Introduction:
Planning Strategy ’11’ is one of the most widely used and one of the
important strategy of the MTS strategies. This strategy is also called
as Gross Requirements Planning.
Strategy ‘11’ is particularly useful for make-to-stock scenarios and
the sales orders have no effect in the production with out considering
the plant stock in to consideration . This strategy is particularly useful if
you need to produce the Product, regardless of whether you have stock or
Master Data:
You need to maintain the following master data for the finished product:
Now convert the first planned order to production order and release
Complete Goods Issue, Confirmation and Goods Receipt of the
Order……after the goods receipt of the Production Order stock gets
increased by 100 and First PIR gets consumed….
then save
Creation of sale order for the Product….
Now it can be observed that Sale order does not have any influence on
the planning situation it will be on display only as shown below…
Now Goods delivery against the sale order through VL01N….
Now final situation of the material….
Thanks
Kumar
Alert Moderator
4 Comments
You must be Logged on to comment or reply to a post.
Hi Kumar,
Nicely explained. You can also add where this type of strategy is used. For
Eg:Cement Industries use this type of strategy where they do not consider the
available stock.
Ramagiri
Hi,
Regards
Kumar
Sharma rakesh
Hi Kumar,
Informative and great explanation. This Doc- would be helpful for young
consultants like me .Expecting few more Doc’s in future.
Rakesh
Hi Kumar,
I have a question, will this work the same way for process orders as well ?
Thanks,
Rajan.