Minor Project
Minor Project
Minor Project
JAMSHEDPUR - 831014
Project Title:
IMPROVEMENT OF OVERALL EQUIPMENT PERFORMANCE
AND COST EFFICIENCY IN A SOFT-DRINK PLANT.
PROJECT OBJECTIVE
[1] To reduce maintenance related costs through implementation of TPM tools, in a
Soft-Drinks Plant.
[2] To use data analytics, lean strategy to increase the Availability function of OEP in
the Soft-Drinks Plant.
[3] Too calculate a stimulated comparison data based on the above amendments.
CASE STUDY
CHARACTERISTICS OF THE PROJECT OBJECT: Soft Drink Bottling Industry
Most soft drinks are made at local bottling and canning companies. Brand name franchise
companies grant licenses to bottlers to mix the soft drinks in strict accordance to their secret
formulas and their required manufacturing procedures.
Soft drink bottling or manufacturing involves five major processes, each with its own issues that
must be evaluated and controlled:
1. Treating water
2. Compounding ingredients
3. Carbonating product
4. Filling product
5. Packaging
Every single fault and unplanned repair order means production inefficiency, reduced number
of produced tones of products and additional costs for company. A schematic data of cost
linked to the repairs has been shown in Table 1:
Cause Cost [rupees/intervention] Cost [rupees/week]
Unplanned repair orders 15k 255k
Planned repair orders 5k 85k
Reported faults 30k 510k
Cost of production stoppage
[rupees/h] 35k
As is evident from the Table2, ‘Availability’ values affect the actual production significantly.
And down time is the major factor determining availability.
It is also important to implement individual responsibility for the machine. That means
that machine or production line will have not only maintenance technician to take care
after them but also every operator have in their responsibilities maintenance of specific
machine.
Skill matrix in place of Demarcation: Company distinguish four levels of skill, every level
have its own color and during every shift, on the or nearby machine there is cuvette
with skill card and picture of operator which works on this shift. According to that when
something is wrong with machine we know to whom we can go.
Those skill cards were created on the base of skill matrix which was designed for every
production line. Trainings are an important part of TPM, so in next step operators are
trained by instructors of TPM. In project we also standardize the trainings of operators.
Operators' skills are developed through the program: "The Academy of Operator". There
were also developed training tools like: training program, skill card and skills matrix.
2) S E M – SPECIALIZED EQUIPMENT MAINTENANCE:
Next large step is to implement SEM. In this part will be distinguished actions which have been
taken to introduce preventive maintenance in TPM project. Firstly were defined tasks for
technicians of AM and PM.
2) P M – PREDICTIVE MAINTENANCE:
Last step is to implement Predictive Maintenance; according to which technicians perform
periodic checks as per the developed instructions of PM. Due to the Preventive Maintenance in
the project, company can optimize expenses on maintenance in the factory by:
o constantly monitor indicators (KPI)
o conduct ongoing analysis of the costs
o monitor the extent of implementation of the budget
o achieve a failure rate of <1.5% through Lean principles
o effectively manage teams
o conduct prudent shopping of parts
o judicious employment of contractors
Figures of level of planning, loading level and types of activities unscheduled in time are on the
every board in every production line, so that employees can see the effects of TPM
implementation. It can be observed from the work time level, loading level and unscheduled
activities decreased. Thanks to that, employees have more time to their work which adds value
to the product.
SIMULATED OUTCOME AND COST BENEFITS:
Defect Analysis
Defect Cumulative percentage of hours lost
Labor issues 44.82
Change over 62.99
No space in godown 72.05
Power failure 82.14
Machinery failure 99.67
Others 100
After conducting a thorough analysis of the reasons for defects/downtime, a simulated data
was obtained presuming the most ideal condition of implementation leading to elimination of
certain reported faults and consequent reduction in downtimes. Accordingly, values for
Availability are also simulated as is presented in the below table:
No. of
week Original Availability Simulated Availability
1 83.84 83.70
2 92.75 93.06
3 88.20 91.11
4 72.73 78.19
5 90.16 91.57
6 87.13 89.05
7 81.14 85.13
8 92.06 93.67
Average 86.01 88.18
80
70
60
50
40 Actual Availability
30
Simulted Availability
20
10
0
1 2 3 4 5 6 7 8
Week
CONCLUSION:
Today, with competition in industry at an all time high, TPM may be the only thing that stands
between success and total failure for companies. It has been proven to be a program that
works. Employees must be educated and convinced that TPM is not just another "Program of
the month" and that management is totally committed to the program and the extended time
frame necessary for full implementation. If everyone involved in a TPM program does his or her
part, an unusually high rate of return compared to resources invested may be expected.
REFERENCES:
[1] S. Nakajima, (1988), Introduction to Total Productive Maintenance, Productivity press,
Cambridge, MA.
[2] Ranteshwar Singh, Ashish M Gohil, Dhaval B Shah & Sanjay Desai, (2005), “Total Productive
Maintenance (TPM) Implementation in a Machine Shop: A Case Study”.
[3] Encyclopedia of Occupational health and safety - International labour office (Chapter 65).
[4] Sorabh Gupta, P.C. Tewari & Avadhesh Kumar Sharma, (2009), “TPM Concept and
Implementation Approach”.