Duqm Refinery-Temporary Site Facilities
Duqm Refinery-Temporary Site Facilities
Duqm Refinery-Temporary Site Facilities
2 HSE Engineers(4) Wall finish All Spaces Dummy cover to install for extra socket
8 HSE Engineers(4) Painting All Spaces Door frame angle apply paint touch up
9 HSE Engineers(4) Wall finish All Spaces Rectify visible scratch & dent in door.
Aluminum
14 Kitchen All Spaces Cupboard & drawer to clean properly
works
17 Kitchen Wall finish All Spaces Door frame angle apply paint touch up
Page1 of 14
Project no. : JI-2037 Client: Duqm
Refinery
Project Name: Duqm Refinery Project EPC Package 2 – Utilities and Offsites
Contractor:
Location : Client office
Petrofac &
Samsung (JV)
commissioning
Engineers/ heavy lift Incomplete sealant application in wall
31 Wall finish All Spaces
engineer/ panel joint
Architects(5)-1
commissioning
Engineers/ heavy lift
32 Flooring All Spaces Floor area to cleaned properly
engineer/
Architects(5)-1
commissioning
Engineers/ heavy lift Remove all dust & stains on electrical
33 Wall finish All Spaces
engineer/ socket & switches.
Architects(5)-1
commissioning
Engineers/ heavy lift
34 General All Spaces All masking tape to be removed
engineer/
Architects(5)-1
commissioning
Engineers/ heavy lift
35 Door All Spaces Door frame angle apply paint touch up
engineer/
Architects(5)-1
commissioning
Engineers/ heavy lift All unwanted screws hole to fill with
36 Wall finish All Spaces
engineer/ sealent.
Architects(5)-1
commissioning
Engineers/ heavy lift Rectify peeling off paint & sealant in wall
37 Wall finish All Spaces
engineer/ panel
Architects(5)-1
commissioning
Engineers/ heavy lift All window rail track dust has to removed
40 Window All Spaces
engineer/ & clean properly
Architects(5)-2
commissioning
Engineers/ heavy lift All unwanted screws hole to fill with
42 Wall finish All Spaces
engineer/ sealent.
Architects(5)-2
commissioning
Engineers/ heavy lift
43 Painting All Spaces Door frame angle apply paint touch up
engineer/
Architects(5)-2
commissioning
Engineers/ heavy lift In wall panel some dent and dark stain to
44 Wall finish All Spaces
engineer/ rectify
Architects(5)-2
commissioning
Engineers/ heavy lift
45 Flooring All Spaces Floor area to cleaned properly
engineer/
Architects(5)-2
commissioning
Engineers/ heavy lift Remove all dust & stains on electrical
46 Wall finish All Spaces
engineer/ socket & switches.
Architects(5)-2
Page2 of 14
Project no. : JI-2037 Client: Duqm
Refinery
Project Name: Duqm Refinery Project EPC Package 2 – Utilities and Offsites
Contractor:
Location : Client office
Petrofac &
Samsung (JV)
From north
Dispilicne field Window sliding system was not working
52 Window side 3rd
Engineers(22)-1 properly
window
Dispilicne field
55 Painting All Spaces Door frame angle apply paint touch up
Engineers(22)-1
Dispilicne field
57 Flooring All Spaces Floor area to cleaned properly
Engineers(22)-1
Dispilicne field
59 General All Spaces All masking tape to remove
Engineers(22)-1
Page3 of 14
Project no. : JI-2037 Client: Duqm
Refinery
Project Name: Duqm Refinery Project EPC Package 2 – Utilities and Offsites
Contractor:
Location : Client office
Petrofac &
Samsung (JV)
Dispilicne field
67 Painting All Spaces Door frame angle apply paint touch up
Engineers(22)-2
Dispilicne field
68 Flooring All Spaces Floor area to cleaned properly
Engineers(22)-2
Dispilicne field
70 General All Spaces All masking tape to remove
Engineers(22)-2
74 Storage room Painting All Spaces Door frame angle apply paint touch up
Page4 of 14
Project no. : JI-2037 Client: Duqm
Refinery
Project Name: Duqm Refinery Project EPC Package 2 – Utilities and Offsites
Contractor:
Location : Client office
Petrofac &
Samsung (JV)
Operations personnal
83 Flooring All Spaces Floor area to cleaned properly
spare
Operations personnal
85 General All Spaces All masking tape to be removed
spare
Operations personnal
86 Door All Spaces Door frame angle apply paint touch up
spare
Operations personnal
90 Sockets All Spaces Rectify damages socket & trunking
spare
Page5 of 14
Project no. : JI-2037 Client: Duqm
Refinery
Project Name: Duqm Refinery Project EPC Package 2 – Utilities and Offsites
Contractor:
Location : Client office
Petrofac &
Samsung (JV)
96 supervisor-1 Door All Spaces Door frame angle apply paint touch up
104 supervisor-2 Door All Spaces Door frame screw hole to fill with sealant
105 supervisor-2 Wall finish All Spaces Wall panel major dent to rectify
108 supervisor-2 False Ceiling Near AC unit Damage ceiling tile to replace
109 supervisor-2 Window All Spaces Window frame screw hole to fill
Document control
113 Wall finish All Spaces Improper sealant application in wall panel
technicians
Page6 of 14
Project no. : JI-2037 Client: Duqm
Refinery
Project Name: Duqm Refinery Project EPC Package 2 – Utilities and Offsites
Contractor:
Location : Client office
Petrofac &
Samsung (JV)
Document control
115 Flooring All Spaces Floor area to cleaned properly
technicians
Document control
117 General All Spaces All masking tape to be removed
technicians
Engineering(Disciplin
121 Door All Spaces Install side beading rail(Mitered profile)
e Engineer) (10)-1
Engineering(Disciplin
122 Wall finish All Spaces Incomplete sealent application in joint
e Engineer) (10)-1
Engineering(Disciplin All window rail track dust has to remove
123 Window All Spaces
e Engineer) (10)-1 & clean properly
Engineering(Disciplin
125 Painting All Spaces In wall panel paint touch to done
e Engineer) (10)-1
Engineering(Disciplin
126 Flooring All Spaces Floor area to cleaned properly
e Engineer) (10)-1
Engineering(Disciplin
128 General All Spaces All masking tape to remove
e Engineer) (10)-1
Engineering(Disciplin
130 Wall finish All Spaces Incomplete sealent application in joint
e Engineer) (10)-2
Engineering(Disciplin
134 Flooring All Spaces Floor area to cleaned properly
e Engineer) (10)-2
Engineering(Disciplin
137 Door Shutter Rectify visible dent in door shutter
e Engineer) (10)-2
Changing
138 Sanitary All Spaces Incomplete sanitary item installation
room/Shower male
Page7 of 14
Project no. : JI-2037 Client: Duqm
Refinery
Project Name: Duqm Refinery Project EPC Package 2 – Utilities and Offsites
Contractor:
Location : Client office
Petrofac &
Samsung (JV)
Changing
141 Flooring All Spaces Incomplete flooring work
room/Shower male
Changing
142 Flooring All Spaces Floor drain trap to fix
room/Shower male
Changing
144 Door Shower room Incomplete door installation
room/Shower male
148 Rest Room/ Male Flooring All Spaces Floor drain trap to fix
149 Rest Room/ Male Electrical Bath room Incomplete installation of hand dryer
151 Rest Room/ Male Sanitary All Spaces Clean all the sanitary item
152 Rest Room/ Male Sanitary Wash basin Adjustment is required for drain tape
Aluminum
153 Kitchen All Spaces Cupboard & drawer to clean properly
works
Page8 of 14
Project no. : JI-2037 Client: Duqm
Refinery
Project Name: Duqm Refinery Project EPC Package 2 – Utilities and Offsites
Contractor:
Location : Client office
Petrofac &
Samsung (JV)
160 Kitchen wall finish Outer side wall Rectify major hole at wall panel
161 Conference room-1 Door Front side Door frame panel wide gap to fill
162 Conference room-1 Door All Spaces Install side beading rail(Mitered profile)
163 Conference room-1 Wall finish All Spaces Incomplete sealent application in joint
169 Conference room-1 Flooring Floor box Floor sheet to fix at the top of floor box
179 manager 2 Wall finish All Spaces Dummy cover to install for extra socket
180 manager 2 False ceiling All Spaces Gap around the wall angle to fill
182 manager 3 & 4 Wall finish Truncking Rectify peeling off sealant in wall.
Page9 of 14
Project no. : JI-2037 Client: Duqm
Refinery
Project Name: Duqm Refinery Project EPC Package 2 – Utilities and Offsites
Contractor:
Location : Client office
Petrofac &
Samsung (JV)
183 manager 3 & 4 False ceiling All Spaces Gap around the wall angle to fill
187 manager 5&6 Wall finish All Spaces Dummy cover to install for extra socket
190 manager 5&6 False ceiling All Spaces Gap around the wall angle to fill
191 manager 7,8,9 & 10 Wall finish Truncking Install trunking cover
192 manager 7,8,9 & 10 Wall finish All Spaces Dummy cover to install for extra socket
193 manager 7,8,9 & 10 False ceiling All Spaces Gap around the wall angle to fill
195 manager 7,8,9 & 10 Wall finish Truncking Rectify peeling off sealant in wall.
All unwanted screws hole & gap above
197 manager 7,8,9 & 10 False ceiling All Spaces the A/C uint to fill with sealent/ ceiling
tile/wall angle
Rest Room/ Male & Rectify clash between the installed floor
199 Door All Spaces
female tile and door leaf.
Rest Room/ Male &
200 Flooring All Spaces Floor drain trap to fix
female
Aluminum
205 Kitchen All Spaces Cupboard & drawer to clean properly
works
212 Kitchen False Ceiling All Spaces Install missing ceiling tile
Page10 of 14
Project no. : JI-2037 Client: Duqm
Refinery
Project Name: Duqm Refinery Project EPC Package 2 – Utilities and Offsites
Contractor:
Location : Client office
Petrofac &
Samsung (JV)
218 Conference room-1 False Ceiling All Spaces Install missing ceiling tile
219 Conference room-1 Wall finish All Spaces Incomplete sealent application in joint
221 Conference room-1 Wall finish All Spaces Dummy cover to install for extra socket
Executive Executive
239 Wall finish Chalk line mark to removed
Management 5&6 Management 6
Page11 of 14
Project no. : JI-2037 Client: Duqm
Refinery
Project Name: Duqm Refinery Project EPC Package 2 – Utilities and Offsites
Contractor:
Location : Client office
Petrofac &
Samsung (JV)
249 Conference room-3 False Ceiling All Spaces Ceiling tile to install properly
251 Conference room-3 Wall finish All Spaces Dummy cover to install for extra socket
Dispilicne field
270 Wall finish All Spaces Remove all masking tape & clean the wall
Engineers(22)-3 & 4
274 Comms/IT Room Flooring All Spaces Incomplete flooring & skirting work
275 Comms/IT Room Wall finish All Spaces Dummy cover to install for extra socket
276 Prayer room1 &2 Flooring All Spaces Incomplete carpet flooring
Page12 of 14
Project no. : JI-2037 Client: Duqm
Refinery
Project Name: Duqm Refinery Project EPC Package 2 – Utilities and Offsites
Contractor:
Location : Client office
Petrofac &
Samsung (JV)
279 Cleaner room Wall finish All Spaces Dummy cover to install for extra socket
Changing
280 Sanitary All Spaces Incomplete sanitary item installation
room/Shower male
Changing
282 Flooring All Spaces Incomplete flooring work
room/Shower male
Changing
283 Flooring All Spaces Floor drain trap to fix
room/Shower male
Changing
284 Door Shower room Incomplete door installation
room/Shower male
290 Corridor area False ceiling False ceiling Install missing ceiling tile
292 Corridor area Flooring Flooring Incomplete flooring & skirting work
294 Corridor area False ceiling Exit light Incomplete exit light installation
296 Corridor area Door Corridor area Incomplete exit door installation
306 Flooring General All Spaces Clean all the flooring, door & window
311 External roof General Panel board External roof panel insulation exposed
Page13 of 14
Project no. : JI-2037 Client: Duqm
Refinery
Project Name: Duqm Refinery Project EPC Package 2 – Utilities and Offsites
Contractor:
Location : Client office
Petrofac &
Samsung (JV)
313 External door Door All Spaces External door was rejected by PSJV
Page14 of 14