This document is a proposal for an extension of time on a road construction project from Thummapala to Bojjannakonda. The key details are:
1) The original completion date for the Rs. 281 lakh project was December 27, 2017.
2) As of the agreed date, 14.4% of the work valued at Rs. 4.55 lakh had been completed.
3) The contractor is requesting an extension until March 27, 2019 to complete the remaining Rs. 20.75 crore of work.
This document is a proposal for an extension of time on a road construction project from Thummapala to Bojjannakonda. The key details are:
1) The original completion date for the Rs. 281 lakh project was December 27, 2017.
2) As of the agreed date, 14.4% of the work valued at Rs. 4.55 lakh had been completed.
3) The contractor is requesting an extension until March 27, 2019 to complete the remaining Rs. 20.75 crore of work.
This document is a proposal for an extension of time on a road construction project from Thummapala to Bojjannakonda. The key details are:
1) The original completion date for the Rs. 281 lakh project was December 27, 2017.
2) As of the agreed date, 14.4% of the work valued at Rs. 4.55 lakh had been completed.
3) The contractor is requesting an extension until March 27, 2019 to complete the remaining Rs. 20.75 crore of work.
This document is a proposal for an extension of time on a road construction project from Thummapala to Bojjannakonda. The key details are:
1) The original completion date for the Rs. 281 lakh project was December 27, 2017.
2) As of the agreed date, 14.4% of the work valued at Rs. 4.55 lakh had been completed.
3) The contractor is requesting an extension until March 27, 2019 to complete the remaining Rs. 20.75 crore of work.
contractor 9 Date fixed for completion of work as : 27-12-2017 per Agreement
10 Value of Work done upto agreed date : 4553300 with 14.40 %
(with percentage)
11 Extension of time granted previously : Nil
12 The value of work done during the :
- extended period 13 Value of Work yet to be done : Rs 20757660/-
14 Details of penalties (if any) levied so :
far
15 If no penal action was taken, reason :
for not aking such an action so far
16 The date upto which the extension of : 27/03/2019
time is aplied for by the Contractor. 17 Extension of time upto which it is : necessary in the opinion of the Superintending Engineer / Executive Engineer
18 General Remarks of the :
Superintending Engineer / Executive Engineer 19 General Remarks of the : Superintending Engineer / Executive Engineer