BDM Section 10 - 20190101
BDM Section 10 - 20190101
BDM Section 10 - 20190101
SECTION 10
FOUNDATIONS
All sampling hammers used to complete field explorations for CDOT projects
shall be tested to determine the energy transfer ratio (the measured energy
transferred to the drill rods divided by the theoretical potential energy of the
sampling hammer) in accordance with ASTM D4633. The testing shall be
completed no more than two years before the date of sampling.
The project geotechnical report or the individual boring logs shall indicate
the energy transfer ratio. The energy transfer ratio shall also be reported on
the geology sheet. In addition, the geology sheet shall indicate whether the
reported penetration resistance values are raw values or values that have been
corrected for hammer efficiency.
For establishing spread footing embedment into stream banks based on scour
considerations, see Section 2.11.2 of this BDM.
The requirements of this section do not apply to MSE wall footers. Refer to
current Staff Bridge Worksheets for MSE Walls for MSE wall requirements
Other H-pile sizes may be used when availability is verified with local suppliers
and when any delays due to custom pile orders do not negatively affect the
project schedule.
Although less frequently used in Colorado, other pile types may be feasible and
preferable to H-piles depending on project requirements. For instance, closed-
end pipe piles may be advantageous at sites with relatively deep bedrock,
where a closed-end pipe pile may develop greater axial resistance at shallower
depths compared to a comparable H-pile section. Sheet piles may be used
for foundation support, especially for projects where such use may benefit the
construction schedule or cost.
When using a less common pile type, the Designer shall confirm that the
selected pile section is available from local suppliers.
Where used, the preferred pile batter is 1 horizontal to 6 vertical (1H:6V). The
maximum batter of driven piles shall not exceed 1H:4V due to constructability
considerations.
Piles less than 15 ft. in length and driven to refusal on bedrock shall not be
battered.
10.5.1.3 Embedment
The Designer should consider the potential for piles to encounter refusal on
bedrock or obstructions, such as boulders, before reaching the depth required
for stability under axial and lateral loading. The Designer may specify a minimum
tip elevation on the plans to address this issue. Pre-boring may be used in
cases where refusal is anticipated to occur above the required minimum tip
elevation, although the Designer should consider using other foundation types
that may be preferable in terms of design or constructability.
In general, corrosion of steel piles is greatest in soils that have been disturbed,
that is, where earthwork activities have occurred. Compared to undisturbed
soils, disturbed soils have increased oxygen content, which supports corrosion.
In undisturbed soils, corrosion may occur in the zone of unsaturated soil above
the groundwater table. Corrosion may be exacerbated in the zone of fluctuation
of the groundwater table. Significant corrosion does not generally occur in
undisturbed soil/rock below the groundwater table.
The Designer shall assume that corrosion occurs over all steel surfaces in
contact with the aggressive soil/rock. Corrosion rates greater than the minimum
value specified herein may be appropriate, particularly where piles are installed
in landfill materials, cinder fills, organic soils, or mine waste/drainage. Corrosion
mitigation is not required in soil/rock below the groundwater table.
Sacrificial steel is not necessary where concrete encasement is used for AASHTO C10.7.5
corrosion mitigation. Piles protected by concrete encasement should be coated
with a dielectric coating near the base of the concrete jacket.
For non-weathering steel piles, aggressive conditions shall be assumed for the
first 5 ft. of pile below grade and for the entire portion of the pile exposed to
atmospheric conditions.
In general, it is anticipated that piles driven into the relatively weak sedimentary
bedrock typically encountered along the Front Range would classify as “Soft
Rock,” while piles driven to higher strength bedrock where significant bedrock
penetration is not typically achieved would classify as “Hard Rock.”
Pile protection (tips, points, or shoes) shall be included for all piles driven to
bedrock.
• A pile type, section, or driving procedure not routinely used in local practice
(see Section 10.5.1.1) is proposed.
• A pile with an axial resistance greater than what is typically used in local
practice or which may require the use of a pile driving hammer larger than
typically used in Colorado (nominal resistance greater than approximately
500 kip) is proposed.
• A pile will be driven into a relatively deep bearing layer such that the driving
resistance is likely to exceed the required geotechnical axial resistance
(over-driving).
10.5.3 Top of Pile Fixity
The following simplified method may be used to calculate the minimum pile
embedment required to classify the connection at the top of the pile as fixed.
Where:
Table 10-1 presents the calculated embedments for the most common HP
shapes, based on a φ of 0.7 and f’c of 4.5 ksi.
For specific criteria regarding pile embedment at integral abutments, see BDM
Section 11.
In accordance with AASHTO, higher resistance factors for geotechnical axial AASHTO Table
resistance may be used if dynamic testing is completed during pile installation. 10.5.5.2.3-1
The Designer should note that for bridges with more than 100 piles, the test
frequency required by AASHTO to use a resistance factor of 0.65 is more
stringent than the test frequency required by CDOT Standard Specification 502.
Therefore, if a resistance factor of 0.65 is used for a bridge with more than
100 piles, a Project Special Provision is required to modify the dynamic testing
frequency indicated in the Standard Specification to maintain compliance with
AASHTO.
• Pile size
• Maximum factored axial load per pile
• Maximum service load per pile
• Cutoff elevation
• Estimated bedrock elevation
• Estimated tip elevation
• Scour elevation
• Minimum required tip elevation (see Section 10.5.1.3 for applicability)
• CJP minimum splice elevation (see Section 10.5.4 for applicability)
• A location to record the as-built tip elevation of each pile
When load testing is completed, the entity completing the load test shall prepare
a report sealed by a professional engineer licensed in the State of Colorado
summarizing test results.
10.6.1 General
10.6.1.1 Geometry and Dimensions
Drilled shafts used to support bridges and retaining walls shall have a minimum
diameter of 24 in. Drilled shafts used to support sound walls shall have a
minimum diameter of 18 in. Length to diameter ratios, L/D, are typically less
than 25.
Where a drilled shaft supports a single column, the top of shaft shall be
embedded a minimum of 2 ft. below ground surface, unless the Geotechnical
Engineer recommends deeper embedment.
In contrast to AASHTO, CDOT allows the use of drilled shafts that are smaller in AASHTO
diameter than the columns they support. This allows constructability advantages, 10.8.1.3
such as eliminating the need for separate column dowels embedded into the
caisson.
The resistance factor of 0.75 recommended by Abu-Hejleh et al. (2003) for the AASHTO Table
“soil-like claystone” method shall not be used because this value exceeds typical 10.5.5.2.4-1
resistance factors specified by AASHTO, including the maximum resistance
factor of 0.70, which assumes load testing is completed.
A resistance factor of 0.60 shall be used with the “soil-like claystone” method
(Abu-Hejleh et al., 2003). The resistance factor was calculated by fitting to
allowable stress design (ASD) assuming the following:
For sites with bedrock N-values typically greater than 100 and where rock coring AASHTO
produces suitable core recovery (i.e., samples can be recovered for strength 10.8.3.5
testing and the rock mass can be characterized to an appropriate degree), it
is preferable to evaluate axial resistance using design methods based on the
unconfined compressive strength, as described in AASHTO and FHWA Report
No. FHWA-NHI-10-016 (Brown et al., 2010).
Because shear rings are difficult to inspect, they shall not be used unless
approved by Staff Bridge. As an alternative to using shear rings to increase
axial resistance, the drilled shaft could be lengthened or increased in diameter.
Methods based on the analysis of stress waves, such as sonic echo and impulse
response, shall not be used as the primary test method unless access tubes
are unavailable.
All testing shall be completed in accordance with the applicable ASTM standards.
CSL access tubes shall be installed in all non-redundant drilled shafts. With
respect to CSL testing requirements, a non-redundant drilled shaft is defined as
any drilled shaft at an abutment or a pier supported by two or fewer drilled shafts.
CSL access tubes shall also be installed in all drilled shafts to be constructed
in a water crossing and in all drilled shafts that will be constructed in soil/rock
requiring the use of temporary excavation support (i.e. casing or drilling fluid).
At the discretion of the Designer, other drilled shafts on the project may be
selected to require CSL testing, such as largely spaced shafts.
CSL testing shall be completed on all non-redundant drilled shafts. CSL testing
shall be completed on a minimum of 50 percent of drilled shafts equipped with
CSL access tubes, at the discretion of the Engineer. If CSL testing indicates
anomalies, the remaining drilled shafts at the pier/abutment shall also be tested.
Installation of CSL access tubes and integrity testing are not required for drilled
shafts with permanent casing socketed into bedrock, regardless of redundancy
or shaft location.
Other agencies, such as railroads, may have more stringent testing requirements.
The designer shall determine if any non-CDOT entities have applicable testing
requirements.
The Designer shall indicate in the plans the minimum number of drilled shafts
to be tested.
If test methods other than CSL are proposed, the Designer shall specify criteria
for the evaluation and acceptance of test results in a Project Special Provision.
When load testing is completed, the entity completing the load test shall prepare
a report sealed by a professional engineer licensed in the State of Colorado
summarizing test results. The report shall include all necessary information and
data to enter the test into the DSHAFT load test database (see Garder et al.,
2012).
10.7 R EFERENCES
Abu-Hejleh, N., O’Neill, M.W., Hanneman, D., Atwooll, W.J., 2003, Improvement
of the Geotechnical Axial Design Methodology for Colorado’s Drilled Shafts
Socketed in Weak Rocks, Report No. CDOT-DTD-R-2003-6.
Brown, D.A., Turner, J.P., Castelli, R.J., 2010 Drilled Shafts: Construction
Procedures and LRFD Design Methods, NHI Course No. 132014, Geotechnical
Engineering Circular No. 10, Report No. FHWA NHI-10-016.
Garder, J.A., Ng, K.W., Sritharan, Sri, and Roling, M.J., 2012, Development of a
Database for Drilled SHAft Foundation Testing (DSHAFT), Report No. 10-366,
Bridge Engineering Center, Institute for Transportation, Iowa State University.