Location via proxy:   [ UP ]  
[Report a bug]   [Manage cookies]                

LD EL3

Download as pdf or txt
Download as pdf or txt
You are on page 1of 30
At a glance
Powered by AI
The key takeaways from the project included lessons learned around difficulties dealing with external stakeholders, lengthy LUP and land acquisition processes, and the need for clear roles and responsibilities in securing approvals.

The project scope involved expanding the North Jeddah Bulk Plant to increase storage capacity and provide additional infrastructure. It also involved developing the new Yanbu Distribution Hub grassroots facility to aggregate products from local refineries.

Some of the challenges faced by the project team included dealing with multiple external stakeholders in a timely manner, lengthy internal Saudi Aramco procedures that delayed meetings and agreements, and unclear roles around securing necessary LUPs and land acquisitions.

Lessons Learned Collection

Workshop Report

BI 10-02399
Additional Capacity
North Jeddah Bulk Plant &
Yanbu Distribution Hub - FEL3

Prepared by: Majdi Ali Alsaleh


Project Management Office Department
September 2016
Additional Capacity North Jeddah Bulk Plant & Yanbu Distribution Hub

Executive Summary

This report highlights lessons learned and the unique challenges BI 10-02399 (Additional Capacity
North Jeddah Bulk Plant & Yanbu Distribution Hub) IPT faced during the FEL3 phase of the project.
The lessons in this report were documented during the Lessons Learned Collection workshop that was
held in Khobar on September 1st, 2016. The objective of the workshop was to identify lessons learned
from (Additional Capacity North Jeddah Bulk Plant & Yanbu Distribution Hub) project for the benefit
of future projects. The workshop participants included Project Management personnel, Proponent
representatives, Facility Planning Department representatives and Designer Project Manager and Leads.

This report is organized as follows:

1.0 Project Scope Summary


2.0 Proposed Lessons Learned
3.0 Key Lessons Learned

The key lessons learned highlights the dominant and recurrent issues that were developed and discussed
during the lessons learned collection workshop.

The proposed lessons learned is the entire list of lessons learned captured during the workshop. The key
lessons learned were selected from this list on the basis of “potential value” and “widespread applicability”
to future projects.

The project scope summary section prefaces the rest of the report and provides a concise description of
the scope of (Additional Capacity North Jeddah Bulk Plant & Yanbu Distribution Hub) project and
lays the foundation for an understanding of the complexities of the project and the challenges that the
project management teams were confronted with.

Project team members should capitalize on successes achieved and avoid problems encountered by the
(Additional Capacity North Jeddah Bulk Plant & Yanbu Distribution Hub) IPT, some of which are
highlighted in this report. However utmost care should be exercised in applying these lessons to projects.
IPT’s should first seek to understand the context and basic concepts presented in the lessons, and adapt
them to their unique projects situation.

Saudi Aramco: Company General Use


1 September 2016
Additional Capacity North Jeddah Bulk Plant & Yanbu Distribution Hub

1.0 Project Scope Summery


The budget item is intended to provide a reliable refined products supply for Makkah province by
expanding North Jeddah Bulk Plant (NJBP) and providing the grassroots facility Yanbu Distribution
Hub (YDH). NJBP Expansion provides additional 1,000 MB of products storage, loading bays, Jet A-
1 unloading bays, and all supporting infrastructure. YDH provides a grassroots tank farm facility to
aggregate refined products from three (3) local refineries (SAMREF, YASREF, and Yanbu Refinery
Terminal) with a provision for future SA Yanbu Grassroots Refinery to facilitate shipment to NJBP.
YDH provides 3,400 MB product storage, shipper pump stations for PG95/PG91/DPK/DO, and all
associated infrastructure

Contracting Strategy
DBSP: GES+ Contract, Mustang HDP
Project Proposal: GES+ Contract, Mustang HDP
Detailed Design: GES+ Contract, to be advised
Construction: 3 LSTK Contracts, to be advised

Project Timeline
Duration
Task / Milestone Start Finish
(months)

BUSINESS CASE / / / /
FEL 1 / / / /

/ / / /

STUDY / / / /
FEL 2
DBSP Sep-2015 Jun-2016 9
/ / / /

PROJECT PROPOSAL Jun-2016 Dec-2016 6


FEL 3
/ / / /

/ / / /

DETAIL DESIGN Oct-2016 Oct-2017 12


Execution
CONSTRUCTION July-2017 July-2020 37

/ / / /

Saudi Aramco: Company General Use


2 September 2016
Additional Capacity North Jeddah Bulk Plant & Yanbu Distribution Hub

2.0 Proposed Lessons Learned

Originator Detailed
No. Proposed Lesson Topic
(initials) Lesson #

01 Difficulty in Dealing with External Stakeholders AAM 21

02 LUP’s and Land Acquisition Issues AAM 22

IPT Involvement and Understanding of Roles


03 BTG 13
and Expectations

Creation, Continuity and Focus of Core Team


04 BTG
(FPD, PMT, Proponent and Contractor)

Deviation from The Main Purpose of the


05 Project, Leading to Lack of Focus and Short BTG 14
Term Solutions

Implementation of CMS (Unclear Expectations and


06 BTG
Deliverables)

07 Late Implementation of Studies (SRA) AMT 15

Consideration of Existing Facilities in the


08 TSI 16
Project

09 Late Review of Plot Plan Limits TSI

No Clear Direction to Use Single or Multiple


10 Lupe Oil for Pumps, it Only Shows in Standard TSI 17
Drawings

11 Disconnection of Proponent from Project Cost TSI 18

Not having Allowance for Changes in Service


12 TSI 19
Order Budget

Discrepancy in Design Package related to Project


13 TSI
Narrative

Communicating Urgency of Project to Other


14 TSI 20
Departments

Saudi Aramco: Company General Use


3 September 2016
Additional Capacity North Jeddah Bulk Plant & Yanbu Distribution Hub

15 Conflict in SOW for Developing of the DBSP PND 04

Interface Study with Other BI’s was Not Done


16 PND 02
during FEL2b & 3

Interface Engineering to Accommodate


17 Relevant Engineering Standards of PND 03
Stakeholders

Late Consideration of Using Thrust Boring


18 PND 01
rather than Conventional Culvert

Consideration of Prior Approval Expenditure


19 PND
Request and Novation to Improve Project Schedule

Difficulty Getting Approval and Finalization for


20 AZ 06
Different Studies (BRA & RAM)

21 Poor Handling of Comments Log AZ 05

Design Improvements and Clarification were


22 missed because of Working Parallel on FEL2b AS 07
& FEL3

23 Late Tie-In Location Information Approvals AS 08

Number of Storage Tanks Changes Compared


24 AS 09
to PSP

Difference in Elevation between Existing and


25 MAM 11
New Area

Disposal of Heel Recovery Product Not Elaborated


26 MAM
in PSP

Interconnecting between 2 Pipelines was


27 MAM 12
Considered for a Flexible Operations

28 Conducting Laser Scanning Late MTI 10

Saudi Aramco: Company General Use


4 September 2016
Additional Capacity North Jeddah Bulk Plant & Yanbu Distribution Hub

3.0 Key Lessons Learned

Index of Lessons

No. Title Originator

01 Consideration for Thrust Boring v/s Culvert PND

02 Inadequate Interface Study with Other BI’s during FEL 2B & 3 PND

03 Interface Engineering & Relevant Engineering Standards PND

04 Key Consideration for DBSP SOW PND

Improper Handling of Comment Response Log for the 90% Project


05 AZ
Proposal

06 Difficulty in Getting Approval of Subcontracts AZ

Design Improvements and Clarifications were missed because of


07 AS
Parallel Working on FEL2B and FEL3

08 Late Tie-In Location Approval AS

09 Number of Storage Tanks Changes AS

10 Conducting Laser Scanning Late MTI

11 Elevation Difference between New and Existing Area MAM

12 Interconnection between Surge Relief Tank/Pump MAM

13 IPT Involvement and Understanding of Roles and Expectations BTG

Deviation from the Main Purpose of the Project, Leading to Lack of


14 BTG
Focus and Short Term Solutions

15 Conducting SRA Late in Brown Field BI’s AMT

16 Consideration of Existing Facilities in the Project TSI

17 No Clear Direction to Use Single Lube Oil for Each Pump TSI

18 Disconnection of Proponent from Project Cost TSI

19 Not Having Allowance for Changes in Service Order TSI

Saudi Aramco: Company General Use


5 September 2016
Additional Capacity North Jeddah Bulk Plant & Yanbu Distribution Hub

20 Communication Urgency of Project to Other Departments TSI

21 Difficulty in Dealing with External Stakeholders AMA

22 LUP’s and Land Acquisition Issues AMA

Saudi Aramco: Company General Use


6 September 2016
Additional Capacity North Jeddah Bulk Plant & Yanbu Distribution Hub

Proposed Lessons Learned

#01- Consideration for Thrust Boring v/s Culvert

Background

BI-10-02399, Proposed to set up Distribution Hub at Yanbu & Expansion of storage capacity at North
Jeddah for which DBSP was being developed by GES+ Contractor with IPT Team under CMS. This
project has pipelines, electrical cables & instrument cables crossing roads at various locations outside
the battery limit of the plant. Culverts design were recommended for crossing the roads. Construction of
culvert over the major roads could delay the project schedule as well increase the cost. Study was
conducted to use thrust boring for the pipelines to cross the roads. Drawings with thrust boring for the
pipelines were accomplished and submitted for the required approvals.

Root Cause/Benefit

Major cost benefits as well as positive impact on the schedule could be seen as achievable.

Recommendation

Due considerations must be provided for use of thrust boring in lieu of culverts where possible for
locations outside the battery limits of the plants.

Originator

Pradeepkumar N. Das, Engineer I, Pipelines, Distribution & Terminal Projects Department / North Jeddah
Bulk Plant Project Unit

Saudi Aramco: Company General Use


7 September 2016
Additional Capacity North Jeddah Bulk Plant & Yanbu Distribution Hub

#02- Inadequate Interface Study with Other BI’s during FEL 2B & 3

Background

BI-10-02399, Proposed to set up Distribution Hub at Yanbu & Expansion of storage capacity at North
Jeddah for which DBSP was being developed by GES+ Contractor with IPT Team under CMS.
Opportunity was observed during the DBSP development phase that installation of VRU unit could be
de-scoped from the on-going project.

Root Cause/Benefit

One of the prime reasons identified was that under BI-10-01036, standalone Vapor Recovery Unit (VRU)
was for existing facility and hence associated expansion was not considered. Therefore planning to
consider and study new / future projects was implemented at the existing facility, so that necessary
modifications / redesign could be done to achieve project purpose. In this case detail analysis was done
to accommodate requirement of expansion under BI-10-02399 which eventually called for modification
of design basis of VRU.

Cost savings (approximately 7 MMUSD) without any impact on the project schedule could be
accomplished as separate VRU unit for the expansion was not required.

Recommendation

Associated projects on-going as well as near future projects anticipated must be studied to consider the
benefits and opportunities available.

Originator

Pradeepkumar N. Das, Engineer I, Pipelines, Distribution & Terminal Projects Department / North Jeddah
Bulk Plant Project Unit

Saudi Aramco: Company General Use


8 September 2016
Additional Capacity North Jeddah Bulk Plant & Yanbu Distribution Hub

#03- Interface Engineering & Relevant Engineering Standards

Background

BI-10-02399, Proposed to set up Distribution Hub at Yanbu & Expansion of storage capacity at North
Jeddah for which DBSP was being developed by GES+ Contractor with IPT Team under CMS. This
project has interface with MARAFIQ, SAMREF, Yanbu Refinery and Yanbu Royal Commission. It was
encountered during DBSP development that relevant engineering standards differed from SA
Engineering Standards and guidelines. Ambiguity are observed and design may change to accommodate
the prevailing standards & guidelines.

Root Cause/Benefit

Interface was not designed with consideration to the design standards followed by the respective
stakeholders.

Identifications at early stage of the design development was not done to rule out duplication of design
engineering and eliminate major changes.

Recommendation

Significant considerations to the prevailing design standards among the stakeholders must be considered
during the design phase so that no major changes are encountered.

Originator

Pradeepkumar N. Das, Engineer I, Pipelines, Distribution & Terminal Projects Department / North Jeddah
Bulk Plant Project Unit

Saudi Aramco: Company General Use


9 September 2016
Additional Capacity North Jeddah Bulk Plant & Yanbu Distribution Hub

#04- Key Consideration for DBSP SOW

Background

BI-10-02399, Proposed to set up Distribution Hub at Yanbu & Expansion of storage capacity at North
Jeddah for which DBSP was being developed by GES+ Contractor with IPT Team under CMS. GES+
Contractor was approached with SOW specified in PSP. It was noticed and observed during DBSP
development phase that deliverables were derived from PSP. These deliverables were not sufficient to
complete the DBSP for SOW intended to be completed under BI-10-02399.

Root Cause/Benefit

One of the prime reason identified was only SOW covered under PSP would be developed by GES+ in
the form of DCL. Conflict had arisen as there were certain SOW which were not identified as DCL and
hence not covered under SOW which could eventually not develop a good DBSP package.

Recommendation

During the clarification meeting with the GES+ Contractor prior to awarding the job, GES+ Contractor
must be explained the intent of the project and relevant SOW should be considered by GES+ for
developing sound DBSP package for further progress of the project.

Originator

Pradeepkumar N. Das, Engineer I, Pipelines, Distribution & Terminal Projects Department / North Jeddah
Bulk Plant Project Unit

Saudi Aramco: Company General Use


10 September 2016
Additional Capacity North Jeddah Bulk Plant & Yanbu Distribution Hub

#05- Improper Handling of Comment Response Log for the 90% Project Proposal

Background

The 90% comment response log for North Jiddah bulk Plant Expansion package was handled improperly.

BI Number 10-02399
BI Title Yanbu Distribution Hub and North Jeddah
Order 10-02399-0001
Order Title Preliminary Eng. North Jeddah Bulk Plant
Order Remarks
90% PP/DBSP of North Jeddah Bulk Plant (Exclude Package 2 - Kerosene
Review Title
Unloading Skids)
Phase Project Proposal
Cycle 90%
Planned Start Date 6/1/2016
Planned End Date 6/14/2016
Actual Start Date 6/2/2016
Actual End Date 6/15/2016

The comment response review meeting was scheduled on 22nd of June 2016 as per attached attendance
sheet. Design Contractor kept on receiving the comments until 20th of June 2016 by emails. This was e-
review system but Design Contractor received many emails as comments after the cutoff date.

Many commentators were unavailable at the comments review meeting and then lot of e-mail
correspondences had to be done to close out the comments.

Root Cause/Benefit

 Comments review meeting was not attended by commentators.


 Cutoff date for receiving comments was not successful and cutoff date for receiving responses to
comments was not successful.

Recommendation

 Comment review meeting shall be attended by commentators or a cutoff date shall be announced
that if responses are not received from commentator it is understood that GES+ contractor responses
are acceptable.
 It is better if all comments shall come through the e-review system.

Originator

Abdul Rehman Zakir, Project Engineer, Mustang HDP


Saudi Aramco: Company General Use
11 September 2016
Additional Capacity North Jeddah Bulk Plant & Yanbu Distribution Hub

#06- Difficulty in Getting Approval of Subcontracts

Background

Many sub contracts were executed during FEL2b and FEL3 stage of the project. More specifically we
had difficulty in getting the finalization and approval of Reliability, Availability and Maintainability (RAM)
Report. The draft report was commented on several times and the report was required to be revised
several times.

Root Cause/Benefit

Commenting on the draft report several times by the same commentator.

Recommendation

Comments shall be received from all commenters only one time by the due cutoff date and not in piece
mail basis.

Originator

Abdul Rehman Zakir, Project Engineer, Mustang HDP

Saudi Aramco: Company General Use


12 September 2016
Additional Capacity North Jeddah Bulk Plant & Yanbu Distribution Hub

#07- Design Improvements and Clarifications were missed because of Parallel Working on FEL2B
and FEL3

Background

For BI-10-02399 (YDH portion), SA asked to work on 60% FEL3 and same to be submitted as FEL2B.
Accordingly, Design Contractor worked on 60% FEL3 and some of its deliverables submitted with FEL2B.
This caused one less submission of the project due to which design freeze could not be done at FEL2B.

Root Cause/Benefit

Due to squeeze of project schedule.

Recommendation

FEL3 should be started after approval of FEL2B.

Originator

Azeem Sajjad, Process Engineer, Mustang HDP

Saudi Aramco: Company General Use


13 September 2016
Additional Capacity North Jeddah Bulk Plant & Yanbu Distribution Hub

#08- Late Tie-In Location Approval

Background

For the tie-ins at SAMREF for product transfer to YDH, initial visit was carried out at the start of the
project. During the visit, Design Contractor identified the tie-ins along with FPD, Proponent and SAMREF
operations. After the visit a site visit report was issued and later 60% FEL3 but Design Contractor did not
receive any information about tie-in confirmation. Then at very late stage when 90% FEL3 was ready for
submission, different tie-in location proposal was received from SAMREF.

Root Cause/Benefit

1. No feasibility was done for these tie-ins.


2. Specific area / approving authority were not present during the visit.

Recommendation

1. SAPMT and proponent should emphasize on approvals of all site related issues especially tie-ins and
these should be resolved as soon as possible.
2. There should be active participation from all stakeholders at beginning stage of the project to decide
and concur on the tie-ins.

Originator

Azeem Sajjad, Process Engineer, Mustang HDP

Saudi Aramco: Company General Use


14 September 2016
Additional Capacity North Jeddah Bulk Plant & Yanbu Distribution Hub

#09- Number of Storage Tanks Changes

Background

At the start of the project, PSP proposed certain numbers of storage tanks for the facility. However, it
gets changed along with some other major changes like use of existing pumps at YR instead of new
pumps.

Root Cause/Benefit

Reduction in project CAPEX, project will be executed in phases.

Recommendation

Such kind of major scope changes should not be done after award of the project.

Originator

Azeem Sajjad, Process Engineer, Mustang HDP

Saudi Aramco: Company General Use


15 September 2016
Additional Capacity North Jeddah Bulk Plant & Yanbu Distribution Hub

#10- Conducting Laser Scanning Late

Background

Laser scanning is part of Design Contractor scope in North Jiddah Bulk Plant Expansion. It took too long
to receive the scanning data for the existing facility due to licensing and technical reasons. By the time
60% milestones were already achieved, most of the piping routes had already been finalized based on
the site visit and existing drawings. When laser scanning data (Point cloud data) was superimposed on
the 3D model (piping), it was found that there is a lot of clashes with the existing facility. This caused a
lot of changes in pipe routings.

Root Cause/Benefit

There are two reasons for the above:

1. Existing drawings from the i-plant are not as built.


2. Laser scanning information received at a late stage of the project.

Recommendation

There are two recommendations:

1. Laser scanning should be mandated for brown field projects in order to avoid changes during
subsequent phases.
2. Laser scanning should be conducted at DBSP stage or immediately after DBSP but before FEL3
stage.

Originator

Muhammad Tufail, Lead Piping Engineer, Mustang HDP

Saudi Aramco: Company General Use


16 September 2016
Additional Capacity North Jeddah Bulk Plant & Yanbu Distribution Hub

#11- Elevation Difference between New and Existing Area

Background

North Jiddah Bulk Plant is an expansion project which has existing and new area. Topo survey was
conducted and the results were available late. The different elevations between the existing area and the
new area was reported in the Topo report at a time when design was already in progress. Different
elevation between these two areas may cause design lapse mainly during hydraulic calculation.

Root Cause/Benefit

Topo survey report was not available at the early stage of the project.

Recommendation

The designer shall consider the difference in elevation between the new and the existing areas to have
the correct design.

Originator

Mujtaba A. Matar, Lead Process Engineer, Mustang HDP

Saudi Aramco: Company General Use


17 September 2016
Additional Capacity North Jeddah Bulk Plant & Yanbu Distribution Hub

#12- Interconnection between Surge Relief Tank/Pump

Background

Two pipelines are received from Yanbu Distribution Hub. One is 24 inch (DO, DPK) and the other pipeline
is 20 inch (PG91, PG 95). Initially each pipeline had a dedicated surge relief tank/pump. Later on SAPMT
requested to have interconnection line between them to get more flexibility in operation.

Root Cause/Benefit

Due to any maintenance of surge relief tank or surge relief pump the other surge tank/pump can be
utilized.

Recommendation

To provide interconnecting line at tank outlet, pump suction and pump discharge for more flexible
operation.

Originator

Mujtaba A. Matar, Lead Process Engineer, Mustang HDP

Saudi Aramco: Company General Use


18 September 2016
Additional Capacity North Jeddah Bulk Plant & Yanbu Distribution Hub

#13- IPT Involvement and Understanding of Roles and Expectations

Background

During the creation of the project team all the way thru to the end of FEL2B, there has been a learning
process with all of the team members regarding their roles within the project team and how the team as
a whole functions. In some instances there are divisional walls where one member will not perform a task
as it is the responsibility of another group. I have experienced several times where team members were
unaware of their roles and what/ how they should do something. For example CMS mandates that a
document must be signed off by the department, yet the IPT member for that department will not sign the
document. Finally there is a struggle aligning everyone’s intentions and actions as a single unified team
to complete the project. Unfortunately there are some groups or individuals who believe that they are a
transactional contributor to the team and their function is to challenge to the letter of the regulation. The
guiding principle of the IPT is to tear down the walls that divide and unite the team to creatively and
collectively complete the project.

Root Cause/Benefit

The CMS is ultimately attempting to change the culture to a move collective, ownership culture. While
shifts like this take time, they also require significant training, communication, and alignment of objectives.

Recommendation

Possibly additional training or a few larger meetings with all of the members would have helped align all
of the IPT. Additionally monthly working level IPT meetings may be a good idea.

Originator

Bryan T. Gorrell, Facilities Planning Specialist, Facilities Planning Department / Distribution Group

Saudi Aramco: Company General Use


19 September 2016
Additional Capacity North Jeddah Bulk Plant & Yanbu Distribution Hub

#14- Deviation from the Main Purpose of the Project, Leading to Lack of Focus and Short Term
Solutions

Background

During the initial phases of this project, there was a significant amount of time placed (+3months) against
creating short term solutions for supply gaps before the project was completed. FPD and the IPT are
mandated to work on the design and oversite of capital projects and thus the team was performing
activities outside of their team focus.

Root Cause/Benefit

 A weak initial team charter and understanding of the IPT’s core function lead to the lack of project
focus.
 Misalignment work borders with the IPT and proponent teams.

Recommendation

 Training to IPT members and the senior leadership on the remit and function of the IPT team to
understand their boundaries.
 Additionally, a stronger team focus communicated across all levels could be performed at the
beginning of each new project.

Originator

Bryan T. Gorrell, Facilities Planning Specialist, Facilities Planning Department / Distribution Group

Saudi Aramco: Company General Use


20 September 2016
Additional Capacity North Jeddah Bulk Plant & Yanbu Distribution Hub

#15- Conducting SRA Late in Brown Field BI’s

Background

In NJBP during DBSP, SRA was conducted late and came up with scope changing recommendations
that caused delay in issuance of DBSP design package.

Scope changes was basically to upgrade existing fence along with IDAS system which accordingly
required changes in the design especially in the instrumentation and civil scopes as well as spacing in all
related drawings.

Root Cause/Benefit

SRA usually conducted at later stages in grass root projects because there is no exiting plant to assess.

Recommendation

In brown field projects, SRA shall be conducted at early stages in order to capture all scope changing
recommendation in the DBSP package.

Originator

Abdul Majeed M. Taresh, Engineer IV, PD&T Projects & Technical Support Department / D&T Project
Planning Unit

Saudi Aramco: Company General Use


21 September 2016
Additional Capacity North Jeddah Bulk Plant & Yanbu Distribution Hub

#16- Consideration of Existing Facilities in the Project

Background

Any new project in Saudi Aramco is required to comply with the latest standards and procedures which
include brown field projects that deal with existing facilities. North Jiddah Bulk Plant Expansion Project is
part of BI-10-02399 which includes connection and modification scope to existing facilities. Therefore,
complying with the latest standards and procedures for existing facilities will have a cost and schedule
impacts. Otherwise, processing a waiver if it is not possible to comply with the new requirements which
leads to major schedule impact on the project.

Root Cause/Benefit

As there is no consideration of brown field in Saudi Aramco standards and procedures, the project has
to comply with Saudi Aramco standards and procedures which are made considering the new facilities.

Recommendation

As Saudi Aramco is growing up and more projects are coming for existing facilities, Saudi Aramco
standards and procedures shall include clauses and exceptions for the brown field projects that deal with
existing facilities.

Originator

Talal S. Isa, Engineer IV, Pipelines, Distribution & Terminal Projects Department / Yanbu-North Jeddah
Dist. & P/L Projects Division

Saudi Aramco: Company General Use


22 September 2016
Additional Capacity North Jeddah Bulk Plant & Yanbu Distribution Hub

#17- No Clear Direction to Use Single Lube Oil for Each Pump

Background

There are 3 diesel shipper pumps and 3 gasoline shipper pumps shall be provided for Yanbu Distribution
Hub which is part of BI-10-02399. There was a value engineering idea to combine the lube oil system for
each 3 pumps and it was raised to CSD for evaluation because there was no clear direction to use lube
oil system for each pump in SAES-G-005. CSD replied as following: per the standard drawing AA-036858,
separate lubrication system shall be used for each pump (each shipper pump in your case). However, it
is fully clear in the standard drawing to provide a separate lubrication system for each pump.

Root Cause/Benefit

There is no clear direction in Saudi Aramco standards and procedures to use lube oil system for each
pump.

Recommendation

There shall be a clear guidance in SAES-G-005 whether to use single lube oil for each pump or combined
lube oil for several pumps. In case this will vary based on the pump size and service, then guidance for
selection shall be detailed with required information.

Originator

Talal S. Isa, Engineer IV, Pipelines, Distribution & Terminal Projects Department / Yanbu-North Jeddah
Dist. & P/L Projects Division

Saudi Aramco: Company General Use


23 September 2016
Additional Capacity North Jeddah Bulk Plant & Yanbu Distribution Hub

#18- Disconnection of Proponent from Project Cost

Background

The project cost in Saudi Aramco is not connected to the proponent cost center. Therefore, the proponent
is not involved in the responsibility of the project cost and schedule as it should be.

Root Cause/Benefit

The proponent is not involved fully in the responsibility of the project cost and schedule as per the
company system and policy.

Recommendation

The project cost shall be connected to the proponent cost center which will lead to proponent involvement
in the responsibility of project cost and schedule and that will add a great force to complete the project
on time with minimum cost.

Originator

Talal S. Isa, Engineer IV, Pipelines, Distribution & Terminal Projects Department / Yanbu-North Jeddah
Dist. & P/L Projects Division

Saudi Aramco: Company General Use


24 September 2016
Additional Capacity North Jeddah Bulk Plant & Yanbu Distribution Hub

#19- Not Having Allowance for Changes in Service Order

Background

During DBSP and Project Proposal, any minor change required service order revision which consumed
a lot of time to be completed and that impacted the project schedule. Sometimes, we will find a minor
change after the service order revision is completed and that also required another service order revision.

Root Cause/Benefit

There is no allowance for changes in the service order for Project Proposal to incorporate changes
without revision for the service order.

Recommendation

There shall be allowance for changes in service order which can be added as optional to incorporate the
minor changes without revision for the service order.

Originator

Talal S. Isa, Engineer IV, Pipelines, Distribution & Terminal Projects Department / Yanbu-North Jeddah
Dist. & P/L Projects Division

Saudi Aramco: Company General Use


25 September 2016
Additional Capacity North Jeddah Bulk Plant & Yanbu Distribution Hub

#20- Communicating Urgency of Project to Other Departments

Background

BI-10-02399 is considered as a fast truck and urgent project to meet the required demand of Gasoline,
Diesel and Kerosene in Makkah Province. There are a lot of documents and deliverables to be reviewed
and approved by other Saudi Aramco departments. However, the urgency of this project is not identified
for other departments by official letter or identification. Therefore, the review or approval of any project
deliverables or reports will go through the normal cycle and it will take the normal time without treating
them as a priority.

Root Cause/Benefit

There is no official identification of the urgent projects for Saudi Aramco departments to expedite the
process for them and give these projects priority.

Recommendation

There shall be a formal way in Saudi Aramco to identify the urgent projects and this identification could
be a letter from the highest authority in the company will give this project the priority by other departments.

Originator

Talal S. Isa, Engineer IV, Pipelines, Distribution & Terminal Projects Department / Yanbu-North Jeddah
Dist. & P/L Projects Division

Saudi Aramco: Company General Use


26 September 2016
Additional Capacity North Jeddah Bulk Plant & Yanbu Distribution Hub

#21- Difficulty in Dealing with External Stakeholders

Background

It was difficult dealing with multiple external stakeholders in timely manner which lead to delay of many
agreement and high level of uncertainty (RISK). Also, internal Saudi Aramco procedure is limiting in
communication and setting up the meeting. The process is lengthy and not in the favor of the project.
Example, IPT requested a meeting with YRC since May, 2016 and till end of September, 2016 SA GA
could not be able to confirm. This will lead to delay of PP approval by MC as many open items are not
resolved, agreement not signed, and related LUP’s are not secured.

Root Cause/Benefit

Because IPT is utilizing ordinary method and tools, while this is a critical accelerated schedule project.

Recommendation

I would recommend for any future project will be schedule driven and fast track schedule, task force to
be established with high support from upper management to ease working with external entities.

Originator

Abdulrahman M. Abahussain, Scheduling Engineer III, Pipelines, Distribution & Terminal Projects
Department / Yanbu, Jeddah Pipeline

Saudi Aramco: Company General Use


27 September 2016
Additional Capacity North Jeddah Bulk Plant & Yanbu Distribution Hub

#22- LUP’s and Land Acquisition Issues

Background

LUP’s/Land Acquisition identification and process is too lengthy and the IPT role/responsibility is not clear
in securing them. LUP’s and Land acquisition being submitted at late stage where DBSP approved
without securing all LUP’s nor Land Acquisition.

Root Cause/Benefit

As this project schedule is in a fast tracking mode and many activities sequence is broken, risk is become
higher in losing efforts and time.

Recommendation

LUP’s and Land acquisition plan to be developed by SME at early stage (FEL2A). This management plan
is to identify the high level of LUP’s/Land acquisition and plan effort/activities toward securing them at
the earliest.

Originator

Abdulrahman M. Abahussain, Scheduling Engineer III, Pipelines, Distribution & Terminal Projects
Department / Yanbu, Jeddah Pipeline

Saudi Aramco: Company General Use


28 September 2016
Additional Capacity North Jeddah Bulk Plant & Yanbu Distribution Hub

Workshop Participants

No. Name User ID/ E-mail Dept. /Organization

Facilities Planning Department /


1 Bryan T. Gorrell gorrelbt
Distribution Group

Pipelines, Distribution & Terminal


2 Abdulrahman M. Abahussain abahusam Projects Department / Yanbu,
Jeddah Pipeline

Pipelines, Distribution & Terminal


Projects Department / Yanbu-North
3 Talal S. Isa isats
Jeddah Dist. & P/L Projects
Division

Pipelines, Distribution & Terminal


4 Pradeepkumar N. Das DASPN Projects Department / North
Jeddah Bulk Plant Project Unit

Pipelines, Distribution & Terminal


5 Ahmad A. Rebh REBHAA0E Projects Department / Yanbu Tank
Farm Project Unit

PD&T Projects & Technical


6 Abdul Majeed M. Taresh TARESHAM Support Department / D&T Project
Planning Unit

PD&T Projects & Technical


7 Talal B. Basseet BASSEETB Support Department / Refined
Products Pipelines Unit

Mohamed.Ebeid@musta Project Manager


8 Mohamed Ebeid
nghdp.com MHDP

Abdul.Zakir@mustanghd Project Engineer


9 Abdul Rehman Zakir
p.com MHDP

Azeem.Sajjad@mustang Process Engineer


10 Azeem Sajjad
hdp.com MHDP

Mujtaba.AlMatar@musta Process Engineer


11 Mujtaba A. Matar
nghdp.com MHDP

MUHAMMAD.TUFAIL@ Piping Engineer


12 Muhammad Tufail
mustanghdp.com MHDP

Saudi Aramco: Company General Use


29 September 2016

You might also like