Project Management 3
Project Management 3
Project Management 3
Q.1(a)
Solution: -
(A) Blenders = Per hour rate * hours per day*NT* no. of Blenders
Similar for all Activities
cost
Crash per
Number Number Number Total
Preced. Limit Blenders Packers Fillers day
Activity NT CT of of of Cost
Activity (NT- (B) (P) (F) activity
Blenders Packers Fillers Ʃ=B+P+F
CT) wise
=Ʃ/NT
A 4 3 1 3 24000 0 0 24000 6000
B 3 3 0 1 1 6000 0 4800 10800 3600
C A,B 3 2 1 2 1 0 2400 4800 7200 2400
D A 6 4 2 1 2 12000 4800 0 16800 2800
E C,D 5 4 1 1 2 0 2000 16000 18000 3600
F A,B 10 6 4 2 1 1 40000 4000 16000 60000 6000
G E,F 3 2 1 2 0 0 9600 9600 3200
Total 146400
Diagram
By SaceL
Project Management Paper May 2018
Critical Path: - A – D – E – G
The Lowest cost per day on critical Activity is D which is Rs. 2800
Thus
Critical Path: - A – D – E – G
As per the situation the cost for reduction increases the cost by twice the cost per day
Now we cannot crash the Activity D because, even if we have the limit of one more day but crashing doesn’t have effect
on the total duration, so now, crashing the activity which has the lowest cost per day other than D is Activity G
Critical Path: - A – D – E – G
As per the situation the cost for reduction increases the cost by twice the cost per day
By SaceL
Project Management Paper May 2018
Q1 (b)
Given: -
Frist year Sale: - 1700 units, Increase Sale by 85 units per year
Capital: - RS.600000
Loan: - Rs.1200000
(Revenue – Op ex)
(Op exp + 20000)
(EBIT – Interest )
Operating exp
Depreciation
Units * Price
(EBT – TAX )
Tax @35 %
Revenue =
Principal
Interest
EBITDA
Units
Price
Year
EBIT
EAT
EBT
1 1700 600 1020000 178000 240000 144000 170000 842000 672000 528000 184800 343200
2 1785 615 1097775 198000 240000 115200 153000 899775 746775 631575 221051 678724
3 1870 630 1178100 218000 240000 86400 137700 960100 822400 736000 257600 702500
4 1955 645 1260975 238000 240000 57600 123930 1022975 899045 841445 294506 728469
5 2040 660 1346400 258000 240000 28800 111537 1088400 976863 948063 331822 756578
By SaceL
Project Management Paper May 2018
EAT+Depreciation+Interest
DSCR first year = 𝐼𝑛𝑡𝑒𝑟𝑒𝑠𝑡+𝑃𝑟𝑖𝑛𝑐𝑖𝑝𝑎𝑙 𝐴𝑚𝑜𝑢𝑛𝑡
= 1.71
EAT+Depreciation+Interest
DSCR Second year =
𝐼𝑛𝑡𝑒𝑟𝑒𝑠𝑡+𝑃𝑟𝑖𝑛𝑐𝑖𝑝𝑎𝑙 𝐴𝑚𝑜𝑢𝑛𝑡
= 2.67
EBIT
ICR first year = 𝐼𝑛𝑡𝑒𝑟𝑒𝑠𝑡
672000
= 144000
= 4.67
EBIT
ICR Second year = 𝐼𝑛𝑡𝑒𝑟𝑒𝑠𝑡
746775
= 115200
= 6.48
By SaceL
Project Management Paper May 2018
Q.2
after 5 months
completion to
COMPLETION
month) *100
% Scheduled
ACWS (time)
BCWS (time)
ACWP (cost)
BCWP (cost)
(NT/ after 5
PRECEDING
completion
% ACTUAL
NC * % AC
NT * % SC
NT* % SC
ACTIVITY
ACTIVITY
actual
NC
NT
AC
AC
be
CPI = BCWP/ACWP
= 19.2 / 25
= 0.77
SPI = 19.2/16
= 1.200
By SaceL
Project Management Paper May 2018
= 70 + 16.10
= 86.10
= 58 + 11.60
= 69.60
By SaceL
Project Management Paper May 2018
Q.3 (a)
= 55.6 /3
= 18.55
= (36 + 34 + 32)/3
= 34
Q.3 (b)
= 14.82 /5
= 2.96
= 31.94
By SaceL
Project Management Paper May 2018
Q.4
(a)
NPVa = NPV at ra
NPVb = NPV at rb
ra = 10 %
= 224.6 – 200
= 24.6
Rb = 10 %
= 188.2 – 200
= - 11.8
= 16.76 %
By SaceL
Project Management Paper May 2018
(b)
Cumulative
Discounting rate (10%) Discounted
Year Inflow Discounted
= (1-(rate of discounting)^yr. Inflow
Inflow
1 25 0.90 22.5 22.5
2 55 0.81 44.6 67.1
3 155 0.73 113.0 180.0
4 200 0.66 131.2 311.3
Total NPV 311.3
= 3 +0.2
= 3.2 years
(c)
Discounted rate is = 10 %
= 521.6 – 500
= 21.6
By SaceL
Project Management Paper May 2018
Q. 5
E complete building 10 34 22 D 22 16 0
F Insert scales 66 66 66 E 66 0 0
By SaceL
Project Management Paper May 2018
1. Critical Path: - B – C – D – E – F
σ = 10
2. Critical Path: - B – C – D – E – G – H – I
σ = 15.23
As the Deviation which is lower must be considered for the probability 85%
Probability: - 85%
By SaceL
Project Management Paper May 2018
Z = (x - Ϻ) /σ
σ = deviation (lowest) = 10
therefore;
1.04 = (x – 138) / 10
= 148.4
~ 149 days
149 days we can say that there are 85 % chances of completing the project
By SaceL
Project Management Paper May 2018
Q.7
Gantt Chart: -
By SaceL
Project Management Paper May 2018
Suggestion so that the number of men can be kept equal and minimum is as follows;
BEST OF LUCK
GUYS !!!
CRACK IT THIS TIME
Do call if any Query
By SaceL