Chapter 4
Chapter 4
Chapter 4
pdf
Pavement Engineering
and Materials
Pavement Evaluation
and Materials
Pavement Evaluation
and Materials
Pavement Evaluation
and Materials
Pavement Evaluation
and Materials
Pavement Evaluation
Shahabad to
338 226 640 418 214 1836 2046
Bawana
2
Bawana to
Shahabad 401 270 473 407 279 1830 2040
future after its completion, under road expansion/ Based on the assumptions made, as mentioned
connectivity plans. Assumptions made to calculate above, the design parameters were finalized.
the expected traffic loading after the construction
of proposed road are as under: The projected traffic computed for Kanjawala to
Rithala and Rithala to Kanjawala carriageways
Commercial vehicles plying on Bawana during the design life of 15 years are 92 msa and
road will be fully diverted (100 percent) 88 msa respectively. As can be seen, Kanjawala
onto the proposed / new road when the to Rithala carriageway has slightly higher
project road will be connected in the design traffic loading (92 msa) than Rithala
near future to Western Yamuna Canal to Kanjawala carriageway (88 msa). It was
Road. ultimately decided to design each carriageway
In the above scenario, half of the traffic of new flexible pavement for 100 msa. The
will be diverted to “Kanjawala to Rithala total pavement thickness thus comes out to be
direction” and the remaining half traffic 700 mm for traffic loading of 100 msa. Design
will be diverted to “Rithala to Kanjawala options arrived from the analyses of data are
direction”. as given under:
The above traffic will be added, as per their Option–I: Structural Composition of
respective directions, to the commercial Flexible Pavement for Full Design Life
vehicles plying on Rithala corridor.
Total Pavement thickness for subgrade CBR of
The construction period will be about 18 6 percent and design traffic loading of 100 msa
months. comes out to be 696 mm, which can be very well
CRRI New Delhi
53
Pavement Engineering
and Materials
Pavement Evaluation
assumed as 700 mm. The structural composition Base Course = 250 mm Wet Mix
of flexible pavement, as worked out from IRC Macadam (WMM)
37-2001 for a total pavement thickness of 700
Subbase Course = 260 mm Granular Sub
mm, is as follows:
base (GSB)
Wearing Course = 40 mm Bituminous
(CBR of not less than
Concrete (BC)
30 percent)
Binder Course = 150 mm Dense
Fig. 66 shows the cross section of main
Bituminous Macadam
carriageway.
(DBM)
Keeping in view the gross uncertainties with Sub base Course = 260 mm GSB (2 layers
regard to extent of traffic and axle loading likely of 130 mm)
to use the new road (as is usually the case) The above design is applicable for about 5
which will be diverted / generated and also the years design life, at which time the projected
proposed future plans for development of new traffic loading is about 30 msa. The pavement,
roads and upgradation / connectivity / expansion as constructed above, can be evaluated after
plans for existing roads in the project area, 5 years of its operation since by this time the
it will be better to go for stage construction. traffic would have stabilized on the newly
Towards this end, the following design of flexible constructed road. At this point of time, detailed
pavement is recommended: structural evaluation by measuring Benkelman
beam deflections and the magnitude of traffic
Wearing Course = 40 mm BC loads can be undertaken for arriving at the
structural overlay requirements, if any, for the
Binder Course = 100 mm DBM (2 layers next 10 years design life. The pavement design,
of 50 mm) as recommended, shall be adopted for the entire
and Materials
Pavement Evaluation
length of project road. It is recommended that and around the parking area and stadium area.
Option-II may be preferred. Towards this end, New Delhi Municipal Council
(NDMC) has decided to develop the green field
As far as the service road is concerned, it is
area within Safadarjang Airport campus, as a
expected that the type of traffic likely to use
park and ride facility for the spectators / visitors
service road(s) will be light and local in nature
of Jawahar Lal Nehru Stadium. The total parking
and will be very less. Therefore, the structural
composition of flexible pavement for service area, to be developed inside Safadarjung Airport,
road (on either sides of the main carriageway) will be a large parking facility and is of the order
has been designed for 2 msa and should serve of 1,75,000 Sq. m. The parking facility being
the purpose. The pavement design recommended created will be able to accommodate 6000 two-
for service road is given below: wheelers, 3000 cars and 400 buses at any given
time. In addition, circulation plan for movement
Wearing Course = 25 mm Semi Dense of different types of vehicles viz., Two wheeler’s
Bituminous Concrete (Scooters / M. Cycles), Cars and Buses, which
(SDBC) will only be allowed to use this parking facility,
Binder Course = 50 mm Bituminous also needs to be developed. Pavement designs
Macadam (BM) and construction specifications for the new
Base Course = 225 mm Water Bound roads (to be developed as internal roads inside
Macadam (WBM) / Airport area), widening of existing roads, and
Wet Mix Macadam strengthening / rehabilitation requirements
(WMM) of existing roads also need to be developed /
formulated.
Sub base Course = 175 mm Granular Sub
base (GSB) The assignment was taken up at the request of
New Delhi Municipal Council (NDMC) with the
Pavement Designs and Circulation objectives to (i) formulate pavement designs and
Plan for Parking Facility at materials / construction specifications for the
development of parking facilities to be used by
Safdarjung Airport Area
different types of vehicles inside Safadarjung
airport area (ii) construction of new roads
A variety of sports / events are planned to be (inside airport area), widening and strengthening
organized at Jawahar Lal Nehru Stadium, near requirements of existing roads in and around the
Safdarjung Airport, Lodhi Road during October airport area, and (iii) Development of circulation
2010 for the Common Wealth Games – 2010. plan for movement of buses, cars, two-wheelers
In order to provide comfort and convenience etc. which will be using the parking facility so
to the spectators likely to visit this stadium, it created / developed.
is essential that an adequate parking plan be
developed along with a proper transportation/ Field investigations in and around the airport
circulation plan for movement of vehicles in area was undertaken to appraise the site
and Materials
Pavement Evaluation
conditions and to fully understand the NDMC Wet Mix Macadam 150 mm
requirements. Based on the field and laboratory (WMM) Base layer
investigations, recommendations on pavement
Granular Sub-base 150 mm
designs separately for parking facility of
(GSB) layer
two wheelers, cars and buses were given as
under: The pavement designs, as recommended above,
have been suggested keeping in view the special
i. Pavement Design for Parking requirements of parking facilities on the eve
Facility of Two Wheelers and of forthcoming Common Wealth Games, by
Cars assuming that the facilities being created are
Strength of Concrete M-40 to be used only for a shorter duration and may
Paver Blocks not be used extensively in a regular way after
the games are over.
(Specified Compressive (40 MPa)
Strength of Paver Blocks In general terms, the concrete paving blocks are
at 28 Days) required to have adequate strength to withstand
their handling, construction stresses and affect
Thickness of Concrete 80 mm of traffic, though the strength as such is not
Paver Blocks considered a vital factor in the satisfactory
Bedding Sand 30 mm performance of block pavements. However, it
is recommended that the minimum compressive
Wet Mix Macadam 150 mm strength of a single block should be above 35
(WMM) Base layer MPa for parking facility of two wheelers / cars
and 45 MPa for parking facility of buses.
Granular Sub-base 150 mm
(GSB) layer iii. Pavement Design for Internal
Roads in Airport Area
ii. Pavement Design for Parking
Facility of Buses Wearing Course 40 mm Bituminous
Concrete (BC)
Strength of Concrete M-50
Paver Blocks Binder Course 50 mm Dense
Bituminous Macadam
(Specified Compressive (50 MPa)
(DBM)
Strength of Paver
Blocks at 28 Days) Base Course 150 mm Wet Mix
Thickness of Concrete 100 mm Macadam (WMM)
Paver Blocks
Granular Sub-base 150 mm Granular Sub
Bedding Sand 40 mm Base (GSB)
and Materials
Pavement Evaluation
iv. Pavement Design for External both sides of the proposed road alignment and
Roads laboratory evaluation of materials was done in
laboratory. CBR of subgrade soil, as determined
a. For Widened Portion
for pavement design purpose, is considered as
Wearing Course 40 mm BC minimum 6 per cent.
and Materials
Pavement Evaluation
Expected No. of Commercial Vehicles Per Day on New Road (After Construction) = 6857
this generated traffic (i.e. 50 percent lane divided carriageway and eight lane divided
of commercial vehicles), half of it will carriageway were finalized.
further get distributed evenly in up and
down directions of the new road facility, As computed, Mundaka to Western Yamuna
when the project road will be connected Canal carriageway (i.e. from NH-10 to NH-1)
to Western Yamuna Canal Road and at has slightly higher design traffic loadings of 128
Mundaka on NH-10, in future. msa and 77 msa for four lane and eight lane
divided carriageway respectively, while it is 94
The construction period will be about 18 msa and 56 msa for Western Yamuna Canal to
months. Mundaka (i.e. from NH-1 to NH-10) carriageway
Based on the assumptions made, as mentioned respectively. It was ultimately decided to design
above, the input parameters for design of four flexible pavement based on the higher loading
and Materials
Pavement Evaluation
amongst the two carriageways i.e. for four lane msa comes out to be 687 mm. The structural
divided carriageway to be designed for a traffic composition of flexible pavement for eight lanes
loading of 128 msa while eight lane divided divided flexible pavement for full design life
carriageway designed traffic loading would be (Option-IB), as worked out from IRC 37-2001,
77 msa. for a total pavement thickness of 687 mm is
as follows:
Total Pavement thickness for subgrade CBR
of 6 percent at design traffic loading of 128 Wearing Course = 40 mm BC
msa comes out to be 710 mm. The structural
Binder Course = 140 mm DBM
composition of flexible pavement for four lanes
divided flexible pavement for full design life Base Course = 250 mm Wet Mix
(Option-IA), as worked out from IRC 37-2001, Macadam (WMM)
for a total pavement thickness of 710 mm is as
Subbase Course = 260 mm Granular Sub
follows:
base (GSB) (CBR not
less than 30 percent)
Wearing Course = 50 mm Bituminous
Concrete (BC) Fig. 67 & 68 show the cross section of main
carriageway for four lane and eight lane
Binder Course = 150 mm Dense divided carriageway. Keeping in view the gross
Bituminous Macadam uncertainties with regard to the extent of traffic
(DBM) and axle loading likely to use the new road
Base Course = 250 mm Wet Mix which will be diverted / generated and also the
Macadam (WMM) proposed future plans for development of new
roads and upgradation / connectivity / expansion
Subbase Course = 260 mm Granular Sub plans for existing roads in the project area, the
base (GSB) (CBR not alternate pavement design for flexible pavement
less than 30 percent) under stage construction for four lane divided
Total Pavement thickness for subgrade CBR carriageway (Option – IIA) is also recommended
of 6 percent at design traffic loading of 77 as given below:
Fig. 67 A cross section of main carriageway for four lanes divided carriageway
and Materials
Pavement Evaluation
Fig. 68 A cross section of main carriageway for eight lanes divided carriageway
Wearing Course = 40 mm BC Base Course = 250 mm WMM (2 layers
of 125 mm thick each)
Binder Course = 100 mm DBM (2 layers
of 50 mm thick each) Sub base Course = 260 mm GSB (2 layers
of 130 mm thick each)
Base Course = 250 mm WMM (2
layers of 125 mm thick The above pavement design is applicable for 5
each) years design life, at which time the projected
traffic loading is expected to be about 17.00
Sub base Course = 2 6 0 m m G S B ( 2
msa. The pavement, as constructed above,
layers of 130 mm thick can be evaluated after 5 years of its operation
each) (when the resurfacing also becomes due) since
The above pavement design is applicable for 5 by this time the traffic would have stabilized on
years design life, at which time the projected the newly constructed road. It is recommended
traffic loading is expected to be about 28.44 that Option-II may be preferred. The structural
msa (about 30 msa for the maximum number composition of flexible pavement for service
of commercial vehicles of 3961). The pavement, roads (on either sides of the main carriageway)
as constructed above, can be evaluated after has been designed for a projected traffic loading
5 years of its operation (when the resurfacing of 2 msa during the design life and should serve
also becomes due) since by this time the traffic the purpose. The pavement design recommended
would have stabilized on the newly constructed for service roads is as given below:
road. It is recommended that Option-II may be Wearing Course = 25 mm Semi Dense
preferred. Bituminous Concrete
(SDBC)
Similarly, as above, the alternate pavement
Binder Course = 50 mm Bituminous
design for flexible pavement under stage
Macadam (BM)
construction for eight lane divided carriageway
(Option – IIB) is recommended as given under: Base Course = 225 mm Wet Mix
Macadam (WMM)
Wearing Course = 40 mm BC
Sub base Course = 175 mm Granular Sub
Binder Course = 75 mm DBM base (GSB)
and Materials
Pavement Evaluation
and Materials
Pavement Evaluation
2445 commercial vehicles were weighed scenario and have contributed heavily
which is 68.20 per cent. The overall VDF to the increase in value of VDF and
for the road in up direction is found to be deterioration of road. Most of these
35.93 trucks, on the other hand, were found
either emptied or lightly loaded while
A total of 7356 commercial vehicles (both
heavy and light) were counted during the returning to Azamgarh, leading to a wide
period of traffic survey (i.e. 168 hours difference in the values of VDF between
round the clock for 7 days) in down the two directions of travel.
direction (towards Azamgarh). A total of Overloading affects significantly the
4092 commercial vehicles (both heavy pavement’s service life and leads
and light) were counted during the period to pre-mature failure/distress of the
of axle loads survey (i.e. Day1, Day 3, Day road. It is, therefore, suggested that
5 and Day 7 round the clock) out of which
stringent measures may be taken
2222 commercial vehicles were weighed
by enforcement authority to control
which is 54.30 per cent. The overall VDF
a n d / o r m i n i m i z e t h e e x c e s s i ve
for the road in down direction is found to
overloading by trucks, particularly
be 1.69.
vehicles carrying construction materials
The cumulative numbers of standard towards Gorakhpur in order to (i) ensure
axles are 203 and 224 million standard desired level of pavement performance /
axles (msa) during a design life of 8 years serviceability within the design period,
at growth rates of 7.5 percent and 10 (ii) avoid the risk of pre-mature distress
percent per annum respectively. / failure, and (iii) minimize maintenance
It was noticed during the period and rehabilitation costs and road user
of surveys that large scale road costs.
construction activities are currently Evaluation of Serviceability of
in progress towards Gorakhpur. Pavement Surface of Eastern and
Substantial numbers of overloaded Western Express Highways in
trucks, transporting the construction Mumbai Region
materials, were found to be using the
project road which may be temporary This assignment was referred by Mumbai
or seasonal. The extent of overloading Construction Circle, P.W.D. Mumbai to evaluate
by trucks, in up direction, carrying the serviceability or functional quality in terms
construction materials are abnormal of riding quality (roughness) and surface friction
and beyond imagination. However, characteristics of the Eastern and Western
these overloaded trucks/dumpers have Express Highways from traffic safety point of
significantly influenced the loading view in Mumbai region.
and Materials
Pavement Evaluation
and Materials
Pavement Evaluation
of NTPC plants located in Dadri and Badarpur specifications, preparation of BOQs, job
including rehabilitation / strengthening. mix designs, and limited construction
quality checking / supervision of road
Field visits and inspection of various roads
sections. .
in the plant areas (NTPC-Dadri and Badarpur
Campus) were made in order to have physical 2. Association during laying of demonstration
assessment of the roads which have to be stretches for use of fly ash in Bituminous
rehabilitated / strengthened / resurfaced within Concrete (BC), Stone Matrix Asphalt
NTPC Dadri plant campus and to appraise the (SMA) and Slurry Seal / Micro-
current condition of project roads. Subsequently, Surfacing.
detailed investigations / surveys related to the 3. To develop periodic pavement performance
pavement evaluation on the identified project data (such as deflection, roughness,
roads which needed maintenance / rehabilitation surface distress, traffic volume etc.)
were also undertaken. at six months interval for a period of 3
years.
The primary objective of the R&D study is
to evaluate performance of road sections The road length considered under this study in
constructed with different types of bituminous Dadri is about 5414 meter having variations in
surfacings constructed by using fly ash as mineral pavement width from 3 to 7 meter. The details
filler vis-a-vis constructed in a conventional way of road length of project roads are presented in
(by using lime as mineral filler). Table VII.
The scope of work of the study included Detailed investigations (structural and functional
evaluation) were undertaken on the project
1. Pavement condition survey before roads with a view to assess the condition of
construction, materials and construction existing pavements. Tasks / activities included
Table VII Details of Length and Width of Project Roads in the Study Area
S. Link / Road Name Length Width Total Road Traffic Category (in
No. (m) (m) Length (m) terms of CVs*)
and Materials
Pavement Evaluation
assessment of pavement surface condition years. On the other hand, pavement surface
(visual basis), roughness measurements, roughness for these roads indicates that these
Benkelman Beam deflection measurements, roads are in poor condition. Hence, in order to
traffic volume surveys (only commercial vehicles) improve the current condition of project roads /
and test pit observations links from their functional point of view and to
provide comfortable ride to the users, renewal /
The major types of surface distress recorded
resurfacing treatments in terms of 40 mm thick
in terms of percentage of the total pavement’s
surface area are cracking, ravelling, pot holes, Bituminous Overlay is recommended. Table IX
shoving, bleeding, corrugation and rutting etc. shows the proposed specifications on various
The structural inadequacy of pavement is sections of different project roads, which are
worked out by using characteristic deflection to be constructed using lime and fly ash as the
values and cumulative number of standard mineral filler.
axles. Using average characteristic deflection
data (average of all the roads / links) and Design of Pavement around Rotary
projected traffic loading (msa), the overlay Junction 26 between Sectors 16 to
thicknesses have been worked out for 17 and 22 to 23 at Chandigarh
different project roads in terms of Bituminous The rotary (Junction No. 26) i.e. between
Macadam (BM) for 10 years design life as Sectors 16 to 17 and 22 to 23 is a very busy
per IRC: 81- 1997. The overlays required roundabout, which is located very close to
for different project roads are given in Table Interstate Bus Terminus (ISBT). This rotary
VIII. caters to a very large number of mixed types
Table shows that the existing roads / links are of vehicles consisting of two-wheelers,
structurally adequate for a design period of 10 cars, three wheelers, buses and commercial
Table VIII Overlay Thickness Required for Different Project Roads (Design
Life=10 Years)
Average Design Overlay
Direction Traffic VDF Characteristic Traffic Requirements
(CVPD) Deflection (mm) (msa) (BM), in mm
495 4.5 10 Nil
Gate No. 3 to T-Junction
Notes: CVPD = Commercial Vehicles per Day; VDF= Vehicle Damage Factor;
MSA = Million Standard Axles ; BM= Bituminous Macadam
and Materials
Pavement Evaluation
and Materials
Pavement Evaluation
and Materials
Pavement Evaluation
Assessment of pavement surface (10 cm) diameter cylindrical cores were marked
condition through visual inspections / identified. Cores were taken for determining
the layer thicknesses and for evaluating the
Extraction of 4” diameter cylindrical
construction quality of asphalt mixes. Concrete
cores
cores were also recovered from the runway end
Measurement of layer thicknesses in the / turning pad. As reported by AAI, runway was
pavement structure classified into five distinct sections, as given
below:
Test pits observations and collection of
i. Central 30 m wide portion of old
subgrade soils and other road building
runway from 0 to 1400 m
materials used for construction of
runway pavement This section of runway is not showing any
signs of rutting, depression, deformation or
Laboratory evaluation of in-situ materials
any other distress types except for segregation
and mixes retrieved from the existing
of bituminous mix on top layer at few isolated
pavement structures for ascertaining
locations.
the construction quality of pavement
component layers ii. Widened portion on both sides of the
old runway from 0 to 1400 m(15 m to
Analysis of data / results to estimate 22.5 m)
PCN of different sections of the runway
Widened portion of the old runway from 0 to
pavement
1400 m (15 to 22.5 m on East and West sides
Recommend remedial measures to from the central line of runway) had developed
improve the current condition of different / witnessed (in the past) some depressions /
sections of runway pavement so as settlements at scattered locations of varying
to make the whole runway pavement length and width in April 2007 which were
suitable for the anticipated proposed subsequently repaired in July 2007 itself by
aircraft operations. removing bituminous layers in some portions
and relaying and by providing additional bitumi-
Surat airfield is presently being used by various
nous layer (DAC) in some portion. The present
types of aircrafts such as A319, A320 and
surface condition of this section of runway is
CRJ700 on “one flight a day” basis. The airfield
satisfactory with no visible distress found on
pavement is to be evaluated for determination
of PCN towards finding out its suitability for the pavement surface.
unrestricted operations / use by different types
iii. Extension portion from 1400 to 1585 m
of aircrafts (A 319, A320 and A321) on ultra low
for full width of 45 m
subgrade strength (in terms of CBR). Based on
the general appraisal of the pavement surface This section also includes RESA portion of
condition, representative locations for taking 4” 60 m from chainage 1525 to 1585 m. Some
and Materials
Pavement Evaluation
and Materials
Pavement Evaluation
and (v) Rigid turning pad at 22 End from (MP-1 Road) and Udyog Marg in Noida towards
2094 to 2250 m including dumbbell, are determining the likely causes of distress/
80/F/D/W/T, 36/F/D/W/T, 27/F/D/W/T, defects developed on these roads and to
22/F/D/W/T and 70/R/D/W/T respec- suggest remedial measures needed to overcome
tively. the problem (s).
4. Problematic areas / locations assessed The scope of work included the following major
during the evaluation of runway pave- activities:
ment include extended portion of the
a. Field investigations
runway pavement from 1400 to 1585 m
(45 m wide). This section of runway is Functional evaluation of pavement
recommended to be reconstructed for a surface through roughness
design PCN value of 63 on the existing measurements, using duly
‘Ultra Low’ subgrade strength, as per calibrated fifth wheel bump
AAI / ICAO design guidelines. integrator, on each lanes of both
carriageways for the entire length
5. Widened portion of original runway from of project roads
0 to 1400 m (30 to 45 m) and the ex-
Assessment of pavement surface
tended section of runway pavement
distress (types and extent) by
from 1595 to 2094 m, are recommend-
visual observations.
ed to be strengthened / overlaid with the
following specifications: Structural evaluation of pavement
by Benkelman Beam deflection
a) Widened portion of old runway measurements (11 points per Km
on both sides (30 to 45 m) in each carriageway), covering the
Provide bituminous overlay of 125 mm entire length of project roads
thick (75 mm DBM + 50 mm BC)
Test pits evaluation (about 2
b) Extended portion of runway to 3 on each of the two roads,
pavement (1585 to 2094 m) representing variations in surface
Provide bituminous overlay of 200 mm condition)
thick (2x75 mm DBM +50 mm BC)
Classified traffic volume surveys
at one location for 24 hours round
Evaluation of Master Plan Road the clock on each road
No.1 and Udyog Marg in Noida
b. Laboratory evaluation by determining
The assignment was taken up at the request the engineering properties of materials
of New Okhla Industrial Development Authority retrieved from different layers of the
(NOIDA) to carry out detailed investigations existing pavement structures of two
of the two roads i.e. Master Plan Road No. 1 roads.
and Materials
Pavement Evaluation
Following are the major likely causes which Fig. 78 Patching, potholes and loss of materials on
may be responsible for development of distress/ Udyog marg
and Materials
Pavement Evaluation
and Materials
Pavement Evaluation
and Materials
Pavement Evaluation
receive heavier types of aircrafts for its future runway pavement, which was then tested in
operation. the laboratory for their properties.
Necessary field works / investigations Four test pits, one on sound condition of the
undertaken for the evaluation of existing pavement and three on problematic areas of
runway pavement included assessment of the runway, of size 1.25 x 1.25m, on / near
surface condition of the runway pavement the edge of the pavement were cut open for
by visual inspection. It was observed that determination of thickness of component
there was no visible distress in the first 600 layers and field density etc. Road construction
metres length of the runway except that the materials from different component layers in
pavement surface was hungry. Pavement was the pavement structure were also collected
found to be distressed mainly from 600 to for laboratory evaluation.
1020 m along and across the centre line on
most used lanes. Distresses observed from Further analysis of data and report prepara-
600 to 1020 m on the main runway are in tion is in progress.
the form of oozing of water, in the form of
patches on the surface, cracking, raveling, State-of-Art Equipments/
deformation, patch work, and pot holes. Facilities Created
Majority of the locations were highly Network Survey Vehicle System
distressed / badly cracked. This has primarily
occurred probably due to entrapment of water The Network Survey Vehicle (NSV) system is
in the lower bituminous layers. Similar kind based on the latest survey techniques utilizing
of distresses were observed on stretch Laser, Global Positioning System and Video
from 1020 to 1200 m. Stretch from 1200 to image processing tools etc (Fig. 79). The
1800 m was found to be hungry surface with Survey Vehicle is being used for automatic
some patches due to oozing of water on the collection of road condition related data
surface. Vegetation growth was also seen at for National Highways. The inventory data
very few locations on the shoulders. Drainage collected include measurement of gradient
and shoulder conditions of the runway were (rise and fall), horizontal curvature, pavement
found to be in fair to poor condition. surface condition (distress), roughness, and GPS
coordinates (X, Y, Z) viz. longitude, latitude &
Based on the general appraisal of pavement altitude etc. Based on the information collected
surface condition, representative locations through NSV and using the map data, a user
for taking 4” (10 cm) and 6” (15 cm) friendly GIS based interactive system is currently
diameter cylindrical cores were taken over under development.
the entire length of runway for determining
the layer thicknesses and for evaluating Key Features of the Network Survey Vehicle
System are:
the construction quality etc. A total of 26
bituminous cores were recovered from the a. High survey speed up to 100 km/hr
and Materials
Pavement Evaluation
and Materials
Pavement Evaluation