Rehabilitation of Damaged Concrete Structures: Peter Barlow
Rehabilitation of Damaged Concrete Structures: Peter Barlow
Rehabilitation of Damaged Concrete Structures: Peter Barlow
Concrete Structures
Peter Barlow
Beam Repair
Detail-Form &
Pour
Column Repair Detail-Form & Pour
Cement Plant Unloading
Dock
Cement Plant Unloading Dock
Cement Plant Unloading Dock
#5 Bars
Cement Plant
Unloading
Dock
Saw Cut & Chip
Repair Strategy
Epoxy Inject
Internal Post
Tensioning
Repair
Strategy
Internal Post
Tensioning
Flexural
Strengthening
Case Study
Internal PT
Flexural Strengthening Case
Study Internal Post
Tensioning
Note Bar
Termination
80 Year Old Building Seismic Rehabilitation
Edges of
Plate
Sealed
Gray’s Harbor Courthouse
Earthquake Repairs 1999
GFRP Shear Strengthening
Column Strengthening-Using Glass Fiber and
Grouted Steel Jackets
GFRP
Cement Grouting
Seismic Upgrade Anchorage Alaska
The Problem
Shear Deficient
Over Turning
Minimize Addition of
Mass to Foundation
Epoxy Inject Cracks & Install GFRP
GFRP
Epoxy Injected
Cracks
Some Challenges—Transferring Load Distribution from
Foundation to Roof Elevation
Radiused Plate
Washers
CFRP Cord Members to Create Overturning
Resistance
GFRP CFRP Note Curtailment of CFRP
Repair of Seismic Damage Nisqually
Earthquake 2001
Epoxy Inject Cracks and GFRP
GFRP
3-Layers of CFRP
Project Completed on Time & Without
Interruptions
Bridge Structure
Seismic
Rehabilitation Using
GFRP 1995
Fiber Saturating
Machine
3-Layers Circumferentially
3-Layers Transversely
GFRP Installed 1995
Revisited in 2006
Survived the 2001
Nisqually Earthquake
CFRP Bridge Column Seismic Strengthening
Completed & Painted Column Surfaces