood and agreed that the Contractor accepts the minutes as true
and complete record of the meeting.
ca
tio
ns
20
14
6.6
at
ar
on
st
ru
ct
io
Sp
ec
ifi
END OF PART