Gantt Chart
Gantt Chart
A Gantt chart is a type of bar chart that illustrates a project schedule. This chart lists the tasks to be
performed on the vertical axis and time intervals on the horizontal axis. The width of the horizontal bars
in the graph indicate the duration of the activity.
Gantt chart illustrates the start and finish dates of the terminal elements and summary elements of the
project. Terminal and summary elements constitute the Work Breakdown Structure of the project.
Modern Gantt charts also show the dependency relationships between activities. They can also be used
to show current schedule status using percent-complete shadings and a vertical ‘TODAY’ line.
Gantt charts are usually created initially using an early start time approach, where each task is scheduled
to start immediately when its pre-requisites are complete. This method maximizes the float time
available for all tasks.
1. Using a forward schedule: starting with the list of activities and a given start date; follow
them forwards in time until the given deadline.
2. Using a backward schedule: look at the deadline; from that date work in the logical list of
activities.
Advantages:
Limitations:
1. The Gantt chart doesn’t explain the reasoning behind the chosen duration of each activity.
2. The Gantt chart is very difficult to update when changes to the project plan take place. This
makes it time consuming and results in long term planning being difficult.
3. It encourages a one-step approach to planning- this prevents flexibility in project planning.
4. Modern day Gantt charts using PC software can look very professional without actually having
meaning, preventing project teams from challenging their content. This can lead to difficulties
later in the project.
5. They are difficult to update manually and can often become obsolete.
6. The chart doesn’t compare project resources and cost
Example:
Gantt chart