Procedure System of Control For Non Conformance Control
Procedure System of Control For Non Conformance Control
Procedure System of Control For Non Conformance Control
Procedure
System of CONTROL FOR NON CONFORMANCE
CONTROL
1 Revision History
Revision Description of
DATE Initiated By Completed By
No# Changes
15th Management Integration for ISO Management
November Representative 14001 and OHSAS Representative
01
2018 18001 & ISO 31000
RISK MANAGEMENT
2 Distribution List
Sr. No/ Designation Issue Date Distributed by
04 Management
Chairman 15th November 2018
Representative
Copyright
This document contains confidential information. It may be copied in full or in parts only by Al-Jaber
International Company and only for the purpose of Al-Jaber International Company related activities.
Disclosure of any information contained within this procedure to any person (s) outside the employee of Al-
Jaber International Company without written permission of the Top Management is strictly prohibited.
Page 1 of 8
Al-Jaber International Company
Procedure System of
CONTROL FOR NON CONFORMANCE CONTROL
Original Issue Date: Revision Issue date:
Doc. No: AJB-CFNCC-PR-01 Issue Number: 01 Revision Number: 01
01st January 2016 15th November 2018
TABLE OF CONTENTS
This document is the property of Al-Jaber International Company. Any copying and distribution of this document
without the approval of the Management is prohibited. Page 2 of 8
Al-Jaber International Company
Procedure System of
CONTROL FOR NON CONFORMANCE CONTROL
Original Issue Date: Revision Issue date:
Doc. No: AJB-CFNCC-PR-01 Issue Number: 01 Revision Number: 01
01st January 2016 15th November 2018
1.2 Acronyms
Acronym Description
DS Degassing Station
IMS Integrated Management System
ECP Evaporative Cooler Project
NCR Non-Conformance Reports
QMS Quality Management System
QA/QC Quality Assurance / Quality Control
RCA Root Cause Analysis
TSC Technical support Services
SGPS Suleimanya Gas Power Station
This document is the property of Al-Jaber International Company. Any copying and distribution of this document
without the approval of the Management is prohibited. Page 3 of 8
Al-Jaber International Company
Procedure System of
CONTROL FOR NON CONFORMANCE CONTROL
Original Issue Date: Revision Issue date:
Doc. No: AJB-CFNCC-PR-01 Issue Number: 01 Revision Number: 01
01st January 2016 15th November 2018
2 INTRODUCTION
The plant is located in the town of Chamchamal, which is located about 60 Km to the west of
Suleimanya city.
MGH has signed a contract with the Ministry of Electricity in Kurdistan Region to build SGPS with
a Capacity of 1500 MW on basis BOO (Build,Operate and Own). Work Started at site early 2008.
In the first and second phases (simple cycle), eight Frame-9E gas turbines were installed and
operated to produce 1000 MW and the contract for the simple cycle was signed with the
American Company GE and the German Company ABB.
As the Third Phase of the project, MGH started converting SGPS into a Combined Cycle with
additional 500 MWs capacity, by utilizing the gas turbine exhaust heat emissions to produce
steam in Heat Recovery Steam Generators (HRSG), which will used to generate electricity in two
steam turbines. This process increases the production efficiency without using extra fuel. It also
reduces the amount of CO2 emissions and frees the environment from combustion emission.
After the completion of the combined cycle, the plant capacity will be upgraded to 1500 MW.
It is worth mentioning that Sulaymaniyah power station is designed to operate on two types of
fuel, the prime fuel (natural gas) and secondary fuel (diesel).
The substation accompanying the plant is 132 KV for a Simple Cycle and a 400 KV for the
combined cycle, both were supplied by the Swedish company ABB and the power is transferred
from the station site via fourteen high voltage lines connected to the national grid in the
Kurdistan region.
This document is the property of Al-Jaber International Company. Any copying and distribution of this document
without the approval of the Management is prohibited. Page 4 of 8
Al-Jaber International Company
Procedure System of
CONTROL FOR NON CONFORMANCE CONTROL
Original Issue Date: Revision Issue date:
Doc. No: AJB-CFNCC-PR-01 Issue Number: 01 Revision Number: 01
01st January 2016 15th November 2018
3 PURPOSE
The purpose of this procedure is to ensure that non-conforming product are clearly identified,
segregated and controlled, so that unauthorized or inadvertent use is prevented, their disposition
formally agreed and recorded.
4 PROCESS INPUTS
The following process inputs are required for this procedure:
Material Receiving Inspections
In-progress Inspections / Testing
5 PROCESS OUTPUTS
6 PROCEDURE
The Non-Conformance Procedure and process shall cover all phases of the
project. That shall include Engineering, Procurement, Fabrication, Construction
and Installation. It covers all product related Non- Conformances during all
phases of the project.
Vendor / Supplier shall cover NCR during their own manufacturing process as
per their own procedure.
However should supplier not raise NCR against the identified product Non-
Conformance, CONTRACTOR NCR procedure shall be adhered.
Any material that is identified as not meeting the stated requirements shall be
placed in quarantine and recorded by issue of an NCR.
This document is the property of Al-Jaber International Company. Any copying and distribution of this document
without the approval of the Management is prohibited. Page 5 of 8
Al-Jaber International Company
Procedure System of
CONTROL FOR NON CONFORMANCE CONTROL
Original Issue Date: Revision Issue date:
Doc. No: AJB-CFNCC-PR-01 Issue Number: 01 Revision Number: 01
01st January 2016 15th November 2018
After issuing a NCR the product shall be identified with an NCR label with the
NCR number marked on it. The label shall remain on the product until a
concession is granted or the product is rejected, reworked or replaced.
The original NCR shall be forwarded to the Project QA/QC Manager or his
nominee for authorization.
This document is the property of Al-Jaber International Company. Any copying and distribution of this document
without the approval of the Management is prohibited. Page 6 of 8
Al-Jaber International Company
Procedure System of
CONTROL FOR NON CONFORMANCE CONTROL
Original Issue Date: Revision Issue date:
Doc. No: AJB-CFNCC-PR-01 Issue Number: 01 Revision Number: 01
01st January 2016 15th November 2018
The nonconformity log shall be updated on a regular basis to reflect the status
of the nonconformities.
It is the responsibility of the Project QA/QC Manager (or his nominee) to ensure
that all Quarantine areas are cleared regularly and that materials contained
there are either salvaged or replaced.
6.7 General
This procedure covers all product related Non-Conformance during all phases
of the project.
EMIL Quality, Project Management and Engineering group review and approve
all disciplines.
This document is the property of Al-Jaber International Company. Any copying and distribution of this document
without the approval of the Management is prohibited. Page 7 of 8
Al-Jaber International Company
Procedure System of
CONTROL FOR NON CONFORMANCE CONTROL
Original Issue Date: Revision Issue date:
Doc. No: AJB-CFNCC-PR-01 Issue Number: 01 Revision Number: 01
01st January 2016 15th November 2018
All major NCR and COMPANY issued NCR, a formal RCA session shall be
conducted with the relevant project personnel in attendance.
Trend Analysis and Root Cause Analysis (RCA) shall be completed for all NCR
by the Project QA/QC Manager.