Diff BWT Is 800 101
Diff BWT Is 800 101
Diff BWT Is 800 101
Thesis
8 May 2018
Abstract
The purpose of this thesis was to define the origin of the value for maximal reinforcement
area for reinforced concrete walls and columns, and to create a useful design instruction
for the design of densely reinforced structures. Also, the thesis aimed to provide a clear
picture of possible applications of dense reinforcement for cast-in-situ structures and to
define factors which need to be considered during the design and construction processes.
A significant part of this research was based on interviewing experts at structural design
companies as well as at construction sites. In addition, the thesis was based on literacy
research of previous and current structural design norms.
The information that retrieved from interviews and studies explained the origin of maximal
reinforcement area value and the problems occurring in densely reinforced concrete struc-
tures.
This knowledge can be applied in structural design process to minimize the possibility of
mistakes occurring, as well as to develop the efficiency of structural design and construc-
tion implementation processes. In addition, a unique structural guide for the design of
densely reinforced concrete walls and columns was created.
List of Abbreviations
1 Introduction 1
2 Theoretical Background 2
5 Reinforcement Overlapping 14
10 Conclusion 36
References 38
Appendices
Appendix 1. Structural Design Instruction
Appendix 2. Additional Figures & Images
List of Abbreviations
As = Reinforcement area
b = Width
c/c = Centre-to-centre
d = Diameter
EN = Eurocode
NA = National Annex
1 Introduction
Eurocode is the European standard for conducting structural design processes. Addi-
tionally, Eurocodes require that countries have their own additional regulations which
are called National Annexes. In Finland, the Ministry of Environment (Ympäristöminis-
teriö) is responsible for the National Annex for buildings. The Finnish Standard Asso-
ciation SFS develops, publishes and controls the national standards.
Eurocode 1992-1-1 regulates reinforced concrete structures and gives the basic rules
and concepts for construction. Finnish Engineering Union has an instruction for con-
crete works implementation, it is called RIL 149-1995. Eurocode 1992-1-1 states the
maximum value of reinforcement in concrete walls. However, it is not explained why
this value cannot be exceeded and how the coefficient of the maximum value is calcu-
lated. Currently, when designing a reinforced concrete wall or column, it is recom-
mended to not exceed the maximum value of the vertical reinforcement area. (2.)
In special situations reinforced concrete wall or column structures are needed to carry
large loads when certain properties of the wall/column (such as width) cannot be in-
creased. Eurocode 1992-1-1 gives a limit for the reinforcement area in a concrete wall
or column that cannot be exceeded. However, there are situations where it is impossi-
ble to change the properties of the structure such as cross-section area. In these
cases, an engineer needs to design a structure with the given properties. This thesis
studies these situations, and examines the origin of the maximum value, as well as
factors which affect it.
2
2 Theoretical Background
Dense reinforcement problems can appear in any type of structures, such as columns,
walls and beams. However, dense reinforcement usually appears at connection be-
tween structures and in bending structures. In columns or walls, dense reinforcement is
rarely seen. However, a structure will often have dense reinforcement in connection
areas with other structures such as columns with slabs, or walls with slabs. In columns,
the amount of concrete mass used is small, the speed of casting is usually high, which
leads to an unequal distribution of aggregates and concrete mass that finally may lead
to cracking. (1.)
In thin reinforced concrete walls, the same problem happens as in other densely rein-
forced concrete structures. Due to a tight reinforcement net, aggregates are separated
from cement and get stuck between rebars. Ultimately it leads to unequal distribution of
concrete mass. In reinforced concrete walls openings have dense reinforcement. (1.)
3
The main task of columns and walls is to transfer loads of upper structure elements to
the foundation. Columns and walls are compressed structures where tension occurs
due to large moment forces. Concrete has high compression strength capacity when
reinforcement resists well tension in the structure that happens due to moment forces.
In vertical structures, it is possible that second order bending occurs, which needs to
be prevented to keep the structures stable. Reinforced concrete columns and walls are
similar structures and can be calculated with the same formulas. The vertical rein-
forcement of a wall, however, needs to be checked additionally.
Vertical reinforcement shall be checked for minimum reinforcement area, symbols are
As,vmin for walls and As,min for columns. Secondly, maximum value of reinforcement area
shall be checked, symbol are As,vmax for walls and As,max for columns. Svmax - Distance
between rods shall be calculated. (2.)
Eurocode also gives the minimum value for vertical reinforcement, 0.2 % of the cross-
section area. (12.) The following formula is given:
4
Also, minimum reinforcement area can be calculated with the following formula:
As,vmin (2.)
For the minimum reinforcement area allowed in reinforced concrete structures, the Fin-
nish NA has the same value as EN 1992-1-1. (12.)
The maximum distance between the vertical rods can be calculated with the formula:
Sv,max (2.)
Horizontal reinforcement is calculated differently for walls and for columns. In walls,
horizontal reinforcement are bars which go all the way through the wall. In columns
they are stirrups. In vertical structures, horizontal reinforcement prevents buckling of a
vertical rebar. If a vertical rebar in a column starts to buckle, the stirrup does not allow
it. It also involves other vertical bars in preventing the buckling. In walls, when a vertical
rod is under load and starts to buckle, horizontal reinforcement does not allow it, and
also involves other rods to resist the force. However, it is important to place a horizon-
tal reinforcement closer to the edge than a vertical reinforcement. Figure 1 shows the
correct and incorrect locations of horizontal and vertical reinforcements. If a vertical
reinforcement is located on the outside, a transverse reinforcement should be applied.
5
When vertical reinforcement is outside of the horizontal one, at least 4 units of trans-
verse reinforcement must be used per square meter. However, it is not needed when a
reinforcement net is done by welding and the maximum diameter of a rod is 16 mm and
concrete cover is at least 2 x diameter. (2.)
Scv,t,max
7
The center to center distance decreases in the connection area of the structures with
other structure. Distance should be less or equal to 0.6 * maximum centre-to-centre
distance of transverse reinforcement. (2.)
According to the standard EN1992-1-1 FIN NA, the maximum value of reinforcement
area is 12 % of cross-section area in overlapping reinforcement areas. It is calculated
with this formula:
As,vmax c (12.)
However, 12 % is a very big value, often the structure is not going to function properly if
12 % is used.
8
EN1992-1-1 gives a recommendation value for the maximum and minimum area of
reinforcement. Moreover, it mentions that the maximum value can be presented in the
National Annex. As mentioned above, the Finnish NA sets the maximum value for area
of reinforcement larger than does the EN1992-1-1. However, the method of calculation,
reasons and factors that affect it are not mentioned. (11.)
The maximum values of reinforcement areas in columns and walls are not supported
by any theoretical factors. For this research no calculations which can show how the
6% value was gained could be found. Therefore, it is possible to say that the rein-
forcement maximum area value is a practical value that was presumably gained
through tests, experience and other factors which are going to be considered further.
Densely reinforced concrete structures require a lot of work at the construction site and
to implement densely reinforced concrete structures is very challenging. Additionally, a
long time is spent to install the rebars in the correct positions in narrow structures,
where concrete pouring and vibration works are difficult. Furthermore, in densely rein-
forced structures concrete does not cast equally and workers need to concentrate to
ensure that it mixes as equally as possible. (9.)
Additional problems occur in the overlapping area. All the work costs money and mate-
rials, especially if many steel rods are needed. This is why, it is not economical to cre-
ate densely reinforced concrete structures. Project engineers can consider substituting
reinforced concrete columns by composite or steel structures. However, it is not possi-
ble to substitute it by any other wall material. (9.)
goal of vertical structures is to transfer the loads of the building from the roof to the
foundation. (9.)
The safety factor can be referred as creep of concrete, that it is dangerous to have
such a relation loads to capacity structures all the time under large stresses. Since one
part of a column or wall is always in tension and another is always in compression,
deformation increases, the moment grows and risks of the structure collapsing grows
respectively. Creep must be taken into account in the design phase as well as to figur-
ing out what type of loads affects the structure. If the permanent load is the main load
and also the largest load, the designer should understand that the structure is going to
be under high stresses all the time, which can cause creep. In the case if live load is
the main, the situation is not dangerous since the structure is not always under
stresses. The designer should always take into account what type of loads affect the
structure. (9.)
Another reason why the 6 % reinforcement area cannot be exceeded is the difficulties it
would cause with implementation at the construction site. 6 % is a high value and if it is
exceeded, it means that the rebars are very close to each other. This means that pour-
ing the concrete equally becomes challenging and vibration works cannot be done
properly. Thus, the concrete does not obtain the required properties between the re-
bars, meaning that the structure will not work properly. (8.)
10
It is possible to group the main reinforcements to get more space between rebars.
However, not more than 3 rebars can be grouped. Moreover, if reinforcement is
grouped, the reinforcement area of the grouped rods is decreased. The reinforcement
area of grouped reinforcement can be calculated with the following formula:
⌀n (11.)
A = ⌀n 2
A bunch of 3 rebars with a diameter of 32 mm, when ⌀n is 55 mm, covers 2375 mm2
reinforcement area. Grouping improves the conditions, but not significantly.
11
The regulation SP 52-103-2007 states that the value of reinforcement in the cross-
section area cannot exceed 10 % in any location. (5.) The minimum value for rein-
forcement is 0.1 % of the cross-section area. (6.)
The Russian code does not provide a formula to calculate the maximum reinforcement
area value. However, it states that the maximum reinforcement is defined through tests
in a laboratory. The results show that over 10 % reinforcement does not increase the
bearing capacity. A higher value can only make the situation worse, and cause installa-
tion problems at the construction site. (6.)
According to SP, reinforced concrete structures where shear force cannot be born only
by concrete, stirrups with centre to centre not larger than 0,5 * smallest width of the
column or 300 mm must be installed. Rebars should have durable anchoring at both
ends, either due to overlapping or welding, in order to have a durable connection. Ac-
cording to the Russian code, overlapping reinforcement is applied to rebars with a di-
ameter less than 40 mm. (4.)
12
In German National Annex, the values are similar to those in Eurocode 1992. The
minimum required diameter of vertical reinforcement for columns is 12 mm. The mini-
mal area of reinforcement is calculated by the following formula:
As,vmin
Chapter NDP ZU 9.5.2 (3) states the maximum area of reinforcement, as 9 % of the
cross-section area, thus a value of 0.09 is used. This value is applied for every area of
the column, both the main reinforcement as well as reinforcement overlapping. (3.)
According to DIN 1992-1-1/NA:2013-4, for the requirements are similar reinforced con-
crete walls. Minimum reinforcement area value is calculated the same way as for rein-
forced concrete columns, with the following formula:
As,vmin (3.)
For slim walls or if: c, the formula that should be used is:
As,vmin (3.)
The maximal value for the main reinforcement area is 4 % or 0.04 of cross-section
area. In reinforcement overlapping area it is allowed to use double value, 8 % or 0.08
of the cross-section area. (3.)
According to the American code the maximal reinforcement area shall not exceed 0.08
or 8 % of cross-section area for nonprestressed columns and for prestressed which
compressive stress is less than 1.55 MPa. The minimal reinforcement area must not be
less than 0.001 of the cross-section area. The value of maximum reinforcement area is
considered practically. This value allows for concrete to consolidate around the rebars
and engineer to design a column the way it was tested. The 0.08 value applies to all
13
parts of the column, including reinforcement overlapping areas. Therefore, vertical rein-
forcement cannot exceed 0.04 or 4 % of the cross-section area. (7.)
As mentioned above, the overlapping area can have 8 % of the cross-section area.
However, ACI 318-14 gives a drawing that shows that the bars in the overlapping area
from lower or higher level shall be bent inside the column, as can be seen in figure 4.
This provides clear spacing between the rebars. (7.)
ACI 318-14 gives the minimum reinforcement values for vertical and transverse rein-
forcement in table (11.6.1, page 169). The maximum reinforcement area value is not
stated in the chapter R11 – Walls. Possibly, the maximum reinforcement area value is
the same as for columns, 4 % for vertical reinforcement and 8 % for reinforcement
overlapping. (7.)
14
5 Reinforcement Overlapping
RIL 149-1995 mentions that in densely reinforced concrete structures the process of
choosing concrete mass requires additional attention. It is very important to consider
the flexibility, aggregate properties and coherence of the concrete. Usually the best
result is achieved with liquefied concrete that easily gets through dense reinforcement.
However, the vibration works requirements are the same as for ordinary concrete, de-
spite the of use of liquefied concrete in dense reinforcement structures. The main ad-
vantage of liquefied concrete is that it goes between the rebars and settles equally. (1.)
Concrete is mixed in a truck and while it is waiting to be poured in the form, it is neces-
sary to add a liquefier so that it casts easier. A liquefier slows down the reaction be-
tween the cement and water, which in high and thin structures helps to cast properly.
Despite the liquefier, liquefied concrete keeps its properties and functions as well as
ordinary concrete. (1.)
For liquefied concrete, the formwork must be strong and able to hold the pressure. In
densely reinforced concrete structures more vibration works are done than in regular
structures. Thus, the formwork must be stable and not let the concrete to leak from the
formwork. (1.)
Aggregates should be of approximately the same size and distributed equally in the
structure. If the aggregates are too small they will drop down to the bottom, which will
lead to unequal distribution. If the aggregates are too large, they will get stuck between
the rebars which does not allow the concrete to fill the formwork properly. In densely
reinforced concrete structures, the maximum size of aggregates can be 0.85 of the
distance between rebars of the same direction. (1.)
Concrete aftercare ensures the correct quality of the structure according to the norms,
for example in a period of 10 days, quality control might be performed every 3 rd day
and any necessary action or adjustment can be undertaken. The action might include
keeping the temperature difference minimal throughout the whole structure. Due to a
chemical reaction between cement and water, the temperature in the structure can be
16
Shrinkage does not depend on the density of reinforcement, it happens of itself and
depends, for example, on the cement, the size of aggregate, the chemical elements,
the amount of water. Thus, densely reinforced concrete structures are subject to usual
shrinkage. The higher the concrete strength, the more shrinkage occurs. Since higher
concrete strength, means more cement and water and when the water leaves, shrink-
age happens. In this case, it is possible to use sulfate resisting cement which has a low
water-to-cement ratio and is suitable when high durability of concrete is needed. It is as
strong as regular cement but the shrinkage is smaller. (10.)
6.2 Casting
During the casting process, the concrete mass generally is not allowed to fall more
than 1 meter. Pipes can be used ensure a low drop height. A pipe is put down into the
structure between the rebars to a suitable level, and the structure is cast. This method
is broadly used to cast reinforced concrete structures. In densely reinforced concrete
structures it can be challenging. If the structure is thin and the reinforcement is dense
there will not be enough space for a pipe to be put in. This is why this method is not
suitable for densely reinforced structures. (1.)
Another option is to make a hole in the formwork and pour concrete through the hole to
avoid high fall. For example, if a wall is 3 meters high, a hole can be made at the 1 me-
ter level and concrete can be poured. (1.)
17
In densely reinforced concrete structures it is important to control the speed and the
quality of casting. The speed should not be too high to allow for proper vibration works.
Pumping is too fast for dense reinforcement, there is not enough time to perform vibra-
tion works correctly. In high structures, such as columns or walls, the height can be too
large, meaning that not all parts of the structure are necessarily vibrated. Densely rein-
forced concrete structures should be cast first to have enough time to control the cast-
ing and to fix problems if necessary. Generally, regular casting height is used. Howev-
er, it is necessary to take into account how vibration works are going to be done. (1.)
For reinforced concrete, a mechanical vibrator is the most suitable since it is efficient
and provides a high-quality result. Sometimes mould vibration is used to vibrate the
structure. (1.)
In densely reinforced concrete there is not much space between rebars, which is why a
smaller diameter of the rod should be used. Sometimes, rods get stuck between rebars
and it is impossible to get them out. Therefore, there should be enough equipment and
tools available at construction site to save time of the construction process. Also, cast-
ing or vibration works can take more time than originally planned. Therefore, the labour
resources should be sufficient to allow for an increase of the number of workers in a
certain place to keep the process going. (1.)
According to the drawing in figure 6, the structure seems functioning properly. How-
ever, the picture changes in the reinforcement overlapping area as can be seen in fig-
ure 7. The main vertical reinforcement is doubled, which makes a continues row of re-
bars, or in other words, a column of rebars. According to EN1992-1-1, the reinforce-
ment overlapping areas can be 8 % of the cross-section area, or according to Finnish
NA, it can be 12 %. However, in this case the overlapping reinforcement area is 6 %
and the structure does not function properly since there is no access for concrete be-
tween the rebars. The situation gets worse since additional anchors and muffs are lo-
cated inside the column which worsen the vibration works capability.
19
Figure 7. Reinforcement overlapping area of the column. The main reinforcement makes a
row of rebars. (14.)
In this case, there is an alternative for how the structure can be done. The main rein-
forcement of the upper or lower column could be bent inside. Thus, it would not be a
row of rebars, but rather one reinforcement would be near the edge as can be seen in
figure 6 and the bent rebars would be inside, next to the other rebar.
The next example is a reinforced concrete wall with 350 mm width. In the structure
there is an overlapping area with rebars from the lower level, there are rebars with 25
mm diameter and centre-to-centre is 125 mm. The main reinforcement is 2 rebars of 32
mm diameter with 150 mm centre-to-centre. The rebars are doubled, located next to
each other. In this area the reinforcement area is 8,5 % of cross-section area, in the
overlapping area, the maximum reinforcement area allowed is 12 % of the cross-
section area. Additionally, stirrups of various length and type support the main rein-
forcement horizontally.
20
Figure 8 is a photograph of the wall when the rebars were installed. The reinforcement
is extremely dense. Some areas have rows of main reinforcement rebars from 50 to
100 mm. When there is such a long row of reinforcement, the structure is not going to
function as it does with 1 or 2 rebars together. The drawing of the reinforcement area of
the column can be seen in figure 9.
In this case, the main reinforcement from the lower level could be done with a larger
diameter, for example 32 mm. This would reduce the amount of rebars in the wall and
there would be more space for vibration works and for the concrete to get between the
rebars.
21
The sample column is a rectangular reinforced concrete column that connects with a
circular composite column. The column is 1500 mm x 910 mm. In the connection area,
where the rectangular column connects with the circular column the cross section of
the rectangular column is increased and is 1500 mm x 1200 mm. The diameter of the
circular column is 535 mm. As figure 10 shows, the reinforcement is located too
densely in the connection area. The vertical stirrups have 50 mm centre-to-centre when
their diameter is 12 mm. According to these values, space between rebars is 38 mm. It
is important to take into account the ribs of the rebars which are 5-7 mm. From this we
get that the distance between the rebars is 28-24 mm. It is extremely difficult to imple-
ment this structure at the construction site. In this case, problem occurs only with stir-
rups, there is enough space between the vertical reinforcement. Stirrups with 16 mm
diameter could be used in order to increase the centre to centre distance between the
rebars. The structure was done with a 45 mm concrete cover, that means that the con-
crete is filled around the structure. However, it is important that the concrete cover
connects with the concrete which is inside the column. Otherwise, if the concrete cover
is separate from the concrete of the column, the structure is not going to function well.
Figure 10. Vertical section of connection area of rectangular column and composite column.
(17.)
22
In the same column, additional reinforcement has been added. However, it has not
been noticed that the main reinforcement is cut by additional reinforcement. In figure
11, it is possible to see that the main reinforcement interrupts with the additional rein-
forcement on the side edges of the column. It is not acceptable to leave reinforcement
interrupting another reinforcement without mentioning it in the drawing. Due to the addi-
tional reinforcement, it was necessary to cut the main reinforcement and substitute it
with overlapping rebars. It required additional work at the construction site, and the
bearing capacity of the column could be decreased. (9.)
Figure 11. Plan view of the rectangular column with additional reinforcement located on the
edges. (18.)
In figure 12, can be seen an additional reinforcement that is placed in the same loca-
tion as the main reinforcement of the column.
In figure 13, it is clearly seen that the rib of the rebar decreases the space from the
distance between the rebars.
24
The rib is from 5 to 7 mm, as mentioned above. That is why it is crucial to take it into
account during the design of densely reinforced concrete structures. (8.)
When planning HVAC holes and openings, it is necessary to take into account that the
areas are going to be densely reinforced.
25
Every hole and opening needs to be considered individually. Depending on the main
reinforcement, and the conditions for vibration works, the space in the structure, struc-
tural engineer needs to decide whether to set many rebars with smaller diameter or a
few rebars with larger diameter. Figure 14 demonstrates as an additional rebars are
installed around the openings.
The correct structural design of this column would be to keep the main reinforcement of
the upper column in the same position as the lower one but bend either the upper or
the lower reinforcement inwards in the area of overlapping reinforcement as figure 17
shows.
27
With this method the length of the required overlapping is longer. However, with this
method there will be no problems with concrete and its vibration works. Figure 13
shows the section of the column. In reinforcement overlapping area centre-to-centre
distance of stirrups should be 0.6 * maximum stirrups centre-to-centre distance. (11.)
Figure 18. Overlapping area of the main vertical reinforcement, when reinforcement from the
lower level is bent inside.
In figure 18, it is shown the total distance of reinforcement overlapping and the actual
working overlapping distance. The actual overlapping distance which transfers the
forces is shorter than the total overlapping. Therefore, the engineer must calculate ac-
tual reinforcement overlapping distance separately.
28
In Finland difficult projects are constantly designed. It requires structural design exper-
tise and experience, and cannot be done using general knowledge and common meth-
ods. It is crucial to understand that more difficult projects cannot be constructed the
same way as an ordinary building. Underestimation of the loads and forces, mistakes
and late changes in the preliminary planning stage can cause situations when engi-
neers need to design densely reinforced concrete structures. (9.)
The most important step is to correctly evaluate future loads and forces on the building
and estimate the proper values. Loads calculations should be done carefully because
they have a great impact on the future process of the project. It is exactly in this stage
engineers design the whole building with approximate values. It means that the values
of width, heights, and lengths of future structures elements are given. (9.)
For several reasons, engineers sometimes underestimate loads in the building in the
preliminary planning stage. Challenging projects usually do not seem difficult, and the
planning stage is done the same way as for an average building. However, some spe-
cial points are not taken into account. (9.)
After engineers have given approximate values for the structure, architects start to
work in their field, and the owner starts to sell square meters. At this stage the project
is started and any changes should be discussed and explained since any change can
affect all of the project processes.
However, detailed design of the structure starts approximately in 1-2 years after the
preliminary planning stage. At that point, architects have gone far with work in the pro-
ject, and the owner has sold most of the space. When engineers start to design the
structures in detail, it reveals that some elements of the structure cannot support the
loads and they need to be strengthened. The easiest option is to increase the cross-
section of the structure. However, it is not that easy because of the architecture of the
building and space inside the building. Since every square meter counts this is an eco-
nomical question. (9.)
29
In the preliminary planning stage, engineers should pay attention and include a margin
for changes or unexpected situations into the design to solve structural design prob-
lems more smoothly if anything unexpected appears.
During the preliminary planning stage, the approximate design process should be done
carefully, involving experts who have worked in challenging projects and have solved
many problems. Companies can create a database for knowledge and experience that
can significantly improve the efficiency of projects.
During the design process it is crucial that design engineers cooperate with structural
calculation engineers. Sometimes there are misunderstandings happens between de-
sign engineers and structural design engineers. (9.)
The design engineer receives details of the structure and loads in the implementation
design. If there is not space in the structure for enough reinforcement, and the utiliza-
tion percentage is close to 100, the design engineer must say that structure is not go-
ing to function. It is not acceptable to send a drawing to a construction site and hope
that the construction method will be figured out there.
30
In case structure cannot function properly, other solutions need to be discussed in or-
der to find the most suitable solution for a structure. It can be a substitution of a rein-
forced concrete structure by a composite or steel structures. Designing structures, the
engineer must pay more attention to what he designs. All details of the structure must
be taken into account.
8.3 Expertise
Sometimes people do not want to share and analyse mistakes. If an employee makes
a mistake, but stays quiet and does not share with others, it simply leads to another
employee can easily repeat a mistake. The experience should be discussed as it is the
fastest way to educate employees and prevent mistakes in the future. Otherwise, the
mistake can be repeated infinitely until everyone learns it. Mistakes in the design proc-
ess are expensive for a company. Therefore, it is efficient to create a system of analys-
ing mistakes to increase the efficiency of work in companies.
An experience sharing system should collect mistakes, analyse them and share these
with employees. Through such as system, employees can educate themselves quickly
by analysing examples of various cases, and future mistakes will be prevented.
Engineers who have already been involved in challenging construction should be the
first ones in new project to help others to prevent mistakes. A difficult project may not
seem as challenging as it is. This can lead to an underestimation of the project that will
cause problems later in the designing stage. (9.)
31
Designers should model structures in a BIM program the same way as they want the
structure to be constructed. By correct positioning, the designer will be able to under-
stand whether the structure is going to function properly or whether it is too densely
reinforced. BIM is a tool that simplifies construction process. (9.)
FEM programs are widely used in the structural engineering field. Their use saves time
in the structural design process, and, therefore, saves money for the company. FEM
programs are useful and can calculate the majority of structures. The results are mostly
correct and reliable. However, when using the programs, it is possible to make a mis-
take which can lead to a mistake in the design. When using the FEM program, the
most important thing for an engineer is to have an approximate, estimated results in
their mind, before the program calculates that. Therefore, the designer can compare
32
his or her results to those of the program. An approximate result can be calculated
quickly by hand and then compared with the calculations of the FEM program. If the
results look similar, the engineer can use the detailed numbers from the program. In
simple cases, it is easier for engineers to calculate by hand and be 100 % sure of the
results. (9.)
8.6 Drawings
In the reinforcement drawing of a structure, all pictures for the reinforcement (the plan,
sections, details, etc) included in the structure should be in the same drawing. It is not
recommendable to place detail views and sections of the structure separately with the
plan and other parts of the structure. It is extremely difficult to search for drawings of
other parts of the structure at construction site and it can be easily forgotten.
3D modelling programs support the drawing preparation a lot. Everything that is mod-
elled is shown in the drawing. It aids the designer to remember everything. A change of
structure in the model automatically changes the drawing. However, BIM programs
allow the user to change location, quantity and other properties of reinforcement in the
drawing phase. For example, if the rebars are shown by many lines in the drawings,
the drawing looks chaotic. It is possible to hide the lines and only leave one of them
visible in the middle of the group, or adjust the location of the rebar. This makes the
33
drawing look clear, and the structure does not seem too densely reinforced in the draw-
ing. However, all properties, such as the amount of rebars, centre-to-centre, and di-
ameter are still the same. Later at construction site, when all reinforcement is installed
workers will notice that the structure is too densely reinforced and concrete will not cast
evenly. At this point it will be difficult to change anything dramatically to improve the
situation. To prevent cases like this, it is necessary to prepare a drawing which shows
the real picture of the structure and reinforcement.
34
The design of densely reinforced concrete structures should be done with additional
attention. There are points that must be checked in order to design and construct the
structure correctly. The structural design instruction can be seen in Appendix 1.
Firstly, the engineer needs to check that concrete has an access to any part of the
structure. Horizontal movement of concrete must be as small as possible. Secondly,
the engineer must remember about the space for vibration works. Vibration work is one
of the most important phases of casting. Concrete gains full strength and properties by
correct implementation of vibration works. Therefore, in the structure there should be
enough space between the rebars for vibration works. Rebars can be grouped to allow
more space between the reinforcement. It is crucial also to consider that the ribs of the
rebar take a 5 to 7 mm of space. Vibration work process is explained in detail in chap-
ter 6.3.
It is crucial to provide clear work instruction to construction site. Drawings of the struc-
tures, work instructions, views of details and formwork should be clear for implementa-
tion.
In case the structure does not carry the loads and the engineer sees that structure is
not going to function properly, the engineer must point this out to the project manager
and suggest another solution or other materials.
Overlapping area is the most densely reinforced area. According to EN1992-1-1, Fin-
nish NA, reinforcement can cover 12 % of the cross-section area in overlapping areas.
(11.) This value is large; thus, engineers need to check that the space between rebars
is large enough for concrete to be cast.
The length of anchorage and overlapping reinforcement must follow the regulations.
The engineer must check whether there is enough space in the structure. If there is not
enough space, overlapping reinforcement should be bent inwards. When rebars are
bent inwards, actual overlapping distance is decreased. At some point, the lower level
bent rebar gets far away from the upper level rebar, and does not transfer the loads
anymore. The engineer must calculate the real functional overlapping distance. Accord-
ing to EN1992-1-1, in overlapping area, maximal distance between overlapped rebars
35
can be 4 * diameter or 50 mm. (11.) Another option for reinforcement joints is use of
couplers. It has a larger diameter than the rebars, however, rebars are not needed to
be overlapped and bent inside. Couplers can fully substitute the reinforcement overlap-
ping.
Each structure with holes and openings needs to be considered separately. In some
cases, it is better to use some rebars with a higher diameter than many smaller ones to
have enough space for vibration works. In some cases, it is more suitable to use many
rebars of lower diameter to have space for an equal distribution of aggregates. The
main task for an engineer is to take into account the concrete casting process and vi-
bration works.
All additional components must be considered during the design of the reinforcement
process. The process should be modelled and seen in the same drawing as the rein-
forcement. It is important to evaluate working joint area to ensure that there is enough
space for reinforcement. If TS joint reinforcement is used, it is necessary to check the
width, and to assess whether there is enough space for the reinforcement, as well as
check that it does not intersect with other rebars.
A higher concrete class increases the shrinkage of concrete which is not suitable for
densely reinforced concrete. In densely reinforced concrete structures, larger shrinkage
can cause cracking. Therefore, the structural engineer must use the most suitable con-
crete class to maintain the bearing capacity and to not allow large shrinkage. (10.)
The diameter of the rebars used in densely reinforced concrete structures should be as
large as possible to get more space for the concrete to be cast. In densely reinforced
concrete structures, the maximum size of aggregates can be 0.85 of the distance be-
tween rebars of the same direction. (11.)
36
10 Conclusion
Densely reinforced concrete structures are common in new challenging projects. How-
ever, Eurocode 1992-1-1, as well as other structural design materials regulates the
maximum value of allowed reinforcement. However, the origin and reasons for the
value are not explained. The purpose of this paper was to provide an overall picture of
densely reinforced concrete wall and column design. Another aim was to research the
origin of the maximum value for reinforcement, and examine problems of its implemen-
tation at the construction site. The final aim was to prepare a structural design guide for
densely reinforced concrete wall and column design. In order to gather sufficient and
valuable information, literary research as well as interviews with experts in the con-
struction field were carried out.
Despite densely reinforced concrete design being a common problem, it became ap-
parent during the research that this issue is not adequately studied and it is mostly ex-
perts who possess the ability to talk about this topic. The theoretical basis of the maxi-
mum value of reinforcement in a column or wall has not been found. The value is ar-
rived at through experience of application, economic efficiency, as well as laboratory
tests. An adequate value is 6 % of the cross-section. This should not be exceeded to
ensure that the structure functions correctly. However, even 6 % can be too large a
value for a structure. The reinforcement overlapping area, which can be 12 % of the
cross section according to EN1992-1-1, is too large. It is crucial to locate the rein-
forcement correctly so that the distance between the rebars is large enough for the
concrete to fill the space completely. Furthermore, enough space is required for the
vibration works.
The reason why densely reinforced concrete structures exist is alterations of the plans,
or an underestimation of the structure during the preliminary planning stage. Therefore,
it is crucial to consult as many experts and experienced project managers as possible
in the preliminary planning stage to minimize densely reinforced concrete structures.
37
Sometimes dense reinforcement is not noticed due to haste and mistakes during the
design stage.
In summary, preventing future mistakes is far more likely if those within the industry are
willing to share and discuss their negative experiences and previous mistakes.
38
References
10. Komonen Juha, interview. Research Manager, Contesta Oy. Vantaa, February
2018
16. Reinforcement overlapping area in the wall. Sweco Rakennetekniikka Oy. 2017.
17. Vertical section of connection area of rectangular column and composite col-
umn. Sweco Rakennetekniikka Oy. 2017
18. Plan view of the rectangular column with additional reinforcement located on
the edges. Sweco Rakennetekniikka Oy. 2017
1. Concrete distribution in the struc- Concrete should be able to access any part
ture of the structure. Horizontal movement of
concrete should be as small as possible.
2. Space for vibration works Vibration is one of the most important stages
of casting. Correct implementation of vibra-
tion works allows the structure to gain its full
properties. Therefore, there should be
enough space between the rebars for vibra-
tion works. Rebars can be grouped to allow
more space between the reinforcements. It
is crucial to consider that the ribs in the rebar
take a 5mm to 7mm of space. Vibration work
process is explained in detail in chapter 6.3.
4. In case structure cannot be de- If the structure does not have a capacity to
signed correctly, an engineer carry the required loads, an engineer must
must say about it. point this out to the project manager and
suggest to look for another solution or other
materials.
Appendix 1
2 (5)
7. Holes, openings, etc. Each case with holes and openings needs to
be considered separately. In some cases, it
is better to use some rebars with a higher
diameter than many smaller ones to have
enough space for vibration works. In some
cases, it is more suitable to use many rebars
of lower diameter to have space for an to be
equal distribution of aggregates. The main
task for an engineer is to take into account
the concrete casting process and vibration
works.
Figure 1. A row of rebars installed for a wall at construction site. Too little space is left for vibra-
tion work.
Appendix 2
2 (7)
Figure 2. Too densely reinforced concrete structure. (Sweco Rakennetekniikka Oy. 2017)
Appendix 2
3 (7)
Figure 6. Drawing of densely reinforced concrete wall. (Sweco Rakennetekniikka Oy. 2017)
Appendix 2
6 (7)
Figure 8. Additional reinforcement which is located in the same location as the main reinforce-
ment. (Sweco Rakennetekniikka Oy. 2017)