Philrock Vs Construction
Philrock Vs Construction
Philrock Vs Construction
*
G.R. Nos. 132848-49. June 26, 2001.
http://www.central.com.ph/sfsreader/session/00000168d76e64115a863952003600fb002c009e/t/?o=False 1/18
2/10/2019 SUPREME COURT REPORTS ANNOTATED VOLUME 359
_______________
* THIRD DIVISION.
633
634
PANGANIBAN, J.:
635
The Case
http://www.central.com.ph/sfsreader/session/00000168d76e64115a863952003600fb002c009e/t/?o=False 4/18
2/10/2019 SUPREME COURT REPORTS ANNOTATED VOLUME 359
The Facts
_______________
636
http://www.central.com.ph/sfsreader/session/00000168d76e64115a863952003600fb002c009e/t/?o=False 5/18
2/10/2019 SUPREME COURT REPORTS ANNOTATED VOLUME 359
“The Cid spouses then filed with said Branch of the Regional
Trial Court of Quezon City a Motion To Set Case for Hearing
which motion was opposed by Philrock.
“On June 13, 1995, the trial court declared that it no longer
had jurisdiction over the case and ordered the records of the case
to be remanded anew to the CIAC for arbitral proceedings.
“Pursuant to the aforementioned Order of the Regional Trial
C[o]urt of Quezon City, the CIAC resumed conducting
preliminary conferences. On August 21, 1995, herein [Petitioner
Philrock requested to suspend the proceedings until the court
clarified its ruling in the Order dated June 13, 1995. Philrock
argued that said Order was based on a mistaken premise that ‘the
proceedings in the CIAC fell through because of the refusal of
[Petitioner] Philrock to include the issue of damages therein,’
whereas the true reason for the withdrawal of the case from the
CIAC was due to Philrock’s opposition to the inclusion of its seven
officers and engineers, who did not give their consent to
arbitration, as party defendants. On the other hand, private
respondent Nelia Cid manifested that she was willing to exclude
the seven officers and engineers of Philrock as parties to the case
so as to facilitate or expedite the proceedings. With such
manifestation from the Cid spouses, the Arbitral Tribunal denied
Philrock’s request for the suspension of the proceedings.
Philrock’s counsel agreed to the continuation of the proceedings
but reserved the right to file a pleading elucidating the position
he [had] raised regarding the Court’s Order dated June 13, 1995.
The parties then proceeded to finalize, approve and sign the
Terms of Reference. Philrock’s counsel and representative, Atty.
Pericles C. Consunji affixed his signature to said Terms of
Reference which stated that ‘the parties agree that their
differences be settled by an Arbitral Tribunal x x x x‘ (p. 9, Terms
of Reference, p. 200, Rollo).
637
_______________
638
http://www.central.com.ph/sfsreader/session/00000168d76e64115a863952003600fb002c009e/t/?o=False 7/18
2/10/2019 SUPREME COURT REPORTS ANNOTATED VOLUME 359
_______________
639
Issues
“A.
Whether or not the CIAC could take jurisdiction over the case of
Respondent Cid spouses against Petitioner Philrock after the case
had been dismissed by both the RTC and the CIAC.
“B.
“C.
“D.
“E.
“F.
_______________
6 This case was deemed submitted for decision upon this Court’s receipt
on October 21, 1999, of the Memorandum filed and personally signed by
Respondent Nelia Cid; Vicente, her husband, had died in the meantime.
The Memorandum for petitioner was signed by Atty. Pericles C. Consunji
of Ponce Enrile Reyes & Manalastas, while the Memorandum for Public
Respondent was signed by Assistant Solicitor Carlos N. Ortega and
Solicitor Geraldine C. Fiel-Macaraig.
http://www.central.com.ph/sfsreader/session/00000168d76e64115a863952003600fb002c009e/t/?o=False 9/18
2/10/2019 SUPREME COURT REPORTS ANNOTATED VOLUME 359
640
“G.
First Issue:
Jurisdiction
_______________
http://www.central.com.ph/sfsreader/session/00000168d76e64115a863952003600fb002c009e/t/?o=False 10/18
2/10/2019 SUPREME COURT REPORTS ANNOTATED VOLUME 359
“The jurisdiction of the CIAC may include but is not limited to violation
of specifications for materials and workmanship; violation of the terms of
agreement; interpretation and/or application of contractual provi
641
_______________
http://www.central.com.ph/sfsreader/session/00000168d76e64115a863952003600fb002c009e/t/?o=False 11/18
2/10/2019 SUPREME COURT REPORTS ANNOTATED VOLUME 359
642
Second Issue:
Cause of Action
http://www.central.com.ph/sfsreader/session/00000168d76e64115a863952003600fb002c009e/t/?o=False 12/18
2/10/2019 SUPREME COURT REPORTS ANNOTATED VOLUME 359
_______________
11 See Spouses Benitez v. Court of Appeals, 266 SCRA 242, January 16,
1997.
12 Camara v. Court of Appeals, 310 SCRA 608, 618, July 20, 1999; Delos
Reyes v. Court of Appeals, 285 SCRA 81, 85, January 27, 1998; heberman
Realty Corporation v. Typingco, 293 SCRA 316, 327, July 29, 1998.
13 Baluyot v. Court of Appeals, 311 SCRA 29, 45, July 22, 1999;
Vergara v. Court of Appeals, 319 SCRA 323, 327, November 26, 1999;
Leber-man v. Typinco, ibid., p. 328.
643
“Accordingly, this Tribunal finds that the mix was of the right
proportions at the time it left the plant. This, however, does not
necessarily mean that all of the concrete mix delivered had
remained workable when it reached the jobsite. It should be noted
that there is no evidence to show that all the transit mixers
arrived at the site within the allowable time that would ensure
the workability of the concrete mix delivered.
“On the other hand, there is sufficiently strong evidence to
show that difficulties were encountered in the pouring of concrete
mix from certain transit mixers necessitating the [addition] of
water and physically pushing the mix, obviously because the same
[was] no longer workable. This Tribunal holds that the
unworkability of said concrete mix has been firmly established.
“There is no dispute, however, to the fact that there are defects
in some areas of the poured structures. In this regard, this
Tribunal holds that the only logical reason is that the unworkable
14
concrete was the one that was poured in the defective sections.”
Third Issue:
Monetary Awards
http://www.central.com.ph/sfsreader/session/00000168d76e64115a863952003600fb002c009e/t/?o=False 13/18
2/10/2019 SUPREME COURT REPORTS ANNOTATED VOLUME 359
_______________
14 CIAC Decision dated September 24, 1996; CA rollo for G.R. SP No.
42443, p. 42.
644
15
are supported by substantial evidence. The Court,
however, has consistently held that despite statutory
provisions making the decisions of certain administrative
agencies “final,” it still takes cognizance of petitions
showing want of jurisdiction, grave abuse of discretion,
violation of due process, denial of16 substantial justice or
erroneous interpretation of the law. Voluntary arbitrators,
by the nature of their functions, act in a quasi-judicial
capacity, such that
17
their decisions are within the scope of
judicial review.
Petitioner protests the award to respondent spouses of
P23,276.25 as excess payment with six percent interest
beginning September 26, 1995. It alleges that this item was
neither raised as an issue by the parties during the
arbitration case, nor was its justification discussed in the
CIAC Decision. It further contends that it could not be held
liable for interest, because it had earlier tendered a check
in the same amount to respondent spouses, who refused to
receive it.
Petitioner’s contentions are completely untenable.
Respondent Nelia G. Cid had already raised the issue of
overpayment even prior to the formal arbitration. In
paragraph 9 of the Terms of Reference, she stated:
“9. Claimants were assured that the problem and her demands
had been the subject of several staff meetings and that Arteche
was very much aware of it, a memorandum having been
submitted citing all the demands of [c]laimants. This assurance
http://www.central.com.ph/sfsreader/session/00000168d76e64115a863952003600fb002c009e/t/?o=False 14/18
2/10/2019 SUPREME COURT REPORTS ANNOTATED VOLUME 359
_______________
15 Villaflor v. Court of Appeals, 280 SCRA 297, 330, October 9, 1997; Philippine
Merchant Marine School, Inc. v. Court of Appeals, 244 SCRA 770, 785, June 2,
1995; COCOFED v. Trajano, 241 SCRA 262, 268, February 15, 1995.
16 Villaflor v. CA, ibid.; De Ysasi III v. National Labor Relations Commission,
231 SCRA 173, 185, March 11, 1994.
17 Chung Fu Industries (Phils.), Inc. v. Court of Appeals, 206 SCRA 545, 556,
February 25, 1992.
645
of only P102,586.25,
18
which [claimant refused to accept by saying,
’saka na lang.’ ”
http://www.central.com.ph/sfsreader/session/00000168d76e64115a863952003600fb002c009e/t/?o=False 15/18
2/10/2019 SUPREME COURT REPORTS ANNOTATED VOLUME 359
_______________
646
_______________
21 Rollo, p. 198.
22 Respondent Nelia Cid’s Explanation; rollo, pp. 184-186.
23 Go v. Intermediate Appellate Court, 197 SCRA 22, 28-29, May 13,
1991; Ventanilla v. Centeno, 1 SCRA 215, 220, January 28, 1961;
RobesFrancisco Realty v. Court of First Instance, 86 SCRA 59, 65-66,
October 30 1978.
647
http://www.central.com.ph/sfsreader/session/00000168d76e64115a863952003600fb002c009e/t/?o=False 17/18
2/10/2019 SUPREME COURT REPORTS ANNOTATED VOLUME 359
——o0o——
648
http://www.central.com.ph/sfsreader/session/00000168d76e64115a863952003600fb002c009e/t/?o=False 18/18